Incor Newsletter q
Incor Newsletter q
Tower A
Activity Work Progress
No Oct-24 Nov-24
Block work floors wise status : Block work Floors wise status :
a. 3rd to 23rd floor block work a. 3rd to 23rd floor block work
Completed. Completed.
b. 2nd and 1st floor 80% block work b. 2nd and 1st floor 90% block Block works only 80%
Brickwork completed. work completed. canged as 90%, but no
2 & Plastering work floor wise status : Plastering work floorwise status : works going on.
Plastering a. 18th to 12th floor, 6th to 10th a. 18th to 12th floor, 6th to 10th Plsting Works no changes,
floor plastring works completed. floor plastring works completed in progress.
b. 2nd, 3rd, 4th, 5th,11th floor and b. 1st to 5th floors, 11th floor and
19th floor Plastering works in 19th to 23rd floors Plastering works
progress. in progress.