Details of Work
Details of Work
2 MS-VM Section - Construction of Pre cast RCC Box M/s.Sree Constructions - 8220161113 MAS32OF23194S/ ₹ 3,74,99,939.11 ₹ 5,58,74,909.27 ₹ 4,75,66,444.69 149.00 126.84 15-01-2024 31-10-2024 Insertion of Box Culvert at Work is in
Culverts at 5 locations on (at KM:3/700) on Deposit Hyderabad 00995850087046 MS Progress(Deposit
Terms Dt:15-09-2023 Work)
3 Supply of drinking water by tank mounted on lorry to M/s. Sri Lakshmi Narayana 9884011840 MAS37OF23218S/ ₹ 84,63,559.40 ₹ 1,04,10,177.57 ₹ 1,00,70,603.86 123.00 118.99 13-11-2024 NIL Supply of Water to Railway Work is in Progress
Railway colonies Stations and Service buildings in Transport 00877240091011 Colonies, Stations and
SSE/W/TBM Section Dt:13-11-2023 Service buildings
4 Privision of electronics based equipments of 25 KV M/s. SRM Services - 9884490073 MAS26OF22255S/ ₹ 28,06,615.82 ₹ 30,87,277.40 ₹ 9,92,540.00 110.00 35.36 22-04-2023 31-08-2024 Construction of Lab in Emu Work is in Progress
AV EMU with 3 Phase propulsion system at EMU Kanchipuram 00882220068316 Workshop
Workshop, Tambaram. Dt: 22-12-2022
5 SRCETC/TBM - Proposed improvements for Digital M/s. K.S Sudesh Kumar - 9789282820 MAS14OF21232WS/ ₹ 1,39,90,755.15 ₹ 87,93,926.59 ₹ 73,94,851.07 62.86 52.86 02-11-2022 31-12-2024 Improvements to SRCETC Work is in Progress
Learning in Training centre. Thiruvallur 8838979597 01007870050512
Dt:02-03-2022
6 Provision of various amenities at Goods shed at M/s. Hari Thiruvallur 9094882277 MAS0OF22293S/ 4372622.14 ₹ 9,15,558.93 nil 64.90 0 13-08-2023 30-11-2024 Construction of Rest room Work is in Progress(
Mundiyambakkam, Chengalpattu and Tambaram. 00959780071476 TBM Value - 1408552.21 and Toilets Combined agreement)
Dt:13-02-2023
7 MS-VM section - Pway works atKilambakkam M/s R SENTHILKUMAR- 7550182133 MAS51OF23295S / ₹ 1,76,80,949.92 7249189.467 NIL 41.00 0.00 09-08-2024 Nil Making Embankment for Work is in Progress
(Deposit work) ARIYALUR 00845840097198 Track.
Dt:09-02-2024
8 Repairs and maintainance of staff quarters, staion M/s. K.S Sudesh Kumar - 9789282820 MAS03OF24019S/ ₹ 85,61,664.73 ₹ 42,80,832.36 ₹ 21,83,858.53 50.00 25.51 26-05-2025 Nil Maintainance of quarters, Work is in Progress
and service buildings in SSE/W/TBM section for Thiruvallur 7010973087 01007870103871 station and service buildings
period of one year. Dt:26-05-2024 work
9 Tambaram Sanatorium - Repairs to collection Well at M/s. Skyscrapper Designs 7010301873 MAS09OF22085S/ ₹ 39,46,987.97 ₹ 34,34,236.00 ₹ 34,34,236.00 87.01 87.01 18-12-2022 31-03-2024 Construction of collection Contractor not turned
Subway LC23 and Constructions - Vellore 01439060060200 well at TBMS up
Dt:18-08-2022
10 Provision of Material Recovery facility covered shed M/s. Vilcon Infra - Nellore 8309822955 MAS09OF21154S/10337300042243 ₹ 10,98,267.00 ₹ 1,98,500.23 Nil 18.07 0.00 30-11-2022 Nil Contractor not turned
at various locations including Electrical works Dt:24-09-2021 up
11 Tambaram - Repairs to approach road along with M/s. SRM Services - 9884490073 M/W.496/South/663 ₹ 72,75,090.00 ₹ 35,33,936.00 ₹ 24,33,936.00 48.58 33.46 31-02-2023 Repairs to Road
drain from TBM Station to Office of Sr.DEE/RS/TBM Kanchipuram Dt: 30-01-2019
2 Zone 'S2' : Maintenance of TBM Car VST BUILDERS- 9094870676 MAS21OF24144S/ ₹ 9,58,051.21 ₹ 9,00,000.00 ₹ 5,00,000.00 93.94 52.19 12-08-2025 Nil Repair works Work is in Progress
shed, TBM Coaching yard, Training Institutes - KANCHIPURAM 10261390110147
SRCETC & DPWTC at Tambaram in
Dt:12/08/2024
SSE/W/TBM SECTION " ( 2024-2025)
3 Zone 'S1' : Maintenance of all buildings, S V S CONSTRUCTIONS- 8220161113 MAS30OF23170S/ ₹ 54,37,483.16 ₹ 49,72,701.47 ₹ 31,72,742.83 91.45 58.35 06-10-2024 Nil Repair works Work is in Progress
signal cabins and platform, P.way, watering KANCHEEPURAM 10109730088482
arrangements, fencing and walling station buildings, Dt:06/10/2023
staff qrs., service buildings etc. excluding TBM Car
shed, TBM Coaching yard & Training Institutes in
SSE/W/TBM SECTION ie., at stations TBM &
TBMS." ( 2023-2024)
4 Zone 'S2' : Maintenance of TBM Car S V S CONSTRUCTIONS- 8220161113 MAS30OF23171S/ 10109730087582 ₹ 11,16,846.24 ₹ 6,21,504.57 ₹ 6,21,504.57 55.65 55.65 24-09-2024 Nil Repair works Work is in Progress
shed, TBM Coaching yard, Training Institutes - KANCHEEPURAM Dt:24/09/2023
SRCETC & DPWTC at Tambaram in
SSE/W/TBM SECTION " ( 2023-2024)
5 Zone 'S1' : Maintenance of all buildings, PILLILA SAI CHAND- 6305779737 MAS17OF22172S/01491760067781 ₹ 55,88,989.99 ₹ 67,36,740.41 ₹ 67,36,740.41 120.54 120.54 14-12-2023 31-12-2024 Repair works One work order yet to
signal cabins and platform, P.way, watering NELLORE 9703639777 Dt:14/12/2022 be billed
arrangements, fencing and walling station buildings,
staff qrs., service buildings etc. excluding TBM Car
shed, TBM Coaching yard & Training Institutes in
SSE/W/TBM SECTION ie., at stations TBM &
TBMS.( 2022-2023)