Chap5 Project Implementation
Chap5 Project Implementation
Introduction
Project Implementationstageinvolves
transforming the project proposal into the
actual project or reality.
– Project implementation refers to the execution of all tasks that are necessary to
The project implementation stage brings the project from the feasibility
1
09-Jul-22
2
09-Jul-22
• Adequate formation
• sound project organization
• proper implementation planning
• timely available of funds
• judicious equipment
tendering and procurement
• efficient contract management
• effective monitoring, etc
5
3
09-Jul-22
4
09-Jul-22
Tools of planning
• Gantt chart
• Network Techniques
Activities
Time in weeks from project start
10 20 30 40
Design
Purchase of parts
Fabrication
Assembly
10
5
09-Jul-22
11
Network Techniques
• In this technique, the
• activities,
• events, and
• their relationships
are presented by a network diagram, also
called an arrow diagram.
12
6
09-Jul-22
13
7
09-Jul-22
8
09-Jul-22
9
09-Jul-
1
09-Jul-
Dummyactivity:anactivitythat
does not consume time or resources.
It shows merely the dependencies or
proper relationship between
activities.
A dotted arrow represents dummy.
21
Network: this is the combination of activities, dummy activities and events in logical
22
1
09-Jul-
Activity Identification
• Short description: example, Lay foundation,
erect frame, etc.
• Alphabetic or numeric code: example, A, B,
C, etc., or 100, 101, 108 etc.
• Using tail and head event numbers:
example, 1-2, 2-3, 3-4, 3-6, etc
23
Example,
A building project consists of the following
activities: A = Lay foundation
B = Erect
framework C =
install millwork D
= install wiring
E = install
plumbing F =
plaster walls
G = install siding
H = decorate the
interior I = finish the
1
09-Jul-
25
Giventheaboveinterrelationshipthe
network diagram for the project is:
A Network Diagram
4
H
1 A 2 3 7 9
B D
E
F 5
G 6
I
26
1
09-Jul-
Network exercise 1
Activity Preceding Activity
A -
B _
C A
D A
E A
F C
G C
H C
J B, D
K F, J
L E, H, G, K
M E, H
N L, M
27
Answer 3
M
7
E
8
A H
1
L N
0 C
G
4 6
D
B F
J K
5
28
1
09-Jul-
29
Exercise
Activity Preceding Activity Activity durations (Weeks)
A - 9
B _ 3
C A 8
D A 2
E A 3
F C 2
G C 6
H C 1
J B, D 4
K F, J 1
L E, H, G, K 2
M E, H 3
N L, M 4
Required: Find the critical path and the duration for this project.
30
1
09-Jul-
Answer
3
M (3)
7
E (3) 8
N (4)
A (9) H (1)
1
L (2)
C (8)
G (6)
4 6
D (2)
B (3) F (2)
2
K (1)
J (4)
5
31