JSA for Piling work final
JSA for Piling work final
Job area is considered: Green & Battery area of Proposed PBR Establishment/Project: Dated: - 15.02.2024
plant. Poly Butadiene Rubber Plant – IOCL Panipat. Rev:00
Project No: 203168C001
EPC Contractor: HARIOM BUILDERS Review & Approved by Consultant: Technip Energies
Participated in India Ltd & Client: IOCL
preparation of Job Safety
Mr. Rajesh Singh – Civil Lead/Dy. RCM Mr.DP Singh Rana- Dy.RCM
Analysis.
Mr. Ravi Pandey – HSE Engineer Mr. Pratap Yadav- Area Manager-Civil & Str
tools, and tackles the third-party inspection from competent authority from Site Engineer
the concerned state and certificate of the same to be made
Movement of Collision of vehicles available.
vehicles/equipment Slip, trip, and fall. SWL shall not be exceeded. SWL shall be marked on each
equipment.
and unloading of Unauthorized/uninspected Test lift to be done before proceeding to load these blocks
materials equipment /tools at site in trailer.
SLI to be functional in all cranes/Farana’s.
Inclement weather
Operator shall have valid license and he shall be trained
condition through defensive driving training.
All lifting equipment’s shall be inspected with a checklist
prior to deployment.
Lift plan shall be made available if the load is more than
10T.SOP for heavy lifting to be available and scheme to be
get approved by PMC and client.
Wheel chocks/hand brakes shall be used while parking the
trailer/dumpers.
Ensure deployment of trained Flagman during movement
of any earth moving/construction equipment’s.
Ensure PTW system wherever applicable.
Restrict movement of heavy vehicles during adverse
weather condition
Ensure safe transportation of equipment and materials at
the workplace.
Failure of tools and Obtain PTW prior to start the work & Conditions of PTW to
be adhered strictly.
Boring of pile tackles Pile machine TPI certified, and periodically inspected & its Site Engineer
Entanglement operator should be with valid license, gone through
screening procedure, site HSE induction.
injury/Pinch point injury Arrange fire extinguisher, water hose/sand bucket along
Failure of piling machine with fire watcher.
Pile rig TPI certified, and daily inspected & its operator
Deployment of should be with valid license, gone through screening
procedure, site HSE induction.
untrained/unauthorized Keep away all unauthorized people during movement of
operator heavy vehicle/equipment.
Ensure appropriate & inspected accessories being utilized
Sludge accumulation and for drilling.
Access blocked. Restrict movement of heavy vehicles/equipment in
rain/fog
Collision/Hit by vehicle. Gumboots and rubber hand gloves to be used by working
crew in addition to the general PPE.
Fall of person in bore
Flagman/Signal man to be deployed while machine in
hole. operation.
Muck/Sludge shall be removed from the working area
daily.
All piles bore holes to be covered with Iron Mesh and the
Hot work (welding, Electrocution Obtain Hot work permit prior to start of hot work &
conditions of the PTW shall be strictly followed.
gas cutting, etc.) Fire/Explosion All electrical connections routed through 30mAmps Site Engineer
ELCB / RCCB with industrial DB’s and canopy.
Burn injury to working
All electrical joints should be made with proper lugs/Male
crew. female sockets.
All the combustible material shall be removed from the
Inhalation of welding work area.
fumes. Double earthling shall be done for all electrical equipment.
Regular Electrical & machine inspection to be done by
HSE and Electrical Department.
Lowering of tremie Failure of tools and D-shackle arrangement shall be there to lower the tremie
pipe no makeshift methods are allowed.
pipe and tackles Provide guy rope to control the concrete sway of funnel. Site Engineer
concreting work Fall of tremie pipe/tools Follow proper slinging method.
Inspection of tools tackles shall be done prior to use.
Concrete spillages on skin Ensure proper signal to driver.