0% found this document useful (0 votes)
175 views12 pages

Checklist of Building Construction

Uploaded by

sunilrayrjd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
175 views12 pages

Checklist of Building Construction

Uploaded by

sunilrayrjd
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 12

M.

S WORK CHECKLIST

ACTIVITY: METAL (MS) WORKS


Location Date :

|SR. NO. DESCRIPTION YES N.A. REMARKS


Has the area been prepared for executing the work?

PRE-EXECUTION CHECKS
Are proper electrical connections and working platform
Javailable, in case of on-site fabrication
|Are the required tools and safety equipments(scaffolding)
Javailable?

CHECKS DURING EXECUTION


4 Have all joints been welded from both sides and excess
|weld ground
5|Has metal paste been applied to all edges and corners
6|Have all parts been sanded
7Are rosettes in position before fixing?
8|Have all coats of metal primer and paint been applied?
POST-EXECUTION CHECKS
9|Have all mortar spillage stuck to MS works been cleared
|Checked By; |Approved By:

Name Sign Date Sign


CHECKLIST

ACTIVITY: FORMWORK
Location: Date

SR. NO. DESCRIPTION YES N.A. REMARKS


1|Name, Date and Number of the Drawing
2|Are the latest "Good for Construction" drawings available ?
3| Is adequate quantity of shuttering material available?
4|Has the required barricading and safety measures been taken ?
5|Has the shuttering material been properly cleaned before use ?
|Does the level of the slab and beam shuttering correspond to the
|levels given in the drawing?
|Has the shuttering been checked for proper fixing and sufficient
|support for concreting?
8]1s the shuttering checked for vertical and horizontal alignment ?
9|Are the required tools available?
10 Are all the required cut outs and shaft openings in place and
checked for correct measurement ?
11Isthe brown tape in place andthe oil properlyapplied ?
12 |Is the deshuttering time as per specification and done in an
|orderly and safe manner ?
13|Has the consultant inspected the formwork before concreting ?
Ckecked By; |Approved By:

Name Sign Date Sign


PAINTING CHECKLIST

ACTIVITY: PAINTING
Location: Date :

SR. NO. DESCRIPTION YES N.A. REMARKS


1|Name, Date and Number of the Drawing
PRE-PAINTING CHECKS

2
Has the shade, type of paint been approved by the architect
|and duly certified ?
3
Has it been ensured that wall and ceiling surfaces are
|completely dry ?
Have all the loose particles, dirt and dust been scrubbed
4
off fromn the surface ?

5 Has proper scaffolding arrangement been done With safety


measures ?
6 Are the required tools available?
7Are there any specific requirements of the client?
CHECKS DURING PAINTING
8|Is the primer application done ?
9 Has the putty been applied after 24 hours of primer
Japplication ?
Has the 2nd coat of putty been applied after the 1Ist coat
10|
has completely dried ?
11 Have all undulations been covered using putty?
12 Has sanding of the surfaces been done properly to render a
smooth surface?

13 Has the dust from the surface been thoroughly Wiped off
after sanding the puttied surface?
14 Has it been ensured that the first coat of paint is applied
|and finished with roller?
Has it been ensured that the final coat is applied after 4 to
15| 6 hours of first coat?

POST-PAINTING CHECKS

16
Has it been ensured that the area which is painted is
Iprotected?
Checked By; |Approved By;

Name Sign Date Sign


FLOOR TILE
ACTIVITY: FLOOR TILING
Location: Date :

REMAR
SR. NO. DESCRIPTION YES N.A.
KS
1|Name, Date and Number of the Drawing
PRE-TILING CHECKS
2|Has the surface been prepared for tiling ?
|Is the surface smooth, free from dust and other
contamination ?
4|Has the setting out been done ?
If ceramic tiles are used, have they been soaked for
5
atleast 30 minutes ?
6| Has the thickness of mortar bed checked ?
7Are the required tools available ?
8|Are there any specific requirements of the client ?
9|Has the tile code number and tile name ensured ?
CHECKS DURING TILING
10|Has slope been provided wherever required?
11
|Have the tiles been gently tapped after laying on the
|motar bed?
POST-TILING CHECKS
12 Have the joints been cleaned to remove loose mortar?
13| No hollow sound on the tile when tapped
14| Is the finished floor, level ?
15 Has it been ensured that grouting is only done after
24hrs of laying of tiles?
Has the area been barricaded so as not to allow foot
16
movement?

Ckecked By; Approved By:

Name Sign Date Sign


- PLASTER CHECKLIST

ACTIVITY: PLASTERING
Location: Date

SR. N0. DESCRIPTION YES N.A. REMARKS


|Name, Date and Number of the Drawing
PRE-PLASTERING CHECKS

2 Is the latest "Good for Construction" drawings available ?


3 Is access available for starting plastering?
4 Has the required barricading and safety measures been
taken?
Is the concrete surface beam/column hacked with a
5
minimum of 80 hackings/sq.ft?
6 Are Button marks placed at appropriate intervals?
Has the GI mesh been nailed between all RCC&
7
masonry members
8 Are the corner beadings in place and plumb?
Have openings of doors & windows been fixed using
aluminium templates?
10 Is the electrical conduiting works completed?
11 Is the PHE piping works in toilets & kitchen completed?
16 Is the blockwork cured for atleast 7 days?
Is the surface wet & free from dust, oil & all forms of
17
contami nation?
8 Has the dried mortar been cleaned off the surface?
19 Are there any specific requirements of the client?
20 Are the required tools available?
21 Are the required materials available?
CHECKS DURING PLASTERING

23 Is the mixing of cement mortar being done correctly, on


MS sheet?
24 |Is the plaster in proper line & verticality ?
25 |Is the wall being plastered to given specifications, to
plumb and even?
26 Rough finish (tile application/first coat)?
POST-PLASTERING CHECKS

32
Is curing been carried out for a minimum of 10 days, with
the date of plastering on the wall?
33 Are grooves, drip mould and mortar bands given as per
design?
Checked By: |Approved By;

Name Sign Date Sign


BRICK WORK CHECKLIST

ACTIVITY: BRICKMASONRY
Location: Date:

SR. NO. DESCRIPTION YES N.A. REMARKS


1|Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2\Are the latest "Good for Construction" drawings available?
3Are the required number of Brick available ?
4|Have the Brick been properly stacked ?
8|Has the hacking at contact surfaces of column&beam been done ?
9| Has cement mortar slurry been applied over the hacked surface?
10 Have aluminium templates used for door'window openings ?
I1|Are the required tools available?
12|Is there any specific requirements of the client ?
13|Cement - is it of the approved grade and less than I mont old ?
14| Sand -is it medium grity, clean and silt-free (less than 5%)?
CHECKS DURING EXECUTION
15| Is bricks soaked in the water to just penetrate the whole depth of thebricks?
I6Ls the mortar in proportion 1:5 on MS sheet using farma box ?
17 Has the thickness for joints been checked ?
18|Has raking and pointing of joints been done?
19| Has the procedure of not constructing more than 1.2 meter coursesa day been followed ?

20| Has the top course been packed below the concrete beam?
POST-EXECUTION CHECKS
21| Has the curing of asonry been done for atleast 7days?
22| Has care been taken of not entertaining excessive chasing?
23| Has anail been driven to test the strength of joint after 7days of curing?
|Ckecked By: Approved By:,
Sign Sign
RCC- CHECKLIST
ACTIVITY: RCC CHECKLIST
Location: Date :

SR. NO. DESCRIPTION YES N.A. REMARKS

1|Name, Date and Number of the Drawing


PRE-EXXECUTION CHECKS
2|Are the latest "Good for Construction" drawings available ?
3|Have the required barricading and safety measures been taken?
|Are the required number of cement bags available on site? (or
adequate quantity of RMC been ordered )
5|Are the required tools available at site to ensure correct work ?
6Have the vibrators been checked before start of the concrete ?
|Are calibrated farma available for measurement (weigh batcher
|in case of weigh batching) .
8|Is the platform and scaffolding material secure ?
|Is the necessary shuttering and reinforcement complete and in
place?
10 Has the shuttering material been properly aligned using
lappropriate equipment?
11]Is the dimensional accuracy of shuttering material correct?
|Have the dimensions and orientation of the excavated pit been
12\checked ?
13|Is the test report of cement and steel available at site office ?
14 Has the aggregate been checked? (In case of Site Mix)
15 Has the diameter and spacing of reinforcement been checked?
Are spare hessain cloth or tarpaulin sheet available as
protection from the elements?
CHECKS DURING EXECUTION
17|Are all the labourers wearing gum boots while concreting ?
Is the concrete been properly compacted with a vibrator or
18|manually ?
If the depth to be concreted is more than 500 mm, then is
19
concreting being done in layers?
20 Are the markings on the dowels done and a line dori being
used to maintain correct concrete level?
21 Has the slump cone test been conducted on fresh concrete?
POST-EXECUTION CHECKS
22|Is curing been ensured?
Has deshuttering been done carefully without damaging the
23
concrete surface?
Checked By; |Approved By:

Name Sign Date Sign


PCC - CHECKLIST

ACTIVITY: PLAIN CEMENT CONCRETE P.C.C


Location : Date :

SR. NO. DESCRIPTION YES N.A. REMARK


1Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2Are the latest "Good for Construction" drawings
3 Have the required barricading and safety measures
4Are the required number of cement bags available on
5| Have the vibrators been checked before start ofthe
6|Are spare hessain cloth or tarpaulin sheet available as
7|Has the pit been cleaned by removing all the loose
8|Has the excavated pit watered and rammed for better
CHECKS DURING EXECUTION
9 Are allthe labourers wearing gum boots while
10|0s the right grade of concrete being used ?
11| Has the level of P.C.Cbeen maintained ?
12|Has the levelling and finishing of P.C.Cdone ?
POST-EXECUTION CHECKS
13]Has it been ensured that hessain cloth is provided and
14Has it been ensuredthat no looseearthhasfallen on the
|Ckecked By: |Approved By:

Name Sign Date Sign


FILLING AND COMPACTION

ACTIVITY: FILLING AND COMPACTION


Location:. Date_:

S.NO. DESCRIPTION YES N.A. REMARK


Name, Date and Number of the Drawing
2 |Are the latest "Good for Construction" drawings
available ?

3 |Are safety measures required for the neighbouring


|construction activities ?

4 |Are all the requirements met for maintaining


dewatering ?
5Are the required tools available ?
6
Is the compacting of the backfilled earth done by
|the appropriate method ?
|Does the backfilling material meet the acceptable
soil characteristics?
|Checked By; Approved By:
Name Sign Sign
EXCAVATION CHECKLIST

ACTIVITY: EXCAVATION
Location: Date :

S.NO DESCRIPTION YES N.A. REMARKS


Name, Date and Number of the Drawing
PRE-EXECUTION CHECKS
2|Are the latest "Good for Construction" drawings
3| Is the soil investigation report kept on-site?
4|Have TBMs been established?
|Storage or intermediary storage identified for
5superficial mass of earth excavated?
6 Are access routes available ?
7|Are trees present ?
8|Is it possible to deploy larger excavation machinery ?
9|Is a ramp for vehicular movement required ?
10 Has a grid line marking been done at appropriate
11 Are safety measures required for the neighbouring
12|Is a First Aid it available on site ?
13 Are all the requirements met for maintaining
14 Is it pssible toemploy water pumps ?
15 Does the depth to be excavated include the depth of the
16|Has the consultant inspected the site before
17|Are the required tools available ?
CHECKS DURING EXECUTION
18| Has the Block Level Register been maintained ?
19 Are the layout &alignment as per drawings ?
20 Has the required depth of cut been achieved ?
21 If excavation is beyond 1.25m are there steps provided
22 Has proper shoring and strutting been done in loose
23|Is the excavation barricaded at a distance of l meter ?
24 Has the point of height indicator been installed ?
|Are the marking pillars safely barricaded or protected
25 to avoid any disturbance of marking points ?
If blasting is necessary, is it being carried out by a
26|certified,licensed contractor ?
Checked By; |Approved By:
Name Sign Date |Sign
CHECKLIST

SAFETY AND HOUSEKEEPING


Location Date

SR. DESCRIPTION
NO YES N.A. REMARKS

1
Is the general status of safety and orderliness in
the area maintained?

2
|Are the workers wearing their helmets and safety
belts when required?
3 |Are all openings (shafts, doors, balconies) and
lcut outs safely barricaded or covered?
4 Is the staircase area barricaded?

5 |Is the toilet area inspected daily for cleanliness?

|Is the ladder access area on the floor safely


6accessible and the ladders checked for damage?

7 |Are all the floor tiles/ granite/ marble properly


covered to avoid damages?
Is the cleaning taking place on a daily and
|orderly manner?
10 |Are the trenches and excavations properly
barricaded?

1
|Is the construction material properly stacked or
removed to a collection point?
Is barricading provided
12 especially in the staircase
lopening areas?
Checked By: |Approved By:
Name Name

Sign Sign
Date Date
REINFORCEMENT CHECKLIST
ACTIVITY: REINFORCEMENT
Location: Date :

SR. NO. DESCRIPTION YES N.A. REMARKS|


1|Name, Date and Number of the Drawing
2|Are the latest "Good for Construction" drawings available ?
Are test results of bars available at site before starting the
fabrication work ?
4 Has the required barricading and safety measures beentaken?
|Is the area to be reinforced compatible with the drawings that are
provided?
6|Are the required tools available at site to ensure correct work?
|Is the reinforcement kept ready on wooden runners to keep them
clean?

8
Is the reinforcement free from oil, mud, grease and other forms of
contamination?
9 Is the overlapping ensured and the laps are staggered?
10|Has the anchoring been checked ?
Are the dowels for columns, beams and slabs in place and
checked for proper length ?
12
Are the required hooks fixed and is the chair height for the upper
layer of reinforcement correct?
13|Is the reinforcement done as per specification and drawing ?
14
|Are cover blocks provided and fixed in a systematically correct
manner and as per specifications?
15
Is the lock set properly mixed and the reinforcement turned into the
fresh lock set?
Has the consultant inspected the reinforcement before the
16
concreting has started?
17] Has adequate lap lengths been provided for all the column bars ?
18
|Is the steel scrap and the rings used for bundling collected in a
safe place to avoid any accidents ?
Ckecked By; Approved By:

Name Sign Date Sign

You might also like