Method Statements for Piping Erection
Method Statements for Piping Erection
0 Issue for
approval
Rev Date Description Checked Approved Note
Contract no:
Title:
METHOD STATEMENTS FOR PIPING ERECTION
SUB CONSTRUCTOR:
Name Sign Date
12-12-
GIA HOANG PHU CO.,LTD
Checked LE. V. TRONG 2021
Approve 12-12-
d H.VAN.TUNG 2021
CONTENTS
1.
SCOPE ......................................................................................................
....................
2.PURPOSE................................................................................................
.......................
3.AREA OF
INSTALL.....................................................................................................
.
5. PREPARATION
WORK...............................................................................................
6. PIPING
ERECTION………........................................................................................
.......
7.PAINTING….............................................................................................
.....................
Doc. No : 001-NESTLE-
METHOD STATEMENTS GHP-MSPE-2021
Rev : 0
FOR PIPING ERCETION Date : 12-12-2021
1.0 SCOPE :
This method shall be described the work for piping erection works at
PHIN TRI AN FACTORY Project
2.0 PURPOSE :
The objectives of this procedure plan are covered to
-To serve as a Construction Method accordance with Project
Specification Require
-To ensure that the construction works take place under the
requirement of project
quality and safety plan.
The equipments or tools for the operation are shown as below listed:
See Equipements List attached
5. PREPARATION WORK.
5.1 The latest drawing shall be used for construction work.
5.4 Work Permit (included Lifting permit) will be issued for approval
to PROJECT ENGINEER, after approve, Permit will be shown at all time
on site.
5.5 The primary cords, cables, and grounding wires of all welding
equipment shall be of sufficient size, and any conductors with
damaged insulation shall not be used. They shall also be inspected
periodically.
6. PIPING ERECTION:
6.1. Installation of piping on pipe rack :
a) Generally, since air-cooled heat exchangers are placed on top of
the pipe rack, and pumps are placed underneath, the precedence for
installing piping shall be determined in consideration of the time
required for installing such equipment, the number of stages of the
pipe rack itself, etc. In principle, piping installation will be performed
from the bottom to the top levels. When installing piping, a check
shall be performed to ensure that the pipe rack beams have been
painted.
Doc. No : 001-NESTLE-
METHOD STATEMENTS GHP-MSPE-2021
Rev : 0
FOR PIPING ERCETION Date : 12-12-2021
c) After the pipe has been laid on the rack, the pipe shall be tied with
steel wire to prevent it from falling off until the weld joints are made.
The pipe fittings and weld lines (seams) shall be installed so as not to
be positioned on the beams.
Translation :6 mm
Separation :6 mm
Parallelism :1mm fer 125
mm of nomonal pipi
diameter but not more than
5mm Fig 1
b) The valve shall be checked for its class, body material, and trim
material to prevent any misuse.
Doc. No : 001-NESTLE-
METHOD STATEMENTS GHP-MSPE-2021
Rev : 0
FOR PIPING ERCETION Date : 12-12-2021
c) Before installing the valve, the flange faces of the valve and the
connected piping shall be checked to see that they are not damaged or
dirty, and that they are parallel with each other.
d) Valves shall be installed in the closed position, except for plug valves
and ball valves. After being installed, valves shall not be opened
except for pressure testing. Additionally, welding for installation of the
closed position, to prevent the valve seat from being damaged.
e) For lubricant type plug or ball valves, the disc shall be left in the
open position and the lubricant shall be replenished to prevent loss of
the sealant.
f) Globe valves, check valves, control valves, and other similar valves
shall be installed in accordance with the marked direction by checking
the flow direction.
b) All safety valves shall be installed after the specified set pressure has
been tested in the field.
c) The seal securing the cap to the safety valve body shall not be
removed without GHP approval.
Doc. No : 001-NESTLE-
METHOD STATEMENTS GHP-MSPE-2021
Rev : 0
FOR PIPING ERCETION Date : 12-12-2021
d) The safety valve with a lever shall be installed with the lever oriented
as shown on the drawing.
b) Expansion joints shall be installed after confirming that the line has
been completely assembled with all anchors, guides, and stoppers
installed in place as shown on the piping drawings.
f) After installation, all shipping bolts and fixtures shall be removed and
the joints shall be checked to ensure that nothing obstructs the
expansion movement.
7.PAINTING :
Painting if pipe spools shall be done in accordance to the “Painting
procedure “
Before installation ,all pipe spool welded joint which carried out the
piping shop shall be full coated with specified paint system except field
welding areas.
But all field welding joint are to be left un-insulated and unpainted for
examination during the hydrostatic testing.