MEP-Bid Form T8 Program Management - SCHEDULE DetailedV5

Uploaded by

ashrafqatar2000
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views

MEP-Bid Form T8 Program Management - SCHEDULE DetailedV5

Uploaded by

ashrafqatar2000
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

King Salman Knowledge District (KSKD) – MEP PACKAGE 1 - Salman University Subcontract Classic Schedule Layout 15-Dec-24 17:15

Activity ID Activity Name Original Start Finish 2025 2026


Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Duration
King Salman Knowledge District (KSKD) – MEP PACKAGE 1539 18-Mar-25University
- Salman 06-Dec-26 Subcontract

Mobilisation 75 18-Mar-25 12-Jun-25

All Areas 75 18-Mar-25 12-Jun-25


All Zones 75 18-Mar-25 12-Jun-25
All Floors 75 18-Mar-25 12-Jun-25
Comm00 Commencement Date 0 18-Mar-25 Commencement Date, 18-Mar-25
Comm10 Site office, facilities and laydown areas 22 18-Mar-25 12-Apr-25 Site office, facilities and laydown areas
Comm20 Manpower and equipment 22 18-Mar-25 12-Apr-25 Manpower and equipment
Comm30 Method statements and submittals 60 05-Apr-25 12-Jun-25 Method statements and submittals

Comm40 Permits and approvals 30 05-Apr-25 08-May-25 Permits and approvals


Engineering 504 26-Mar-25 03-Nov-26

All Areas 504 26-Mar-25 03-Nov-26


All Zones 504 26-Mar-25 03-Nov-26
Key Milestones and Submissions 66 26-Mar-25 10-Jun-25
ENG110 Project Kickoff 0 26-Mar-25 Project Kickoff, 26-Mar-25
ENG120 Material Submissions 60 02-Apr-25 10-Jun-25 Material Submissions
Submission of Other Principal Technical Documentation 498 02-Apr-25 03-Nov-26
ENG150 Material Data Sheets (MDS) 60 02-Apr-25 10-Jun-25 Material Data Sheets (MDS)
ENG160 Inspection and Test Plans (ITP) 30 02-Apr-25 06-May-25 Inspection and Test Plans (ITP)
ENG140 Shop Drawings 60 10-Apr-25 18-Jun-25 Shop Drawings
ENG170 As-Built Drawings 60 26-Aug-26 03-Nov-26 As-Built Drawings

ENG180 O&M Manuals 60 26-Aug-26 03-Nov-26 O&M Manuals


Key Mock-Up and Mock-Up Drawing Submissions for Critical Path Items 30 07-May-25 10-Jun-25
ENG190 HVAC Ductwork Mock-Up 30 07-May-25 10-Jun-25 HVAC Ductwork Mock-Up
ENG200 Electrical Panel Mock-Up 30 07-May-25 10-Jun-25 Electrical Panel Mock-Up
ENG210 Fire Fighting Mock-Up 30 07-May-25 10-Jun-25 Fire Fighting Mock-Up
Review and Approval Durations 60 27-Apr-25 05-Jul-25
ENG220 Shop Drawing Approv al 60 27-Apr-25 05-Jul-25 Shop Drawing Approv al
ENG230 Material Approv al 60 27-Apr-25 05-Jul-25 Material Approv al
ENG240 Mock-Up Approv al 30 24-May-25 26-Jun-25 Mock-Up Approv al
Procurement 188 13-Apr-25 17-Nov-25

All Areas 188 13-Apr-25 17-Nov-25


All Zones 188 13-Apr-25 17-Nov-25
Procurement of Sub-Consultants, Sub-Contractors, and Suppliers 45 18-Jun-25 09-Aug-25
ENG250 Pre-Qualification of Vendors 30 18-Jun-25 22-Jul-25 Pre-Qualification of Vendors
ENG260 Contract Awards 30 06-Jul-25 09-Aug-25 Contract Awards
Major Material Purchase Orders (POs) 109 08-May-25 11-Sep-25
ENG270 PO Issuance 90 08-May-25 20-Aug-25 PO Issuance
ENG290 Material Delivery to Site 90 25-May-25 06-Sep-25 Material Delivery to Site
ENG280 Inspection and Quality Review 90 31-May-25 11-Sep-25 Inspection and Quality Review
Long Lead Items and Identification of Early Awards Dates 188 13-Apr-25 17-Nov-25
ENG300 Identify Long-Lead Items 7 13-Apr-25 20-Apr-25 Identify Long-Lead Items
ENG310 Early Procurement for Long-Lead Items 21 21-Apr-25 14-May-25 Early Procurement for Long-Lead Items
ENG320 Manufacturing Progress Monitoring 40 15-May-25 30-Jun-25 Manufacturing Progress Monitoring
ENG330 Delivery of Long-Lead Items 120 01-Jul-25 17-Nov-25 Delivery of Long-Lead Items
Expediting Strategy and Resources 75 13-Apr-25 08-Jul-25
ENG340 Assign Expediting Team 7 13-Apr-25 20-Apr-25 Assign Expediting Team
ENG350 Vendor Communication Schedule 14 21-Apr-25 06-May-25 Vendor Communication Schedule
ENG360 Progress Reports 40 07-May-25 22-Jun-25 Progress Reports
ENG370 Escalation Plan 14 23-Jun-25 08-Jul-25 Escalation Plan
Delivery Times in Support of Construction 111 13-Apr-25 19-Aug-25
ENG380 Delivery Schedule Development 7 13-Apr-25 20-Apr-25 Delivery Schedule Development
ENG390 On-Site Storage Preparation 14 21-Apr-25 06-May-25 On-Site Storage Preparation
ENG400 Delivery Coordination with Sub-Contractors 30 07-May-25 10-Jun-25 Delivery Coordination with Sub-Contractors
ENG410 Inspection at Delivery 60 11-Jun-25 19-Aug-25 Inspection at Delivery
Construction (MEP Work) 378 27-Apr-25 11-Jul-26

Academic Core 295 27-Apr-25 05-Apr-26


Zone 05 (KSU-05) 275 27-Apr-25 12-Mar-26
Basemnet 2 115 27-Apr-25 07-Sep-25
10000 E/M 1st fix in block walls 40 27-Apr-25 11-Jun-25 E/M 1st fix in block walls
10010 E/M 1st fix in under tiles 40 27-Apr-25 11-Jun-25 E/M 1st fix in under tiles

Actual Level of Effort Critical Remaining Work Page 1 of 6 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
King Salman Knowledge District (KSKD) – MEP PACKAGE 1 - Salman University Subcontract Classic Schedule Layout 15-Dec-24 17:15
Activity ID Activity Name Original Start Finish 2025 2026
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Duration
10020 Electrical 2nd fix 80 26-May-25 26-Aug-25 Electrical 2nd fix
10030 Mechanical & HVAC 2nd fix 80 26-May-25 26-Aug-25 Mechanical & HVAC 2nd fix
10040 Electrical final fix 60 30-Jun-25 07-Sep-25 Electrical final fix
10050 Mechanical & HVAC final fix 60 30-Jun-25 07-Sep-25 Mechanical & HVAC final fix
Basement 1 115 12-Jun-25 23-Oct-25
10060 E/M 1st fix in block walls 40 12-Jun-25 28-Jul-25 E/M 1st fix in block walls
10070 E/M 1st fix in under tiles 40 12-Jun-25 28-Jul-25 E/M 1st fix in under tiles
10080 Electrical 2nd fix 80 12-Jul-25 12-Oct-25 Electrical 2nd fix
10090 Mechanical & HVAC 2nd fix 80 12-Jul-25 12-Oct-25 Mechanical & HVAC 2nd fix
10100 Electrical final fix 60 16-Aug-25 23-Oct-25 Electrical final fix
10110 Mechanical & HVAC final fix 60 16-Aug-25 23-Oct-25 Mechanical & HVAC final fix
Ground Floor 115 29-Jul-25 09-Dec-25
10120 E/M 1st fix in block walls 40 29-Jul-25 13-Sep-25 E/M 1st fix in block walls
10130 E/M 1st fix in under tiles 40 29-Jul-25 13-Sep-25 E/M 1st fix in under tiles
10140 Electrical 2nd fix 80 27-Aug-25 27-Nov-25 Electrical 2nd fix
10150 Mechanical & HVAC 2nd fix 80 27-Aug-25 27-Nov-25 Mechanical & HVAC 2nd fix
10160 Electrical final fix 60 01-Oct-25 09-Dec-25 Electrical final fix
10170 Mechanical & HVAC final fix 60 01-Oct-25 09-Dec-25 Mechanical & HVAC final fix
First Floor 115 14-Sep-25 25-Jan-26
10180 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
10190 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
10200 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
10210 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
10220 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
10230 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
Second Floor 115 30-Oct-25 12-Mar-26
10240 E/M 1st fix in block walls 40 30-Oct-25 15-Dec-25 E/M 1st fix in block walls
10250 E/M 1st fix in under tiles 40 30-Oct-25 15-Dec-25 E/M 1st fix in under tiles
10260 Electrical 2nd fix 80 29-Nov-25 01-Mar-26 Electrical 2nd fix
10270 Mechanical & HVAC 2nd fix 80 29-Nov-25 01-Mar-26 Mechanical & HVAC 2nd fix
10280 Electrical final fix 60 03-Jan-26 12-Mar-26 Electrical final fix
10290 Mechanical & HVAC final fix 60 03-Jan-26 12-Mar-26 Mechanical & HVAC final fix
Zone 06 (KSU-06) 235 27-Apr-25 25-Jan-26
Basement 1 115 27-Apr-25 07-Sep-25
10300 E/M 1st fix in block walls 40 27-Apr-25 11-Jun-25 E/M 1st fix in block walls
10310 E/M 1st fix in under tiles 40 27-Apr-25 11-Jun-25 E/M 1st fix in under tiles
10320 Electrical 2nd fix 80 26-May-25 26-Aug-25 Electrical 2nd fix
10330 Mechanical & HVAC 2nd fix 80 26-May-25 26-Aug-25 Mechanical & HVAC 2nd fix
10340 Electrical final fix 60 30-Jun-25 07-Sep-25 Electrical final fix
10350 Mechanical & HVAC final fix 60 30-Jun-25 07-Sep-25 Mechanical & HVAC final fix
Ground Floor 115 12-Jun-25 23-Oct-25
10360 E/M 1st fix in block walls 40 12-Jun-25 28-Jul-25 E/M 1st fix in block walls
10370 E/M 1st fix in under tiles 40 12-Jun-25 28-Jul-25 E/M 1st fix in under tiles
10380 Electrical 2nd fix 80 12-Jul-25 12-Oct-25 Electrical 2nd fix
10390 Mechanical & HVAC 2nd fix 80 12-Jul-25 12-Oct-25 Mechanical & HVAC 2nd fix
10400 Electrical final fix 60 16-Aug-25 23-Oct-25 Electrical final fix
10410 Mechanical & HVAC final fix 60 16-Aug-25 23-Oct-25 Mechanical & HVAC final fix
First Floor 115 29-Jul-25 09-Dec-25
10420 E/M 1st fix in block walls 40 29-Jul-25 13-Sep-25 E/M 1st fix in block walls
10430 E/M 1st fix in under tiles 40 29-Jul-25 13-Sep-25 E/M 1st fix in under tiles
10440 Electrical 2nd fix 80 27-Aug-25 27-Nov-25 Electrical 2nd fix
10450 Mechanical & HVAC 2nd fix 80 27-Aug-25 27-Nov-25 Mechanical & HVAC 2nd fix
10460 Electrical final fix 60 01-Oct-25 09-Dec-25 Electrical final fix
10470 Mechanical & HVAC final fix 60 01-Oct-25 09-Dec-25 Mechanical & HVAC final fix
Second Floor 115 14-Sep-25 25-Jan-26
10480 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
10490 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
10500 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
10510 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
10520 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
10530 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
Zone 07 (KSU-07) 235 12-Jun-25 12-Mar-26

Actual Level of Effort Critical Remaining Work Page 2 of 6 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
King Salman Knowledge District (KSKD) – MEP PACKAGE 1 - Salman University Subcontract Classic Schedule Layout 15-Dec-24 17:15
Activity ID Activity Name Original Start Finish 2025 2026
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Duration
Basement 1 115 12-Jun-25 23-Oct-25
10540 E/M 1st fix in block walls 40 12-Jun-25 28-Jul-25 E/M 1st fix in block walls
10550 E/M 1st fix in under tiles 40 12-Jun-25 28-Jul-25 E/M 1st fix in under tiles
10560 Electrical 2nd fix 80 12-Jul-25 12-Oct-25 Electrical 2nd fix
10570 Mechanical & HVAC 2nd fix 80 12-Jul-25 12-Oct-25 Mechanical & HVAC 2nd fix
10580 Electrical final fix 60 16-Aug-25 23-Oct-25 Electrical final fix
10590 Mechanical & HVAC final fix 60 16-Aug-25 23-Oct-25 Mechanical & HVAC final fix
Ground Floor 115 29-Jul-25 09-Dec-25
10600 E/M 1st fix in block walls 40 29-Jul-25 13-Sep-25 E/M 1st fix in block walls
10610 E/M 1st fix in under tiles 40 29-Jul-25 13-Sep-25 E/M 1st fix in under tiles
10620 Electrical 2nd fix 80 27-Aug-25 27-Nov-25 Electrical 2nd fix
10630 Mechanical & HVAC 2nd fix 80 27-Aug-25 27-Nov-25 Mechanical & HVAC 2nd fix
10640 Electrical final fix 60 01-Oct-25 09-Dec-25 Electrical final fix
10650 Mechanical & HVAC final fix 60 01-Oct-25 09-Dec-25 Mechanical & HVAC final fix
First Floor 115 14-Sep-25 25-Jan-26
10660 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
10670 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
10680 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
10690 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
10700 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
10710 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
Second Floor 115 30-Oct-25 12-Mar-26
10720 E/M 1st fix in block walls 40 30-Oct-25 15-Dec-25 E/M 1st fix in block walls
10730 E/M 1st fix in under tiles 40 30-Oct-25 15-Dec-25 E/M 1st fix in under tiles
10740 Electrical 2nd fix 80 29-Nov-25 01-Mar-26 Electrical 2nd fix
10750 Mechanical & HVAC 2nd fix 80 29-Nov-25 01-Mar-26 Mechanical & HVAC 2nd fix
10760 Electrical final fix 60 03-Jan-26 12-Mar-26 Electrical final fix
10770 Mechanical & HVAC final fix 60 03-Jan-26 12-Mar-26 Mechanical & HVAC final fix
Zone 04 (KSU-04) 255 12-Jun-25 05-Apr-26
Basement 1 115 12-Jun-25 23-Oct-25
10780 E/M 1st fix in block walls 40 12-Jun-25 28-Jul-25 E/M 1st fix in block walls
10790 E/M 1st fix in under tiles 40 12-Jun-25 28-Jul-25 E/M 1st fix in under tiles
10800 Electrical 2nd fix 80 12-Jul-25 12-Oct-25 Electrical 2nd fix
10810 Mechanical & HVAC 2nd fix 80 12-Jul-25 12-Oct-25 Mechanical & HVAC 2nd fix
10820 Electrical final fix 60 16-Aug-25 23-Oct-25 Electrical final fix
10830 Mechanical & HVAC final fix 60 16-Aug-25 23-Oct-25 Mechanical & HVAC final fix
Ground Floor 115 29-Jul-25 09-Dec-25
10840 E/M 1st fix in block walls 40 29-Jul-25 13-Sep-25 E/M 1st fix in block walls
10850 E/M 1st fix in under tiles 40 29-Jul-25 13-Sep-25 E/M 1st fix in under tiles
10860 Electrical 2nd fix 80 27-Aug-25 27-Nov-25 Electrical 2nd fix
10870 Mechanical & HVAC 2nd fix 80 27-Aug-25 27-Nov-25 Mechanical & HVAC 2nd fix
10880 Electrical final fix 60 01-Oct-25 09-Dec-25 Electrical final fix
10890 Mechanical & HVAC final fix 60 01-Oct-25 09-Dec-25 Mechanical & HVAC final fix
First Floor 115 14-Sep-25 25-Jan-26
10900 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
10910 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
10920 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
10930 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
10940 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
10950 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
Second Floor 115 30-Oct-25 12-Mar-26
10960 E/M 1st fix in block walls 40 30-Oct-25 15-Dec-25 E/M 1st fix in block walls
10970 E/M 1st fix in under tiles 40 30-Oct-25 15-Dec-25 E/M 1st fix in under tiles
10980 Electrical 2nd fix 80 29-Nov-25 01-Mar-26 Electrical 2nd fix
10990 Mechanical & HVAC 2nd fix 80 29-Nov-25 01-Mar-26 Mechanical & HVAC 2nd fix
11000 Electrical final fix 60 03-Jan-26 12-Mar-26 Electrical final fix
11010 Mechanical & HVAC final fix 60 03-Jan-26 12-Mar-26 Mechanical & HVAC final fix
Roof Floor 95 16-Dec-25 05-Apr-26
11020 E/M 1st fix in block walls 40 16-Dec-25 31-Jan-26 E/M 1st fix in block walls
11030 E/M 1st fix in under tiles 40 16-Dec-25 31-Jan-26 E/M 1st fix in under tiles
11040 Electrical 2nd fix 40 20-Jan-26 07-Mar-26 Electrical 2nd fix
11050 Mechanical & HVAC 2nd fix 40 20-Jan-26 07-Mar-26 Mechanical & HVAC 2nd fix

Actual Level of Effort Critical Remaining Work Page 3 of 6 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
King Salman Knowledge District (KSKD) – MEP PACKAGE 1 - Salman University Subcontract Classic Schedule Layout 15-Dec-24 17:15
Activity ID Activity Name Original Start Finish 2025 2026
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Duration
11060 Electrical final fix 40 18-Feb-26 05-Apr-26 Electrical final fix
11070 Mechanical & HVAC final fix 40 18-Feb-26 05-Apr-26 Mechanical & HVAC final fix
Health & Wellness 255 29-Jul-25 21-May-26
Zone 08 (KSU-08) 255 29-Jul-25 21-May-26
Basement 1 115 29-Jul-25 09-Dec-25
11080 E/M 1st fix in block walls 40 29-Jul-25 13-Sep-25 E/M 1st fix in block walls
11090 E/M 1st fix in under tiles 40 29-Jul-25 13-Sep-25 E/M 1st fix in under tiles
11100 Electrical 2nd fix 80 27-Aug-25 27-Nov-25 Electrical 2nd fix
11110 Mechanical & HVAC 2nd fix 80 27-Aug-25 27-Nov-25 Mechanical & HVAC 2nd fix
11120 Electrical final fix 60 01-Oct-25 09-Dec-25 Electrical final fix
11130 Mechanical & HVAC final fix 60 01-Oct-25 09-Dec-25 Mechanical & HVAC final fix
Ground Floor 115 14-Sep-25 25-Jan-26
11140 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
11150 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
11160 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
11170 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
11180 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
11190 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
First Floor 115 30-Oct-25 12-Mar-26
11200 E/M 1st fix in block walls 40 30-Oct-25 15-Dec-25 E/M 1st fix in block walls
11210 E/M 1st fix in under tiles 40 30-Oct-25 15-Dec-25 E/M 1st fix in under tiles
11220 Electrical 2nd fix 80 29-Nov-25 01-Mar-26 Electrical 2nd fix
11230 Mechanical & HVAC 2nd fix 80 29-Nov-25 01-Mar-26 Mechanical & HVAC 2nd fix
11240 Electrical final fix 60 03-Jan-26 12-Mar-26 Electrical final fix
11250 Mechanical & HVAC final fix 60 03-Jan-26 12-Mar-26 Mechanical & HVAC final fix
Second Floor 115 16-Dec-25 28-Apr-26
11260 E/M 1st fix in block walls 40 16-Dec-25 31-Jan-26 E/M 1st fix in block walls
11270 E/M 1st fix in under tiles 40 16-Dec-25 31-Jan-26 E/M 1st fix in under tiles
11280 Electrical 2nd fix 80 14-Jan-26 16-Apr-26 Electrical 2nd fix
11290 Mechanical & HVAC 2nd fix 80 14-Jan-26 16-Apr-26 Mechanical & HVAC 2nd fix
11300 Electrical final fix 60 18-Feb-26 28-Apr-26 Electrical final fix
11310 Mechanical & HVAC final fix 60 18-Feb-26 28-Apr-26 Mechanical & HVAC final fix
Roof Floor 95 01-Feb-26 21-May-26
11320 E/M 1st fix in block walls 40 01-Feb-26 18-Mar-26 E/M 1st fix in block walls
11330 E/M 1st fix in under tiles 40 01-Feb-26 18-Mar-26 E/M 1st fix in under tiles
11340 Electrical 2nd fix 40 08-Mar-26 22-Apr-26 Electrical 2nd fix
11350 Mechanical & HVAC 2nd fix 40 08-Mar-26 22-Apr-26 Mechanical & HVAC 2nd fix
11360 Electrical final fix 40 06-Apr-26 21-May-26 Electrical final fix
11370 Mechanical & HVAC final fix 40 06-Apr-26 21-May-26 Mechanical & HVAC final fix
University Hub 298 29-Jul-25 11-Jul-26
Zone 01 (KSU-01) 255 29-Jul-25 21-May-26
Basement 1 115 29-Jul-25 09-Dec-25
11380 E/M 1st fix in block walls 40 29-Jul-25 13-Sep-25 E/M 1st fix in block walls
11390 E/M 1st fix in under tiles 40 29-Jul-25 13-Sep-25 E/M 1st fix in under tiles
11400 Electrical 2nd fix 80 27-Aug-25 27-Nov-25 Electrical 2nd fix
11410 Mechanical & HVAC 2nd fix 80 27-Aug-25 27-Nov-25 Mechanical & HVAC 2nd fix
11420 Electrical final fix 60 01-Oct-25 09-Dec-25 Electrical final fix
11430 Mechanical & HVAC final fix 60 01-Oct-25 09-Dec-25 Mechanical & HVAC final fix
Ground Floor 115 14-Sep-25 25-Jan-26
11440 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
11450 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
11460 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
11470 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
11480 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
11490 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
First Floor 115 30-Oct-25 12-Mar-26
11500 E/M 1st fix in block walls 40 30-Oct-25 15-Dec-25 E/M 1st fix in block walls
11510 E/M 1st fix in under tiles 40 30-Oct-25 15-Dec-25 E/M 1st fix in under tiles
11520 Electrical 2nd fix 80 29-Nov-25 01-Mar-26 Electrical 2nd fix
11530 Mechanical & HVAC 2nd fix 80 29-Nov-25 01-Mar-26 Mechanical & HVAC 2nd fix
11540 Electrical final fix 60 03-Jan-26 12-Mar-26 Electrical final fix
11550 Mechanical & HVAC final fix 60 03-Jan-26 12-Mar-26 Mechanical & HVAC final fix

Actual Level of Effort Critical Remaining Work Page 4 of 6 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
King Salman Knowledge District (KSKD) – MEP PACKAGE 1 - Salman University Subcontract Classic Schedule Layout 15-Dec-24 17:15
Activity ID Activity Name Original Start Finish 2025 2026
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Duration
Second Floor 115 16-Dec-25 28-Apr-26
11560 E/M 1st fix in block walls 40 16-Dec-25 31-Jan-26 E/M 1st fix in block walls
11570 E/M 1st fix in under tiles 40 16-Dec-25 31-Jan-26 E/M 1st fix in under tiles
11580 Electrical 2nd fix 80 14-Jan-26 16-Apr-26 Electrical 2nd fix
11590 Mechanical & HVAC 2nd fix 80 14-Jan-26 16-Apr-26 Mechanical & HVAC 2nd fix
11600 Electrical final fix 60 18-Feb-26 28-Apr-26 Electrical final fix
11610 Mechanical & HVAC final fix 60 18-Feb-26 28-Apr-26 Mechanical & HVAC final fix
Roof Floor 95 01-Feb-26 21-May-26
11620 E/M 1st fix in block walls 40 01-Feb-26 18-Mar-26 E/M 1st fix in block walls
11630 E/M 1st fix in under tiles 40 01-Feb-26 18-Mar-26 E/M 1st fix in under tiles
11640 Electrical 2nd fix 40 08-Mar-26 22-Apr-26 Electrical 2nd fix
11650 Mechanical & HVAC 2nd fix 40 08-Mar-26 22-Apr-26 Mechanical & HVAC 2nd fix
11660 Electrical final fix 40 06-Apr-26 21-May-26 Electrical final fix
11670 Mechanical & HVAC final fix 40 06-Apr-26 21-May-26 Mechanical & HVAC final fix
Zone 02 (KSU-02) 255 14-Sep-25 07-Jul-26
Basement 1 115 14-Sep-25 25-Jan-26
11680 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
11690 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
11700 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
11710 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
11720 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
11730 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
Ground Floor 115 30-Oct-25 12-Mar-26
11740 E/M 1st fix in block walls 40 30-Oct-25 15-Dec-25 E/M 1st fix in block walls
11750 E/M 1st fix in under tiles 40 30-Oct-25 15-Dec-25 E/M 1st fix in under tiles
11760 Electrical 2nd fix 80 29-Nov-25 01-Mar-26 Electrical 2nd fix
11770 Mechanical & HVAC 2nd fix 80 29-Nov-25 01-Mar-26 Mechanical & HVAC 2nd fix
11780 Electrical final fix 60 03-Jan-26 12-Mar-26 Electrical final fix
11790 Mechanical & HVAC final fix 60 03-Jan-26 12-Mar-26 Mechanical & HVAC final fix
First Floor 115 16-Dec-25 28-Apr-26
11800 E/M 1st fix in block walls 40 16-Dec-25 31-Jan-26 E/M 1st fix in block walls
11810 E/M 1st fix in under tiles 40 16-Dec-25 31-Jan-26 E/M 1st fix in under tiles
11820 Electrical 2nd fix 80 14-Jan-26 16-Apr-26 Electrical 2nd fix
11830 Mechanical & HVAC 2nd fix 80 14-Jan-26 16-Apr-26 Mechanical & HVAC 2nd fix
11840 Electrical final fix 60 18-Feb-26 28-Apr-26 Electrical final fix
11850 Mechanical & HVAC final fix 60 18-Feb-26 28-Apr-26 Mechanical & HVAC final fix
Second Floor 115 01-Feb-26 14-Jun-26
11860 E/M 1st fix in block walls 40 01-Feb-26 18-Mar-26 E/M 1st fix in block walls
11870 E/M 1st fix in under tiles 40 01-Feb-26 18-Mar-26 E/M 1st fix in under tiles
11880 Electrical 2nd fix 80 02-Mar-26 02-Jun-26 Electrical 2nd fix
11890 Mechanical & HVAC 2nd fix 80 02-Mar-26 02-Jun-26 Mechanical & HVAC 2nd fix
11900 Electrical final fix 60 06-Apr-26 14-Jun-26 Electrical final fix
11910 Mechanical & HVAC final fix 60 06-Apr-26 14-Jun-26 Mechanical & HVAC final fix
Roof Floor 95 19-Mar-26 07-Jul-26
11920 E/M 1st fix in block walls 40 19-Mar-26 04-May-26 E/M 1st fix in block walls
11930 E/M 1st fix in under tiles 40 19-Mar-26 04-May-26 E/M 1st fix in under tiles
11940 Electrical 2nd fix 40 23-Apr-26 08-Jun-26 Electrical 2nd fix
11950 Mechanical & HVAC 2nd fix 40 23-Apr-26 08-Jun-26 Mechanical & HVAC 2nd fix
11960 Electrical final fix 40 23-May-26 07-Jul-26 Electrical final fix
11970 Mechanical & HVAC final fix 40 23-May-26 07-Jul-26 Mechanical & HVAC final fix
Zone 03 (KSU-03) 258 14-Sep-25 11-Jul-26
Basement 1 115 14-Sep-25 25-Jan-26
11980 E/M 1st fix in block walls 40 14-Sep-25 29-Oct-25 E/M 1st fix in block walls
11990 E/M 1st fix in under tiles 40 14-Sep-25 29-Oct-25 E/M 1st fix in under tiles
12000 Electrical 2nd fix 80 13-Oct-25 13-Jan-26 Electrical 2nd fix
12010 Mechanical & HVAC 2nd fix 80 13-Oct-25 13-Jan-26 Mechanical & HVAC 2nd fix
12020 Electrical final fix 60 17-Nov-25 25-Jan-26 Electrical final fix
12030 Mechanical & HVAC final fix 60 17-Nov-25 25-Jan-26 Mechanical & HVAC final fix
Ground Floor 115 30-Oct-25 12-Mar-26
12040 E/M 1st fix in block walls 40 30-Oct-25 15-Dec-25 E/M 1st fix in block walls
12050 E/M 1st fix in under tiles 40 30-Oct-25 15-Dec-25 E/M 1st fix in under tiles
12060 Electrical 2nd fix 80 29-Nov-25 01-Mar-26 Electrical 2nd fix

Actual Level of Effort Critical Remaining Work Page 5 of 6 TASK filter: All Activities
Remaining Work Milestone © Oracle Corporation
King Salman Knowledge District (KSKD) – MEP PACKAGE 1 - Salman University Subcontract Classic Schedule Layout 15-Dec-24 17:15
Activity ID Activity Name Original Start Finish 2025 2026
Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Duration
12070 Mechanical & HVAC 2nd fix 80 29-Nov-25 01-Mar-26 Mechanical & HVAC 2nd fix
12080 Electrical final fix 60 03-Jan-26 12-Mar-26 Electrical final fix
12090 Mechanical & HVAC final fix 60 03-Jan-26 12-Mar-26 Mechanical & HVAC final fix
First Floor 115 16-Dec-25 28-Apr-26
12100 E/M 1st fix in block walls 40 16-Dec-25 31-Jan-26 E/M 1st fix in block walls
12110 E/M 1st fix in under tiles 40 16-Dec-25 31-Jan-26 E/M 1st fix in under tiles
12120 Electrical 2nd fix 80 14-Jan-26 16-Apr-26 Electrical 2nd fix
12130 Mechanical & HVAC 2nd fix 80 14-Jan-26 16-Apr-26 Mechanical & HVAC 2nd fix
12140 Electrical final fix 60 18-Feb-26 28-Apr-26 Electrical final fix
12150 Mechanical & HVAC final fix 60 18-Feb-26 28-Apr-26 Mechanical & HVAC final fix
Second Floor 118 01-Feb-26 17-Jun-26
12160 E/M 1st fix in block walls 43 01-Feb-26 22-Mar-26 E/M 1st fix in block walls
12170 E/M 1st fix in under tiles 43 01-Feb-26 22-Mar-26 E/M 1st fix in under tiles
12180 Electrical 2nd fix 80 05-Mar-26 06-Jun-26 Electrical 2nd fix
12190 Mechanical & HVAC 2nd fix 80 05-Mar-26 06-Jun-26 Mechanical & HVAC 2nd fix
12200 Electrical final fix 60 09-Apr-26 17-Jun-26 Electrical final fix
12210 Mechanical & HVAC final fix 60 09-Apr-26 17-Jun-26 Mechanical & HVAC final fix
Roof Floor 95 23-Mar-26 11-Jul-26
12220 E/M 1st fix in block walls 40 23-Mar-26 07-May-26 E/M 1st fix in block walls
12230 E/M 1st fix in under tiles 40 23-Mar-26 07-May-26 E/M 1st fix in under tiles
12240 Electrical 2nd fix 40 27-Apr-26 11-Jun-26 Electrical 2nd fix
12250 Mechanical & HVAC 2nd fix 40 27-Apr-26 11-Jun-26 Mechanical & HVAC 2nd fix
12260 Electrical final fix 40 26-May-26 11-Jul-26 Electrical final fix
12270 Mechanical & HVAC final fix 40 26-May-26 11-Jul-26 Mechanical & HVAC final fix
12280 Finish Of Construction Works Milestone 0 11-Jul-26* Finish Of Construction Works Milestone,
Commissioning and Close-out 88 26-Aug-26 06-Dec-26

All Areas 88 26-Aug-26 06-Dec-26


All Zones 88 26-Aug-26 06-Dec-26
All Floors 88 26-Aug-26 06-Dec-26
Comm100 Systems testing and commissioning 60 26-Aug-26 03-Nov-26 Systems testing and commissi
Comm110 permanent power & water required 0 26-Aug-26* permanent power & water required, 26-Aug-26*
Comm130 Systems integration commissionin 14 04-Nov-26 19-Nov-26 Systems integration com
Comm160 Project close-out including documentation and spare parts14 04-Nov-26 19-Nov-26 Project close-out includin
Comm200 Tests after completion 14 04-Nov-26 19-Nov-26 Tests after completion
Comm140 Tests of completion 14 21-Nov-26 06-Dec-26 Tests of completio
Comm170 Demobilisation 14 21-Nov-26 06-Dec-26 Demobilisation
Comm190 Defects/snagging notification period 14 21-Nov-26 06-Dec-26 Defects/snagging
Comm150 Taking-Over 0 06-Dec-26 Taking-Over,

Actual Level of Effort Critical Remaining Work Page 6 of 6 TASK filter: All Activities