Lecture 09 - CIVL 3052
Lecture 09 - CIVL 3052
Lecture 09
CIVL 3052
MUNICIPAL ENGINEERING 1
EUGENE WAT, P.ENG.
BINEGA MARKOS, P.ENG.
FALL 2023
2
Course Contents - Municipal Engineering 1 (CIVL 3052)
1. Introduction to Urban Developments
2. Site Planning Considerations
3. Subdivision Design (access, lot layout)
4. Off-Site Servicing 1: Water, Sanitary & Storm
5. Off-Site Servicing 2: Road, Street lighting, Utilities (dry), Landscaping
6. Regional Growth Strategy, Official Community Plan, Rezoning Process, (Community
Impacts)
7. Subdivision Process (Legislation & Bylaws)
8. Environment & Sustainability
9. Finance & Benefit/Cost Analysis
10. Integrated Storm Water Management (Detention)
11. Asset Management
3
9. Project Cost Estimation
1. Project Cost Estimate
❑ Classification of Estimates
4
1. Project Cost Estimate
What is a Project Cost Estimate?
5
Purpose of a Project Cost Estimate
6
Purpose of a Project Cost Estimate
❑The primary purpose of a project cost estimate is to
provide a basis for developing, amending, or
reviewing a project budget
❑Contractor – estimate too high & the bid may go to
someone else; estimate too low, wins the bid & later
he wishes it went to someone else
❑Developer – estimate too low, additional financing
cost down the road or lose of profit
❑City – too high estimate could lead to killing a
project, political ramification, lose of public trust
11
Principles of Project Cost Estimating
Contingency:
12
Principles of Project Cost Estimating
➢ An estimate assumes things as:
– Errors will not be made and quantities will not
change
– Resources will be available
– The work will be done according to the
execution plan
– The project is well defined and decisions will be
made on time
– Contractor’s work will flow smoothly and
produce deliverables per the schedule
– Contractor will have materials, equipment, and
information as per the schedule
❖ Contingency is meant to cover likely variations to
these assumptions 13
Principles of Project Cost Estimating
Contingency:
❑ What does Contingency Include?
➢ Normal design development changes
➢ Normal variations in project execution
➢ Normal variations in estimating (e.g. between
estimated and actual quantities and costs)
❑ What does Contingency Exclude?
➢ Significant changes in scope
➢ Major changes in project execution
➢ Extraordinary variations in cost (Escalation)
➢ Major (unexpected) work stoppages
➢ Disasters (earthquakes, tornadoes, etc.)
14
Principles of Project Cost Estimating
Contingency - Points to remember:
– Project cost estimates should always include
contingency to cover certain uncertainties and
risks
– Contingency is an item in a cost estimate like
any other. It is best presented as a separate line
to clearly identify it
– Contingency should be estimated and included
in every estimate and every budget
– Contingency evolves with the level of project
understanding
– An estimate that contains too much contingency
is overpriced; such estimates can negatively
impact project ‘go/no-go’ decisions
15
Classification of Estimates
AACE Process Industry Estimate Classification
AACE LEVEL OF PROJECT EXPECTED ACCURACY
END USAGE METHODOLOGY TYPICAL CONTINGENCY
ESTIMATE DEFINITION RANGE
Expressed as % of Complete To Achieve 50% Probability of
CLASS Typical Purpose of Estimate Typical Estimating Techniques At 90% Confidence Level
Project Definition Overrun/Underrun
Preliminary Project Capacity Factored,
Screening Estimate, Parametric Models,
Capital Budget OOM Judgment, Analogy, Low: -20% to -50%
5 <= 2% Estimate, Alternate Historical Project 15% to 40%
High: +30% to +100%
Schemes Evaluation, Comparisons, Gross Unit
Strategic Analysis Cost
Preliminary Project Equipment Factored,
Estimate, Reality Check Parametric Models,
Estimate, Alternate Historical Relationship Low: -15% to -30%
4 1% to 15% 10% to 25%
Schemes Evaluation, Factors, Broad Unit Cost High: +20% to +50%
Feasibility Study Data
18
10-Minute
Break
19
Factors influencing an estimate
• PUP (Public Utility Plans): Plans
for managing and relocating
utilities like water, electricity, and
gas affected by a project.
• QTRIP (Queensland Transport and
Roads Investment Program): A
multi-year funding and planning
framework for transport and road
projects in Queensland, Australia.
• Brownfield: Projects on previously
developed land, often requiring
cleanup or demolition.
• Greenfield: Projects on
undeveloped land, requiring new
infrastructure but offering design
flexibility.
20
2. Cost Predictability in Construction
Definition:
21
Issues and Considerations in Cost Predictability
➢ Local or national construction industries are becoming increasingly
affected by global trends and influences, which can create significant and
unexpected volatility and unpredictability in the construction marketplace
24
Issues and Considerations in Cost Predictability
25
Issues and Considerations in Cost Predictability
➢ Estimates should not be altered to meet limited budgets. If the estimate exceeds the
budget, owners should achieve the intended result by either increasing the budget or
modifying the scope of work
26
Recommendations for Improved Cost
Predictability
1. Utilize qualified estimating personnel throughout the life of
the project
2. Ensure all stakeholders have input early and often. Clear
definition of project objectives, program and scope will avoid
potentially expensive surprises, such as scope growth
3. Give designers sufficient time to finalize bid documents
4. Consider developing & maintaining a usable construction
cost database
27
Recommendations for Improved Cost
Predictability
5. Include sufficient contingency to address market volatility, timing of
construction, and other exclusions in the estimate
28
Recommendations for Improved Cost
Predictability
6.2 During Tender
29
Recommendations for Improved Cost
Predictability
6.3 After Tender
✓ involve the cost consultant in the post tender review
✓ analyze bid results against estimates for lessons learned; and
✓ keep a record of historical estimate versus bid data
30
2. Cost Predictability in Construction
Cost Predictability Guarantee
✓ In reality, there are too many variables influencing final bid prices to expect
100% accuracy. However, there are many proven recommendations and
methodologies one can follow to help improve and define the cost
predictability of projects.
31
Thank you!
32