Checklist of Building Construction
Checklist of Building Construction
S WORK CHECKLIST
PRE-EXECUTION CHECKS
Are proper electrical connections and working platform
Javailable, in case of on-site fabrication
|Are the required tools and safety equipments(scaffolding)
Javailable?
ACTIVITY: FORMWORK
Location: Date
ACTIVITY: PAINTING
Location: Date :
2
Has the shade, type of paint been approved by the architect
|and duly certified ?
3
Has it been ensured that wall and ceiling surfaces are
|completely dry ?
Have all the loose particles, dirt and dust been scrubbed
4
off fromn the surface ?
13 Has the dust from the surface been thoroughly Wiped off
after sanding the puttied surface?
14 Has it been ensured that the first coat of paint is applied
|and finished with roller?
Has it been ensured that the final coat is applied after 4 to
15| 6 hours of first coat?
POST-PAINTING CHECKS
16
Has it been ensured that the area which is painted is
Iprotected?
Checked By; |Approved By;
REMAR
SR. NO. DESCRIPTION YES N.A.
KS
1|Name, Date and Number of the Drawing
PRE-TILING CHECKS
2|Has the surface been prepared for tiling ?
|Is the surface smooth, free from dust and other
contamination ?
4|Has the setting out been done ?
If ceramic tiles are used, have they been soaked for
5
atleast 30 minutes ?
6| Has the thickness of mortar bed checked ?
7Are the required tools available ?
8|Are there any specific requirements of the client ?
9|Has the tile code number and tile name ensured ?
CHECKS DURING TILING
10|Has slope been provided wherever required?
11
|Have the tiles been gently tapped after laying on the
|motar bed?
POST-TILING CHECKS
12 Have the joints been cleaned to remove loose mortar?
13| No hollow sound on the tile when tapped
14| Is the finished floor, level ?
15 Has it been ensured that grouting is only done after
24hrs of laying of tiles?
Has the area been barricaded so as not to allow foot
16
movement?
ACTIVITY: PLASTERING
Location: Date
32
Is curing been carried out for a minimum of 10 days, with
the date of plastering on the wall?
33 Are grooves, drip mould and mortar bands given as per
design?
Checked By: |Approved By;
ACTIVITY: BRICKMASONRY
Location: Date:
20| Has the top course been packed below the concrete beam?
POST-EXECUTION CHECKS
21| Has the curing of asonry been done for atleast 7days?
22| Has care been taken of not entertaining excessive chasing?
23| Has anail been driven to test the strength of joint after 7days of curing?
|Ckecked By: Approved By:,
Sign Sign
RCC- CHECKLIST
ACTIVITY: RCC CHECKLIST
Location: Date :
ACTIVITY: EXCAVATION
Location: Date :
SR. DESCRIPTION
NO YES N.A. REMARKS
1
Is the general status of safety and orderliness in
the area maintained?
2
|Are the workers wearing their helmets and safety
belts when required?
3 |Are all openings (shafts, doors, balconies) and
lcut outs safely barricaded or covered?
4 Is the staircase area barricaded?
1
|Is the construction material properly stacked or
removed to a collection point?
Is barricading provided
12 especially in the staircase
lopening areas?
Checked By: |Approved By:
Name Name
Sign Sign
Date Date
REINFORCEMENT CHECKLIST
ACTIVITY: REINFORCEMENT
Location: Date :
8
Is the reinforcement free from oil, mud, grease and other forms of
contamination?
9 Is the overlapping ensured and the laps are staggered?
10|Has the anchoring been checked ?
Are the dowels for columns, beams and slabs in place and
checked for proper length ?
12
Are the required hooks fixed and is the chair height for the upper
layer of reinforcement correct?
13|Is the reinforcement done as per specification and drawing ?
14
|Are cover blocks provided and fixed in a systematically correct
manner and as per specifications?
15
Is the lock set properly mixed and the reinforcement turned into the
fresh lock set?
Has the consultant inspected the reinforcement before the
16
concreting has started?
17] Has adequate lap lengths been provided for all the column bars ?
18
|Is the steel scrap and the rings used for bundling collected in a
safe place to avoid any accidents ?
Ckecked By; Approved By: