DPWH - LABOR CAPABILITIES
DPWH - LABOR CAPABILITIES
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
I. EARTHWORKS
800 - CLEARING AND GRUBBING
a.) Undergrowth & Tress 12" dia. sq.m. 136.00 m2/MD 17.0000 m2/Hr.
b.) Undergrowth & Small Bushes sq.m. 272.00 m2/MD 34.0000 m2/Hr.
803 - STRUCTURES EXCAVATION
a.) Common Earth cu.m. 1.00 m3/MD 0.1250 m3/Hr.
b.) Sand cu.m. 5.17 m3/MD 0.6463 m3/Hr.
c.) Clay cu.m. 4.15 m3/MD 0.5188 m3/Hr.
d.) Rock cu.m. 2.58 m3/MD 0.3225 m3/Hr.
804 - EMBANKMENT
a.) Backfilling cu.m. 8.30 m3/MD 1.0375 m3/Hr.
b.) Spreading, Tampimg & Grading cu.m. 14.21 m3/MD 1.7763 m3/Hr.
c.) Placing Escrombo Fill (Debris) cu.m. 16.00 m3/MD 2.0000 m3/Hr.
d.) Gravel Fill
d-1.) Hand Placed cu.m. 1.36 m3/MD 0.1700 m3/Hr.
d-2.) Placing Binder-Gravel cu.m. 4.00 m3/MD 0.5000 m3/Hr.
Page 1 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
e-1.) 0 to 0.50M sq.m. 4.01 m2/MD 0.5013 m2/Hr.
e-2.) 0.50 to 1.0M sq.m. 2.04 m2/MD 0.2550 m2/Hr.
e-3.) 1.0m Up sq.m. 2.04 m2/MD 0.2550 m2/Hr.
f.) Elevated & Shored Slab
f-1.) Forming Only sq.m. 0.75 m2/MD 0.0938 m2/Hr.
f-2.) Forming & Shoring sq.m. 0.61 m2/MD 0.0763 m2/Hr.
C. FORMWORKS STRIPPING
a.) Wall on Ground sq.m. 27.20 m2/MD 3.4000 m2/Hr.
b.) Wall above Ground sq.m. 5.24 m2/MD 0.6550 m2/Hr.
c.) Beams sq.m. 6.60 m2/MD 0.8250 m2/Hr.
d.) Columns sq.m. 7.96 m2/MD 0.9950 m2/Hr.
e.) Suspended Slab
e-1.) 0 to 0.50M sq.m. 8.16 m2/MD 1.0200 m2/Hr.
e-2.) 0.50 to 1.0M sq.m. 6.26 m2/MD 0.7825 m2/Hr.
e-3.) 1.0m Up sq.m. 6.26 m2/MD 0.7825 m2/Hr.
f.) Elevated & Shored Slab sq.m. 1.91 m2/MD 0.2388 m2/Hr.
g.) Slab on Grade (Form Stripping) sq.m. 2.38 m2/MD 0.2975 m2/Hr.
D. FORMWORKS
Time req'd. for erecting & stripping per 100m2 of Contact Surface
a.) Footing/Foundations sq.m. 1.77 m2/MD 0.2213 m2/Hr.
b.) Slab on Grade sq.m. 2.58 m2/MD 0.3225 m2/Hr.
c.) Columns & Beams sq.m. 1.22 m2/MD 0.1525 m2/Hr.
d.) Walls sq.m. 1.36 m2/MD 0.1700 m2/Hr.
e.) Culvert & Manholes sq.m. 1.29 m2/MD 0.1613 m2/Hr.
In General Two man can erect 20BD.FT/Hr. and Remove forms at the rate of 44BD.FT/Hr.
904 E. REINFORCEMENT
a.) Fabrication (Cut & Bend) kg. 68.00 kg/MD 8.5000 kg/Hr.
b.) Placing
b-1.) Footing/Foundatios kg. 95.74 kg/MD 11.9675 kg/Hr.
b-2.) Slab on Grade kg. 95.74 kg/MD 11.9675 kg/Hr.
b-3.) Columns, Beams and R.C. Walls kg. 85.00 kg/MD 10.6250 kg/Hr.
b-4.) Culvert and Manholes kg. 61.00 kg/MD 7.6250 kg/Hr.
Page 2 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
909 F. CONCRETE POURING
a.) Place, Finish & Concrete curing
a-1.) Footing/Foundatios cu.m. 3.32 m3/MD 0.4150 m3/Hr.
a-2.) Slab on Grade cu.m. 1.89 m3/MD 0.2363 m3/Hr.
a-3.) Columns cu.m. 1.02 m3/MD 0.1275 m3/Hr.
a-4.) R.C. Walls cu.m. 0.94 m3/MD 0.1175 m3/Hr.
a-5.) Structural Slab (6") cu.m. 0.88 m3/MD 0.1100 m3/Hr.
a-6.) Cast-In-Place Culverts cu.m. 1.32 m3/MD 0.1650 m3/Hr.
a-7.) Cast-In-Place Manholes cu.m. 2.65 m3/MD 0.3313 m3/Hr.
b.) Placing Concrete
b-1.) Slab on Fill cu.m. 1.36 m3/MD 0.1700 m3/Hr.
b-2.) Slip Form cu.m. 0.27 m3/MD 0.0338 m3/Hr.
b-3.) Chute from Truck cu.m. 0.95 m3/MD 0.1188 m3/Hr.
b-4.) Crane & Bucket cu.m. 0.48 m3/MD 0.0600 m3/Hr.
b-5.) Wheeling cu.m. 0.20 m3/MD 0.0250 m3/Hr.
b-6.) Elevated & Shored Slab Chute & Fortalift cu.m. 0.34 m3/MD 0.0425 m3/Hr.
b-7.) Floor Fin. Unhardened cu.m. 6.80 m3/MD 0.8500 m3/Hr.
b-8.) Concrete Finish Hardened cu.m. 4.76 m3/MD 0.5950 m3/Hr.
c.) Concrete Mixing
c-1.) Manual Mixing cu.m. 0.41 m3/MD 0.0513 m3/Hr.
c-2.) One-Bagger Mixing cu.m. 3.81 m3/MD 0.4763 m3/Hr.
V. MASONRY WORKS
506 (1) - MASONRY WORKS
a.) CHB Laying
a-1.) CHB 4" sq.m. 5.10 m2/MD 0.6375 m2/Hr.
a-2.) CHB 6" sq.m. 4.25 m2/MD 0.5313 m2/Hr.
a-3.) CHB 8" sq.m. 3.40 m2/MD 0.4250 m2/Hr.
b.) Brick Works (1.00 x 0.20m) sq.m. 13.60 m2/MD 1.7000 m2/Hr.
c.) Red Bricks (0.25" x 2" x 8") sq.m. 1.36 m2/MD 0.1700 m2/Hr.
d.) Laying of Adobe sq.m. 5.98 m2/MD 0.7475 m2/Hr.
Page 3 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
a-4.) Wood Walls & Partitions cu.m. 13.60 m3/MD 1.7000 m3/Hr.
a-5.) Wood Walls Partitions cu.m. 13.60 m3/MD 1.7000 m3/Hr.
a-6.) Panel Wall sq.m. 0.95 m2/MD 0.1188 m2/Hr.
a-7.) Double Wall Partitions cu.m. 13.60 m3/MD 1.7000 m3/Hr.
b.) Floor
b-1.) T & G Flooring bd.ft 48.55 Bd.Ft/MD 6.0688 Bd.Ft/Hr.
b-2.) Floor Framing bd.ft 14.01 Bd.Ft/MD 1.7513 Bd.Ft/Hr.
c.) Wooden Post Erection bd.ft 15.98 Bd.Ft/MD 1.9975 Bd.Ft/Hr.
d.) Ceiling
d-1.) Ceiling Frame (Joist, Nailers & Handrails) sq.m. 5.10 m2/MD 0.6375 m2/Hr.
d-2.) Plywood shts. 6.80 shts/MD 0.8500 shts/Hr.
d-3.) Fiber Cement Board Installation shts. 6.80 shts/MD 0.8500 shts/Hr.
d-4.) Acoustic Ceiling sq.m. 5.64 m2/MD 0.7050 m2/Hr.
d-5.) Ceiling Eaves Installation sq.m. 5.64 m2/MD 0.7050 m2/Hr.
d-6.) Facia Board Installation sq.m. 16.32 m2/MD 2.0400 m2/Hr.
e.) Cabinet
e-1.) Cabinet Framing bd.ft 52.29 Bd.Ft/MD 6.5363 Bd.Ft/Hr.
e-2.) Cabinet Boarding bd.ft 37.61 Bd.Ft/MD 4.7013 Bd.Ft/Hr.
e-3.) Built-in Wood Cabinet bd.ft 37.81 Bd.Ft/MD 4.7263 Bd.Ft/Hr.
f.) Base Board Installation lm 34.00 Lm/MD 4.2500 Lm/Hr.
g.) Wooden Stairs plight 17.00 Plight/MD 2.1250 Plight/Hr.
h.) Wooden Moulding/Comice lm 61.81 Lm/MD 7.7263 Lm/Hr.
Page 4 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
e-2.) Fixed G.I. Sheets pc. 1.00 Pc/MD 0.1250 Pc/Hr.
Page 5 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
c-5.) Door Lockset sets 4.25 set/MD 0.5313 set/Hr.
Page 6 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
c.) Installation of Valley Roll Lm 42.50 Lm/MD 5.3125 Lm/Hr.
d.) Installation of Flashing Lm 42.50 Lm/MD 5.3125 Lm/Hr.
e.) Installation of Gutter Lm 42.50 Lm/MD 5.3125 Lm/Hr.
1017 - ROOF DRAIN AND STRAINERS
a.) Installation of Roof Strainers pc. 8.00 Pc/MD 1.0000 Pc/Hr.
b.) Installation of Downspout Lm 51.00 Lm/MD 6.3750 Lm/Hr.
c.) Installation of Insulation sq.m. 14.00 m2/MD 1.7500 m2/Hr.
X. FINISHING WORKS
1018 - CERAMIC TILES
a.) Ceramic Glazed Tiles sq.m. 2.24 m2/MD 0.2800 m2/Hr.
b.) Ceramic Unglazed Tiles sq.m. 1.56 m2/MD 0.1950 m2/Hr.
1019 - WOOD TILES
a.) Narra Parquet Finish sq.m. 9.30 m2/MD 1.1625 m2/Hr.
b.) Tanguile Parquet Finish sq.m. 9.30 m2/MD 1.1625 m2/Hr.
SPL a.) Marble Tiles Finish sq.m. 3.40 m2/MD 0.4250 m2/Hr.
b.) Granite Tiles Finish sq.m. 3.40 m2/MD 0.4250 m2/Hr.
c.) 0.5" x 2" x 8" Red Blocks sq.m. 1.36 m2/MD 0.1700 m2/Hr.
d.) Manolithic Terrazo Finish sq.m. 6.04 m2/MD 0.7550 m2/Hr.
e.) Synthetic Marble Tiles sq.m. 1.49 m2/MD 0.1863 m2/Hr.
Page 7 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
f.) Wall Papers sq.m. 0.88 m2/MD 0.1100 m2/Hr.
g.) Plastered Ceiling sq.m. 2.24 m2/MD 0.2800 m2/Hr.
h.) Mozaic Floor Tiles sq.m. 0.82 m2/MD 0.1025 m2/Hr.
Page 8 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
b.2) 3/4" Diameter Lm 0.41 Lm/MD 0.0513 Lm/Hr.
b.3) 1" to 1.25" Diameter Lm 0.47 Lm/MD 0.0588 Lm/Hr.
b.4) 1.50" to 2" Diameter Lm 0.52 Lm/MD 0.0650 Lm/Hr.
b.5) 2.50" Diameter Lm 0.62 Lm/MD 0.0775 Lm/Hr.
b.6) 3" Diameter Lm 0.68 Lm/MD 0.0850 Lm/Hr.
b.7) 4" Diameter Lm 0.83 Lm/MD 0.1038 Lm/Hr.
c.) Cast Iron Pipe
c.1) 2" Diameter Lm 1.39 Lm/MD 0.1738 Lm/Hr.
c.2) 4" Diameter Lm 2.07 Lm/MD 0.2588 Lm/Hr.
c.3) 6" Diameter Lm 3.11 Lm/MD 0.3888 Lm/Hr.
c.4) 8" Diameter Lm 4.15 Lm/MD 0.5188 Lm/Hr.
c.5) 10" Diameter Lm 6.22 Lm/MD 0.7775 Lm/Hr.
c.6) 12" Diameter Lm 6.57 Lm/MD 0.8213 Lm/Hr.
c.7) 14" Diameter Lm 7.63 Lm/MD 0.9538 Lm/Hr.
c.8) 16" Diameter Lm 8.67 Lm/MD 1.0838 Lm/Hr.
c.9) 18" Diameter Lm 9.72 Lm/MD 1.2150 Lm/Hr.
c.10) 20" Diameter Lm 10.37 Lm/MD 1.2963 Lm/Hr.
c.11) 24" Diameter Lm 11.51 Lm/MD 1.4388 Lm/Hr.
Page 9 of 12
ITEM DERIVED/OUTPUT
DESCRIPTION UNIT
NO. (UNIT/MANDAYS) (UNIT/HOURS)
b.8) 6" Diameter Lm 1.56 Lm/MD 0.1950 Lm/Hr.
Page 10 of 12
1) EARTHWORK - Example :
A construction crew of 6 is tasked to excavate 67cu.m of earth
Determine the duration of this task. Likewise they are also tasked
to clear 150sqm of bushes, grasses and shrubs