Module 3 - Predictive, Plan based Methodologies (Part A)1
Module 3 - Predictive, Plan based Methodologies (Part A)1
Module 3 (Part A)
1
Course Agenda
Module Course
1 Introduction to CAPM Certification
2 Project Management Fundamentals and Concepts
3 Predictive, Plan Based Methodologies
4 Agile Frameworks/Methodologies
5 Business Analysis Frameworks
Summary
Agenda
Topic
1 The Project Management Process Groups
2 Project Initiation
3 Project Planning
4 Project Execution
5 Project Monitoring & Control
6 Performing Integrated Change Control
7 Closing the Project or Phase
Summary
Monitor
Initiate Plan Execute Close
& Control
Section 1
4
Initiating
The project management
framework can be described by
these 5 process groups
Planning
Closing
What is a Process?
Produces an output or product
Linked to the other processes by the output it produces
Consists of 3 elements:
Initiating Processes
Recognize the project should be done
Determine what the project should accomplish
Define the expectations of the stakeholders
Identify the assumptions and constraints
Define the criteria for project success
Create the Project Charter
Planning Processes
Establish tasks and activities to achieve the project goal
Sequence activities in the most effective manner
Establish a realistic schedule and budget
Assign resources to activities
Create the Project Management Plan and obtain approval
from stakeholders
Executing Processes
Implement the Project Management Plan
Manage the project team
Report on progress
Resolve problems during the project
Closing Processes
Review the processes used in the project
Measure achievements
Meet with team to review what can be learned
Project report
Disband team
Project Initiation –
Developing the Project Charter
Monitor
Initiate Plan Execute Close
& Control
Section 2
19
Project Initiation
Determine need for project
Establish goals of the project
Develop Statement of Work
Create initial project requirements
Determine feasibility
Define initial project scope
Consider risks and constraints
Create the project charter
STATEMENT
OF
WORK
PROJECT
REQUIREMENTS
Project Initiation
Also need to consider
Project risks
Project constraints
Organizational influences – Organizational Process Assets
External influences – External Environmental Factors
Project Risks
The Project Manager must evaluate the project risks when developing
the project
Project Constraints
What limitations must you work within:
The budget, schedule, scope
Availability of people and equipment
Compliance issues (e.g. regulations)
Environmental
Other customer or stakeholder constraints
Project Planning –
Developing the Project Plan
Monitor
Initiate Plan Execute Close
& Control
Section 3
35
Project Planning
In the initiation phase, the project goals, initial requirements and initial
scope were established and you set up your core project team
Project Planning
Project planning process
The detailed project requirements
The Scope Statement Project Management Plan
The WBS • Requirements management plan
• Scope management plan
The schedule • Schedule management plan
The budget • Cost management plan
• Quality management plan
Project team & other resources planning
• Resource management plan
Strategy for managing risks • Communications management plan
Strategy for managing communications • Risk management plan
• Procurement management plan
Quality assurance & control planning • Stakeholder engagement plan
Plan for managing procurements
Plan for managing stakeholders
© 1999-2021 National Project Management Inc 37
Scope Planning
38
SOR
Scope Statement
A tool the Project Manager can use to define and obtain agreement on scope
Document which describes what is to be done to complete the project
Provides a basis for more detailed planning
Prepared by the Project Manager
Based on meeting the SOR
Scope
Statement
Why is the Scope Statement needed?
Documents what tasks are included
Establishes a common understanding among stakeholders of tasks to be
performed, documents what tasks are included
Establishes a baseline for project planning, monitoring and control
Provides a vehicle for sign-off from the customer and other stakeholders on
the project scope
© 1999-2021 National Project Management Inc 41
Scope Statement
An example of the Scope Statement
Provides inclusions and exclusions
Specific scope
Task Task Task Task Task
Schedule
Budget Sub-task Sub-task Sub-task Sub-task
Responsibility Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Work
Package
Schedule Planning
45
Schedule Management:
Ensures that all and only the activities required to complete the
project are part of the project
The included processes overlap and interact continuously
Project Schedule
Places project activities in a logical order and time sequence
Based on WBS activities
Defines time constraints of activities including:
Duration of tasks
Start/stop dates
Relationships between tasks
'01 Mar 04 '01 Mar 11 '01 Mar 18
ID Task Name Duration Start Finish F S S M T W T F S S M T W T F S S M T W T F
1 A 4 days Fri 01/03/02 Wed 01/03/07
Why is it needed?
2 B 4 days Thu 01/03/08 Tue 01/03/13
3 C 3 days Wed 01/03/14 Fri 01/03/16
4 D 1 day Mon 01/03/19 Mon 01/03/19
5 E 4 days Mon 01/03/19 Thu 01/03/22
Management tool
7 G 3 days Mon 01/03/19 Wed 01/03/21
Bar Chart
Gantt Chart
Schedule Network Diagram
Project management software
Scheduling Terms
Activity – specific task which requires time
Network – a combination of project activities Path Duration
A-B-C-D-I 22 days
Path – a series of activities between events A-E-F-G-I 19 days
Critical path – path of activities with longest A-E-I 10 days
duration, any activity delay on
the critical path delays
completion of the project Critical Path
Critical Path
Estimates the minimum project duration and
determines the amount of schedule flexibility
on the logical network paths within the
schedule model.
Scheduling Terms
Fast Tracking Crashing
Compressing the project Compressing the project
schedule by doing schedule by throwing more
different activities money or resources at it
concurrently that would This should be done on
Faster!
normally be critical path activities
done in sequence
Typically increases project
costs
Example:
Constructing the Example:
foundation
Doubling the labour to
before the design
complete a task faster
is completed
on a structure
© 1999-2021 National Project Management Inc 55
E F H
A
Derived from the WBS Work Work Work Work Work Work
Sequencing Activities
Identifying and documenting logical relationships
between schedule activities
Accurately sequencing project activities will
contribute to a realistic and achievable schedule
Predecessor Successor
Cost Planning
61
Why is it needed?
Management tool
Provides a framework to allocate resources to project tasks
Provides a baseline to monitor and control project activities
Establishes the total project budget and cashflow requirements
Dollars
Class “A” within 5% accuracy
Class C Class A
(+/- 15%) (+/- 5%)
Rough Order of Magnitude (ROM) - Done at early stage of the project, least accurate,
range of accuracy –25 to + 75 %, typically used for Project Charter
Budgetary estimate - Used to establish project funding needs,
range of accuracy –10 to + 25 %
Definitive estimate - Based on well defined scope of work,
range of accuracy –5 to + 10%
r 1999-2021 National Project Management Inc 65
Summary
Readings