Birzeit University

Department of Civil and Environmental Engineering


Term project
Professional Practice and Projects Management (ENCE4341)
First Semester 2022/2023

The goal of this project is to allow students to acquire a professional life experience. This real-life
project will allow students to practice professional responsibilities by reading drawings and other
contract documents. Acting as contractors, students will prepare a detailed schedule of the project
activities using Primavera software only. Project items include the following points:

1. Excavation and backfilling works


2. Concrete works
3. Stone works
4. Block works
5. Plastering works
6. Tiles works
7. Carpentry works
8. Steel and aluminum works
9. Painting works

Students should work in teams four students each team, to learn how to communicate effectively. Each
team must submit a detailed report showing all their work. The report should include the following
points:

1. Introduction (Why we use project planning 2- brief description of the software that you have
used) (5 %)
2. Assumptions (State the reasons for your assumptions). (3%)
3. Table that includes your quantities, and sample calculation of each item (excluding
excavation and backfilling works). (10%)
4. BOQ with the estimated quantities for the project items above excluding excavation and
backfilling work. (15 %)
5. Work breakdown structure (WBS) of the project using master format. (10%)
6. Using Primavera software Project Planning and Scheduling: i) a complete bar chart
showing activities names, durations, early start, early finish, late start, late finish,
predecessors, total float, and free float. Show the project’s critical path in a different pattern.
ii) An AON network showing activities names, durations, early start, early finish, late start,
late finish and total float. (25 %)
7. Price estimation for all the items above excluding excavation and backfilling works
assuming that the project overhead is 10% of the direct cost , general overhead is 6% of the
direct cost, and the profit is 15% of the total cost.(Note: You should use primavera
software to calculate the Total cost of the items. Also, you should print S-curve for the
Total cost of the calculated items using primavera (extra points) or excel, and you
should fill the prices for these items in the BOQ. (25 %)
8. Conclusions. (4%)
9. References (using Harvard style). (3%)
10. Appendices (secondary information if you want to support the main contents).
11. Soft copy of your software planning.

It should be noted that there will be a discussion on your work and it


will be calculated from your total project mark.

Project Planning and Scheduling Guidelines:


Each report is to be of professional quality and follow the following guidelines: The report must
be stapled in the upper left-hand corner, and have 1” margins at the top, bottom and on each side.
The paper must be typed using double-spaced lines. The type size must be clear and readily legible,
in a standard size of 12 points and please use Times New Roman for font type. Each report should
include a title page showing the names of each team members.

1. Calculate the quanttities that will help you to do the plan of the project and and estimate
the direct cost.

2. Break down the project into activities (perform a WBS). Prepare a list of all possible
activities.

2. Identify the logical relationships among project’s activities. Remember to answer the
following questions for each activity in the list:
a. What activity(ies) must be finished before the current one can start?
b. What activity(ies) must be constructed concurrently with the current one?
c. What activity(ies) must follow the current one?

3. Remove redundancy and prepare a schedule that includes all projects’ activities.

4. You have to assign the resources, i.e. material and crews to the plan.

5. Assume duration for each activity in the project based on the quantity that you have
calculated and the productivity (See Table 1 below that shows the productivity of
some items (you can use more than one crew), and you should find the productivity
of the remaining items). Bearing in mind that the total project duration is assumed to be
300 Calendar days, Friday and Saturday are holiday, and the project will start on
04/06/2023. For the excavation and backfilling assume that it will take 18 days.
Table 1: Productivity for Some of the Activities

Activity Productivity Crew


Shuttering 30 m2/day 1 General+1 Skilled
Steel Fixing (footings, shear walls...) 600 kg/day 1 General+1 Skilled
Steel Fixing (Slabs) 1000 kg/day 1 General+1 Skilled
Concrete Pouring 140 m3/day 3 General
De-shuttering 40 m2/day 1 General
Blocks building 30 m2/day 1 General
Scaffolding installation 30 No./day 1 General
Stone building 30 m2/day 1 Skilled+ 1 General
Blocks behind stone 9 m2/day 1 General
Plastering 20 m2/day 1 Skilled+ 1 General
Painting 35 m2/day 1 Skilled+ 1General
Tiling 30 m2/day 1 Skilled+ 1 General

Submission of the final report

A Final report should be submitted on Tuesday 31/01/2023 on


Ritaj.