Corrected Pages
Corrected Pages
Amount in words…........................................................................................................................
2V PAINTING 554,820.60 - - -
Clearing site
-
2D2 Excavation -
-
2D2.1 Bulk excavation in all classes of soils
to reduce the ground level to required
level, dewatering and disposal of
1300.00 m³ 315.25 409,825.00 641.00 202,075.25 647.29 204,058.17 1,288.290 406,133.42
excavated material off site as per
instructions of the Engineer
(Provisional Quantity).
-
2D2.2 Top soil preservation,commencing
from exsisting ground level,disposited 250.00 m² 48.50 12,125.00 - - - -
in soil heaps; average depth 150mm.
-
2D2.3 Excavating pits, exceeding 1.00m,
commencing from 150mm below 95.00 m³ 679.00 64,505.00 77.580 52,676.82 - - 77.580 52,676.82
existing ground level.
-
Trenches width > 300mm; depth not
exceeding 1.0m comencing from
150mm below from Original Surface - - - -
including Disposal of excavated
material on site..
-
For foundation; -
2D2.4 225 mm thk wall 120.00 m³ 679.00 81,480.00 - - - -
2D2.5 112.5 mm thk wall 5.00 m³ 679.00 3,395.00 - - - -
-
BOQ PREVIOS CURRENT CUMULATIVE
ITEM DISCOUNTED
DESCRIPTION QTY UNIT AMOUNT Qty Amount Qty Amount Qty Amount
NO RATE
2D3 Filling -
-
2D3.1 To sides of trenches with selected
excavated earth 150mm thick layers 69.00 m³ 1,164.00 80,316.00 - - - -
on site well rammed and consolidated.
-
2D3.2 To make up levels;; average thickness
75-150mm with imported earth well 50.00 m³ 2,056.40 102,820.00 50.110 103,046.20 381.22 783,940.81 431.330 886,987.01
rammed and consolidated.
-
2D4 Surface Treatment -
-
2D4.1 Anti - termite treatment to building
area including pavement area, beyond
3m from pavement from an approved
specialist's sub contractor according
to the specification and technical 500.00 m² 311.37 155,685.00 - - - -
literature, including 10 years warranty
(from the specialist's sub contractor)
to be issued in the name of the
Employer.
-
2D5 Earth work supports -
-
Distance between opposing faces <
2.00 m -