Chapter 3 Process Costing System
Chapter 3 Process Costing System
3. The job cost sheet is the key document 3. The department production report is the
BY TAMRAT G. 1
Rift valley University / Department of ACFN/ CH3-Process costing System
controlling the accumulation of costs by a key document showing the accumulation
job. and disposition of costs by a department.
4. Unit costs are computed by job on the 4. Unit costs are computed by department
job cost sheet. on the department production report.
In manufacturing process costing setting, each unit is assumed to receive the same
amount of direct materials cost, direct manufacturing labor costs, and indirect
manufacturing costs. Units are computed by dividing total costs by the number of
units.
The principal difference between process costing and job costing is the extent of
averaging used to compute unit costs of products or services. In job-costing
system, individual jobs use different quantities of production resources. Thus, it
would be incorrect to cost each job at the same average production cost.
In contrast, when identical or similar units of products or services are mass
produced, and not processed as individual jobs, process costing averages
production costs over all units produced.
The difference between job order and process costing system is, thus, the
extent of the averaging used to compute unit cost. In job order costing
each job differs in terms of material used, labor incurred, and
manufacturing overhead. Hence, it is impossible to assign the same cost
for different jobs. On the contrary, identical units produced in mass took
equal amount of direct material, direct labor, and manufacturing
overhead. Thus, the unit cost can be found by dividing total cost by the
number of units produced.
The Flow of Costs in Process-Costing System with Sequential
Production Departments
1. As direct materials and direct labor are used in production department A, these
costs are added to the Work-in Process inventory account for Department A.
Overhead is applied using predetermined overhead rate. The POR is determined
in the same way in job order and process costing.
Work-in Process: Production Department A xxx
Raw Materials xxx
Wage Payable xxx
Manufacturing overhead applied xxx
2. When production department A completes its work on some units of product,
these units of product are transferred to production department B. The costs
assigned to these goods are transferred from the Work-in Process Inventory
account for department A to work-in Process inventory account in department B,
BY TAMRAT G. 2
Rift valley University / Department of ACFN/ CH3-Process costing System
the costs assigned to those partially completed products are called transferred-in
costs1.
1
Transferred-in costs are assigned to partially completed products that are transferred into one production
department from a prior department.
BY TAMRAT G. 3
Rift valley University / Department of ACFN/ CH3-Process costing System
Assumptions: ABC Manufacturing Company manufactures thousands of Products A.
These components are assembled in the Assembly Department, upon completion the
units are completely transferred to the Testing Department. The process-costing
system for Product A has a single direct cost category (direct materials) and a single
indirect-cost category (conversion costs). Direct materials are added at the beginning
of the process in Assembly. Conversion costs are added evenly during Assembly.
Case 1: Process costing with zero beginning and zero ending
work in process inventory that is all units are started and fully
completed by the end of the accounting period.
Data for the Assembly Department for January 2023
Physical Units for January 2023
Work in Process, beginning inventory (January 1) 0 units
Started during January 400 units
Completed and transferred out during January 400 units
Work in Process, ending inventory (January 31) 0 units
Total Costs for January 2023
Direct materials costs added during January Br.32,000
Conversion costs added during January 24,000
Total Assembly Department costs added during January 56,000
Solution:
Direct Material costs per unit (32,000/400) Br. 80
Conversion costs per unit (24000/400) 60
Assembly Department costs per unit 140
BY TAMRAT G. 4
Rift valley University / Department of ACFN/ CH3-Process costing System
In addition, the Assembly Department estimates that the partially assembled units are on
averages 60% complete as to conversion costs.
How should the co. calculate the cost of fully assembled units in February 2023 and
the cost of partially assembled units still in process at the end of February 2023?
Steps:
Summarize the flow of physical units of output.
Compute output in terms of equivalent units.
Compute equivalent unit costs.
Summarize total costs to account for.
Assign total costs to unit’s completed and to units in
ending work in process.
Equivalent Units: A key Concept
Material, labor and overhead costs are incurred at different rates in production
process. Direct material usually placed in production at one or more discreet
points in the process. In contrast, direct labor and manufacturing overhead, called
conversion costs, and usually are incurred continuously throughout the process.
When an accounting period ends, the partially completed goods that remain in
process generally are at different stages of completion with respect to material and
conversion activity.
Example: Suppose there are 1000 physical units in process at the end of an accounting
period. Each of the physical units is 75% complete with respect to conversion. How much
conversion activity has been applied to these partially completed units?
Conversion activity occurs uniformly throughout the production process. Therefore, the
amount of conversion activity required to do 75% of the conversion on 1000 units is
equivalent to the amount of the conversion on 750 units. The number is computed as
follows:
1000 partially completed physical units in process * 75%
complete with respect to
Conversion = 750
The term equivalent units is used in process costing to refer to the
amount of manufacturing activity that has been applied to a batch of
physical units. The 1000 physical units in process represent 750
equivalent units of conversion activity.
The term equivalent unit is also used to measure the amount of direct materials
represented by the partially completed goods. Since direct materials are incorporated at
the beginning of the production process, the 1000 physical units represent 1000
equivalent units of direct material ( 1000 physical units * 100% complete with respect to
direct materials).
Physical units and Equivalent units (Step 1&2)
BY TAMRAT G. 5
Rift valley University / Department of ACFN/ CH3-Process costing System
Equivalent units is a derived amount of output units that takes the quantity of each
input (factor of production) in units completed or in work in process, and converts it into
the amount of completed output units that could be made with that quantity of input.
Equivalent Units
Flow of Production Physical Direct Conversion
Units Materials costs
Work in process, beginning 0
Started during current period 400
To account for 400
Completed and transferred out during current
period 175 175 175
Work in process, ending 225
225*100%; 225*60% 225 225
Accounted for 400
Work done in current period 400 310
Journal Entries
Work in Process- Assembly 32,000
Account Payable Control 32,000
(To record direct materials purchased and used in production)
BY TAMRAT G. 6
Rift valley University / Department of ACFN/ CH3-Process costing System
Work in Process- Assembly 18,600
Various accounts 18,600
(To record Assembly department conversion costs)
Work in Process- Testing 24,500
Work in Process- Assembly 24,500
(To record cost of goods completed and transferred from Assembly to
Testing Department)
Case 3: Process costing with some beginning & some ending
work in process inventory.
Data for the Assembly Department for March 2023
Physical Units for March 2023
Work in Process, beginning inventory (March 1) 225 units
Direct Materials (100% complete)
Conversion costs (60% complete)
Started during March 275 units
Completed and transferred out during March 400 units
Work in Process, ending inventory (March 31) 100 units
Direct Materials (100% complete)
Conversion costs (50% complete)
Total Costs for March 2023
Work in process, beginning inventory
Direct materials (225 equivalent units * Br. 80/unit) Br. 18,000
Conversion costs (135 equivalent units * Br.60/unit) 8,100 Br. 26,100
Direct materials costs added during March 19,800
Conversion costs added during March 16,380
Total costs to account for Br.62, 280
Weighted-Average process costing method
This method calculates the equivalent unit cost of the work done to date (regardless
of the period in which it was done) and assigns this cost to equivalent units
completed and transferred out of the process and to equivalent units in ending work
in process inventory.
The weighted average cost is the total of all costs entering in the work in process
account (regardless of whether it is from the beginning work in process or from work
started during the period) divided by total equivalent units of work done to date.
Physical units and Equivalent units (Step 1&2)
Equivalent Units
Flow of Production Physical Direct Conversion
Units Materials costs
Work in process, beginning 225
Started during current period 275
To account for 500
Completed and transferred out during current
BY TAMRAT G. 7
Rift valley University / Department of ACFN/ CH3-Process costing System
period
Work in process, ending 400 400 400
100*100%; 100*50% 100
Accounted for 100 50
Work done in current period 500
500 450
BY TAMRAT G. 8
Rift valley University / Department of ACFN/ CH3-Process costing System
A distinct feature of the FIFO process-costing method is that work done on
beginning inventory before the current period is kept separate from work done in the
current period.
Costs incurred in the current period and units produced in the current period are used
to calculate costs per equivalent unit of work done in the current period.
In contrast equivalent unit and cost per equivalent unit calculations in the weighted
average method merge the units and costs in beginning inventory with units and
costs of work done in the current period.
Physical units and Equivalent units (Step 1&2)
Equivalent Units
Flow of Production Physical Direct Conversion
Units Materials costs
Work in process, beginning 225
Started during current period 275
To account for 500
Completed and transferred out during current
period
From beginning work in process 225
225*(100%-100%); 225*(100%-60%) 0 90
Started and Completed 175
175*100%, 175*100% 175 175
Work in process, ending 100
100*100%; 100*50% 100 50
Accounted for 500
Work done in current period 275 315
Calculation of Product Costs (Steps 3, 4, and 5)
Total Direct Conversion
Production Materials costs
Costs
(Step 3) Work in process, beginning Br.26,100
Costs added current period 36,180 19,800/ 16,380/
Divided by equivalent units of work done in 275 315
current period
Costs per equivalent unit of work done in the Br. 72 Br. 52
current period
(Step 4) Total costs to account for Br.62,280
(Step 5) Assignment of Costs
Completed and transferred out (400 units)
Work in process, beginning (225 units) Br. 26,100
Direct Materials added in current period 0 0*72
Conversion costs added in current period 4,680 90*52
Total from beginning inventory 30,780
BY TAMRAT G. 9
Rift valley University / Department of ACFN/ CH3-Process costing System
Started and completed (175 units) 21,700 175*72 175*52
Total costs of units completed & transferred 52,480
BY TAMRAT G. 10
Rift valley University / Department of ACFN/ CH3-Process costing System
Transferred in costs are treated as if they are a separate type of direct
material added at the beginning of the process. In other words, when
successive departments are involved, transferred units from one
department become all or a part of the direct materials of the next
department; however, they are called transferred-in costs, not direct
material costs.
Example: In our example as the assembly dpt. process is completed the department
transfers the units to its Testing Department. Here the units receive additional direct
materials, such as packing materials for shipment, at the end of the process.
Conversion costs are added evenly during the Testing Department’s process. As units
are completed in Testing, they are immediately transferred to Finished Goods.
Data for the Testing Department for the month of March 2023 are:
Physical Units for March 2023
Work in Process, beginning inventory (March 1) 240 units
Transferred-in costs (100% complete)
Direct Materials (0% complete)
Conversion costs (62.5% complete)
Transferred in during March 400 units
Completed during March 440 units
Work in Process, ending inventory (March 31) 200 units
Transferred-in costs (100% complete)
Direct Materials (0% complete)
Conversion costs (80% complete)
Costs of Testing Department for March 2023
Work in process, beginning inventory
Transferred-in costs (240 equivalent units*140/ equ. Un) Br. 33,600
Direct materials 0
Conversion costs (150 equivalent units * Br.120/unit) 18,000 Br. 51,600
Transferred-in costs during March
Weighted-average 52,000
FIFO 52,480
Direct materials costs added during March 13,200
Conversion costs added during March 48,600
BY TAMRAT G. 11
Rift valley University / Department of ACFN/ CH3-Process costing System
Equivalent Units
Flow of Production Physical Transferr DM CC
Units ed in costs
Work in process, beginning 240
Transferred in during current period 400
To account for 640
Completed and transferred out during
current period 440 440 440 440
Work in process, ending 200
BY TAMRAT G. 12
Rift valley University / Department of ACFN/ CH3-Process costing System
To record cost of goods completed and transferred from Testing to finished goods.
BY TAMRAT G. 13
Rift valley University / Department of ACFN/ CH3-Process costing System
To record cost of goods completed and transferred from Testing to finished goods.
Finished Goods Control 122,360
Work-in Process: Testing 122,360
BY TAMRAT G. 14