Key_Components_of_EVM
Key_Components_of_EVM
Definition: PV is the budgeted cost for the work scheduled to be completed by a specific date. It
Example: If a project has a total budget of $100,000 and is planned to be 30% complete after 3
months:
This means by the end of 3 months, the project was planned to deliver $30,000 worth of work.
Definition: EV is the value of the work actually completed by a specific date. It represents the
budgeted amount for the work that has been done so far.
This means by the end of 3 months, $25,000 worth of work has been completed according to the
project plan.
Definition: AC is the actual cost incurred for the work completed by a specific date. It represents how
Example: If the project has spent $27,000 to achieve 25% of the work:
AC = $27,000
This means by the end of 3 months, the actual cost of completing 25% of the work is $27,000.
4. Cost Variance (CV)
Definition: CV is the difference between the earned value and the actual cost. It shows whether the
Formula: CV = EV - AC
Definition: SV is the difference between the earned value and the planned value. It shows whether
Formula: SV = EV - PV
Definition: CPI is the ratio of earned value to actual cost. It measures the cost efficiency of the work
completed.
Formula: CPI = EV / AC
A CPI of 0.93 means that for every dollar spent, the project is earning only $0.93 worth of work.
Definition: SPI is the ratio of earned value to planned value. It measures the efficiency of time
An SPI of 0.83 means that the project is progressing at 83% of the planned rate.
Definition: EAC is the expected total cost of completing all work on the project. It is calculated based
on performance to date.
Example: If the total budget (BAC) is $100,000 and the CPI is 0.93:
This suggests that the project will likely cost $107,527 to complete, exceeding the original budget.
Definition: ETC is the expected cost to finish all remaining project work.
This means that an additional $80,527 will be needed to complete the project.
Definition: VAC is the difference between the budget at completion and the estimate at completion.
It indicates how much over or under budget the project will be.
This indicates that the project is expected to exceed the budget by $7,527.