Risk Assessment for Excavation & Laying of Telecom Ducts
Risk Assessment for Excavation & Laying of Telecom Ducts
MAIN CONTRACTOR CHINA NATIONAL CHEMICAL ENGINEERING & CONSTRUCTION CORPORATION SEVEN MIDDLE EAST LLC
Manu Kishore
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 1 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 2 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
works.
If work any elevated area, Proper access and egress, fall
protection system to be provided
Workers shall be instructed to take care of their vicinity for
any obstructions while working.
Do not sit or take rest on the dunes or near to the bushes;
use only designated rest areas.
Rebar caps must be utilized to protect protruding steel rods.
Appropriate PPEs shall be always used by all operatives.
2 Excavation Damage to Minor / 3 3 9 Ensure to comply with DM code of CSP Chapter 9 Excavation 1 3 3 Foreman /
Work by underground Major Work & Chapter 6 Signs, signals, and Barricades Project
Mechanical utilities, injuries, Engineer /
Obtain NOC / work permit from the relevant authorities.
Equipment Fatality, HSE Officer
Edge collapse, Electrocuti Confirm no underground services prior to start the
on excavation.
Property damage
Check existing drawings, metal / cable detector to identify
Hit by Moving any existing services.
Heavy Equipment
Obtain excavation permit from CNCEC HSE dept. prior to
Toppling down of start the work.
heavy Equipment Arrange all necessary arrangements to prevent man /
material or equipment fall to the excavation area.
Ensure appropriate barricade around the excavation area.
Post warning sign boards & warning lights
Provide hard barricade where vehicle access / continuous
traffic areas.
Ensure Pre-task briefing is carried out prior to start work.
Ensure proper & safe access to the excavation.
Provide proper slope for the edges
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 3 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Keep the spoil materials at least 60CM away from the edges.
Concerned supervisor should monitor the activity
continuously.
Identify and cordon of the area to avoid unauthorized entry.
Assign third part certified flagman for control the plant
movement.
Ensure to follow the approved method statement and Risk
assessments.
3 Manual • Working in or • Fatality 4 3 1 Ensure to comply with DM code of CSP Chapter 9 Excavation 1 3 3 Site
Excavation around • Personal 2 Work & Chapter 6 Signs, signals, and Barricades engineer,
(where excavations/ Injury foreman,
Obtain required permits & NOCs
existing trenches, • Property All workers,
services are inadequate Never use the mechanical equipments. Flagman,
damage
available) angle of trench, Health Use only hand shovel (do not use axe); Do not apply
inadequate Issues excessive force,
step height, Excavate inclined manner, not vertically
improper
access& Egress, Excavation less than 1.2m:
Soil heap on The requirement for a protective system is a judgment call
edge of for the competent Person.
excavation,
Excavation more than 1.2m:
collapse,
toppling of Safe access and egress must be always provided for all
excavator, toxic employees. Never climb up or down using the timber or steel
fumes. supports - always use the ladder, stairways, or ramps.
• Flooding, Ensure the floors of the excavation are kept clear of loose
Oxygen spoil, debris, tools and timber.
deficiency, Ladders, stairways, and ramps should be provided for access
Improper Edge to surfaces either 1 Meter above or below ground level.
Protection,
Improper If trenches are more than 1.5m deep ladders or stairways
illumination, must always be provided.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 4 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 5 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 6 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
the injuries. Ensure to provide safe access / egress to the excavation area. Foreman/
excavation /
Provide Hand hold / hand rails for the access steps of the HSE Officer
lowered
excavation area, if very deep
area.
Ensure proper edge protection
Conduct pre-task briefing prior to start the job.
Regularly monitor and maintain the access.
Provide access sign boards for all the excavation area access.
Do not use any damaged or improper access and immediate
rectification is required.
5 Working Contaminate Serious 4 4 1 Obtaining NOC prior to start excavation / lowering work. 2 2 4 Project
Adjacent / soil, gases Injury, 6 Manager /
All authority requirements belongs to this activity shall be
Nearer to Accumulation • Property Foreman /
complied while executing the work
Undergroun Soil damaged Project
d Services Striking Full details of underground services be obtained in advance Engineer /
(HV / LV/ underground from the relevant authority, including television HSE
Sewage services communication relay companies and private property Officer / All
Line, Etc.,) Fire, owners. Worker
explosion, The lines of service will be marked, using paint, wooden
damages to pegs, etc.
existing
utilities C.A.T scan is required to identify all unknown services if
Contact with necessary.
electricity or All services will be assumed to be live until proven otherwise.
gas supplies,
Flooding from Management will ensure that services are located and
water marked before work begins.
services Full consultation will be held with relevant authorities to
• Contact with agree precautions will be carried out before work begins.
sewage line
All staff, machine operators and subcontractors will be fully
briefed before they begin work.
All temporary services will be properly marked.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 7 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 8 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
6 Working • Moving traffic • Severe 4 4 1 Required Permit should be obtained from authorities (DM, 1 2 2 Project
near / with • Incompetent personal 6 DEWA, RTA, etc.,) Manager,
live traffic workers injury Constructio
Visual checks on the location of traffic and
Members of Fatality n Manager,
public volume. Site
Wear complete PPEs while working near live traffic Engineer,
(especially hi-visibility vest) Foreman,
HSE
Flagman should be appointed for traffic diversions
Keeping employees visible and in well-lit areas.
Making sure employees can communicate with each other
and call for help.
Conduct training on all dangers and the corresponding safety
measures prior to working in traffic
Conduct pre-start briefing prior to start the work
Clearly identify the work zone with signage as required.
Keep the work zone in such a way that the workers will be
visible to all drivers (e.g., vehicles passing through, work
vehicles, etc.).
Use barriers, barricades, markers, cones, etc. to guide traffic
and to protect workers.
Ensure that any signs, devices, or barriers are visible in all
varying conditions of light and weather.
Drivers must be given clear guidance on how to proceed
through the work zone.
Cover the permanent traffic signs and markings if temporary
markings and signs are used.
Do not work on the edge or outside of the work zone.
Do not unload or load a vehicle from the live side of the
traffic.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 9 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
the same near to the injuries, Conduct Pre task briefing prior to start the job. Officer /
location at plan / Operator /
Slip, Trip & Install warning sign & barricade at the work location
site) machinery at Flagman /
Fall Assign banks-man / signal man for each plant at work
construction All Worker
location.
site. Fatality,
Ensure all personnel at work site must equipped with all
required PPE’s. (Safety Helmet, Safety Shoe, Safety Glass,
Hand gloves, Hi visibility work vest)
Loss of
reputation, Valid UAE driving license/third party certificate required for
Drivers /Operators for vehicles/equipment.
Property
damage. All vehicle/ equipment shall have valid registration/third
party certification.
Inspection and preventive maintenance of all equipment
shall be carried out regularly.
Provision of speed limit as per site condition must be in place
and clearly displayed in the site.
Designated pedestrian walkways/crossing to be provided
and are clearly marked/indicated.
Traffic management signage, speed humps and lighting shall
be installed as necessary.
No phone is allowed while driving / during work.
Flashing or warning lights shall be provided on the drive way.
Reverse audible alarms shall be provided to all construction
vehicles.
Drivers/operators use seat belt at all times.
Blind spot shall be identified and adequate control measures
shall be implemented.
Ensure 360-degree view of all equipment or fitted with 360-
degree visibility aid.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 11 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 12 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 13 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
12 Shuttering Fire, Cut Wound, 3 4 1 Ensure to comply with DM code of CSP Chapter 10 Concrete 1 3 3 Project
& Bruise, 2 & Masonry for Form work activities Manager /
Inhalation of
Deshutterin Fracture, The materials should be stacked properly and without Project
Dust,
g works Dislocation, obstructing the access Engineer/
Abrasion, Foreman
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 14 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Machinery Sprain, Strain, Only trained carpenters & form work workers are allowed to /HSE Officer
Risks, damage to do the form work activities. / Carpenter
property. All power tool operators should be trained & competent.
Electrocution,
The workforce should be given TBT, Pre-task briefing prior to
Slips /Trips,
start the work
eye/ Face risks
(Flying Proper (right) & safe equipment should be used for the
particles), activity
Foreman and operatives should inspect the condition of all
Shuttering
tools & equipment to ensure the good & safe condition
failure, falls or
accidents while All equipments must be color coded
shifting shutter Foreman should not hurry the workforce to follow the
shortcut
Fire, inhalation
of dust, Ensure no smoking and proper fire control measures.
electrocution, Ensure all machines are properly guarded and operators are
exposed trained in their operations.
rotating parts,
Ensure proper housekeeping always.
slips, trips
Ensure operatives are using adequate mandatory PPEs &
task specific PPEs (Goggles / Face shield / Ear plug / gloves /
Full sleeve) all the times
Adequate supervision to be ensured.
Ensure right tool for the job.
Deshuttering should follow proper method
Ensure proper cables and sockets for electrical connections.
No smoking and firefighting arrangement at place.
Machines to be properly guarded and operators to be
trained.
Maintaining proper housekeeping.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 15 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 16 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 17 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Foreman
While swinging the bucket / boom, ensure that there are no
overhead services
14 Drilling / Only trained and competent personnel to be assigned 1 3 3 Foreman,
Chipping of Power tool
Selection of tool for the right job
concrete by operator,
using Check the tools for defects prior to start the work HSE Officer,
Breaker / Never use damaged power tools Project
Jack Engineer
Hammer All power tools to be inspected by the competent person and
to be identified by color code
Ensure the tools are properly insulated
Damaged tools, Serious Provide training for safe usage of hand and power tools
Flying objects, injuries, Arrange the electrical cables properly to avoid tripping
electrocution, fracture, eye hazards
2 3 6
vibration, dust injury, cut Wear appropriate PPE’s such as goggles, face shield, ear
emission, noise injury, crush plugs, heavy duty gloves along with mandatory PPE’s
pollution. injury.
Remove the debris from work area and maintain good
housekeeping
Adequate training and instructions to the work force
Close supervision
Conduct TBT meeting prior to start the activity
Risk assessment to be communicated
Job rotation shall be done
Provision of welfare facilities.
15 Backfilling & Falling into Crushed 5 3 1 Ensure to comply with DM code of CSP Chapter 6 Signs, 2 3 6 Foreman /
Compaction Lifting into 5 signals, and Barricades & Chapter 20 Road Works / Site Project
Operations machine, Planning / Site Transport Engineer /
Incompetent Injury HSE Officer
The compactor will be registered as per as local rules.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 18 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 19 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 20 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
compactor.
Less noise generating equipment shall be selected for the
job.
All the equipment should be in good condition.
Dust should be controlled by spraying water.
17 Application Contact with Eye, Skin 3 3 9 Ensure to comply with DM code of CSP Chapter 20 – 1 2 2 Project
of Water water Proofing Exposure, Miscellaneous (Safety for handling Bituminous materials in Engineer,
Proofing Materials, irritation, and Road works) and Chapter 18 – Chemical Materials Hazard & Foreman,
other health Labelling Applicator,
Not using PPEs HSE Officer
issues The liquid state chemicals should be stacked inside the Drip
Incompetent tray to avoid spillages on the ground.
workers / Applicators provided with required PPEs & full body coveralls
supervisor to reduce contact with chemicals.
Avoid inhalation of vapors and ensure adequate ventilation
in the working place.
Fire and naked flame should be kept at a distance.
Suitable protective masks, gloves and goggles should be
worn during application.
Fire extinguisher to be provided.
Water proofing materials required to be stored in a
designated area displayed with MSDS and COSHH.
Storage area must be shaded area and be protected from
sun/ rain/ dust.
Water proofing material name shall be maintained and
incorporate major risk control measures from MSDS
Required task specific PPEs should be provided
Competent supervisor should supervise the job regularly
Daily TBT and pre-task briefing should be conducted to the
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 21 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
workforce.
All Hazardous waste materials, container & dipped woods
are all should be separately stacked & disposed in line with
DM Environmental Dept.
COSHH materials should not be kept under the hot sun,
proper storage should be provided
DM requirements should be followed for the storage &
handling of chemical materials
The COSS application workers should be internally trained.
Only trained workforce should be deployed for job under the
competent supervisor.
18 Manual Improper Body pain, 2 3 6 Ensure to comply with DM code of CSP Chapter 7 Manual 1 3 3 Project
Handling manual finger injury. Handling & Storage for Manual Handling activities Engineer
handling Pinch point. /Foreman/
Heavy lifting should not be allowed by workers, especially
technique Workers.
Minor or near Excavation / at height
serious Ensure that ground condition is firm, not wet / slippery, not
Heavy Load,
injuries. loose soil.
Protruding
edges. Ensure that workers not approaching the excavation edges
too closely to avoid collapse of edge & falling into the
Unsafe excavation
ground (loose
/ wet) Ensure skilled personnel to handle the task.
Use good conditions of tools.
Do not use defective tools.
Sharp edges to be identified and protected prior to handle.
TBT and training to be conducted based on manual handling
technique.
Ensure Job rotation for the workers (if required)
Maintain housekeeping standard in work place.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 22 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 23 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 24 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 25 of 26
PB-116 External Paving/ Landscape at the Consulate
General of the People's Republic of China
FOLLOWING STEPS TO BE FOLLOWED WHILE EVALUATING THE HAZARDS AND RISK FOR EACH ACTIVITY.
CONSEQUENCES SCALE LIKELIHOOD / PROBABILITY SCALE If the severity rating lies between 12 to 25, then
corrective actions need to be taken by concerned
FATALITY 5 CERTAIN 5 persons with documentary evidence
MAJOR INJURY / DAMAGE, DISABLING
4 VERY LIKELY 4 LIKELIHOOD / PROBABILITY (L)
ILLNESS
9 12 15
3 3 6
SEVERITY (S)
COLOUR CODE RISK LEVEL 12 16 20
MEASURES TO BE TAKEN 4 4 8
Final Provided that there are no deviations from control measures, the residual risk assumed is low.
Assessment: Supplementary measures should include using the correct PPE and safety Tool Box Talk to ensure that all workers are fully aware of the
control measures.
Appendix 1 – Risk Assessment for Installation of Telecom Ducts (POE-PB116-GGL-MSS-006 Rev-00) Page 26 of 26