0% found this document useful (0 votes)
50 views

JSA for Piling work final

jsa piping

Uploaded by

sahiltalwar987
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
50 views

JSA for Piling work final

jsa piping

Uploaded by

sahiltalwar987
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 8

POLYBUTADIENE RUBBER PROJECT

CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT


REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

Job area is considered: Green & Battery area of Proposed PBR Establishment/Project: Dated: - 15.02.2024
plant. Poly Butadiene Rubber Plant – IOCL Panipat. Rev:00
Project No: 203168C001
EPC Contractor: HARIOM BUILDERS Review & Approved by Consultant: Technip Energies
Participated in India Ltd & Client: IOCL
preparation of Job Safety
Mr. Rajesh Singh – Civil Lead/Dy. RCM Mr.DP Singh Rana- Dy.RCM
Analysis.
Mr. Ravi Pandey – HSE Engineer Mr. Pratap Yadav- Area Manager-Civil & Str

JOB DESCRIPTION: - Bored piling works by using Hydraulic Drilling Rig.

ACTIVITIES HAZARD & RISKS CONTROL MEASURE RESPONSIBLE


PERSON
Slice the job into the Describe all hazards identified Describe fully all equipment, facility, and/or procedure controls Responsible person
sub-tasks and record for each task based on applicable for each hazard. to implement the
them in sequence. observations and experience. controls.
Area preparation  Dust Inhalation  Dust Mask to be used by working crew. Water sprinkling is Site Engineer
to be done for controlling dust suppression.
 Slip/Trip
 Area to be cleaned and removed all obstructions before
the start of the work. Area levelling to be ensured.
 After 6pm area lighting to be arranged by contractor for
better visibility.

 Failure of equipment,  Lifting tools shall be inspected prior to use in addition to

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 1 of 8
POLYBUTADIENE RUBBER PROJECT
CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT
REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

tools, and tackles the third-party inspection from competent authority from Site Engineer
the concerned state and certificate of the same to be made
Movement of  Collision of vehicles available.
vehicles/equipment  Slip, trip, and fall.  SWL shall not be exceeded. SWL shall be marked on each
equipment.
and unloading of  Unauthorized/uninspected  Test lift to be done before proceeding to load these blocks
materials equipment /tools at site in trailer.
 SLI to be functional in all cranes/Farana’s.
 Inclement weather
 Operator shall have valid license and he shall be trained
condition through defensive driving training.
 All lifting equipment’s shall be inspected with a checklist
prior to deployment.
 Lift plan shall be made available if the load is more than
10T.SOP for heavy lifting to be available and scheme to be
get approved by PMC and client.
 Wheel chocks/hand brakes shall be used while parking the
trailer/dumpers.
 Ensure deployment of trained Flagman during movement
of any earth moving/construction equipment’s.
 Ensure PTW system wherever applicable.
 Restrict movement of heavy vehicles during adverse
weather condition
 Ensure safe transportation of equipment and materials at
the workplace.

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 2 of 8
POLYBUTADIENE RUBBER PROJECT
CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT
REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

 Specific lifting plan for each critical lift to be made and


reviewed by PMC/client.

 Failure of tools and  Obtain PTW prior to start the work & Conditions of PTW to
be adhered strictly.
Boring of pile tackles  Pile machine TPI certified, and periodically inspected & its Site Engineer
 Entanglement operator should be with valid license, gone through
screening procedure, site HSE induction.
injury/Pinch point injury  Arrange fire extinguisher, water hose/sand bucket along
 Failure of piling machine with fire watcher.
 Pile rig TPI certified, and daily inspected & its operator
 Deployment of should be with valid license, gone through screening
procedure, site HSE induction.
untrained/unauthorized  Keep away all unauthorized people during movement of
operator heavy vehicle/equipment.
 Ensure appropriate & inspected accessories being utilized
 Sludge accumulation and for drilling.
Access blocked.  Restrict movement of heavy vehicles/equipment in
rain/fog
 Collision/Hit by vehicle.  Gumboots and rubber hand gloves to be used by working
crew in addition to the general PPE.
 Fall of person in bore
 Flagman/Signal man to be deployed while machine in
hole. operation.
 Muck/Sludge shall be removed from the working area

daily.
 All piles bore holes to be covered with Iron Mesh and the

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 3 of 8
POLYBUTADIENE RUBBER PROJECT
CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT
REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

piling area to be barricaded.


 Piling vicinity area to be cleared as there should not be
any unauthorized personnel.
 All piling slurry must be removed by the contractor which
may be used for backfilling as when required.

 Reinforcement steel when shifting from one place to


another on tailor secured by chain/rope, avoid over speed
of the vehicle while transferring of the Reinforcement. Site Engineer
 Deploy flagman while shifting. Batton lights to be ensured
 Collision of vehicles during night shift.
 Injury to workmen by  Ensure line of fire activities are not performed during piling
operation.
hitting reinforcement.  Reinforcement shall be stacked properly in the lay down
Making pile cages area; tie all reinforcement after loading into the tailor with
& Shifting of  Deployment of chain properly.
Reinforcement untrained/unauthorized  Stacking area should be barricaded.
steel  Only trained rigger / operators are to perform the loading /
operator/workmen unloading operation.
 Failure of tools and  Tie a Tag Line on both the end, the tag line should be
minimum 3 meters & the personnel holding the tag line to
tackles be healthy.
 Ensure the face shield and ear plug while cutting the rebar
using chop saw machine. Shoulder pad should be used
while shifting the rebar.

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 4 of 8
POLYBUTADIENE RUBBER PROJECT
CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT
REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

 Cage must be lifted with D-shackle arrangement only no


makeshift methods will be allowed.
Fall of cage while lowering  No handmade slings will be allowed. Site Engineer
 Ensure the Involvement of skilled labor.
 Deployment of
 Deliver TBT before commencing work on daily basis and
Lowering of untrained/unauthorized site conditions to be made aware to working crew.
reinforcement steel operator/workmen  Ensure use of inspected & color-coded hand tools &
rigging accessories.
pile cage.  Failure of tools and  The area should be properly barricaded during lifting
tackles operations.
 Ensure Line of fire arrangement during erection activity.
 Injury to workmen  Ensure proper stacking of all materials at the worksite.
 First aid box should be in place at the site.

Hot work (welding,  Electrocution  Obtain Hot work permit prior to start of hot work &
conditions of the PTW shall be strictly followed.
gas cutting, etc.)  Fire/Explosion  All electrical connections routed through 30mAmps Site Engineer
ELCB / RCCB with industrial DB’s and canopy.
 Burn injury to working
 All electrical joints should be made with proper lugs/Male
crew. female sockets.
 All the combustible material shall be removed from the
 Inhalation of welding work area.
fumes.  Double earthling shall be done for all electrical equipment.
 Regular Electrical & machine inspection to be done by
HSE and Electrical Department.

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 5 of 8
POLYBUTADIENE RUBBER PROJECT
CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT
REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

 Trained and dedicated fire watchers must be available at


site.
 Fire Extinguisher should be available at welding work
area.
 All welding cable routed properly.
 Trained & experienced electrician must be available at
site.
 Area should be free from combustible materials.
 Ensure Proper PPE’s. (Welder must be use IFR suit)
 Fire blanket must be used during Hot work (welding
cutting, grinding) activity.
 Stack the cylinders at a safe distance from the cutting
area.
 Flash back arrestor/NRV (ISI marked) should be provided
on both sides of gas cutting set Ensure ISI marked gas
cutting set (i.e.- Gas hoses, Pressure gauges)
 Keep the cylinders always in upright position and secured
with chain on a trolley, these must be transported in trolley
only.

Lowering of tremie  Failure of tools and  D-shackle arrangement shall be there to lower the tremie
pipe no makeshift methods are allowed.
pipe and tackles  Provide guy rope to control the concrete sway of funnel. Site Engineer
concreting work  Fall of tremie pipe/tools  Follow proper slinging method.
 Inspection of tools tackles shall be done prior to use.
 Concrete spillages on skin  Ensure proper signal to driver.

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 6 of 8
POLYBUTADIENE RUBBER PROJECT
CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT
REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

and in Eye Entanglement



injury.

 Make sure that essential & appropriate lighting


arrangement for late-night working hours/shifts, Minimum
90 Lux shall be arranged as per OSHA standard. Site Engineer
Working at Night
 Slip, trip, and fall.  Banksmen shall be deployed with light baton for vehicle
shift
 Poor illumination movement.
 No working should be permitted in case of poor lighting
 Collision of vehicle conditions.
 Ensure proper housekeeping to avoid tripping.
 PTW for night work shall be obtained.

Pile Load Test  Slip, trip, and fall.  Make sure that essential & appropriately lighting
arrangement for late-night working hours/shifts, Minimum
 Poor illumination 90 Lux shall be arranged. Site Engineer
 Kentledge platform  Trained riggers to be deployed for loading/unloading of
load test concrete blocks on kentledge platform.
 Hydraulic Pressure  No working should be permitted in case of poor lighting
 Lifting tools and machine conditions.
 Ensure proper housekeeping to avoid tripping.
failure.  PTW for night work shall be obtained.
 Safety clamps to be provided in all pressurized hydraulic
pipes during testing.

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 7 of 8
POLYBUTADIENE RUBBER PROJECT
CIVIL, PILLING AND STRUCTURAL WORKS AT, “IOCL PANIPAT
REFINERY & NAPHTA CRACKERS COMPLEX “, AT HARYANA

Ref no:-IOCL-PBR/HOB/HSE/JSA/01 JOB SAFETY ANALYSIS HARIOM BUILDERS

 All equipment’s calibration will be must before starting the


job.
 Only authorized persons are permitted in load test working
area.

CONTRACTOR BY HSE CONTRACTOR BY RCM TEN- EXCUTION TEN-HSE


Page 8 of 8

You might also like