Hand Books for Internal Check
Hand Books for Internal Check
ON
INTERNAL CHECKS
2015
RAILWAY ACCOUNTS
Canons of Financial Propriety
These rules also known as Canon of Financial Propriety are the
guiding principles to be followed while incurring any expenditure
from the Public Fund. Therefore, due regard must be paid to these
golden principles as given below:
(1) The expenditure should not prima facie be more than the
occasion demands, and that every Government servant should
exercise the same vigilance in respect of expenditure incurred
from public moneys as a person of ordinary prudence would
exercise in respect of the expenditure of his own money.
(2) No authority should exercise its powers of sanctioning
expenditure to pass an order, which will be directly or
indirectly to its own advantage.
(3) Public money should not be utilized for the benefit of a
particular person or section of the community unless—
(I) The amount of expenditure involved is insignificant;
or
(II) A claim for the amount could be enforced in a court of
law; or
(III) The expenditure is in pursuance of a recognized
policy or custom.
(4 ) The amount of allowances, such as traveling allowances,
granted to meet expenditure of a particular type, should be
so regulated that the allowances are not on the whole sources
of profit to the recipient.
ix
INDEX
2. General Bills 33
3. Contractor’s Bills 59
4. Budget 82
5. Inspection 101
xi
Chapter 1
1. estimates
i. Abstract Estimate
Detailed justification is provided by the branch
officer.
Indication of completion period and currency
of the work is given.
The cost of work with reference to competency
of sanction i.e., GM/DRM, exists.
Detailed allocation has been recorded.
Basis of rates and correctness of related
quantities is given by the department.
Calculation of ROR for remunerative works is
calculated (Para 202 of FI)
Arithmetical accuracy.
For Out Of Turn works, reasons for urgency
have to be placed on file.
(Para 1104 E )
ii. Detailed Estimate
Following points needs consideration while checking
detailed estimates:-
1
Hand Book on Internal Checks (Railway Accounts)
3
Hand Book on Internal Checks (Railway Accounts)
4
Scrutiny in Finance Section
2. QUOTATION PROPOSALS
Quotations are exceptions to the tendering rule, therefore,
need to be resorted sparingly. Following points need
consideration while examining quotations:-
Reasons for dispensing with calling of tender.
Justification for calling of Quotation.
Whether the quotation has been invited as per Rly.
Board’s circulars.
Reference to the enquiry letter.
Approval of the competent authority for inviting
quotations.
Number of offers received (minimum three offers)
Whether the quotations have been opened properly
and on due date.
Whether the proposal is for fancy and furnishing
items.
Reference to the comparative sheet.
Net cost of the work.
Certificate of suitableness, reasonableness, technical
suitability and rate reasonability is submitted for the
valid lowest offer.
Repair is not for condemned items.
Competency of the sanction in terms of item No 14(a)
of SOPWCR Part ‘E’.
Availability of funds.
Adherence to annual ceiling limit of sanctioning
authority in the financial year. Ref: SOPWCR1.15 and
Remarks contained therein.
(Item No. 2.7.4.1 of B.S.Sudhir Chandra
Committee along with Para 1211E and Item
1.15 of SOPWCR)
5
Hand Book on Internal Checks (Railway Accounts)
3. REPAIR PROPOSALS
Following details are required for consideration of repair
proposal:-
Date/cost of procurement, installation/
commissioning.
Repair proposal is not for items which have been
condemned.
The nature of the work done by machine and
prescribed life of the machine.
The prescribed life of asset and work done by the
asset.
Whether the machine is covered under warranty if so,
period of warranty.
Instances of earlier repairs, amount spent on its
repair/maintenance till date, last similar repair,
agency and mode of tender. Comparison between cost
of machine and repair cost.
Date of breakdown of the machines and how the work
is managed after the breakdown.
Justification for the work and mode of tendering
system i.e. open, limited or single; is given. Possibility
to get most competitive rates/conditions must be
explored.
Administrative approval of the competent Authority
exists.
Cost benefit analysis indicating repair cost and
enhanced life of the machine. It should be worth
spending on repairs so that life & performance of the
asset increases commensurately.
Division accountant vetting in case of divisional
proposals.
Reasonability of rates to be certified and should match
with the last accepted rates or actual expenditure.
6
Scrutiny in Finance Section
5. AMC PROPOSALS
• When were the machine /equipment procured and
original cost of machine/equipment?
• Whether the machine is under warranty period, if so
the details thereof.
• Administrative approval is obtained from competent
authority.
• Whether AMC is comprehensive or Non-
comprehensive.
7
Hand Book on Internal Checks (Railway Accounts)
7. MISC. PROPOSALS
Proposal other than Supplementary Work Order’s, Estimates,
M&P Proposals, Indents, M.S., Finance Establishments,
Quotations and brief Notes:-
The proposal of Misc. nature other than quoted above
received in Accounts office are examined as per
8
Scrutiny in Finance Section
9
Hand Book on Internal Checks (Railway Accounts)
11
Hand Book on Internal Checks (Railway Accounts)
12
Scrutiny in Finance Section
15
Hand Book on Internal Checks (Railway Accounts)
18
Scrutiny in Finance Section
19
Hand Book on Internal Checks (Railway Accounts)
20
Scrutiny in Finance Section
21
Hand Book on Internal Checks (Railway Accounts)
NOTE:
1. For variation in quantities accounts concurrence will be
required if variation is in excess/ savings of 25 % of the total
value and individual item in a contract.
2. Chief Engineer (PHOD/CHOD) will have power to approve
these changes in contract approved by the GM/AGM and
Railway Board upto a maximum of 25 % of contract value or
Rs. 25 lakhs which ever is less for each individual contract.
3. Total implication of variation in quantities and variation of
items in a contract will be limited to 25 % of total value of
original contract. In case it is exceeding personal approval of
GM or higher authority which approves the original estimate
and in whose competence the enhanced value lies will have to
be obtained.
4. For controlling the payment in case agreemental value goes
beyond (+) 25%, a regulatory mechanism as part of the
contract shall be built in as part of contract itself. For the first
15 % increase in value beyond 25 % of agreemental value, the
rates will have a reduction of 2 % in the incremental value of
the agreement and for the next 10 % increase in the value,
rates will have an additional reduction of 2% in the further
incremental value of the agreement. The variation clause to
22
Scrutiny in Finance Section
23
Hand Book on Internal Checks (Railway Accounts)
B - Establishment
TEMPORARY AND PERMANENT POSTS
Following points are to be checked:
• Whether the proposal is for extension or creation of post.
• Status of sanctioned cadre and Men on roll.
• Detailed justification for the proposal with reference to
workload and establishment already available.
• Reference to the guidelines and instructions of the higher
authorities.
• Is there no possibility of avoidance of the post concerned?
• Position of divisional surplus bank.
• Yard sticks and benchmarks, if any.
• Whether the posts are for maintenance of existing assets or
new, if so details thereof.
• Nature of post, temporary, permanent.
• If the proposal is for extension of currency clear reference to
the previous noting with detail justification.
• If the post is chargeable to Private Parties details of the same
on the items as under:
i. Details of the previous payments.
ii. Demand / application of the Party concerned.
iii. Percentage of Leave Reserve./Rest Giver. as per
current cadre.
iv. Number of Leave Reserve /Rest giver required as per
yardstick.
• If the post is proposed under DRM’s power, position of surplus
bank of the Division. A certificate of availability of the value
under the surplus.
• Position of matching surrender if any.
• If proposal is for half-yearly review of running crew, reference
to the actual hours of the crew should be made available on
24
Scrutiny in Finance Section
out whether the clerk(s) understand their duties and rules governing
them and do the work allotted to them diligently and whether there is
any tendency to do the work casually. Test check should particularly
be conducted at least once in a month by SO and all officers. The test
checks should not be of routine nature rather they should focus on
system improvement, procedural lacuna and lapses. The underlying
idea should be efficient disposal without any violation of rules and
procedures. The checks should also reflect the updated skills of the
officer. -[PARA 803 A1]
Recording of results of Test- Check; _
The result of test check should be recorded systematically in a
manuscript register in the form given below:-
SR Item of Extent of Particulars Name of the Result of Whether the dis-
NO. work test Test check of vouch- SO/SSO (A) Test check crepancy in col.6
checked prescribed ers elected who had test has been pointed
for test checked the out by the super-
check item visory staff
1 2 3 4 5 6 7
26
Scrutiny in Finance Section
28
Scrutiny in Finance Section
29
Hand Book on Internal Checks (Railway Accounts)
10.
1. Whether it is certified that item being
procured is not under RESTICTED category?
2. In case of RESTICTED item, whether prior
approval of competent authority is obtained
and submitted ?
11. Whether the correct allocation is recorded on indent?
12. Whether the funds availability is certified during the
current Year?
13. Whether the indent is signed by competent authority?
(SOPWCRGEN ref )
14. Whether the bill paying/passing authority is indicated
on indent?
It is certified that all above item have been personally checked by the
undersigned.
30
Scrutiny in Finance Section
Items Yes/
No/ NA
1. Whether it is certified that work is urgent in nature?
2. Whether the justification including quantity is
endorsed on the proposal?
3. Whether the reason for not calling tender is
endorsed?
4. Whether the administrative approval is obtained
from the competent authority?
5. Whether the expenditure of work is within the
power & ceiling limit of the Sanctioning authority as
per SOPWCRGEN item No…………?
31
Hand Book on Internal Checks (Railway Accounts)
32
Chapter 2
GENERAL BILLS
1) General checks for Passing of bills in XI Section: Following
major checks are prescribed during scrutiny and passing
of various bills received from Stores department .( These
checks are illustrative but not exhaustive):-
a) It should be ensured that all bills must be in ORGINAL
format and duly signed by the competent authority.
b) The bills are approved by competent authority.
c) All the bills should be properly allocated & duly
budgeted.
d) Wherever the duplicated claims are received, it
should be seen that the concerned officer has certified
that no payment has been made earlier and there are
sufficient, genuine and valid reasons for the claim
being in the duplicate. The concerned officer should
also submit non-payment certificate along with the
claim.
e) Competent authority has sanctioned expenditure.
f) The expenditure sanctioned for a limited period is not
admitted beyond the period without further sanction.
g) Proper vouchers support the bills.
h) The payment is recorded on the work order/ supply
order Misc. sanction so as to render second claim on
same account impossible.
i) The charge are correctly classified and the prescribed
deductions (S.D. / I.T. / S.T. / ED. Cess / S.C / other
recoveries from contractor) have been made.
j) The signature of officer drawing the bill agrees with
his specimen signature in addition to the general steps
mentioned above, following steps needs to be taken
care of while passing the bills falling under specific
33
Hand Book on Internal Checks (Railway Accounts)
2) PAY ORDERS
While dealing with the claims, it should be ensured that:
i. All the pay orders are passed for different payments
the same procedure is followed. If the pay order is
pertaining to RTO / TAXES, Finance concurrence has
to be obtained.
ii. If the pay order is pertained to payment towards toll
tax finance concurrence has been obtained in each
case.
If the pay order is for RRB examination, the sanction of
CHAIRMAN RRB and Finance concurrence is obtained
in each case. 50 % of total expenditure is first to be
charged to RRB head, and debit of such expenditure
on quarterly basis is to be raised to South Central
Railway by preparing ATD.
37
Hand Book on Internal Checks (Railway Accounts)
3) STORE BILLS
RULES AND PROCEDURES adopted for passing of stores
bills.
The procurement of material on WCR is handled by Controller
of Stores through his subordinate and unit offices. In WCR,
COS Office deals with all material procurement at HQ level,
while in units (Division, Workshops, Loco Sheds) concerned
unit Stores Officers handle procurement of material for their
respective units.
The office of the FA&CAO/WST functions as the associate
finance for Controller of Stores and is responsible for
liquidating all liabilities entered into by COS on behalf of WCR.
All the bills raised by Suppliers for delivery of material are
dealt by FA&CAO/WST office and other unit Account Offices
for arranging payment to suppliers.
Following offices deal with payment of Suppliers bills on
WCR –
- FA&CAO/WST – All Stock and Non Stock Procurement
by COS Office.
- Divisional Accounts Offices – All Non Stock
Procurement and Emergency Stock procurement by
their Depot Stores Officers for Division.
- Workshop Accounts Offices – All Non Stock
Procurement and Emergency Stock procurement by
their Depot Stores Officers for Workshop.
There are following types of store bills–
I. Stock item Bills – The bills pertaining to procurement
of stock items i.e. items kept in the custody of the stores
department which are frequently and regularly required and
whose unit cost justifies incurring inventory carrying cost
associated with these items.
II. Non Stock Item Bills – Items which are not stocked by the
Stores Depots but are required by consumers are procured
as Non Stock procurement to be delivered directly on shop
38
General Bills
39
Hand Book on Internal Checks (Railway Accounts)
40
General Bills
41
Hand Book on Internal Checks (Railway Accounts)
42
General Bills
43
Hand Book on Internal Checks (Railway Accounts)
45
Hand Book on Internal Checks (Railway Accounts)
46
General Bills
47
Hand Book on Internal Checks (Railway Accounts)
48
General Bills
50
General Bills
8) BI MONTHLY STATEMENT.
The details of Security Deposit deducted through bills, year
wise break up is prepared and handed over to EFFY; section
for onward transmission the details to HQ.
51
Hand Book on Internal Checks (Railway Accounts)
52
General Bills
53
Hand Book on Internal Checks (Railway Accounts)
54
General Bills
56
General Bills
57
Hand Book on Internal Checks (Railway Accounts)
58
Chapter 3
CONTRACTORS BILLS
1.0) Contractors Bills
On account and final bills are received from executives in
prescribed format i.e. 1337E, 1338E of Engg. Code. CO6 is
taken from AFRES and internal checks are carried out As
per Para 1354 E &1355(ii) of Engg. Code. If the bill is found
correct in all respects CO7 prepared and is passed for
payment through AFRES module.
1.1) Internal checking of Contractor bills
Standards of financial propriety are followed in terms of Para
116F during any internal check of bill. On receipt of bills, CO6
is taken as per Para 1106-A1. Internal checks are carried out
on all bills. “Scrutiny of Expenditure” is carried out as per
Para 815 A-1, 816A-1 & 1355-E on all bills. If found correct in
all respect, Co-7 are prepared and passed after ensuring the
availability of funds. Apart from the above the following are
also to be ensured ( The list is elaborate not exhaustie):-
• The bill is original and in the prescribed FORM
NO.1337-E & 1338-E and it is prepared according to
the instructions given therein.
• The expenditure relating to the work is covered by a
sanctioned estimate.
• The expenditure is covered by budget allotment.
• Reference to the Agreement/Work Order No. & Date
has been quoted therein.
• Where a formal Contract Agreement has not been
entered into but work has been carried out on
the strength of acceptance letter the sanction of
competent authority has been received along with
the bill for arranging provisional payment pending
sanction of Contract Agreement.
59
Hand Book on Internal Checks (Railway Accounts)
60
Contractors Bills
61
Hand Book on Internal Checks (Railway Accounts)
62
Contractors Bills
63
Hand Book on Internal Checks (Railway Accounts)
64
Contractors Bills
65
Hand Book on Internal Checks (Railway Accounts)
5.3) Clearance:
• After getting details of expenditure from executives
JV have to be prepared by minus Debiting Misc.
Advance and Debiting to final proper head.
• Deposits paid for water, telephone connections are
cleared by booking the expenditure to Final Head,
after receiving the vouchers.
• Wherever details of expenditure/transaction are not
available and possibility of booking the expenditure
to Final head is remote, in such cases, write off option
may be exercised, after taking sanction of competent
Authority. Credit side postings of this Suspense
Register is to be done from the JV entries prepared by
the suspense section or JVs of the respective section
who has debited the amount to this suspense head.
the same is posted on debit side in the MAX ledger,
and the balance amount, which has been deposited by
executive to station earning through MR is posted on
credit side in the MAX ledger. The same is reflected in
the book through MCR/ divisional sheet received by
book section from HQ.
• Having done so, the register is totaled monthly and
reconciled with that of General books available in the
books section.
66
Contractors Bills
68
Contractors Bills
69
Hand Book on Internal Checks (Railway Accounts)
70
Contractors Bills
7.7.1) INTRODUCTION :
In terms of Para 803-AI, the work of a clerk is required to
be Test checked by the subordinate supervisory staff and the
Gazetted Officer in charge of the section and the result of the
test check should be systematically recorded and submitted
for review at prescribed intervals. Test check should be
carried out according to the scale laid down in the Annexure
- I and the results of the test check should be recorded in
a separate register to be maintained for special purpose in
accordance with the instructions given in Accounts Code.
72
Contractors Bills
73
Hand Book on Internal Checks (Railway Accounts)
74
Contractors Bills
75
Hand Book on Internal Checks (Railway Accounts)
76
Contractors Bills
77
Hand Book on Internal Checks (Railway Accounts)
9.2) ATD/ATC
Adjustment of ATD/ATCs:
The expenditure pertaining to this Division incurred by other
units are transferred through ATD/ATCs. The debits include
those of the bills passed for stores, transfer of materials,
workshop debits of POHs, Stock Adjustment Accounts, debits
on Work Orders placed, transfer of deposit credits/debits,
Stores Monthly Summaries, etc.
9.2.1) Procedure
The ATD/ATCs are received from Books Section after
registering in the Inward Register. The same is acknowledged
by the Assistant and entered in his own ATD register allotting
a serial number starting one for the current financial year.
The register should contain ATD No., Month of receipt,
and Nature of debit, Amount, Unit transferring the debit,
acknowledgement and a remark column. The ATDs, once
registered, are sent to the Budget Supervisor by obtaining
78
Contractors Bills
79
Hand Book on Internal Checks (Railway Accounts)
80
Contractors Bills
81
Chapter 4
BUDGET
The main functions of budget section includes (A) framing
of budget estimate, august review, revised estimate budget
estimate, modification to final estimate (B) ensure that the
actual expenditure within the budget grant (C) rectification
of wrong booking (D) funds certification.
82
Budget
83
Hand Book on Internal Checks (Railway Accounts)
DF, OLWR, Capital fund. The level of funds may slightly vary
from budget to budget.
84
Budget
I. Budgetary Reviews:
As a means of controlling the expenditure, a monthly review
comparing actual expenditure with the proportionate budget
allotment is made and an appreciation report bringing out
the special features in respect of each month’s account is
also submitted to the Railway Board. This monthly review is
done right up to the Divisional level and it helps in controlling
the expenditure effectively. This also helps in managing the
finances in a better manner by the respective departments
by postponement, modifications in the physical activities
being contemplated or appropriation of funds.
85
Hand Book on Internal Checks (Railway Accounts)
86
Budget
87
Hand Book on Internal Checks (Railway Accounts)
89
Hand Book on Internal Checks (Railway Accounts)
90
Budget
91
Hand Book on Internal Checks (Railway Accounts)
92
Budget
93
Hand Book on Internal Checks (Railway Accounts)
95
Hand Book on Internal Checks (Railway Accounts)
96
Budget
98
Budget
100
Chapter 5
INSPECTION SECTION
1. NECESSITY FOR INSPECTIONS:
i) Though in certain cases original records are submitted,
a large number of accounts and supporting documents
submitted for internal check are not original records, as such
the internal check conducted in the Accounts Office is largely
dependent for its efficiency on the degree of care exercised
by departmental authorities over the accuracy of the original
records.
ii) It is, therefore, necessary to review the original records as
submitted to Accounts and also to test the degree of care
exercised by the executive officers over the accuracy of such
records and to see that they are maintained properly in the
prescribed forms.
iii) Opportunity is also taken at this time to test check such
Accounts, Vouchers, etc. which are not coming under the
purview of internal check or cannot be checked adequately
except at a local inspection.
iv) Inspection of executive offices at Head Quarters and Divisions
shall ensure the accuracy and authenticity of the transactions
rendered by the executives.
2. RESPONSIBILITIES OF ACCOUNT’S OFFICERS: The
Divisional Accounts Offices are responsible for:-
i) Inspection of all offices under their Accounts control.
ii) Inspection of Railway Schools within their
jurisdiction.
iii) Inspection of all catering units falling within their
jurisdiction.
iv) Check of Book Stall, Platform Stalls at stations.
v) Check of OT/NDA claims at Stations and other offices.
Accounts team is mandated to ask for any record from
101
Hand Book on Internal Checks (Railway Accounts)
3. PERIODICITY OF INSPECTION
i) Schedule of Inspection: It is prepared on the basis of
sensitivity analysis. The sensitive areas are more frequently
inspected as compared to the less sensitive ones. Sensitivity
of an office is decided based on the level of financial
transactions taken up. The money value item dealt with the
possibility of pilferage and leakages and so on also decide
the frequency of inspection. Special emphasis should be
given to post check items like Imprest. Divisional offices are
inspected once in every two years, but the initial accounts of
Engineering expenditure, Open line shall be inspected once a
year. The first inspection of a construction division shall as
far as possible be made within three months of its formation.
The Headquarters Administrative Offices will be inspected
once in two years. - [ 1706 A1]
ii) While inspecting Divisional office, one suboffice in
the case of engineering expenditure and at least two
subordinate offices not in charge of a Gazetted officer
shall also be inspected simultaneously.
iii) As far as possible all the subdivisional offices in a division
shall be inspected within the course of two years.
iv) The offices, where there are not many transactions by way
of miscellaneous cash, issue of passes, PTOs etc. may be
inspected once in 3 years to have.
a) A general review of the procedure relating to initial
accounts of receipts and expenditure of cash and
stores with a view to making helpful suggestions
towards elimination of useless returns, redundancy
of any kind and wasteful methods.
102
Inspection Section
103
Hand Book on Internal Checks (Railway Accounts)
8. The copy of holiday’s list for the year of Bhopal division is also
to be furnished with the programme.
Current position of compliance of approved annual inspection
programme for the current year is also to be furnished in
terms of nos. of inspection due/ carried out and inspection
reports (Part I & II) issued. In case of arrears in this
connection, reasons for the same and steps taken to clear the
arrears is also to be furnished.
A certificate starting that all the units, the inspection of
which is due during the ensuring year are included in the
programme without any omissions is also to be furnished.
Ref:- FA&CAO/I.Au/JBP letter no. HQ/ACS/GA/INSP/001/2009-
10 Dated 04-03-2009
NOTE:- The complete list of various offices on Bhopal division is
annexed as Annexure ‘A’.
Based on above guidelines and keeping in view the inspection
Schedule of Audit department inspection programme
of Accounts office has been finalized and shown as
Annexure –‘B’.
5. FURTHER DISPOSAL OF INSPECTION REPORTS.
Based on the findings observed during inspections, Reports
are prepared and submitted to ADFM for approval. After
getting the approval of ADFM, the inspection reports are
issued to the officer unit in-charge of unit inspected. On
receipt, of the replies the remarks are verified for their
genuineness and appropriateness and the matter is closed
if found acceptable. However, in case the remarks are found
inappropriate and unsatisfactory, the concerned unit in-
charge is written back for corrective actions. On receipt
of further reply, the report is closed with the approval of
Accounts Officer. The Inspection report is issued within 20
working days time from the date of inspection.
During the course of inspection, efforts are made to review
old outstanding Inspection reports of Accounts or Audit
department, if any, and the concerned Executive is impressed
104
Inspection Section
105
Hand Book on Internal Checks (Railway Accounts)
107
Hand Book on Internal Checks (Railway Accounts)
5) PAY ORDERS:
i) The Pay Orders issued by the office are checked to see
that the drawl of amount is justified and sanction of
the competent authority is obtained.
ii) Pay order book is properly maintained and necessary
certificate is recorded to the effect that all the folios
are checked and found correct.
iii) All the pay orders are stamped with seal of the office.
iv) Pay order books are kept under lock and key.
v) Separate register is maintained for issue of pay
orders.
vi) After the amount is drawn, necessary vouchers are
sent to the Accounts Office in time.
vii) Amount drawn through pay order is spent immediately
and only for the purpose for which it is drawn.
109
Hand Book on Internal Checks (Railway Accounts)
9) REVIEW OF AGREEMENTS:
i) Agreements Register should be checked to ensure
that all details are furnished,
ii) Some of the agreements should be checked with
reference to
a) Progress of the work,
b) Supply of Steel, Cement is as per the Agmt. /
Schedules.
c) Test check the measurements recorded and
bills claimed.
d) There is no delay in progress of the work/
supply.
111
Hand Book on Internal Checks (Railway Accounts)
112
Inspection Section
viii) Separate Folios are kept distinctly for items like, PCs,
VCR, TVs, Cameras, and Audio Visual equipments,
Fridge etc.
ix) Departmental Stock verification has been done
periodically and certificate recorded against each
item.
x) Un-serviceable Tools and Plant are condemned
under proper authority and sent to stores Depot.
Expeditiously.
xi) Suitable reference furnished in the Dead Stock
Register for the Articles sent to scrap Depot, Transfer
to other units etc.
14) RAILWAY MATERIAL CONSIGNMENT NOTE (RMC NOTES)
AND CREDIT NOTES:
i) RMC Notes are issued only for the transport of Railway
Materials and the materials are for a bonafide Rly.
Purpose.
ii) Credit Notes are issued only when freight charges
are required to be borne by the Railway as per the
purchase order.
iii) Where credit notes are issued towards wharf
age or demurrage charges, it should be seen the
circumstances under which the charges incurred and
sanction of the competent authority is obtained for
issue of credit notes.
iv) If the charges are incurred due to delay in unloading,
want of staff, negligence of staff etc., the matter should
be reported to the concerned responsible official for
action against the staff.
15) HISTORY BOOKS OF VEHICLES, COMPUTERS/ TYPE
WRITERS ETC :
i) Complete History of the Vehicle, viz. firm name, cost
of the vehicle/item, date of purchase, models etc. are
furnished in the Register.
114
Inspection Section
115
Hand Book on Internal Checks (Railway Accounts)
116
Inspection Section
117
Hand Book on Internal Checks (Railway Accounts)
1) WRITEOFF/SANCTIONS:
i) Proper records are maintained for all sanctions and
writeoff.
ii) Writeoff sanctions have been obtained as per the
provisions of SOPWCR, Codal provisions etc.
iii) Finance concurrence has been obtained, wherever
necessary.
iv) Staff responsibility has been fixed, for the writeoff
proposals involving loss for which Rly. Employees are
responsible.
v) Preventive measures are taken to avoid recurrence
of loss/theft etc., for which writeoff proposal is
obtained.
119
Hand Book on Internal Checks (Railway Accounts)
2) SCALE CHECK:
i) Proper Register/Record is maintained to indicate the
sanctioned posts, category wise.
ii) Checked with Attendance, Pay Bills etc. to see that the
posts operated are as per the sanction strength
iii) Book of sanction reference is indicated against each
Department against the posts sanctioned.
iv) No posts are operated in excess to the sanctioned
strength or without sanction
v) In case of excess operation, action has been taken to
regularise the posts.
4) SERVICE REGISTERS:
i) Service Registers have been opened for all the
employees without delay and necessary Medical
Certificate attached.
ii) All required details have been filled correctly.
iii) Necessary Thumb impressions have been obtained
and certified by FPE/Responsible official.
iv) Service records are kept in safe custody.
v) The Date of Birth recorded in the S.R. agrees with
Medical Certificate, School Certificate etc.
120
Inspection Section
121
Hand Book on Internal Checks (Railway Accounts)
7) LEAVE ACCOUNT:
i) Leave account is maintained correctly for all the staff
on Rolls, and governed by the leave rules the employee
is governed.
ii) Advance crediting of LAP/LHAP are made correctly
taking into account the Dt. of joining, period of leave
without pay etc.
iii) Every leave posting in leave account (Debit) is
supported by leave application, and sanctioned by the
competent authority.
iv) In the case of commuted leave employee’s specific
request is forthcoming and the period of absence is
covered by Medical Certificate.
v) Proportionate reduction in the LAP @ rate of 1/10
for the period of LWP (if any) is done before affording
advance credit every half year.
vi) In the case of ‘LND’, extraordinary leave etc, the leave
period is covered as per the extant rules.
vii) In the case of ‘LHAP’ Leave salary is drawn correctly.
viii) LWP period are recorded correctly in the S.R. and no
wages are drawn.
122
Inspection Section
123
Hand Book on Internal Checks (Railway Accounts)
126
Inspection Section
19) PASSES/PTOS:
i) Stock of passes, PTO books and Blank card passes is
not in excess to the requirement.
ii) Pass/PTO books available in stock are correctly
entered in the Stock Register.
iii) Continuity of the Books (Pass and PTO) are checked
and certified.
iv) Passes and PTOs are issued as per the Rules and as
per the eligibility of each employee.
v) Necessary Register’s are maintained calendar year
wise and all issue of Pass and PTO’s are correctly
entered against each employee’s account.
127
Hand Book on Internal Checks (Railway Accounts)
128
Inspection Section
130
Inspection Section
131
Hand Book on Internal Checks (Railway Accounts)
135
Hand Book on Internal Checks (Railway Accounts)
1. TENDERS:
i) The object and purpose for calling Tenders has to be
checked. Necessary estimate and plan is prepared
and sanctioned by the competent authority for the
work for which tender is to be called for. Tender
Register is maintained with all relevant details.
Tender notice has been issued with complete details
and sufficient time as required has been given. EMD
at prescribed rate has been correctly mentioned. The
name of the tenderers to whom the Tender Forms are
issued and the Money receipt details are indicated
in the Register. Cash collected for the sale of Tender
forms has been accounted correctly.
ii) Tender schedules before floating for Tenders has been
verified by finance (wherever necessary)
iii) Tenders have been called for in advance of the date of
commencement of work, and due publicity has been
given.
iv) The rules in regard to calling for limited, and open
tenders have been observed.
v) Tender opening register is maintained and that this
duly prepared checked and initialled by the executive
and Accounts Officers. It should be ensured that
only firms/Agencies to whom tender forms sold have
tendered.
vi) Late and delayed tenders are dealt as per instruction’s
issued by Railway Board / GM
3. MEASUREMENT BOOKS:
i) The Register of M.Bs maintained in the AEN’s office
have complete details viz., Dt. of opening, to whom
issued, when issued, dt. of return etc.
ii) M. Bs no longer required are returned to AEN’s office
promptly.
iii) Proper arrangements exist for preservation of M.Bs
i.e. for 10 years after completion of the work.
iv) Date of Measurement recorded in the M.B. by the
officials concerned is to be test checked with relevant
record viz., diary, TA Journal etc.
v) Recording of Measurements are done as per rules.
In case of subordinates the measurements are test
checked by officers as per the prescribed percentage.
vi) The measurements recorded in the ‘On Account’ and
‘Final bills’ should agree with the measurements
recorded in the M.Bs maintained in AEN/Office. For
this purpose inspecting official should carry certain
paid vouchers of contractor bills.
137
Hand Book on Internal Checks (Railway Accounts)
4. STANDARD MEASUREMENTS:
Test check that the service/residential buildings for which
paintings/colour washing is done as per entries in the
standard measurement books really exists as per the entries
in the Register of Buildings.
5. CONTRACTORS BILLS:
i) The inspecting official should carry paid vouchers
(contractors bills) and verified with the MBs available
with AEN/Office, to ensure that the work done for
which payment made agree with the initial records.
ii) Material statements accompanying final bills should
be checked with reference to materials issued to
contractors according to issue Note/Challans and
the balance quantity returned and accounted for
correctly. Empty cement bags returned are accounted
properly.
iii) In term of cl.37 (1) of General Conditions of Contract,
all test checks conducted as required by Railway
should be wholly at the expense of the contractor.
Hence, it should be ensured recovery of charges are
effected from the contractors for testing quality of
steel, cement, bricks etc. unless the same is agreed to
be borne by Railway.
iv) Contractors have accepted the final measurements.
v) Bills for earthwork are as per the entries in the level
book, earth work statement and measurement books
etc.,
vi) In case of delay/extension etc. necessary penalty to
be recovered as per the subsidiary Agreement are
done correctly.
vii) The contractor is not issued materials more than the
requirement. Physical progress of the work has to be
compared with the issues during inspection.
138
Inspection Section
6. CONTRACTORS LEDGER:
i) Contractor ledger is maintained properly in the
Accounts Office and all entries are made.
ii) Separate page is maintained for each Agreement and
the ledger is maintained like a personal ledger of
contractors.
iii) The bills passed should be test checked with the
entries in the contractors ledger.
iv) For the stores issued out side the scope of the contract,
the amount is debited in the ledger.
v) Periodical review and reconciliation of the contractor
ledger with work register is being done.
8. STOCK VERIFICATION:
i) Stock sheets received from the Accounts Department
have been attended to promptly and remarks sent.
ii) Excess/Shortfall has been adjusted correctly in the
ledger as per the S.V. Sheets, and remarks sent to
Accounts.
139
Hand Book on Internal Checks (Railway Accounts)
140
Inspection Section
142
Inspection Section
17. SIDINGS:
i) The No. of sidings in the jurisdiction of SE/P.Way and
connected records has to be checked.
ii) Whether the sidings are periodically inspected by
the SE (P.Ways) and the details intimated to Accounts
Office for raising the ‘Debit’ against the siding owners.
(inspection charges)
iii) The inspecting official has to check whether any
extra expenditure incurred during maintenance
of siding and if so the cost of the same advised to
Accounts Office for preferring the claim from the
siding authorities.
iv) The inspecting official has to check whether Railway
Staff working in the siding has availed the rent free
accommodation provided by the siding owner. In such
case, it has to be ensured that they are not drawing
HRA from Railways.
143
Hand Book on Internal Checks (Railway Accounts)
146
Inspection Section
3. WORK ORDERS:
i) It should be seen that work orders are issued correctly
and continuity number is maintained.
ii) There should not be abnormal delay in completing the
job.
iii) In case of completed work orders the charges have
been brought to account correctly.
iv) The list of work orders issued during the month has
been sent to accounts promptly and in which no work
orders should be out of series, and the allocation
furnished is correct as per Accounting classification.
147
Hand Book on Internal Checks (Railway Accounts)
149
Hand Book on Internal Checks (Railway Accounts)
151
Hand Book on Internal Checks (Railway Accounts)
REFUNDS/CONCESSIONS:
It should be seen that the refunds arranged are admissible as
per rules.
153
Hand Book on Internal Checks (Railway Accounts)
SECURITY BRANCH :
The following items should seen during inspection of Security
Branch.
i) The policy and procedure adopted for recruitment of
RPF personnel.
ii) Deployment of RPF personnel to bandobust duties and
recovery of charges from the concerned Ministries/
Departments. It should be seen that charges are
correctly worked out and included in the claim.
iii) Log Book of Vehicles, Uniforms Registers, imprest
account, etc.
iv) Register of Theft detected and reported to the
Security Department by other Departments and
action taken thereon.
v) Register of Arms and Ammunition reviewed to ensure
that receipt is correctly posted.
vi) Register of uniform should be checked. The receipt
and issues are correctly accounted for and issues are
properly acknowledged.
vii) Status of the apprehended cases dealt by RPG and
GRP and the position of enquiries.
GENERAL BRANCH:
Log Book of Office Staff Cars: -
i) It should be seen that the staff cars have been used for
official purposes Only and the officers signatures/
initials obtained against each movement.
ii) If the cars had been used for private purposes,
necessary charges as applicable have been billed and
recovered.
iii) Drawal of petrol commensurate with KMs in usage
and there is no abnormal variation in the consumption
pattern.
154
Inspection Section
iv) Repairs to the Staff cars have been done as per the
provisions contained in ‘SOPWCR’ and all major
repairs had the certification from the nominated
officers of the Mechanical Department.
2. Quarter’s Registers for allotment of quarters to officer
should be checked to see that there is no delay in allotment of
Railway Quarters and the Railway Quarters once allotted is
occupied within 7 days. In case of delay in occupation (after
7 days) rent at prescribed rates have been recovered besides
stoppage of HRA.
3. Retention of Railway Quarters after permissible period
during deputation, transfer etc. are dealt with correctly as
per extant rules.
4. Special Imprest/Entertainment expenses: The accounts
should be verified and satisfied that every transaction is
correctly accounted for and supported by voucher. Balance
amount left over if any after the occasion has been remitted
back to Railways and necessary vouchers submitted to
Accounts Office.
5. The accounts related to the allotment of Rail Kalyan,
Community Hall, allotment of Officer’s Rest House
on private account, etc. should also to be checked
to ensure that the amount collected are properly
accounted and remitted to Railways Account. The
rules relating to the allotment are correctly followed.
STORES BRANCH :
155
Hand Book on Internal Checks (Railway Accounts)
2. RECEIPT NOTES:
The quantity received as per firm’s invoice and quantity
accepted as per Day Book of Receipts/ledger should be
compared to ensure that there is no discrepancy. The stores
received are inspected before delivery as per the inspection
clause wherever applicable.
3. REGISTER OF SAMPLES:
The register should be reviewed to find out whether proper
accounts are maintained for receipts of samples, their
return to the firms or taking them to stock by credit to Stock
Adjustment Account. The disposal of the nonreturnable
samples should be properly exhibited in the register. All
disposals are covered by proper sanction of the competent
authority.
4. REJECTIONS REGISTER:
The register should be reviewed to see that the rejected
stores if any are properly disposed off and the firm advised
for replacement. All such rejections should have proper
sanctions and the Accounts Office and COS advised for
suitable action.
156
Inspection Section
8. SURPLUS STORES:
It should be seen that prompt action has been initiated to form
157
Hand Book on Internal Checks (Railway Accounts)
9. AUCTION SALES:
Stores already declared as surplus should be disposed quickly
through auction sales. It should be ensured that accounts
representative associated in the auction sales.
10. Apart from the above, the following aspects should also been
checked by the inspection team especially in Depots,
a) Material in Depots
b) Bincards (Physical balance with Bincard balance)
c) Weighment Register
d) Inward/outward wagon register
e) Challan Book
f) Cash remittance Notes in case of auction sales
g) Empties accounts
h) Pending stock sheets
ELECTRICAL BRANCH
Agreements entered into with the State Electricity Boards for
purchase of e lectrical energy should be checked.
1. In case of supply Electrical energy for Traction
purposes, the contract demand and actual
consumption should be checked. If the consumption
is very low than the contract demand or higher than
the contract demand electrical department should be
advised for proper review and to revise the contract.
2. Meter Reading;
i) It should be seen that Meter reading has
been done from all the residential quarters
regularly at the prescribed intervals.
ii) The entries are not been made in pencil.
In case, if the Railway Quarter is locked,
158
Inspection Section
159
Hand Book on Internal Checks (Railway Accounts)
160
Inspection Section
161
Hand Book on Internal Checks (Railway Accounts)
8. DIETICIAN ACCOUNT:
i) The imprest cash sanctioned and available with the
dietician should be checked and cash balance verified
and certified.
ii) The nature of transactions met from imprest should
be checked to ensure that the items purchased, viz.,
vegetable, provisions etc. are at reasonable rate and
proper records (ledgers) are maintained.
iii) It should be seen that the items issued to the cook
are according to the scales and the number of meals,
breakfast prepared daily are as per the requirements
certified by the Matron/Doctor as the case may be.
iv) Arrangements (Agreement) exist for supply of
Bread, Milk, Meat etc. should be verified and the
requirements/indents placed are not in excess. The
charges paid are reasonable.
v) The Attendance Register and staff sanctioned for
preparation and supply of diet should be verified to
ensure that there no excess staff.
vi) The stock available in the storeroom should be test
checked and compared with the ledger balance to
ensure that there are no discrepancies.
vii) Tools and Plant Register should be verified and
unused/empties are properly disposed off.
9. LOG BOOK OF AMBULANCE VANS:
i) It should be seen that the movement of the vehicle is
properly shown and acknowledgements obtained.
ii) Charges wherever due are properly collected and
remitted to Railways Account.
10. INSPECTION NOTESREVIEW:
The Inspection Notes of CMD and other Officers should
be reviewed to see that proper corrective action is taken
wherever financial irregularities are noticed.
164
Inspection Section
A) RAILWAY SCHOOLS: -
The Head Quarters as well as Divisional Accounts Office
should undertake as part of their inspection programme,
the inspection of Railway Degree College (Hqrs. only)
Junior colleges and schools. The following items should
be seen especially during inspection of accounts of the
Railway Schools in addition to the items common to all the
offices. Similar checks should also be exercised in respect of
NonRailway schools if they are in receipt of Grantsinaid from
the Railway Administration.
1. CASH BOOK:
The maintenance of Cash Book, Receipts and Payments
should be checked. The Cash Book should be closed daily
and attested by the Principal or Head Master i.e. Head of the
Institution. The Cash Book should have been reconciled with
Bank Pass Book and there should not be any variation.
2. SPECIAL FEE AND TUITION FEE:
It should be seen that:
166
Inspection Section
5. GRANTSINAID:
In the case of Railway Colleges, it should be seen that the ‘UGC’
Grant received has been properly utilised for the specific
activity for which it was granted. The records exclusively
maintained for this purpose should be checked.
6. MISC. CASH :
As the Railway schools and colleges are maintained by the
Railway Administration, the schools premises should not be
utilised for any other purposes unless it is authorised. Licence
167
Hand Book on Internal Checks (Railway Accounts)
168
Inspection Section
170
Inspection Section
171
Hand Book on Internal Checks (Railway Accounts)
172
Inspection Section
173
Hand Book on Internal Checks (Railway Accounts)
174
Inspection Section
175
Hand Book on Internal Checks (Railway Accounts)
176
Inspection Section
177
Hand Book on Internal Checks (Railway Accounts)
178
Inspection Section
180
Chapter 6
STOCK VERIFICATION
The object of the stock verification by the Accounts
department is to ensure that the said material accord with
the description and specification and the balances appearing
in the books and excess or deficiency, if any, noticed on such
verification are properly investigated and accounted for. It is
to ensure that book balance and ground balance tallies and
they are properly maintained. During the verification of any
unit and stock verifier has to ensure that
• Every item is verified after proper counting,
weighment, and measurement in presence of
responsible representative, subordinate or ward
keeper or stock holder himself.
• No items and tally books are left without verification.
• No unaccounted stocks are lying at Depot, ward
and office of the subordinates. In case unaccounted
stock is found, reason has been recorded by the stock
holder.
• Weighing machine used for weighment, is being
checked before verification.
• Proper arrangement exists for the safe custody of
materials.
• Suitable measures exist against loss due to pilferage,
fire and deterioration.
• The godown floors are cemented and, in cases where
such floorings do not exist, the stacking is not done on
the ground but on platforms made of unserviceable
rails and sleepers.
• Is the stacking of heavy materials done in racks and
lines?
181
Hand Book on Internal Checks (Railway Accounts)
182
Stock Verification
183
Hand Book on Internal Checks (Railway Accounts)
185
Hand Book on Internal Checks (Railway Accounts)
186
Stock Verification
187
Hand Book on Internal Checks (Railway Accounts)
189
Hand Book on Internal Checks (Railway Accounts)
190
Stock Verification
191
Hand Book on Internal Checks (Railway Accounts)
192
Stock Verification
193
Hand Book on Internal Checks (Railway Accounts)
(III) Fuel, coal, HSD oil with loco (Optg and Mech
Department)
(IV) Engg. Plants reserve.
(V) Dead stock.
(VI) Tools and plants.
(VII) K-Oil at stations.
(VIII) Voucher check. (Receipt and issue)
In the office of SR. DFM the details of SV sheets / Narrative
Reports are entered in register no 3261/S wherein full details
such as year, stockholder, SV sheet number, Narrative Report
number, date, deficiencies, etc. and their day-to-day progress
is watched by SR ISA (co-ordination). Theremarks/replies of
SV sheets / Narrative Reports received from executives will
be scrutinize by ISA and will be put up to SR DFM for closure,
if acceptable. Otherwise reminder / rejoinder will be issued
for further clarification.
Outstanding SV sheets / Narrative Reports to end of the month
will be brought out in a statement department wise and year
wise, which is the part of the document submitted to HQ. in the
monthly progress report. Similarly the performances of the
ISA’s during the month i.e. lot inspection; test check of ASV’s
special checks, handing over of scrap, etc will be submitted
to HQ. Monthly progress report and monthly performance
report is submitted to HQ before 5th of the following month
through SR DFM.
195
Hand Book on Internal Checks (Railway Accounts)
8) EXPLANATION OF DEFICIENCIES
SR. CAUSES OF DEFICIENCY PARTICULERS TO BE FURNISHED
NO
1 Materials issued but not Party ,voucher no, date, quantity and
Accounted for why issue was not accounted for
2 Due to cross issues Relevant entry noticed under other
account having similar items, S.V.
sheet folio item no brief description
and size surplus quantity recorded
3 Due to fluctuation of Date of last verification and quantity
weather then verified, quantity of material
subsequently received and issued &
shrinkage allowed
4 Material lost in transit Why the papers were not shown to
the ASV or for inclusion in the verified
balance as per Para 1228-s, what
action has since been taken to finalize
the loss
5 Materials escaping Particulars of quantity, where it was
verification lying and how it escaped verification.
How the material has since been
taken to account through department
verification
6 Loss due to theft, fire etc Same as for item(4) above
7 Material sent for ------do----
metallurgical test to be
done by CMT
8 Material classified under Quantity verified as surplus under
a lower class by the stock hand second (or scrap) with
verifier due to damage or particulars of AV sheet folio item
condition of the material. numbers
9 Other issues not covered Suitable remarks depending upon the
by the above nature of the case
196
Stock Verification
200
Stock Verification
201
Hand Book on Internal Checks (Railway Accounts)
14.1 PROCEDURE
14.1.1 Details on Stock Sheets While issuing a stock
sheet for any stockholder, the stockholder’s name,
designation, and date of superannuation shall be
prominently mentioned on top of the stock sheet.
14.1.2 Action by Stockholder The stockholder shall
scrutinize the stock sheet immediately on receipt and
submit his remarks explaining the shortage/excess,
etc to his controlling officer within a period of 45
days.
14.1.3 Action by Controlling Officer The controlling
officer would scrutinize the remarks submitted
by stockholder and forward the same to his branch
officer in divisions and depot officer in sheds and
workshops , as the case may be , within 20 days of
receipt.
14.1.4 The branch officer/ depot officer will submit it within
next 15 days to the concerned accounts officer, after
due scrutiny, duly explaining the shortage/excess,
etc.
14.1.5 However, if remarks furnished by the stockholder
explaining the shortage / excess are not found
satisfactory by the controlling officer, he will himself
202
Stock Verification
203
Hand Book on Internal Checks (Railway Accounts)
206
Stock Verification
207
Hand Book on Internal Checks (Railway Accounts)
208
Chapter 7
ESTABLISHMENT SECTION
CHECKS TO BE EXERCISED IN VARIOUS ESTABLISHEMENT
CLAIMS
The main internal checks summarized in the following
paragraphs are illustrative only and not exhaustive.
209
Hand Book on Internal Checks (Railway Accounts)
210
Establishment Section
211
Hand Book on Internal Checks (Railway Accounts)
• Absentee statements.
• Increment statements. (Gazetted Officers)
• Rent roll statements for the month of April - Rent
variation statements for the subsequent months for
quarters occupied by Railway servants.
• Electrical energy charges statement (once in six
months), prepared after adjusting the amount
recovered in the preceding Six Months against the
amount liable to be recovered on actual consumption
basis.
• Statement of PF recovery.
• List of workshop debits, stores debits and station
debits recoverable through the pay bills.
• Deduction sheets showing recoveries made through
pay bills on account of:-
i. Railway institute fees and subscription.
ii. Amount due to Railway Co-operative credit
Banks/societies.
iii. Amount due to staff Benefit Fund towards
Loans.
iv. Diet charge & recovery statements.
v. List of premium due on Life Insurance policies
realized from the pay of the insured.
vi. Court attachments.
vii. Income tax schedule.
viii. Statement showing the recoveries of various
advances.
ix. Allocation statements.
x. Certified summary of T.A., OT, NDA, and other
allowances.
xi. Sanction of competent authority where
provisional payment is authorized.
212
Establishment Section
215
Hand Book on Internal Checks (Railway Accounts)
216
Establishment Section
217
Hand Book on Internal Checks (Railway Accounts)
218
Establishment Section
220
Establishment Section
222
Establishment Section
224
Establishment Section
8) INCOME TAX
Accounts office is responsible for correct recovery of income
tax and for transfer timely of the recovered amount to the
IT Department. On basis of estimated income for the year,
Bill drawing units should recover approximate amount
every month from the salaries of the employees. For this
purpose, the Bill drawing officer should send a statement
to the Accounts Office every year in advance, showing the
particulars of employees, alongwith the detail estimated
income and savings under various permissible categories.
This should be verified with reference to the pay bill of the
officer concerned.As soon as the Accounts for the financial
year are closed, Form No.16 prepared by Personal Branch is
required to be sent to Accounts for verification. The same
has to be returned after verification for disbursement to the
officers for filling the Income Tax return.
-[1232 – 1233 A1]
225
Hand Book on Internal Checks (Railway Accounts)
227
Hand Book on Internal Checks (Railway Accounts)
228
Establishment Section
229
Hand Book on Internal Checks (Railway Accounts)
231
Hand Book on Internal Checks (Railway Accounts)
232
Establishment Section
233
Hand Book on Internal Checks (Railway Accounts)
234
Establishment Section
235
Hand Book on Internal Checks (Railway Accounts)
Officers in the pay One months basic pay as drawn in the pay scale
scale of HAG+ and
above
All other officers Equal to one months pay is drawn in the
Prescribed pay band + the applicable grade pay
237
Hand Book on Internal Checks (Railway Accounts)
239
Hand Book on Internal Checks (Railway Accounts)
240
Establishment Section
241
Hand Book on Internal Checks (Railway Accounts)
242
Establishment Section
shall make entries and adjust the same in the Books of the
Railways. The details should be recorded in the Register kept
for this purpose. Delay in receipt of FSC should be promptly
brought to the notice of the Executive and Foreign employer
and Railway servant. Interest on outstanding Foreign Service
contributions should be claimed as per terms. A complete
list of staff who were on Foreign service should be furnished
to Accounts Office by personnel Department to enable the
Accounts to watch and verify whether the FSC charges are
realised correctly.
243
Hand Book on Internal Checks (Railway Accounts)
Last Pay Certificate One LPC every month 2 LPCs every month
245
Hand Book on Internal Checks (Railway Accounts)
246
Establishment Section
247
Hand Book on Internal Checks (Railway Accounts)
248
Establishment Section
19) PNM/PPM
19.1) Permanent Negotiation Machinery (PNM)- This
machinery has been set up in the Railway with a
view to maintain an effective contact with labour
and also to see to resolve disputes and differences
arises between the labour and the administration in
day to day working . The solution to various disputes
and differences is sort to be achieved by means of
negotiations for which this machinery has been
introduced.
The PNM works at three levels:-
(a) At divisional level, where the PNM meet the local
administration once in two month and discuss
the problems of employees of the particulars
establishment. Many a problems are solved at such
meeting and better understanding between the
workers and the administration. If some problems
evades at this level, they are referred at the next
higher level. In division DRM/ADRM is the chairman of
the meeting. If any booklet regarding any PNM items
related with establishment claims of the employees is
received, immediate reply of such items is to be given
249
Hand Book on Internal Checks (Railway Accounts)
250
Establishment Section
253
Chapter 8
BILLS RECOVERABLE
1) BILLING:
Bills are prepared for the various facilities, provided by
Railways, such as sidings, land licensing, interest and
maintenance charges for various sidings. Every revision has
done by the executive then these office issues normal bills till
next revision. It is to be seen that the bills are prepared timely
& correctly, with reference to facility, rate, area, previous out
standings, period for which being billed.
Bills for cost of Commercial staff, C&W maintenance charges
since been prepared by concerned executives quarterly. It is
vetted by Accounts and after vetting the same is returned to
them for onward transmission.
Bills for way leave charges not issued by Accounts since
the charges already vetted and demand notes are issued by
ENGG. Department.
254
Bills Recoverable
4) Way-Leave Charges:
Way leave facilities / easement rights on Railway land involve
occasional or limited use of land by a party for a specified
purpose like passage etc. without conferring upon the party
any right of possession or occupation of the land and without
in any way affecting the Railway’s title, possession, control
and use of the land.
-PARA 1033 (ENGG CODE)
Guidelines regarding fixing of way-leave charges were
issued vide Board’s letter No.97/LML/24/3 Of 27-11-01 ,
which clearly defines the modus operandi to be followed
while fixing the way – leave- charges in different matter.
However regarding laying of optic fiber cable (OFC) cable ,
Railway Board vide their letter no. 2001/LML/24/20 Dated
16-08-2005 have issued detailed guide line which may be
kept in mind while dealing any such proposal. Regarding way
255
Hand Book on Internal Checks (Railway Accounts)
5) RENT OF BUILDINGS.
Buildings rented to private parties are treated equivalent to
licensing of land. Hence they are covered under Board’s letter
of 29/08/95. However, policy regarding provision of Quarters
for GRP personnel has been laid down vide Board’s letter
No.92/LM(B)/21/41/Policy of 12/10/93. The letter stipulates
that a rate of 3% of the market value of land is to be charged,
with revisions every 10 years.
6) Assisted Siding
(i) The words “Interest and Maintenance” charges
are used typically in the context of Assisted sidings
who are required to pay an “interest & depreciation
charge” on the capital cost as per book value borne
by Railway in the initial construction at the prevalent
rate of Dividend payable to the general revenue (7%
since 1993, as per Appendix IV of the report of
Railway Convention Committee).
(ii) In addition to interest, the party has to pay
maintenance charges at the rate of 4/2% on the cost
of portion of siding borne by Railways on the present
day cost of the siding. Maintenance charges will be
payable on the portion of siding outside Railway’s
premises and are subject to review every five years.
For example, if in 1996, a siding was provided at
Rs.100/-, the maintenance charge will be Rs.4.50/-.
In the year 2001, if the assessed cost of the review is
Rs.150/-, the maintenance charge will be Rs.6.75/-.
7) Private Sidings
Instructions with regard to levy of maintenance charges
for the private sidings have been laid down vide Board’s
256
Bills Recoverable
257
Hand Book on Internal Checks (Railway Accounts)
258
Bills Recoverable
259
Hand Book on Internal Checks (Railway Accounts)
260
Bills Recoverable
10) DESPATCH:
It is to be confirmed that the bills prepared are dispatched to
the concerned party in time.
261
Hand Book on Internal Checks (Railway Accounts)
262
Bills Recoverable
263
Hand Book on Internal Checks (Railway Accounts)
264
Chapter 9
BOOK SECTION
265
Hand Book on Internal Checks (Railway Accounts)
3) Remittance transaction
The transactions between the railways on the one hand and
departments of central and state government on the other
hand are known as remittance transactions. The following
heads of accounts are operated to record the remittance
transaction:
a. Reserve Bank Suspense
b. Remittance into bank
c. Cheques and bills
d. PAO suspense
e. AG suspense
f. Remittance accounts with Defence and postal
g. Reserve Bank Deposit
267
Hand Book on Internal Checks (Railway Accounts)
268
Books Section
.On receipt of clearance memos from RBI and the focal point
branches in respect of cash and cheques, DD deposited into
bank, books section prepares a JV debiting remittance into
bank “00867011” and crediting to reserve bank deposit. The
balance under the head “remittance into bank” “00867009”
represents the cash or cheque deposited into bank but
not acknowledged by them. Balances in the allocation
“00867011” represent the cash or cheque deposited in bank
and acknowledged by them. The item mentioned in allocation
“00867009” and allocations “00867011” are matched and in
case of any unmatched item and remained uncleared; writing
to RBI for clearance of the same.
269
Hand Book on Internal Checks (Railway Accounts)
270
Books Section
Day wise credits accorded by the focal point as per daily
bundle are entered manually into a register. This daily data
is reconciled manually with the monthly statement sent to FA
& CAO’s office by the focal point. This monthly statement is
called Detailed Monthly Summary (DMS).
The focal point branch also sends the day wise receipt to
Reserve Bank of India for crediting into the Railway Account.
RBI to FA & CAO advises the amount so credited day wise by
RBI into the Railway Account through a statement called RBI
memo.
271
Hand Book on Internal Checks (Railway Accounts)
272
Books Section
3.E AG SUSPENSE:
AG SUSPENSE is operated to settle the transactions with the
state government departments.
273
Hand Book on Internal Checks (Railway Accounts)
4) Transfer Transactions:
The transactions which are settled by way of book adjustment
between two separate accounting units within the same
railway or between two different railways are known as
Transfer Transactions and needs to be kept distinct from
normal transfers.
The following heads of accounts are operated to re-
cord and adjust transfer transactions.
a. Transfers, Railway Revenues}
b. Transfers, Railway Capital} for transactions involving
revenue transactions in the Capital accounts books
and vice versa
274
Books Section
275
Hand Book on Internal Checks (Railway Accounts)
276
Books Section
277
Hand Book on Internal Checks (Railway Accounts)
9) DEPOSIT UNPAID:
When the Pay office returns bills to the Accounts office there
may be some unpaid items in them. The amounts so unpaid
will be remitted by the pay office in to the Bank accompanied
by a statement in Form A –1959 that is known as the unpaid
278
Books Section
280
Books Section
281
Hand Book on Internal Checks (Railway Accounts)
283
Hand Book on Internal Checks (Railway Accounts)
285
Hand Book on Internal Checks (Railway Accounts)
287
Hand Book on Internal Checks (Railway Accounts)
288
Chapter 10
2. STORES
• AAC to be arrived at with due diligence.
• ABC analysis of stores should be carried out.
• Issue note (SHOP/Stores)/Copy Pairing is upto date
with NIL differences.
• Whether Register of Provisional Adjustments
maintained.
• Oldest items awaiting adjustment.
• Store Suspense should be as minimum as possible.
290
Check List for Workshops
3. GATE ATTENDANCE
• OPENING/CLOSING Procedure of Gates Whether any
Loopholes ?
• Clocks are in order or not ?
• Whether GA Cards Punched Four Times.
• Number of people treated absent after Window Gate
Time is Over (30 minutes/3 minutes).
• Absentee Register maintained or not
• Additions/Deletions of attested or not
• Number of Duty Certificates issued/Shops having
highest Duty Certificates & their out turn.
4. INCENTIVE
• Excess Time Cards (Plus Cards) issued and whether
any shop showing regular or excessive issue of plus
cards.
• Whether all completed job cards arrive within 48 hrs.
of completion of job.
• Whether any shop regularly showing profit >50% and
has allowed time reviewed.
• Whether allowed time has been revised due to
improvement in technology through new machines.
• Idle Time Bookings – How much on account of tools/
want of work ? Whether deductions done from
supervisors salaries ? (2% limit)
• Systems of preventive machine maintenance is in
place.
• Whether Master Planning Card made available to
WAO & all allowed time Checked in Rotation.
291
Hand Book on Internal Checks (Railway Accounts)
5. OTHER ITEMS
• Non Stock items Review/Conversion to Stock
• Shop floor Verifications/Custody to Stock.
• Fluctuations in Unit Cost to be watched.
• Leakages of scrap to be eliminated through
qualification from point of generation of Scrap.
• Sensitivity Analysis is to be done for inspection of
Workshop.
• Lateral transfer of store may be indicator of poor
planning.
• Review of staff should be done from time to time
taking into account the work load and off loaded
work.
• Asset Register should be updated from time to time.
• Special studies should be carried out on different
topics every month.
292
Chapter 11
2. Revenue Receipts
For recording the revenue receipts, two suspense heads
namely Traffic Account and Demands Recoverable are
operated. If these amounts remain un-cleared, the balance
under the ‘Suspense Heads’ would go on accumulating and
293
Hand Book on Internal Checks (Railway Accounts)
3. Traffic Account
Traffic Account is a Suspense account operated for the
purpose of recording the revenue earnings on accrual basis
in a month’s account to which they pertain and also for
watching the progress of their realization. The outstanding
balance represents unrealized earnings therefore exhibited
on the Asset Side in the Balance Sheet.
4. Freight Outstanding
“Freight” is the charges levied for the carriage of goods
including transshipment charges. Freight Outstanding will
arise when the way-bills / invoices have been accounted for
in the books of Railways (Station Balance Sheet), but freight
charges have not been realized. Generally around 50 percent
of unrealized earnings of railways are on account of Freight
Outstanding. Therefore, fortnightly review is necessary.
5. Admitted Debits
Every debit raised by the Traffic Accounts office on the
station on account of error in charging fare or freight, short
remittance of cash etc. accepted by the station is known as
Admitted Debits.
6. Objective Debit
Every debit raised by the Traffic Accounts office on the
station on account of error in charging fare or freight, short
remittance of cash etc. but not accepted by the station and
kept pending for want of clearance through withdrawal is
known as ‘Objected Debit’.
railway after the expiry of the free time for such removal.
“Demurrage” means the charge levied for the detention of any
rolling stock after the expiry of free time, if any, allowed for
such detention.
Monthly reviews should be carried out to clear the
outstanding.
8. Demands Recoverable
Demands Recoverable is a suspense head operated to bring
into the books of Accounts on accrual basis all the dues to
the Railways within the same financial year which were not
realized during the year. The closing balance under this head
represent unrealized amount in the form of outstanding
Demands Recoverable which will be exhibited on Assets side
of the Balance Sheet of Indian Railways.
There should be proper mechanism to watch whether bills
are properly raised and realized during the year of incurrence
of expenditure.
Review of Bills Recoverable register should be conducted
monthly .
9. Remittance Transactions
Transactions between the Ministry of Railways and Other
Ministries or States for which the accounts are not maintained
by themselves are ‘Remittance Transactions’. Two suspense
heads (i) Remittance into Bank and (ii) Cheques and Bills are
maintained.
296
Traffic Suspense
“The important and significant areas of internal checks have been covered in this
Hand Book. However, for detailed procedure, railway codes and process manual
notified from time to time by Railway may be referred while examining the
proposals.”
297