The Chemical Engineer - Issue 993
The Chemical Engineer - Issue 993
C
ONTROLLING the level in the steam drum shown responds and reduces boiler firing. The material in the drum
in Figure 1 might at first appear a relatively simple is not totally liquid but includes bubbles of water vapour. The
scheme, manipulating the flow of boiler feed transient increase in the drum pressure will compress these
water to maintain the level at setpoint. However, bubbles so that the water level falls. This is shrink (swell would
two issues conspire to make it difficult. be the result if the steam demand increases).
The first is that we require tight, rather than averaging The level controller responds to shrink by increasing the flow
control. It is important that the level does not become exces- of boiler feed water. However, falling steam demand requires
sively high and risk liquid entering the steam system. Similarly, less water; the level controller has initially made moves in
it must not become too low and risk starving the boiler tubes the wrong direction. As the pressure reverts to setpoint, there
of water. We therefore require a relatively large controller gain. will be surplus water in the drum that the level controller will
The second issue is the change of phase from liquid to vapour. then have to correct. If tightly tuned, the control response can
The drum contents do not behave as a simple liquid. This can become oscillatory. We must employ tuning closer to that used
require us to substantially reduce the controller gain below the for averaging control, potentially risking excessive deviations
desired value. from setpoint.
STEAM
AIR PREHEATER
AIR
FI
WATER ECONOMISER PI
SUPERHEATER
STEAM
LC
STEAM
DRUM
FIREBOX
FC
FUEL WATER
TIME
But the water flow is set by the ratio target (R) and the flow of
steam
FC
WATER
The level is the process variable (PV) of the controller. It
manipulates R, which is thus its manipulated variable (MV). In
general, for an integrating process
THREE-ELEMENT LEVEL CONTROL
Figure 4 shows the scheme designed to deal with the problems
of shrink/swell, inverse response, and noise. It is a very early
example of feedforward/feedback control. By measuring the steam Comparing equations shows that the process gain (Kp) varies
demand, we can keep the flow of water equal to the demand and
so, in theory, the water level will not change. This is the feedfor-
ward part of the scheme. The level controller relies on feedback to
correct any deviation from setpoint or, indeed, permit the operator Boilers can have a 4:1 turndown ratio and so Kp could poten-
to change the setpoint. tially change by a factor of four. In theory this could cause a
Most of the corrective action is taken by feedforward control. tuning problem. However, since the level controller is provid-
This does not stop shrink/swell or inverse response, but the flow of ing only a trim action, it is likely that it can be tuned to be
water is now changed in the correct direction. The level controller robust over the whole operating range.
needs now only take trim action correcting for minor deviations
caused, for example, by flow metering errors. Much slower tuning
can be implemented, so avoiding any oscillatory behaviour. And, NEXT ISSUE
with a much lower controller gain, measurement noise is unlikely Our next article will cover filtering as an example of signal
to cause a problem. conditioning. Filtering may be required to prevent measure-
Conventionally the scheme is configured using a bias algo- ment noise being transmitted to, and potentially damaging,
rithm. The level controller adds (positive or negative) corrective the control valve. We’ll explain the standard filter available
action to the measured steam demand. An alternative scheme in each of the leading distributed control systems (DCS). And
employs a ratio algorithm. This maintains the water flow in we’ll show how a custom filter enables derivative action to
proportion to the steam flow, with the level controller trimming be used without excessively amplifying the noise.
the proportion as necessary.
The bias scheme was first implemented some 80 years ago
when only pneumatic instrumentation existed. Summing pneu- Myke King CEng FIChemE is director of Whitehouse Consulting, an
matic pressures is readily achievable; multiplying them is not. independent advisor covering all aspects of process control. The
However, the disadvantage of the bias scheme is that the flowme- topics featured in this series are covered in greater detail in his book
ters must be calibrated in consistent units. In most of the world this Process Control – A Practical Approach, published by Wiley in 2016
is already likely to be the case. Steam demand is likely measured
in metric tonnes (per hour) and water flow in cubic metres (per
hour). The density of water is very conveniently 1 t/m3. However, Disclaimer: This article is provided for guidance alone. Expert
in the US, water is likely to be measured in US gallons (USG/hr) engineering advice should be sought before application.