Method Of Statement - Earthing System
Method Of Statement - Earthing System
EARTHING SYSTEM
PROJECT: XXXXX
Method Statement for EARTHING SYSTEM
CONTENTS
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
6. EQUIPMENT
8. INSPECTION& TESTING
11. ATTACHMENTS
1.0. PURPOSE
The purpose of generating this method statement is to define the procedure step by step to
implement the correct practices for supply, installation, testing and commissioning of the
Earthing System through the guidelines contained herein so as to ensure that the job
execution complies with the requirements and serves the intended function to a satisfactory
level.
2.0. SCOPE
This method statement refers to various work procedure contained within project control
document which explains and covers the supply, install, test and commission of Earthing
System at all relevant areas.
3.0. REFERENCES
The references are:
1. Approved material submittal (submission started).
2. Approved shop drawing (submission started).
3. Project Specification Section 260526
4. Project quality and safety plan.
4.0 DEFINITIONS
Owner : MOI.
Contractor : Dhabi contracting
QCI : QA/QC Inspector
ITP : Inspection & Test Plan
ITR : Inspection & Test Request
P.P.E : Personal Protective Equipment
HSE : Health, Safety and Environment
MSDS : Material Safety Data Sheet
5.0 RESPONSIBILITIES
PROJECT MANAGER
Project Manager shall be responsible for coordinating with all area engineers and
organizing the necessary resources and ensure the works done as per approved
procedure. He should manage & control all the activities & responsible for overall
execution of work.
CONSTRUCTION
MANAGER
Construction manager shall manage and lead construction supervision team/ QA/QC
processes. He will
Supervise / coordinate with HSE Manager to ensure that HSE goals are met in the
construction packages. He shall review contractor technical submittals (method statements,
QA/QC, etc)
Overall management of site based activities and key liaison with Contractor’s site
management and
Responsible for coordinating and resolving interface issues to avoid potential delivery
delays.
He may ensure timely actions to resolve critical design and construction issues by
coordinating with consultants and contractors and recommending solutions and ensure that
the project close out requirements are implemented by coordinating with discipline
managers. He manages snagging and closeout process and interfacing with Operation staff.
SITE ENGINEER
He Shall organize and manage all the construction activities and overall supervision &
ensure that appropriate safety measures are in place and implemented. Any permit
required prior to commencement of the activity will be signed and obtained by him. He
will inform the foreman regarding any special provision like safeguarding of existing
facilities. Site Engineer shall be responsible for overall coordination and inspection of all
the works. This includes but not limited to notifying the Consultant and Coordination
for all Inspection Witness and Hold Points, prepare stage wise inspection reports and get
them signed by all concern personnel, filing and indexing the same.
QA/QC ENGINEER
He ensures that the requirements of this method of statement are adhered to during
execution of activity onsite and the materials delivered for installation and use during this
activity comply with the requirements of the contract specification and are as per the
approved and submitted material submittal, to implement the requirements of the
inspection and test plan for this activity.
He shall ensure that the works are inspected and checked internally before submitting to
the consultant for inspection and also to enforce the required inspection procedure and
requirements to coordinate with the main contractor during all inspection activities and to
provide correct notice for inspection of the works and also to support the project
management team in the implementation of the method and the safe working procedures
required on the project.
Shall arrange safe working condition and supervise the workforce in all the activity so as
to achieve the proper and safe execution of work. He shall engage all equipment and
plants required for the job in consultation with the general foreman. He will ensure that
the workforce fulfils necessary safety norms.
SAFETY OFFICER
He in conjunction with the site supervisor. He will physically check and confirm that all
approved safety measures have been implemented. He will ensure that the toolbox
talks have conducted, work procedure & its risk has explained among the workers before
starting the job.
MATERIAL
Earthing system material shall be in line with the approved material submittal.
2. Only experienced and skilled technicians shall be engaged for carrying out the
installation work
3. The people involved in the installation shall be use proper PPE such as safety helmet,
safety shoes, safety harness, gloves, safety glass, reflected vest, sunglasses,
coverall, etc. required
4. Supervisor will follow the risk assessment precautionary measures before
commencing work.
5. Safety officer shall ensure that all scaffolding and ladders used at site are having
duly signed tags.
11.0. ATTACHMENTS
- ITP
- Checklist
- Risk Assessment