AHS-3 Data

Uploaded by

1si19pcv01
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views

AHS-3 Data

Uploaded by

1si19pcv01
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

Page 1 of 8

ANNEXURE -1
KARNATAKA STATE POLICE HOUSING & INFRASTRUCTURE DVELOPMENT
CORPORATION LIMITED
AHS-III DISTRICT WISE WORKS DETAILS
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date
BANGALORE RURAL DISTRICT
Bannerghatta, Ramachandra raju
1 12 PC & 2 SI Qtrs 12 2 14 132.95 120.10 15-Apr-09 14-Jan-10
Bangalore K
Doddaballa M/s Veeraswamy
2 24 PC & 2 SI Qtrs 24 2 26 223.70 230.54 23-Apr-09 22-Apr-10
pura Reddy & Sons
3 Hebbagodi 12 PC & 2 SI Qtrs 12 2 14 128.60 118.73 Nataraju B M 30-Apr-09 29-Jan-10
Krishnamurthy S
4 Nandagudi 18 PC Qtrs 18 18 148.90 135.08 23-Apr-09 21-Apr-10
K
M/s Sri Byrava
5 Rajanukunte 12 PC & 2 SI Qtrs 12 2 14 131.60 134.65 23-Apr-09 18-Jan-10
Civil Engg works
Dodda
20 PC & 2 SI Qtrs 20 2 22 194.50 189.97 Raghu T M 31-Dec-09 31-Jan-11
belavangala
6 Sinking additional
Dodda
Borewell to PC & SI 1* 2.77 2.46 Raghu T M 13-Dec-11 31-Dec-11
belavangala
Qtrs
Krishnamurthy S
7 Nandagudi 12 PC Qtrs 12 12 101.75 101.54 K / M/s G B 12-Jan-10 6-Jan-12
Enterprises
M/s Veeraswamy
8 Hosakote 12 PC & 4 SI Qtrs 12 4 16 304.85 323.64 P2 18-Jun-13 17-Sep-14
Reddy & Sons
TOTAL 122 14 136 1369.62 1356.72
BANGALORE URBAN DISTRICT
1 Devanahalli 10 PC Qtrs 10 10 90.00 72.52 Subba Reddy C H 20-Jul-08 31-Oct-09

2 Devanahalli 24 PC & 4 SI Qtrs 24 4 28 252.20 228.90 Nagabhushan P N 24-Jul-09 23-Jul-10

Frazer Town,
24 PC & 2 SI Qtrs 24 2 26 245.29 240.37 Kumar K 16-Sep-09 15-Apr-12
Bangalore
3 Solar Water Heating
Frazer Town, M/s Sapthagiri
system to 24 PC and 1* 9.41 9.56 16-May-12 14-Jun-12
Bangalore Enterprises
2 SI Quarters
4 Chikkajala 24 PC & 6 SI Qtrs 24 6 30 270.00 277.94 Nagabhushan P N 10-Jun-09 9-Jun-10
M/s Anantharaja
5 Kengeri 24 PC & 4 SI Qtrs 24 4 28 262.45 216.13 24-Feb-10 23-Aug-12
Constructions
Vidyaranyapur Veeraswamy
6 24 PC Qtrs 24 24 206.00 200.74 4-Feb-10 31-Dec-10
a Reddy & Sons
Audugodi, 24 PC & 4 SI Qtrs for M/s Surya
7 24 4 28 272.55 284.56 18-Mar-10 24-Oct-11
Bangalore CAR South Constructions
36 PC Qtrs at CAR Veeraswamy
8 Sampigehalli 36 36 317.20 312.70 3-Mar-10 2-May-11
North (Blk 1,2,3) Reddy & Sons
36 PC & 2 SI Qtrs at M/s S R
9 Sampigehalli 36 2 38 352.15 304.71 3-Mar-10 30-Nov-11
CAR North (Blk 4,5,6) Constructions
Coles Road M/s Jampana
10 12 PC Qtrs 12 12 168.00 148.38 P3 28-Jun-13 20-Aug-15
(Commercial Const Pvt Ltd
Street)
TOTAL 238 22 260 2445.25 2296.51
Page 2 of 8
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date
BELGAUM DISTRICT
24 PC & 2 SI Qtrs for M/s KMV Projects
1 Machhe 24 2 26 347.50 325.59 P2 7-Mar-13 6-Sep-14
2nd Btn, KSRP Ltd
M/s KMV Projects
2 Nesargi 12 PC & 2 SI Qtrs 12 2 14 242.00 225.02 P2 7-Mar-13 6-May-15
Ltd
M/s KMV Projects
3 Nesargi 12 PC & 2 SI Qtrs 12 2 14 241.00 243.51 P3 8-Aug-13 7-Oct-15
Ltd
TOTAL 48 6 54 830.50 794.12
BELLARY DISTRICT
1 Hosapete 24 PC & 4 SI Qtrs 24 4 28 228.50 213.89 Karikal V P 1-Apr-09 14-Jun-10
M/s V N
2 Bellary 36 PC & 4 SI Qtrs 36 4 40 318.25 298.62 9-Dec-09 15-Sep-11
Constructions
12 PC & 2 SI Qtrs for
3 Bellary 12 2 14 129.70 116.51 Basavarajappa C 29-Dec-09 28-Feb-11
Traffic PS
Yerriswamy
4 Torangal 12 PC Qtrs 12 12 105.75 91.08 8-Jan-10 31-Jan-11
Reddy
12 PC & 2 SI Qtrs for
5 Bellary 12 2 14 209.80 183.48 P2 Basavarajappa C 8-Mar-13 2-Feb-14
DAR
M/s Standard
6 Bellary 12 PC & 2 SI Qtrs 12 2 14 213.25 213.44 P3 Infratech India (P) 24-Jul-13 23-Jun-14
Ltd
TOTAL 108 14 122 1205.25 1117.03
BIDAR DISTRICT
1 Bidar 24 PC & 8 SI Qtrs 24 8 32 297.70 286.50 Bheem 19-Mar-09 3-Jul-10
12 PC Qtrs for Town,
2 Bidar 12 12 99.60 85.11 Kishore 23-Aug-10 29-Sep-11
Traffic & Market PS
3 Bidar 24 PC Qtrs for DAR 24 24 189.10 166.36 Gurunath Kollur 6-May-10 2-May-11
TOTAL 60 8 68 586.40 537.97
BIJAPUR DISTRICT
APMC, 12 PC Qtrs for APMC Ravi M
1 12 12 88.80 75.70 19-Mar-09 28-Feb-10
Bijapur Pol Stn Deshapande
12 PC & 1 SI Qtrs for
Bijapur 12 1 13 102.75 94.80 Mathapathi P C 19-Mar-09 15-Dec-09
DAR
2
Approach road for PC Shankar Gouda N
Bijapur 1* 5.72 5.50 11-Jul-11 30-Aug-11
Qtrs at DAR Hosamani
Gandhi
3 12 PC & 1 SI Qtrs 12 1 13 101.05 88.80 Deyagond R M 19-Mar-09 31-Dec-09
Chowk PS,
4 Bijapur
Bijapur 12 PC Qtrs for RPS 12 12 88.80 74.55 Patil R P 19-Mar-09 18-Jan-10
5 Bijapur 4 SI Qtrs for Wireless 4 4 49.60 43.00 Rudre Gowda B R 15-May-09 28-Dec-09
12 PC Qtrs for DAR &
6 Bijapur 12 12 105.25 88.13 Mathapathi P C 15-Mar-10 29-Mar-11
Wireless
Gol-Gumbuz, Ravi M
12 PC Qtrs 12 12 97.15 88.83 10-Mar-10 29-Mar-11
Bijapur Deshapande
7
12 PC Qtrs for Traffic
Bijapur 12 12 101.00 91.19 Deyagond R M 10-Mar-10 29-Mar-11
PS
Arikere, 12 PC (Block A1) & 2 M/s Standard
8 12 2 14 347.75 302.07 P2 14-Mar-13 13-Feb-14
Bijapur SI Qtrs for IRB Infratech (I) P Ltd
Arikere,
9 36 PC & 4 SI for IRB 36 4 40 621.80 644.34 P3 Eranna M 20-Jun-13 19-Aug-14
Bijapur
10 Indi 12 PC Qtrs 12 12 179.76 172.94 P3 Eranna M 27-Jun-13 26-May-14
11 Nidagundi 12 PC Qtrs 12 12 170.02 165.00 P3 Eranna M 27-Jun-13 4-Jul-14
TOTAL 156 12 168 2059.45 1934.86
Page 3 of 8
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date
CHAMARAJANAGAR DISTRICT
Chamaraja Maqsood Ali Khan
1 12 PC Qtrs (Block A) 12 12 108.10 104.08 17-Mar-09 2-Nov-09
nagar F
Chamaraja
2 12 PC Qtrs (Block B) 12 12 99.20 98.51 Sharavana D S 17-Mar-09 22-Dec-09
nagar
Chamaraja 12 PC Qtrs (Block - M/s Thirumala
3 12 12 97.90 87.66 20-Feb-10 28-Feb-11
nagar G) for RPS Constructions
Chamaraja 24 PC & 4 SI Qtrs
4 24 4 28 244.25 241.67 Sharavana D S 1-Feb-10 10-Aug-11
nagar (Block C&D) for DAR
Chamaraja 24 PC Qtrs (Group B) Maqsood Ali Khan
5 24 24 189.95 247.09 1-Feb-10 31-Jan-11
nagar for DAR F
Chamaraja M/s Jampana
6 24 PC Qtrs for DAR 24 24 311.66 235.52 P2 20-Feb-13 30-Nov-15
nagar Const Pvt Ltd
Chamaraja M/s Jampana
7 24 PC Qtrs for DAR 24 24 329.54 332.73 P3 11-Jul-13 28-Oct-16
nagar Const Pvt Ltd
TOTAL 132 4 136 1380.60 1347.25
CHIKKABALLAPUR DISTRICT
Venugopal Reddy
1 Dibburahalli 12 PC Qtrs 12 12 100.00 90.35 23-Apr-09 25-Jul-11
TN
Providing Solar Water M/s EMVEE Solar
2 Dibburahalli 1* 4.85 4.91 21-Jul-10 20-Aug-10
Heater to 12 PC Qtrs Systems Pvt Ltd
Manchena
3 6 PC Qtrs 6 6 56.35 43.90 Murali Babu V 23-Apr-09 16-Jun-10
halli
M/s Trivikrama
Nandi 5 PC Qtrs 5 5 62.12 41.68 3-May-11 27-Mar-12
Infrastructure
4
Supply, erection & M/s Sapthagiri
Nandi 1* 2.64 2.61 27-Jun-12 22-Jun-12
commissioning of Electricals
Chikkaballa 6 PC Qtrs for Town &
5 6 6 60.40 48.27 Chandrashekar 10-Mar-10 30-Nov-10
pur RPS
6 Chelur 6 PC Qtrs 6 6 56.75 48.15 Shekar B 2-Jan-10 1-Jul-10
Chikkaballa 24 PC & 4 SI Qtrs M/s N B Const
24 4 28 238.90 241.17 4-Mar-10 3-Mar-11
pur (Group A) for DAR Company
Chikkaballa 24 PC Qtrs (Group B) Veeraswamy
24 24 196.80 203.10 11-Mar-10 10-Mar-11
pur for DAR Reddy & Sons
7
Chikkaballa Sinking of additional
1* 6.60 3.22 Chandrashekar 9-Jan-12 8-Feb-12
pur Borewell and
Chikkaballa Supply, erection & M/s Raja
1* 6.60* 2.85 20-Jan-12 19-Feb-12
pur commissioning of Rajeshwari
8 Dibburahalli 8 PC Qtrs 8 8 70.00 64.96 Ravi Y O 11-Feb-10 10-Oct-10
Shiddalagatta
9 24 PC & 1 SI Qtrs 24 1 25 201.75 211.94 Ravi Y O 15-Mar-10 14-Mar-11
Town & Rural
Gudibande 4 PC Qtrs 4 4 49.40 37.69 Srinivasa K S 10-Feb-10 9-Jun-10
10 Compound wall in N,
Gudibande E & W Sides of the 1* 10.75 9.37 Srinivasa K S 23-Mar-12 22-Oct-12
Police Colony
TOTAL 119 5 124 1117.31 1054.17
CHIKMAGALUR DISTRICT
Koppa 12 PC Qtrs 12 12 114.20 108.69 Chandrashekar R 16-Mar-09 30-Aug-10
1 Providing permanent
Koppa 1* 9.40 0.58 Nagabhushan K R 26-Sep-11 25-Dec-11
water supply to Qtrs
Shringeri 20 PC & 2 SI Qtrs 20 2 22 220.70 215.70 Chandrashekar R 2-Apr-09 30-Sep-10
2 Providing permanent
Shringeri 1* 10.30 5.59 Jagadeesha K R 22-Sep-11 21-Dec-11
water supply to Qtrs
Page 4 of 8
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date

3 N R Pura 18 PC & 1 SI Qtrs 18 1 19 205.30 186.88 Nagabhushan K R 22-Feb-10 30-Apr-11

4 Koppa 6 PC Qtrs 6 6 63.75 51.96 Jagadeesha K R 22-Feb-10 30-Apr-11


5 Basavanahalli 12 PC Qtrs 12 12 173.41 153.91 P2 Chandrashekar R 18-Mar-13 15-Oct-14
6 Chikmagalur 12 PC Qtrs for DAR 12 12 173.41 156.94 P2 Chandrashekar R 5-Oct-13 30-Jan-15
7 Hariharapura 12 PC Qtrs 12 12 189.77 177.52 P2 Chandrashekar R 28-Mar-13 27-Nov-14
TOTAL 92 3 95 1160.24 1057.78
CHITRADURGA DISTRICT
1 Chitradurga 24 PC & 4 SI Qtrs 24 4 28 239.45 212.45 Ghouse Peer B M 9-Feb-09 6-Feb-10
DAR,
2 24 PC Qtrs 24 24 185.10 169.00 Ghouse Peer B M 8-Oct-09 30-Nov-10
Chitradurga
Nayakana
3 12 PC & 2 SI Qtrs 12 2 14 128.50 118.36 Siddappa M 1-Feb-10 30-Jun-11
hatti
TOTAL 60 6 66 553.05 499.81
DAKSHINA KANNADA DISTRICT
DAR,
1 24 PC Qtrs 24 24 221.20 197.79 Venkatesh G P 23-Mar-09 30-Jul-11
Mangalore
2 Bajpe 12 PC Qtrs 12 12 123.55 109.22 Clifford D'Souza 18-Jan-10 23-Oct-10
DAR,
3 12 PC Qtrs 12 12 118.50 106.53 Venkatesh G P 28-Aug-10 15-Mar-12
Mangalore
4 Puttur Rural 12 PC & 1 SI Qtrs 12 1 13 146.35 127.59 Krishne Gowda 3-Mar-10 24-Feb-12
5 Subramanya 12 PC Qtrs 12 12 132.60 115.50 Krishne Gowda 3-Mar-10 10-Feb-12
M/s Vittal
Vittla 12 PC Qtrs 12 12 125.00 112.62 1-Mar-10 31-May-11
Constructions
6 Construction of Septic
Goverdhan &
Vittala Tank (2Nos) & Soak 1* 16.10 15.51 3-Mar-14 24-Jun-14
Company
Pit to Qtrs
Raghuram Shetty
7 Venur 12 PC Qtrs 12 12 129.64 116.84 12-Apr-10 24-Oct-11
B
Pandeshwara
8 48 PC Qtrs 48 48 681.82 698.33 P2 Krishne Gowda 22-Mar-13 10-Sep-15
Mangalore
Krishne Gowda M
9 Attavara 12 PC Qtrs 12 12 174.49 170.93 P3 22-Jul-13 28-Mar-15
C
TOTAL 156 1 157 1869.25 1770.87
DAVANAGERE DISTRICT
1 Basavapatna 12 PC & 1 SI Qtrs 12 1 13 112.53 105.34 Chandrappa M S 13-Mar-09 12-Jan-10
2 Hadadi 12 PC Qtrs 12 12 102.85 88.86 Basavaraja B V 5-Mar-09 31-Dec-09
3 Jagalur 18 PC & 2 SI Qtrs 18 2 20 181.50 162.70 Basavaraja B V 15-Mar-10 28-Mar-11
4 Arasikere 12 PC Qtrs 12 12 106.86 98.34 Chandrappa M S 15-Jan-10 14-Nov-10
5 Honnali 16 PC & 2 SI Qtrs 16 2 18 299.60 244.19 P2 Manohar Y C 28-Feb-13 27-Jun-14
TOTAL 70 5 75 803.34 699.42
DHARWAD DISTRICT
36 PC & 6 SI Qtrs for
1 Rayapur 36 6 42 392.81 299.15 Betageri A S 9-Feb-09 8-Feb-10
2nd Btn
New CAR,
2 60 PC & 6 SI Qtrs 60 6 66 594.35 459.46 Betageri A S 9-Feb-09 7-Apr-10
Hubli
48 PC & 2 SI Qtrs for
Rayapur 48 2 50 445.30 337.93 Bhat G G 16-Nov-09 15-Jan-11
2nd Btn
Page 5 of 8
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date
Supply, Installation,
Testing & Commi-
M/s Nuetach Solar
3 Rayapur ssioning of Solar 1* 19.00 18.94 2-Jun-11 1-Jul-11
Systems Pvt Ltd
water Heater to 48 PC
Qtrs
Compound wall & Raju B
Rayapur 1* 61.08 40.78 12-Jul-12 28-Feb-13
Road works for 2nd Kariyannanavar
DAR, BtnPC
24 KSRP
& 1 SI Qtrs for
4 24 1 25 314.64 298.78 P2 Betageri A S 20-Jun-13 31-Dec-14
Dharwad Dharwad Sub-Urban
Bendigeri, M/s KMV Projects
5 24 PC & 2 SI Qtrs 24 2 26 388.00 413.21 P3 8-Aug-13 7-Oct-14
Hubli Ltd
TOTAL 192 17 209 2215.18 1868.25
GULBARGA DISTRICT
Bhimashankar S
1 Saidapur 12 PC & 1 SI Qtrs 12 1 13 113.40 91.72 19-Mar-09 30-Sep-10
Patil
Bheemashetty C
2 Saidapur 12 PC Qtrs 12 12 97.30 83.29 30-Apr-10 31-Aug-11
Para
3 Shahapur 12 PC Qtrs 12 12 98.80 81.72 Rudre Gowda B R 19-Mar-09 31-May-10
M/s Arun Kumar
4 Afzalpur 6 PC Qtrs 6 6 61.00 47.28 23-Apr-10 22-Jan-12
Patil & Co
TOTAL 42 1 43 370.50 304.01
HASSAN DISTRICT
1 B Katihalli 12 PC Qtrs (Block A) 12 12 98.10 81.14 Syed Sadiq 2-May-09 30-Apr-10
2 B Katihalli 12 PC Qtrs (Block B) 12 12 101.00 81.89 Syed Sadiq 2-May-09 30-Apr-10
Channaraya
3 12 PC Qtrs 12 12 102.95 86.21 Gopi 18-Mar-09 31-Mar-10
patna
24 PC Qtrs (Block A &
4 DAR, Hassan 24 24 192.30 182.47 Syed Sadiq 15-Mar-10 14-Mar-11
B)
24 PC Qtrs (Block C &
5 DAR, Hassan 24 24 192.00 183.55 Syed Sadiq 15-Mar-10 14-Mar-11
D)
24 PC Qtrs (for Town
6 B Katihalli 24 24 201.50 187.31 Subba Reddy U V 11-Feb-10 31-Mar-11
& Traffic PS- Blk
12 PC Qtrs for
7 B Katihalli Pension Mohalla & 12 12 102.65 92.84 Nagesh S K 11-Feb-10 3-Aug-11
Extn PS - Block E)
6 SI Qtrs for Town,
Traffic, Pension
B Katihalli 6 6 66.60 61.16 Subba Reddy U V 11-Feb-10 10-Jan-11
Mohalla, Extn PS &
8 DAR
Shifting of 11 KV line
B Katihalli for construction of 24 1* 0.949 0.91 Subba Reddy U V 28-Dec-11 31-Dec-11
PC & 6 SI Qtrs
9 Konanur 12 PC Qtrs 12 12 110.00 97.52 Gowrish H N 11-Feb-10 10-Mar-11
12 PC Qtrs for
10 Hassan 12 12 176.00 152.26 P2 Nataraju B M 25-Apr-13 24-Sep-15
Wireless
Shravana M/s Jampana
11 12 PC Qtrs 12 12 168.65 159.33 P3 14-Jun-13 31-Mar-15
belagola Const Pvt Ltd
TOTAL 156 6 162 1512.70 1366.59
Page 6 of 8
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date
HAVERI DISTRICT
60 PC Qtrs for 10th
1 Shiggaon 60 60 518.70 465.75 Betageri A S 9-Feb-09 3-Apr-10
Btn, KSRP
60 PC Qtrs for 10th
2 Shiggaon 60 60 534.60 364.44 Betageri A S 2-Apr-10 1-Jun-11
Btn, KSRP
TOTAL 120 0 120 1053.30 830.19
KOLAR DISTRICT
Bethaman M/s Palamaneni
1 12 PC Qtrs 12 12 98.45 100.77 31-Dec-09 15-Dec-10
gala Const Company
M/s Palamaneni
2 DAR, KGF 8 PC & 1 SI Qtrs 8 1 9 80.75 80.27 30-Dec-09 20-Dec-10
Const Company
M/s Palamaneni
3 DAR, KGF 12 PC Qtrs 12 12 98.25 103.84 30-Dec-09 20-Dec-10
Const Company
TOTAL 32 1 33 277.45 284.87
KOPPAL DISTRICT
72 PC & 8 SI Qtrs for
1 Hosahalli 72 8 80 600.05 632.88 Karikal V P 1-Sep-09 30-Jun-11
IRB Btn
Supply, Commission-
ing & Installation of M/s EMVEE Solar
Hosahalli 1* 30.60 31.01 21-Aug-10 19-Sep-10
Solar water Heater to Systems Pvt Ltd
72 PC Qtrs
2
Supply, Commission-
ing & Installation of M/s EMVEE Solar
Hosahalli 1* 5.10 5.14 21-Aug-10 4-Sep-10
Solar water Heater to Systems Pvt Ltd
8 SI Qtrs
3 Koppal 12 PC & 4 SI Qtrs 12 4 16 134.55 123.61 Patil V R 16-Mar-09 16-Mar-10
Gangavathi
4 12 PC Qtrs 12 12 107.50 94.97 Amaresh H 1-Feb-10 29-Nov-10
Town, Rural &
Traffic 60 PC & 8 SI Qtrs for
5 Hosahalli 60 8 68 605.85 579.04 Karikal V P 9-Mar-10 30-Aug-11
IRB Btn
12 PC Qtrs for IRB
6 Hosahalli 12 12 99.10 98.30 Karikal V P 17-Mar-10 31-Mar-11
Btn
36 PC & 6 SI Qtrs for
7 Hosahalli 36 6 42 591.75 534.90 P2 Eranna M 26-Feb-13 30-Jun-14
IRB
64 PC & 10 SI Qtrs for M/s Standard
8 Hosahalli 64 10 74 970.55 1046.60 P3 10-Jun-13 20-Aug-15
IRB Infratech India (P)
TOTAL Ltd
268 36 304 3145.05 3146.46
MANDYA DISTRICT

1 Bellur 12 PC Qtrs 12 12 99.78 91.31 Manje Gowda B N 15-Feb-10 30-Aug-11

Eswara kumar S
2 DAR, Mandya 12 PC Qtrs 12 12 97.60 87.69 20-Feb-10 4-Jul-11
N
Eswara kumar S
3 Nagamangala 12 PC Qtrs 12 12 98.05 87.94 20-Feb-10 30-Aug-11
N
TOTAL 36 0 36 295.43 266.94
MYSORE DISTRICT
Jalapuri,
12 SI Qtrs 12 12 144.00 126.43 Sharavana D S 18-Mar-09 17-Dec-09
Mysore
1 Providing Solar Water
Jalapuri, M/s EMVEE Solar
Heater to Block-A & B 1* 4.50 4.85 29-Jan-10 28-Feb-10
Mysore Lightings
SI Qtrs
Page 7 of 8
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date
Jyothinagar,
12 PC Qtrs 12 12 105.75 87.24 Sharavana D S 18-Mar-09 17-Dec-09
Mysore
2
Jyothinagar, Providing Solar Water M/s EMVEE Solar
1* 4.50 6.09 29-Jan-10 28-Feb-10
Mysore Heater to Block-A & B Lightings
3 Bylakuppe PC Qtrs
12 PC Qtrs 12 108.64 Sharavana D S 18-Mar-09 4-Dec-09
12 115.80
Hunsur 24 PC Qtrs 24 24 211.40 211.73 Sharavana D S 26-Feb-10 30-Jul-11
Providing additional
4 facilities (wash basin,
Hunsur 1* 1.68 1.70 Sharavana D S 6-Jul-12 31-Aug-12
mirror & towel rail) for
Qtrs
24 PC Qtrs for
Jyothinagar,
5 Narasimharaja & 24 24 205.40 187.75 Venkatesh D T 26-Feb-10 25-Feb-12
Mysore
Metagalli PS
24 PC Qtrs for
Jyothinagar,
6 Saraswathipuram & 24 24 196.60 184.13 Venkatesh D T 26-Feb-10 29-Feb-12
Mysore
Kuvempunagar PS
Jalapuri, 24 PC Qtrs for CAR,
7 24 24 205.15 188.03 Venkatesh D T 26-Feb-10 15-Aug-11
Mysore Mysore
12 SI Qtrs for
Jalapuri,
Nazarbad, Udayagiri & 12 12 148.30 121.12 Venkatesh D T 26-Feb-10 30-Aug-11
Mysore
CAR, Mysore
Additional works
(protection wall for
Jalapuri,
utility area & handrail 1* 4.85 4.28 Sharavana D S 6-Jul-12 31-Aug-12
Mysore
to pail area) to 12 SI
8 Qtrs
Jyothinagar, Two Wheeler Stand (2
1* 6.92 6.96 Sharavana D S 17-May-13 16-Nov-13
Mysore Nos) for Qtrs
Jyothinagar, RCC Slab cover over
1* 2.43 2.36 Sharavana D S 8-Aug-13 30-Sep-13
Mysore existing Drain for Qtrs
Jyothinagar, Approach Road to
1* 2.95 2.84 Sharavana D S 15-May-13 29-Jun-13
Mysore Qtrs
Jalapuri, 24 PC Qtrs for Vnagar M/s Jampana
9 24 24 307.50 295.76 P2 4-Mar-13 13-Jul-15
Mysore & VV Puram PS Const Pvt Ltd
M/s Jampana
10 Hebbal 12 PC Qtrs 12 12 168.07 157.70 P3 12-Jul-13 31-Oct-15
Const Pvt Ltd
TOTAL 156 24 180 1835.80 1697.60
RAICHUR DISTRICT
Khaja Mahemood
1 Nethajinagar 12 PC Qtrs 12 12 98.65 85.84 19-Mar-09 30-Mar-10
Patel
Sadar Bazar, Khaja Mahemood
2 12 PC Qtrs 12 12 98.65 84.79 19-Mar-09 30-Mar-10
Raichur Patel
Sindhanoor
3 12 PC & 1 SI Qtrs 12 1 13 112.75 104.16 Basavaraj S 19-Mar-09 31-Jul-10
(Rural)
Sindhanoor
4 1 SI Qtrs 1 1 14.10 12.86 Akthar Pasha S 23-May-09 20-Nov-09
(Town)
Adanagouda A
5 Lingasugur 12 PC & 2 SI Qtrs 12 2 14 127.55 108.30 19-Mar-09 6-Feb-12
Patil
6 Raichur 24 PC Qtrs 24 24 214.30 192.93 Patil R P 19-Jul-10 24-Mar-12
Sadar Bazar, Siddaramagouda
7 6 PC Qtrs 6 6 55.25 50.33 19-Jul-10 1-Apr-11
Raichur S Patil
TOTAL 78 4 82 721.25 639.21
Page 8 of 8
Sl. Est Cost in Expendi Pha Completion
Location Name of the Works PC SI Total Agency Name Start Date
No. Lakhs ture se date
RAMANAGAR DISTRICT
12 PC & 4 SI Qtrs for M/s G B
1 Channapatna 12 4 16 147.05 133.28 20-Apr-09 19-Jan-10
DAR Enterprises
M/s G K
Ramanagar 24 PC & 4 SI Qtrs 24 4 28 245.50 224.75 17-Apr-09 16-Apr-10
Associates
2
Providing Supply and M/s Lakshmi
Ramanagar 1* 1.18 1.29 28-Aug-10 27-Sep-10
erection of Electricals
Submersible Pump M/s G B
3 Channapatna 12 PC Qtrs for DAR 12 12 105.00 93.48 10-Feb-10 9-Dec-10
Enterprises
36 PC Qtrs (Group A, M/s G K
4 Ramanagar 36 36 273.20 295.52 26-Feb-10 25-Apr-11
Blk C,D,E) Associates
Town, Rural &
24 PC Qtrs (Group B, M/s Sri Byrava
5 Ijoor 24 24 216.55 186.88 19-Mar-10 18-Mar-11
Blk F&G) Civil Engg Works
M/s Palamaneni
6 Sathanur 8 PC Qtrs 8 8 79.75 76.09 1-Mar-10 31-Jan-11
Const Company
M/s Jampana
7 Tavarekere 12 PC Qtrs 12 12 180.66 167.70 P3 25-Jul-13 30-Nov-15
Const Pvt Ltd
TOTAL 128 8 136 1248.89 1178.98
SHIMOGA DISTRICT
1 Shimoga 12 PC Qtrs 12 12 103.35 97.09 Iyyanna S 30-Mar-09 29-Jan-10
2 Agumbe 24 PC & 2 SI Qtrs 24 2 26 234.85 221.46 Dinesh Hegde 27-Feb-09 8-Nov-10
DAR, 24 PC Qtrs & 2 SI M/s S R
3 24 2 26 232.60 207.03 2-Nov-09 31-Mar-11
Shimoga Qtrs Constructions
TOTAL 60 4 64 570.80 525.59
TUMKUR DISTRICT
1 Tumkur 36 PC & 4 SI Qtrs 36 4 40 330.55 302.18 Palakshaiah B 20-Feb-09 6-Feb-10
Tumkur Town, M/s Apoorva
2 36 PC & 4 SI Qtrs 36 4 40 343.80 353.70 20-Nov-10 28-May-12
New Extn & Construction Co
3 Turuvekere 6 PC Qtrs 6 6 87.90 80.34 P2 Ravindra Kumar 25-Jun-13 24-Feb-14
M/s N B Const
4 Pavagada 6 PC Qtrs 6 6 89.70 77.18 P2 20-May-13 15-Mar-14
Company
12 PC & 4 SI Qtrs for M/s Jampana
5 Tumkur 12 4 16 229.82 224.72 P3 5-Jul-13 26-Aug-15
Town & Tilaknagar Const Pvt Ltd
TOTAL 96 12 108 1081.77 1038.11
UDUPI DISTRICT
M/s Suprada
1 Byndoor 12 PC Qtrs 12 12 115.30 108.05 12-Mar-09 31-Mar-10
Const Company
2 Padubidri 12 PC Qtrs 12 12 114.20 97.18 Hariprasad Shetty 16-Mar-09 27-Jul-10

3 Byndoor 12 PC Qtrs 12 12 120.00 98.40 Sudhir Kumar M 12-Mar-10 13-Apr-11


Karkala Town Raghuram Shetty
4 12 PC Qtrs 12 12 123.20 110.34 5-Apr-10 29-Feb-12
& Rural B
Malpe & 12 PC Qtrs at Malpe &
5 12 1 13 147.50 121.16 Praveen Kumar 24-Apr-10 28-Aug-12
Padubidri 1 SI Qtrs at Padubidri
Udupi Town &
6 24 PC & 1 SI Qtrs 24 1 25 254.55 240.20 Abdul Gani 12-Mar-10 24-Feb-12
Traffic PS
7 Amasebail 24 PC Qtrs 24 24 236.75 226.54 Sudhir Kumar M 20-Apr-11 31-Oct-12
12 PC Qtrs for
8 Shivalli 12 12 188.05 174.88 P2 Sudeer Kumar M 28-Aug-13 27-Jul-14
Coastal Security
TOTAL 120 2 122 1299.55 1176.76
1 Fast Track Project (10 PC Qtrs) 348.32 348.32
GRAND TOTAL 2845 215 3060 31356.25 29138.44