Method Statement for Lifting Operations.
Method Statement for Lifting Operations.
Page 1 of 6
Engineering
(Lifting Operations)
work
Department Document Ref. No. 01 Issue Date Revision
E.O.T CRANE 01
Table of Content
1.0 Purpose 2
2.0 Objective 2
3.0 Scope 2
4.0 Quality of Installation 2
5.0 Risk Assessment 2
6.0 Equipment 2
Make Sure that the Lifting Tackle: 3
Load 3
Make Sure That the Load Itself Is: 3
Workers 4
8.0 Health & Safety Hazards 4
9.0 Responsibilities 4
Project Manager 4
Project Engineer 4
Supervisor 5
1
Shailedra Method Statement
Page 2 of 6
Engineering
(Lifting Operations)
work
Department Document Ref. No. 01 Issue Date Revision
E.O.T CRANE 01
1.0 Purpose
The general purpose is to ensure that a Safe System of Work (SSOW) applies to the risks associated with lifting,
moving, and lower pipes, concrete rings etc. Each activity has been carefully considered and appropriate
controls implemented. The specific purpose of this Method Statement procedure is to describe the method of
lifting, moving, and lower pipes, concrete rings
2.0 Objective
This method statement is critical to the health and safety (H&S) of the activity it relates to. It is too followed and
adhered, any deviation or changes must be first authorized by the site supervisor
3.0 Scope
We [RAJAT CONSTRUCTIONS] will be using a [Crane/Heavy Lifting Machinery] to lift, move, and lower pipes,
concrete rings etc. The excavations will be up to 5.0 meters deep in some of the areas.
2
Shailedra Method Statement
Page 3 of 6
Engineering
(Lifting Operations)
work
Department Document Ref. No. 01 Issue Date Revision
E.O.T CRANE 01
6.0 Equipment
Before any lifting operation, ensure that the relevant safety checks have been undertaken on the [Crane/Heavy
Lifting Machinery] and any other equipment being used:
● Leather Gloves
● Hard Hat
● Goggle Glass
● Dust Mask
● First Aid Kit
● Two-way radio
● Measuring equipment
3
Shailedra Method Statement
Page 4 of 6
Engineering
(Lifting Operations)
work
Department Document Ref. No. 01 Issue Date Revision
E.O.T CRANE 01
8.0 Responsibilities
Project Manager
• Project Manager shall be responsible for overall project execution.
• He will coordinate with the client and head office.
• He is responsible for progress monitoring, attending review meetings and resource management.
• Overall, he will be responsible for the timely completion of the project following all contractual
requirements.
Project Engineer
• Lifting, moving, are carried out according to the specifications and approved method statement.
• Provision of all necessary information and distribution of responsibilities to his Lifting team in
consultation with the Lifting manager.
• The work progress is monitored following the required program and reports the same to the Lifting
Manager.
4
Shailedra Method Statement
Page 5 of 6
Engineering
(Lifting Operations)
work
Department Document Ref. No. 01 Issue Date Revision
E.O.T CRANE 01
Supervisor
• The carrying-out the work and the proper distribution of all the available resources in coordination with
the Site Engineering daily.
• Daily reports of the works are achieved and coordinated for future planning with the site Engineer.
• Incorporate all the QC and Safety requirements as requested by the concerned Engineer.
• Meeting with any type of unforeseen incident or requirement.
Project/Facility:
5
Shailedra Method Statement
Page 6 of 6
Engineering
(Lifting Operations)
work
Department Document Ref. No. 01 Issue Date Revision
E.O.T CRANE 01