30. Instrument Design Basis
30. Instrument Design Basis
Aparana
DN: cn=R. S. Bali, o=TES,
Anuj Mohan
ou=Process,
Bali
Digitally signed by Aparana Srivastava Digitally signed by Anuj Mohan Agarwal [email protected],
DN: cn=Aparana Srivastava, o=Triune Energy DN: cn=Anuj Mohan Agarwal, o=Triune c=IN
Services Pvt. Ltd., ou=Process, Energy Services Pvt. Ltd., ou=Process, Date: 2019.01.21 13:54:03 +05'30'
Srivastava
[email protected], c=IN
Date: 2019.01.21 13:37:56 +05'30'
Agarwal [email protected], c=IN
Date: 2019.01.21 13:38:17 +05'30'
CONTENTS
1.0 INTRODUCTION 5
2.0 PLANT OPERATION & CONTROL 8
3.0 POWER REQUIREMENT 10
4.0 SITE CONDITIONS 10
5.0 UNITS OF MEASUREMENT 11
6.0 INSTRUMENT PROCESS CONNECTIONS 11
7.0 AREA CLASSIFICATION & INSTRUMENT PROTECTION 12
8.0 FOUNDATION FIELDBUS COMPLIANT FIELD INSTRUMENTATION 14
9.0 FIELD TRANSMITTER 15
10.0 FLOW MEASUREMENT 15
11.0 PRESSURE INSTRUMENTS 22
12.0 LEVEL INSTRUMENTS 23
13.0 TEMPERATURE INSTRUMENTS 27
14.0 HAND HELD COMMUNICATOR & FIELDBUS TESTER, MONITOR 28
15.0 PRESSURE RELIEF VALVES 29
16.0 CONTROL VALVES AND SHUTDOWN VALVES 30
17.0 FLAME ARRESTORS 34
18.0 PROGRAMMABLE LOGIC CONTROLLER 34
19.0 GAS DETECTION 35
20.0 FIRE DETECTION 37
21.0 CCTV SYSTEM 38
22.0 GAS METERING PHILOSOPHY 39
23.0 INSTRUMENT CABLES AND WIRING 39
24.0 INSTRUMENT JUNCTION BOXES 42
25.0 TUBE & TRAYS 42
26.0 EARTHING PHILOSOPHY 43
1.0 INTRODUCTION
The Nandasan Surface Facilities Project (NSFP) is part of the Nandasan Redevelopment
Scheme conceived by ONGC (Client) aiming to enhance production from Nandasan oil
field of Mehsana Asset of ONGC, located in Gujarat State of India. In view of envisaged
increased production from the field and inadequacy/absence of existing emulsion &
effluent treatment facilities at the existing GGS; Client intends to create a new integrated
process facilities complex with new processing facilities for well fluid, emulsion
treatment, effluent treatment, effluent disposal, water injection, Gas processing and Gas
lift. The proposed new process facilities shall have hook ups / tie-ins from existing GGS-
Nandasan which is adjacent to the proposed integrated process facilities complex NSFP.
This document defines the basic design requirements which shall be followed by
Contractor for design engineering, procurement and construction work of
Instrumentation for Nandasan Surface Facilities Project (NSFP).
a) For all detailed design work, reference to, and compliance with the Project
Specifications and Project Drawings shall be made throughout.
b) All the offered instruments/ equipment or equipment of similar design
manufactured by the supplier shall have proven track record of continuous
satisfactory service in similar type of hydrocarbon services for two years
minimum.
c) The design and installation of instruments shall be generally in accordance with
ISA/ API recommended practices and other applicable standards like ASI, IBR
etc. Material specifications and practices shall, in general, conform to appropriate
ASTM or equivalent standards. All standards, code of practice shall be of the
latest edition.
d) All pressure relieving devices shall be designed in accordance with ASME
Section–VIII, Division - 1 for Boilers and pressure vessel and API RP 521/ 520.
e) All Instruments / equipment shall be suitable for installation in specified site
condition.
f) Care shall be taken to keep the variety of instruments to a minimum and to
procure equipment offering the best guarantees in terms of standardization and
local maintenance.
g) Ranges for instruments shall be selected, in general, such that in normal process
operation the indication on the indicator is between 30% to 70% of span for
linear scale and 60% to 80% of span for square root scale.
h) Alarm, safety and interlock contacts shall be closed during plant normal
operation. Solenoid Valves and Relays shall be energized during plant normal
operation. Installation shall be generally “FAIL SAFE” (positive security). All
ESD interposing relays shall be SIL-3 certified with LED „error‟ indication. The
action of valves shall be designed in such a way as to keep the plant under safe
condition in case of main electrical power failure or instrument air failure.
i) All open and close loops shall have an individual switch fuse unit in the Control
room for isolating the field instruments for maintenance. (i.e. for field switches,
transmitters, SOV etc.)
j) All the instruments shall have AI-enabled features and shall have IIOT-based
communication backbone, as far as possible.
k) Pre-fabricated instrument hook ups shall be used for all pressure gauges (PG) and
pressure transmitters (PT).
l) Control valve sizing formula shall, in general, be as per ISA 75.01. Control
valves shall be sized for the available pressure drop at normal flow and in
addition shall permit upto 150% of normal flow or 110% of the maximum flow,
whichever is higher. Contractor shall submit the sizing calculations for all
Control Valves.
m) Network switches shall be Industrial grade, ATEX certified and shall have dual
power supply unit.
n) Field transmitters/ positioners used in normal control/ monitoring loops shall be
Foundation Fieldbus (FF) type, unless mentioned otherwise. For Shutdown
loops/ Safety system loops, HART SMART type transmitters shall be used. In
case, for a particular type of Instrument if FF type is not available, HART
SMART type instrument can be used after taking approval from Client.
o) Fieldbus field transmitters shall be of SMART type compatible to FF protocol,
provided with inbuilt digital output meter in engineering unit/ output gauge at the
transmitter end.
p) All Fieldbus devices shall be intrinsically safe/ FISCO certified to be used in
intrinsically safe installation.
q) Supplier shall be fully responsible for design, material selection, sizing and
selection of the proper instruments for their system. The compliance to this
specification does not absolve the supplier of the responsibility towards
contractual obligations with regards to completeness, proper selection,
satisfactory operation and easy maintenance.
1.2 ABBREVIATIONS
For order of precedence, refer Clause no. 1.6 titled, „Special requirements‟ of section
1.0 titled „Introduction‟ of Bid package.
A new Integrated Control & Safety System (ICSS) and Integrated Operations system
(iOps) shall be provided for the ONGC Nandasan Surface Facility Project, Mehsana
Asset. This shall have redundancy at every level including the IO card-level. ESD
and F&G PLCs shall be SIL-3 type with TMR configuration, as a minimum.
However; a separate redundant, but NON-SIL PLC shall be envisaged for ETP+WIP
Plant. This PLC shall have analog capabilities too. For detailed requirement, refer
Control System Philosophy, Doc. No. 9658-09-CP-001, part of bid package.
The DCS shall use Fieldbus for communication as applicable between DCS and field
instruments of different makes in the same network. The system shall be designed
such that control (simple PID) can be achieved either in the DCS controller or on the
wire (in FF devices).
DCS shall be FF-based or Fieldcom interface. All the field instruments shall be FF-
type. DCS system shall have modern analytics capabilities and shall provide MIS
reports in graphs, excel sheets and trend-analysis form.
The DCS shall be able to accept digital/ Fieldbus compliant/Analog/ HART/ Pulse/
MODBUS etc. signals from field and panel instruments and carryout analog as well
as logic/ PID functions.
The DCS mother board/ back plane shall have universal connectors/ slots for
installation of various types of cards for interfacing field instruments. The DCS I/O
slot shall not be type specific, e.g. DCS I/O card chassis slot shall take any type of
I/O card whether it is analog, digital, pulse, FF compliant or conventional. Only
screw-less, push-in type terminal block shall be used.
Software for Storing Plant „As-built‟ data after commissioning shall be provided in
ICSS. For detailed requirement, refer specification for Distributed Control System,
doc no. 9658-09-TS-007.
The ESD system shall be designed to shut the process facilities in the event of
uncontrolled process conditions. Design of ESD system is to ensure the following
activities are taken into account:
SIL-3 rated with TMR configuration as per IEC-61508, Fault avoidant ESD system
shall be provided.
Fire & Gas system shall be provided to cater F&G detection signal from all the
process facilities and to cover Control Room as well as other rooms. The F&G
system shall be interfaced with DCS.
Following shall be provided as part of F&G system:
F&G system shall be designed to control the detection signals received from the field
mounted detectors such as Gas Detectors (GSD), Flame detectors (FSD) and safety
Push buttons, Manual Alarm Call Points (MAC) etc. All these signals shall generate
a dedicated alarm.
SIL-3 rated with TMR configuration as per IEC-61508, Fault avoidant F & G system
shall be provided.
Spare philosophy for ESD and F&G System shall be as per Specification for PLC,
Document No. 9658-09-TS-006.
Spare philosophy for Distributed Control System (DCS) shall be as per Specification
for DCS, Document No. 9658-09-TS-007.
a. Supplier shall follow the I/O segregation according to the signal types (AI/ AO/
DI/ DO/ FF instruments etc.), while grouping of I/Os at all places including field
wiring, marshalling wiring, control system wiring.
b. Supplier to propose the minimum required number of different types of cards e.g.
If 20 digital outputs (DO) are required (excluding spares) and supplier has
standard 8 and 16 channels cards, the supplier shall propose three 8 channel cards
or two 16 channel cards, not one 16 channel card plus one 8 channel card.
c. In any case minimum one card for each type shall be provided as installed spare.
d. Each I/O card for closed loops shall not have control loops allotted to it of more
than one main processing unit. Main Processing Unit means Production
Separator, Test Separator, Heater Treater or any other such integrated processing
facility. This is to ensure that in the event of the failure of one control loop I/O
card, control operations of no more than one main processing unit are lost.
Temperature
Maximum Ambient Temperature: 48°C
Minimum Ambient Temperature: 2.2 °C
Humidity
Min./ Normal/ Max./ : 47% (min.)/ 87% (max.)/ 100% (design)
Rainfall
Max. hourly avg. 414.5 mm
Following factors shall be considered for proper selection of electrical equipment for
use in hazardous area:
All instruments and controls used in hazardous area shall be certified by statutory
bodies such as FM, UL, ATEX, Baseefa, PTB, PESO, CIMFR etc. All instruments
panels and junction boxes located in open areas shall be certified for use in Class I,
Division 1/ Zone 1 area irrespective of the actual hazardous area classification.
All the electrical equipment installed in hazardous areas shall meet the requirements
of relevant IEC or NEC standards. Equipment suitable for safe/non hazardous area
application shall not be used for Class I Div.1 (Zone-1) and Div.2 (Zone-2)
hazardous area. For Class I, Div. 2 (Zone-2) area equipment conforming to IEC/BS;
namely type Ex „e‟ or Ex „n‟ shall be used as minimum. Increased safety (type Ex
„e‟) equipment shall not be used in Class I, Div.1 (Zone-1) areas.
I.S. Barriers shall be active type and shall be backplane. Barrier input / output
voltage and current shall be 24 V DC and 4~20 mA DC respectively, with maximum
fault voltage of 250 V rms on safe area side. Barrier end to end resistance shall be
less than 250 and accuracy better than + 0.1%.
Isolating barriers shall also be suitable for Fieldbus compliant instruments and
installation configuration shall be as per standard practices for respective Fieldbus.
All field transmitters used in normal control/ monitoring loops shall be Foundation
Fieldbus (FF) type, unless mentioned otherwise. For Shutdown loops/ Safety system
loops, HART SMART type transmitters shall be used. The following specifications
shall also apply:
a) Transmitters shall be provided with external zero adjustment and shall have
integral vent/drain.
b) All transmitters shall be provided with integral intrinsically safe output meter
having LCD display. The transmitter shall be microprocessor based and it shall
incorporate a non-volatile memory which shall store complete configuration data
of transmitter. All necessary signal conversions, including conversion to produce
output with the required protocol shall be carried out in the transmitter
electronics.
c) Transmitter shall also run complete Sub-diagnostic routine. In the event of
detection of failure, the output shall be driven to predefined value, which shall be
field configurable.
d) Temperature sensors shall be provided to compensate for process temperature
and ambient temperature variations.
e) The transmitter shall be able to assure an accuracy of ±0.075% of span for a
rangeability of 100:1. The accuracy shall include the combined effect of
linearity, hysteresis and repeatability. However, for diaphragm seal instruments,
the accuracy of ±0.25% is, acceptable.
f) HART protocol of latest version shall be used with the following features as
minimum:
i) It shall allow multi masters (two for example, primary and secondary) for
configuration, calibration, diagnosis and maintenance. The primary could be
control system or host computer and the secondary could be the hand held
communicator or a maintenance computer.
ii) It shall be capable of implementing universal commands. It must be possible
to communicate all the commands to field transmitters and SMART transmitters
shall be selected accordingly.
g) Unless recommended otherwise by compressor manufacturer, field transmitters
used in anti-surge control loop shall be non-SMART and flameproof type. The
flameproof transmitters shall have their calibration adjustment from outside
without any need to remove the cover.
PRIMARY ELEMENT
RANGE SELECTION
a) The orifice meter differential range shall be 500, 1250, 2500 or 5000mm of water
(20, 50, 100 or 200 inches of water). The range 2500 mm (100 inches) is
desirable wherever possible.
b) For orifice meters the normal flow should be between 60% and 80% of the meter
maximum.
ORIFICE FLANGES
Variable area flow meters shall be as per ISA-RP 16.1, 16.2, 16.3, 16.4, 16.5 and
16.6.
Variable area flow meters shall have float stops at the top and bottom which shall be
easily removable.
Variable area flow meters design shall be such that there are no stagnant areas.
Glass tube Variable area flow meters shall have their metering tube made of
toughened borosilicate glass and shall be thick walled.
Glass tubes shall be used keeping in view the recommended safe working pressures
for different meter sizes and operating temperatures.
All glass tube Variable area flow meters shall be of direct indicating type. They shall
have metal side plates to prevent damage to the metering tube.
Scale for glass tube variable area flow meter shall be fixed adjacent to the metering
tube and shall be of detachable type.
All glass tube meters shall be adequately shielded with safety glass on the reading
side and suitably vented.
End connection size, rating, facing and material for various parts including float shall
be as per datasheet.
Metal tube meters shall have the motion of the float transmitted via a magnetic
coupling for secondary functions like indication, transmission or alarm.
Transmitter
The supplier shall be responsible for the selection of the Cone as a primary element
& accessories suitable for its intended application, its procurement, tagging, packing,
testing & calibration, preparation for shipment, along with accessories, spares, and
assistance where required for its installation & commissioning at site. The general
requirements for cone meter are as below:
Transmitter
Transmitter
a) The Ultrasonic flow meter shall be based on transit time technology. Body
material shall be SS 316 minimum. Flow meter shall be Foundation Fieldbus
type. In case FF type is not available, HART SMART type instrument can be
used after taking approval from Client
d) Ultrasonic flow meter's electronics system including power supplies (if required
in clamp on type), microprocessor, signal processing components and ultrasonic
transducer excitation circuits, may be housed in one or more enclosures mounted
locally or remotely to the meter and is referred to as the Signal Processing Unit
(Transmitter).
Transmitter
a) The turbine flow meters shall be inline type & shall be provided with flanged end
connections, the facing and finish of which shall be as per the piping
specifications. The flow direction shall be clearly stamped or cast on the body.
Following standards/ codes shall be referred:
c) Over range protection for the meter shall be atleast 130% of the specified range.
d) Terminal Housing:
Flying leads are not permitted. Proper NPT cable entries shall be provided for
termination.
The terminal housing shall be suitable for the area classification indicated
elsewhere. The enclosure shall be certified by a statutory body such as ATEX,
BASEEFA, FM, PTB etc. for following requirements as a minimum:
Flameproof housing shall also be made weather proof to IP 65 as per IEC 60529.
e) The turbine meter shall have dual pick-ups with dual pre-amplifiers. Fidelity and
Security of Flow Measurement Pulsed-Data Transmission Systems shall be in
accordance with API Manual of Petroleum Measurement Standards, Chapter 5
Section 5. Any unused pick-up amplifier combination shall be covered as per
area classification requirement.
f) End Connection:
Flange face finish shall be as per ASME B16.5. The face finish shall be as
follows:
g) The material requirements for Turbine Flow Meters shall in general be according
to the pipe class as specified in the PMS. The Supplier shall ensure that all
wetted parts are compatible with the process conditions. Rotors shall be
constructed from Ni 200 or better. Bearings shall be made of Tungsten Carbine
and shall be of self lubricating type.
Totalizer:
Local totalizer with one non-reset able counter and one manually reset able
counter, 6-digit LCD digital readout, rechargeable / permanent batteries, battery
charger (in case of rechargeable batteries) and mounting accessories for 2”
stanchion shall be provided with the turbine flow meter.
The totalizer shall be capable of operating in the absence of power and shall
display the readings when requested.
Battery change shall not cause any loss of data. Permanent batteries (Li-ion or
equivalent) with a minimum life of 3 years shall be provided for Totalizer.
Transmitter
The flow straightener may be of either tube type or vane type. Material of
Construction shall be 316 SS or superior material and supplied from meter
supplier.
11.1 GENERAL
a) Pressure gauge measuring element shall generally be the Bourdon tube type. For
measurement of slurries and viscous and corrosive fluids, diaphragm seals shall
be used. Diaphragm seal shall be catalog listed model of the transmitter OEM
only.
b) Case material for all Pressure gauges, transmitters shall be epoxy coated
Aluminum or SS.
a) Pressure gauge case shall be liquid filled type with external zero adjustment.
b) Case diameters shall be 6" (150 mm).
c) Instrument air/gas supply gauges used as output gauge may have 50 mm (2")
dials.
d) Movement shall be 316 SS or SS304.
e) Accuracy shall be ± 1 % of full scale.
f) Gauges shall have micro-meter pointers and white dial with black numerals and
markings. Gauge pointers shall be adjustable without removal from shaft.
g) Pressure instruments in fields shall have 1/2” NPT (M) bottom connections.
Diaphragm seals with capillary shall generally be 1 1/2" flanged or as specified
in datasheet.
h) All pressure gauges shall be with shatterproof glass.
i) All pressure gauges with maximum operating pressure exceeding 60 kg/cm-g and
gauges in toxic service shall be solid front type.
j) Surface mounted type pressure gauges shall be used for high temperatures
exceeding 200°C.
k) For pressure gauges, multiport gauge valve shall be provided as per data-sheet.
Internal or external type radar type level instrument shall be selected based on the
vessel/ tank configuration including size and location of nozzles and also the process
application. Suitable type of antenna shall be provided for the specified process
conditions including dielectric constant, viscosity and performance requirements.
Inclination and orientation of antenna shall be adjustable to avoid tank wall and
other influences. Condensation drip-off shall be provided. Material of antenna and
other wetted parts shall be selected compatible with process fluid and shall be SS
316 as a minimum.
Radar instrument antenna shall suit nozzle height. Type of antenna shall be
decided by the Supplier based on process conditions and the vessel / Tank
service conditions.
The Radar instrument at normal operation or during field service or bench testing
shall not generate micro-wave power levels considered unsafe for continuous human
exposure and shall certified as compliant to current International health
requirements.
Radar type level instruments on Oil tank shall be non- contact type.
Radar type level instruments on all Water tank shall be GWR (Guided Wave Radar)
type. For tank height upto 3 meters, rigid probe shall be provided. For tank height
greater than 3 meters, flexible probe shall be provided for GWR level transmitter.
Transmitter
Differential pressure transmitters shall be used for longer range spans and where the
liquid is viscous, flashing or subjected to agitation.
Transmitters for closed vessels shall have correction for suppression or elevation.
DP measurements shall normally employ a filled reference leg connected above the
vessel liquid phase, with a reversed transmitter output. Filling of the leg shall be by
condensation method where possible. Where filling of the legs by gravity feed from
sloping impulse piping cannot be guaranteed, constant head chambers shall be
installed.
Transmitter
a) External displacer cages shall be supplied with side/side connections. Where this
is not possible top/ bottom or side/ bottom connections may be provided.
Displacer instruments shall be Torque Tube type construction.
b) Differential pressure level measurement is acceptable for remote level indication
for level range of 1524 mm (60") and above. Seals and wet leg compensation
shall be provided as required. These instruments shall have zero elevation/
suppression adjustment wherever required.
c) All level instruments in toxic and hydrocarbon service shall have blow down
connections to a closed drain.
d) Rotatable heads shall be provided for displacer type instruments.
e) For external cages, block valves are to be installed in horizontal position of both
lines at the vessels. If a vertical nozzle is used the valve shall be arranged so that
no sediment pockets are present. A valve shall be installed to permit draining
each displacer cage and piped to drip pans or deck drains.
f) Units for level indicating scales shall be- 0-100 percent.
Transmitter
a) Body (Float chamber, Float, Float Guide tube & spring assembly) shall be as
specified in Datasheet
b) Float design i.e. its type, size & material requirements shall consider worst case
process conditions also like specific gravity, temperature & pressure specified in
process datasheets.
a) All gauge glasses shall be armored reflex or transparent type with body and
cover material of forged carbon steel as a minimum or as specified in Datasheet
and shall have tempered borosilicate glass with suitable gasket. Sodium glass
shall not be used.
b) Reflex type shall be used for clean and colorless liquids, for liquid level
interface. For low temperature, low boiling point service, large chamber type will
be used. Transparent type will be used on acid, caustic, dirty or viscous, colored
liquids and liquid interface. Transparent type with Mica or Kel-F shields shall be
used for treated water, boiler and condensate services, and for corrosive liquids,
which will attack glass.
c) Transparent type of gauges shall be provided with integral illuminators operating
at 230 V AC, 50 Hz. supply and suitable for electrical area classification
specified. The illuminator shall be supplied complete with mounting brackets and
lighting fixtures.
d) All gauges shall have top and bottom chamber connections, unless otherwise
specified in datasheet.
e) Vent and drain connections shall be fitted with isolation valves and plugs
respectively as per details specified in datasheet.
f) The visible range of level gauge shall be limited to maximum 1490 mm for
single level gauge (However in case of top and bottom type level gauges up to
1740 mm C-C distance can be taken).
g) Visible length and C-C distance of the level gauges shall be selected as per
Datasheet requirement.
h) In general visible length of level gauges shall be selected from the following
(however firm requirement shall be as indicated in datasheet)
220 470
470 720
720 970
980 1230
1230 1480
1490 1740
k) Gauge glass cocks shall be forged off-set type with an integral ball check and
back seating stem. Primary isolation valves are normally required in addition to
the gauge glass cocks.
GENERAL
a) RTD type temperature sensing elements are to be used for all electronic
temperature transmitters and measuring systems. The sensing element shall be
Platinum 100 ohms at 0°C to IEC 60751, 3 wire system.
b) Fieldbus type Field transmitters shall be SMART type compatible to FF protocol,
provided with inbuilt digital output meter in engineering unit/ output gauge at the
transmitter end.
c) Transmitter for interlock & shutdown application shall be 4-20 mA, HART
compliant, 2 wire type.
HART type transmitter shall be 2 wire type. The transmitter shall operate on 24V
DC and shall be HART compatible, intrinsically safe certified.
TEMPERATURE INDICATORS/GAUGES
THERMOWELLS
e) In special applications, not covered above, supplier shall decide the immersion
length based on actual requirements. Immersion length is based on 200 mm
length between flange face and inner wall of pipe.
f) Test thermowells shall have screwed plug and chain.
g) Thermowells for insulated vessels and lines shall have extension necks.
h) The thermowell tip shall be at centerline of pipe but immersion length shall not
exceed 400 mm for higher size pipes.
i) Thermocouples, wherever specified, shall be as per IEC-60584-21/ IS-7358.
ii) Plug in type connections shall be provided with field communicator. Necessary
interconnection cable and any other accessories required for connection shall be
supplied by supplier.
GENERAL
a) All relief valves of size 1" and above shall be full nozzle full lift type. Relief
valves with size less than 1" shall be base or modified nozzle type.
b) Relief valves 1" and larger shall be of the type having a nozzle bushing which
extends through and beyond the base of the inlet bolting flange, and which forms
the gasket bearing surface for the inlet flange.
c) Flanged relief valves for process piping, excluding steam and air pressure
piping, shall be either the enclosed spring type or pilot-operated type.
d) Conventional valves shall be specified for constant back pressure while
bellows seal type valves shall be specified for variable back pressure more than
10% of set pressure or where the service is corrosive. Pilot operated pressure
relief valves shall be used for special services and where set pressure is closer
than 10% of the operating pressure, in general. Balanced bellow materials shall
be SS 316/SS316L or superior material.
CONNECTIONS
a) 3/4" x l" thermal relief valves may have screwed ends All process relief valves
1" size and larger shall have flanged inlet and outlet connections The outlet
flange of relief valves discharging into closed systems shall be at least equal
to the pressure rating of the outlet system at operating temperature.
a) For control valves and shutdown valves actuators shall be spring return
diaphragm or piston type. Necessary dedicated Air filter regulator (AFR) shall be
provided as applicable for positioners and solenoid valves, pilot valves etc. AFR
filter size shall be 5 micron.
b) Control valves sizing shall be done as per ISA standard. Noise and cavitation
check are also to be carried out by supplier for the control valves. For valves with
cavitation, cage guided valves with anti cavitation trim shall be provided. For
valves with noise exceeding 85 dBA, low noise trim shall be provided where
source treatment is not adequate, path treatment shall be provided. Inlet velocity
checks shall also be carried out and if required valve sizes to be increased.
c) End connections shall be as per below:
i. Threaded eng connections shall be to NPT as per ASME B1.20.1
ii. Flanged end connections shall be as per ASME B16.5/ 16.47B.
iii. Flange face finish shall be as per ASME B16.5. The face finish shall be
as follows:
125 AARH : 125 to 250 micro inch AARH
63AARH : 32 to 63 micro inch AARH
iv. Grooves of ring type joint flanges shall be octagonal as per ASME
B16.20.
d) Cv testing certificates for each tag of control valve shall be provided to Client
(ONGC). Software shall be provided to store and access the as-built plant data.
e) Control valve sizing calculations shall be furnished for review and approval.
f) Standard control valve body sizes are 1, 1 1/2, 2, 3, 4, 6, 8, 10, 12, 14 and 16
inches.
g) Globe valves shall be used where throttling is required.
h) Butterfly valves may be used when low pressure loss and high capacity flow is
desirable.
i) All control valves must have sound levels less than 85 dB at 1 meter from
valve. Source treatment shall be used for noise control-as far as possible. For
very high noise levels Source treatment in conjunction with Path treatment shall
be used.
j) Valve stem position indicators shall be provided for all valves. They shall be
calibrated from 0% to 100% in steps of 10%.
a) If a substantial increase in future flow rate is indicated, reduced valve trim shall
be used.
b) Quick Opening & Closing trim shall generally be used for on-off service.
c) Control valves used in safety shut down service shall be single seated tight
shutoff.
d) Anti cavitation trims shall be provided for valves with cavitation in liquid
service.
a) Valve material shall be in accordance with the line classification and Piping/
Valve material specification. Flanged end body connection shall be used for all
valves.
b) Valve plugs, seats and trim shall be AISI type 316 SS or superior material except
if the normal pressure drop exceeds 7 kg/cm2 (l00 psi) or the fluid is flashing,
hardened trim such as stellite shall be used. SS 440C and Tungsten carbide shall
be used for erosive services and very high pressure drops
c) Generally, control valves shall be furnished with bolted packing glands and
Teflon packing up to 200 deg C and Graphoil packing above 200 deg C.
a) Smart Electro pneumatic Valve Positioners shall be provided for all valves on
regulatory control applications in Process Platforms.
b) The smart positioner shall be foundation fieldbus type. All engineering,
configuration, diagnostic and maintenance related data shall be provided by the
positioner. Fieldbus positioners must satisfy the requirements of the field bus
registration laboratory with applicable checkmark like Fieldbus foundation etc.
c) Fieldbus positioners shall have analog output (AO) and controller blocks (PID).
d) Fieldbus positioners must be interoperable and shall have valid interoperability
test clearance like ITK latest version for foundation field bus.
e) Fieldbus positioners shall support peer-to-peer communication with two wire
communicator and bus powered supply.
f) Fieldbus positioners shall not be polarity sensitive.
g) Fieldbus positioners in hazardous area shall be certified as per entity concept or
shall be FISCO approved.
h) In addition to operational and maintenance data provided by the positioner like
actual stem travel, input signal, pneumatic pressure to actuator etc the positioner
shall also provide cycle counting and store accumulation data to help keep the
control valve stem leakage in control.
i) The positioner shall also have built-in manual stroke button for stroke open or
close the valve for quick verification.
j) Valve's operating signatures in the form of hard/soft copy shall also be provided
for each control valve.
k) Valve positioners shall have minimum two nos. Air/Gas gauges.
l) Air/gas-filter/regulator shall be factory mounted on the control valve yoke.
m) In case of HART type positioner:
i. Smart positioner shall be a two wire device having 4-20 mA output signal
from the controller superimposed with two way digital communication in
HART protocol format. All engineering, configuration, diagnostic and
maintenance related data shall be provided by the positioner.
ii. The smart positioner shall provide HART protocol of latest version and
shall be suitable to operate with HART maintenance system (HMS).
a) Actuators shall be sized for throttling service at shut-off pressure. The actuator
shall be designed to move the valve to the failure position.
b) In general the actuators shall be sized for standard spring range of 0.2 to 1.0
kg/cm 2g.
c) Supplier shall be responsible for the sizing and selection of the correct actuator
for the specified control valve. While sizing actuator, vendor shall ensure that the
actuator is able to develop sufficient thrust to properly seat the control valve
plug/ disc at the actuator air pressure and shut-off conditions.
Self Actuated Control Valve drop shall be less than 10% of set point. For regulated
pressure under 0.7 Kg/cm2g (10 psig), a pack-less valve shall be used if available.
a) Shut down valves shall be of Flanged Full Bore Ball Valve with actuator.
b) Shut down valves shall be certified Fire safe as per API 607 or equivalent
standard by a recognized Third Party Testing agency, if specified in Datasheet.
c) All Shutdown valves shall be for Soft seated with Class A as per API 6D &
Metal seated with Class B as per ISO 5208. Metal seating shall be provided in
case of valves with high temperatures and high pressure drops exceeding the
capability of soft seats. For all other valves, fire-safe type soft seats shall be
provided.
d) Actuator type shall be spring return piston type with Quarter turn operation.
e) Body, trim & wetted parts material shall be as per Piping Material Specifications
/ Valve Material Specifications.
f) Butterfly valves shall be preferably of wafer type, suitable for mounting between
flanges. Other designs of butterfly valves may also be used, based on merit.
g) Trim shall be on-off type. Trim material shall generally be SS316 or as per
material indicated in valve material specification.
h) In case of ball-type of on-off valves;
i. The valve design shall ensure valve seat and body protection against
thermal expansion of the entrapped fluid when the on-off valve is fully
close.
ii. In case of ball-type of on-off valves for size up to 4" and rating up to
ASME Class 300, the on-off valve shall have floating ball design. For
ratings ASME Class 600 and above, floating ball is acceptable for sizes
less than 2". For higher sizes trunnion mounted ball design shall be
provide.
16.3.1 ACTUATOR
a) Quantity : 2 nos. per valve (One each for open & close)
b) Output Rating : 24V DC, 2 AMP (proximity NAMUR type, intrinsically safe)
c) Enclosure: Weatherproof (NEMA 4X).
a) Body shall be with retractable element bank. End connections shall be flanged.
Weather hood shall be provided, wherever necessary. Flame arrestor shall be
designed as per EN 12874 and certified by a statutory body.
b) Flame arrestor shall be designed as per EN 12874 and certified by a statutory
body. Deflagration and detonation type shall be selected by supplier based on
piping configuration.
memory, cabinets, and power supply so that system capacity can be expanded by
20 %, just by inserting I/O modules.
d. Each I/O rack shall have a separate independent power supply system. Each
power supply shall be sized to take full load of the I/O rack/signal conditioning
panel/rack and shall be provided with dual redundant power supply.
e. Each processor shall be provided with separate power supply. Failure of one
power supply shall not affect the system operation in case of dual processor
system. Wherever triple redundant system is specified each processor shall
preferably be provided with a separate power supply. Also separate power supply
must be provided for each multiplied process I/O channel.
g. The PLC shall have provision for interface with other host systems.
INTERFACE PHILOSOPHY
Gas Detectors shall meet all the requirement of OISD 189 as minimum. F&G
devices shall be explosion proof certified and IP 66 weather proof certified.
Hazardous area certification shall be by the certified authorities like
FM/UL/CSA/CENELEC/BASEEFA/ATEX & CCOE.
Mounting accessories e.g. mounting kits, Canopy, Tag Plates, calibration kit, Rain &
Dust protection cover, Splash guard, Ex Proof & Weather proof double compression
cable glands etc as required shall be provided for F&G devices.
IR Point type for HC Gas detection shall be provided. Principle shall be Diffusion
based Infrared absorption. Sensors shall be resistant to catalyst poisoning and shall
be "Plug in" type for easy replacement. Range of the detectors shall be 0-100% LEL.
Open Path type Gas Detectors shall be provided in Manifold Area and other
recommended areas based on Gas Dispersion Study.
Hydrogen Sulphide gas sensors shall be electrochemical and plug-in type for easy
replacement.
Hydrogen gas sensors shall be catalytic bead type and plug-in type for easy
replacement.
Construction
i) Protection against dirt and rain.
ii) NEMA 4 and 7 suitable for NEC CL I, DIV.1, Gr. C, D area. However,
Hydrogen Sensor shall be suitable for NEC CL 1, DIV. 1, Gr. B area.
iii) 316 SS/Epoxy coated aluminium Body or as specified in datasheet with SS flame
arrestor/Dust cover/splash guard/Weather Protection for outdoor location.
iv) Capable of providing self diagnostics.
Alarm Beacons
Alarm Sounders
Sounder shall be multiple tone type with a facility of user configuration. Sound level
shall be minimum 105dBA @ 1m. Sounders shall be operable at 24VDC from
system & shall be surface mounted. Enclosure shall be SS316/ Epoxy coated
aluminium Body or as specified in datasheet. Sounders supplied shall be hazardous
area certified.
Detectors shall meet all the requirement of OISD 189 as minimum. F&G devices
shall be explosion proof certified and IP 66 weather proof certified. Hazardous area
certification shall be by the certified authorities like
FM/UL/CSA/CENELEC/BASEEFA/ATEX & CCOE.
IR Sensor
The flame detector shall be performance approved by FM and complies with the
Automatic Fire Alarm signaling performance standard and verified as per FM 3260.
Smoke Detector
Type:
- Aspirator type in control room.
- Optical/ Photo-electric Smoke Detector. Addressable type in other building.
- Shall be capable of self diagnostics.
- Refer attached smoke detector specification.
Enclosure: As specified in Datasheet.
Mounting: Flush mounted the base containing and alarm lamp. Where the
detectors are not normally visible, lamp shall be remotely located
in a visible location. Remote indicator : Remote indication at a
visible place shall be provided for smoke detectors located at
hidden locations i.e. above ceiling or below false floor
Manual call points shall be Break glass type and shall be provided with SS hammer.
The unit shall be operable at 24VDC. Minimum two nos. of hermetically sealed
contacts shall be provided. Enclosure shall be SS316 / Epoxy coated aluminium or as
specified in datasheet.
Fusible thermal plugs shall be lead alloy type. Plug shall be mounted on fixed base
with provision of replaceable plugs. The plug shall melt at 85ºC.
The Closed Circuit Television (CCTV) system shall consist of the following units as
a minimum:
a) Camera Unit.
b) Video encoders (if applicable)
c) CCTV control unit
d) LCD monitors
e) Digital Video Recorder
f) Cables, cable glands, connectors and other accessories
g) CCTV Cabinet with all required accessories
Camera unit shall consist of Video Camera, camera unit enclosure, remote controlled
pan and tilt unit, sun shield, mounting assemblies and, receiver units, junction boxes,
camera poles (if required), shall be provided as required and suitable as per the area
classification. For outdoor applications and where there is a possibility of
condensation on the glass window, the camera unit shall be provided with an anti-
condensation space heater. Cameras shall be installed at the Entry Gate and other
vulnerable points to record activities.
The monitors shall be 32” color LCD monitors with necessary controls like color
brightness, contrast adjustment and monitor ON/OFF control. These functions shall
be possible from the monitor front.
The CCTV cabinet in Rack Room shall house the following components: (i) digital
video recorder(s), (ii) VGA boosters, if any, and miniature circuit breakers etc. as
applicable along with all required hardware accessories. CCTV shall have recording
and storage facility to keep data for 30 days.
In case of distance limitation of co-axial cable, the Optical Fiber Cable (OFC) shall
be used, which shall be CSTA (corrugated steel tape armored, electrolytically
chrome plated low carbon steel) armored cable. The OFC shall have FRP strength
member, loose tubes for single mode optical fibers filled with moisture resistant
jelly, moisture barrier of polymer coated Aluminium tape or water swellable tape,
inner sheath of HDPE and outer sheath of PVC.
In case of OFC, all the other required accessories like patch chord, patch panel,
optical transceivers etc shall be considered.
In general, the design of Gas metering shall be as per AGA-3, AGA-7 & AGA-9
latest standards. Following philosophy shall be followed for Gas metering station:
a. Gas metering station with one common filter and dual chamber orifice meter for
each of the eight local consumers‟ gas supply:
b. Gas metering station with filter and Ultrasonic Meter conforming to ISO 17089-1
V2 for GAIL gas supply with following :
Design, Engineering, Manufacture, Inspection & testing, Calibration, packing
and forwarding, Supply of all metering station instrumentation system including
real time density, pressure and temperature measurement for flow compensation,
redundant flow computers with all accessories like HMI with necessary software,
keyboard etc are to be located in the Control Room with serial link/hardwired
connectivity to DCS/ESD system, flow straightners for flow meters (except
mechanical pipes and fabrication material), thermal relief valves, Isolation
valves, mounting accessories and other associated pressure and temperature
instruments.
c. Gas metering station with filter and single chamber orifice meter for gas grid
supply
FF CABLE SPECIFICATIONS
Type A Fieldbus cable of minimum 18 AWG/ 0.8 mm2 shall be used for the Trunk
as well as Spur connection. Segment length (without repeaters) shall not exceed
1900 meter depending upon the number of devices connected. Cable shall comply
with FF- 844 FS 1.0 and IEC 61158-2 cable specification.
Fieldbus cables shall have characteristic impedance of 100 Ohms ± 20% at 31.25 k.
CONTROL & SIGNAL CABLES
The inner and outer jacket of the cables shall be made of extruded flame retardant 90
deg C PVC to IS 5831 type ST2. The O2 index of PVC shall be over 30. The
temperature index shall be over 250 deg C.
Signal Cables:
For 4-20 mA instruments : Twisted single pair/ triad cables shall be 600 V rated and
shall have 1.5 mm2 PVC covered, 7 stranded Copper conductor, 100% aluminum
Mylar shielding shall be provided with 25% overlap on either side and 18 AWG 7
strands copper drain conductor. These shall have PVC inner jacket, galvanized steel
armoring and overall PVC outer jacket. Ripcord shall also be provided.
Power Cables:
Power cables shall be as per IS-1554 Part–I with 3-core. Minimum conductor size
shall be 2.5 mm2. All these cable shall be PVC insulated and armoured and overall
PVC sheathing.
Special Cables:
Cables for special instruments like Mass flow meter, turbine meter etc. shall be as
per manufacturer‟s recommendation.
Cable Sizes:
Types and sizes shall be as follows:
a) Analogue multipair cables: Overall screen 1.5 mm2 conductors.
b) Digital multipair cables: Overall screen 1.5 mm2 conductors.
c) Digital core cables: For 24 VDC power, no screen, 2.5 mm2 conductors.
Multi-pair signal cables shall have individual as well as pair shielding. All cables
shall be provided with armor as per IS-1554.
Thermocouple extension cables shall be a minimum 1.5 mm2 for single, and 0.5
mm² for multi-pair solid conductors to IEC 584.3 (1989).
Grouping for instrument cables shall be as follows:-
Cables shall be clearly numbered at each end, on both sides of a transit point, and
when entering a panel, junction box or gland plate.
Multi-core & multi-pair cables shall be provided with 20 percent spare pairs of
wires.
Multi-core cables containing shutdown circuits shall not contain any other type of
circuit.
Cables for ESD or Fire and Gas service shall be Fire Resistant to IEC-60331. Other
instrumentation cables shall be Flame Retardant to IEC-60332.
Material of Construction for JBs shall be SS316 for Increased safety type junction
boxes and Copper Free Aluminium (Cu content < 0.4%) epoxy painted for explosion
proof junction boxes.
The junction box shall be supplied with bottom and side entry gland plates. Spare
entries shall be provided with plugs.
The junction box shall be environmentally protected to IP-66/ NEMA 4X for use in
areas and shall be weatherproof to IP-66/ NEMA 4X and ex-proof as per area
classification specified in the design basis for hazardous area applications.
The junction box shall be sized to accommodate 20 percent wired spare terminals as
a minimum.
Different signal types shall not be mixed in the same junction box. The junction box
number shall be clearly indicated by a black on white traffolyte label permanently
attached.
Separate junction boxes shall be used for intrinsically safe, shutdown, fire and gas,
service etc.
TERMINALS
Blue colored terminals shall be used inside control room equipment rooms for IS
circuits.
One terminal shall be provided for each incoming and connection wire. Only one
wire may terminate on each side of a terminal.
Where more than one wire is to be connected on one side of a terminal for looping
purposes, a pre-formed link between adjacent terminals shall be used.
Tubing and fittings shall be of 316 SS as per ASTM A269 unless otherwise
specified. The minimum size shall be ¼” OD. Tubing shall be supported and
protected by steel angle/ channel or ladder/ tray along the complete length of each
run and shall be fastened with stainless steel saddles at a maximum of 1 m intervals
on straight runs.
All tubes/ cables shall be properly laid on cable trays which shall be supported at
regular intervals.
The trays shall be made out of M.S sheets of 2.5 mm thickness unless galvanised
mild steel is specified. The width shall be so selected that 50% of tray space is
available for future use.
a) For all major equipment, the Contractor shall include normal start-up and
commissioning spares in the purchase specifications as a part of the equipment.
c) The Contractor shall also furnish list of recommended spares for two year‟s
trouble free operation along with the prices for purchaser‟s review and future
procurement, if needed.
d) All spare parts shall comply with the same standards and specifications as the
original equipment and shall be fully interchangeable with original parts.
e) All spare parts shall be marked with the manufacturer‟s part number, name and/
or reference number.
f) Contractor shall supply all special tools and test equipment required for operation
and maintenance of all the equipment, as part of the work and their cost shall be
included in the Lump sum Price. Contractor shall ensure that all such items are
clearly identified as to the equipment item for which that is required and
indicated in the bid.
General Requirements:
The Client reserves the right to reject any or all test and calibration work if found not
complying with the Client‟s requirement. The Contractor shall complete and submit
documentation for all calibration, testing and pre-commissioning. Client‟s
Representative prior to (transportation) shipment shall check out panels, consoles,
and packaged instrument assemblies for their compliance with specification
requirements.
All testing, calibration and pre-commissioning shall be done by the Contractor. The
Contractor shall also provide assistance as required during commissioning activities.
The Contractor shall provide suitable workshop facilities and shall provide all
necessary test and calibration instruments and equipment.
The Contractor shall verify in the presence of the Company Representative/ TPI that
all instrumentation in field and control room including local and remote/ central
control panels are complete and operable as per specification requirement by means
of inspection, calibration and loop testing. All testing and calibration shall be subject
to approval of the Client.
Contractor shall provide material test certificate including NACE requirements (if
applicable) for all instruments and items, Calibration/ test certificates for all
instruments including control valves, safety valves, Seat leakage test for control
valves, shutdown valves and safety valves, Test certificate for safety valve set
pressure and reseat pressure, Hydrotest certificate for all inline instruments, pipes,
tubes, fittings etc., Conformity certificate from sub-supplier.
Functional and simulation tests for all instruments supplied shall be carried out at
sub-supplier's works and witnessed by Purchaser/ purchaser's representative.
Flushing of Lines
The Contractor shall remove in line instruments like flow meter, control valves/
safety valves, if necessary, and provide spool pieces/ flanges prior to flushing of
lines.
Instrument air piping and tubing shall be disconnected upstream of all filter/
regulators before testing, the piping and tubing shall then be hydrotested and shall be
blown down to remove hydrotest water, slag and mill scale from lines.
Instrument air supply lines shall be blown with instrument air prior to connecting to
instruments. Instrument air mains shall be isolated from the instrument and
pressurized to 1.5 times maximum working pressure with instrument air, they shall
be isolated from the pressure source and the pressure reading on a test gauge shall
not fall by more than one psig in ten minutes.
Pneumatic signal tubes shall be flushed and tested with instrument air for any leak at
a pressure of 1.5 kg/cm2g. After pre commissioning the line, the source of pressure
is cut off and rate of fall in pressure shall be ensured to be less than 1 PSI for each
100 feet for a period of 3 minutes as per ISA.
Instrument signal lines shall be blown with instrument air prior to connecting to
instruments. All air/ gas tubing shall be tested and inspected by one of the methods
given in ISA RP 7.1 “Pneumatic control circuit pressure test”. Clean and oil free
instrument air shall be used for the test. Instrument air lines will be service tested
only for any leak after pressuring and isolating the main root valve by soap solution.
Impulse Lines
All process impulse lines shall be disconnected and flushed with potable water. Air
lines shall be blown down with filtered air. Hydraulic lines shall be flushed with
hydraulic oil. After flushing process impulse lines shall be isolated from the
instrument and pressurized hydraulically to 1.5 times maximum working pressure
corrected for ambient temperature. They shall then be isolated from the pressure
source and the pressure reading on a test gauge shall not fall at a rate exceeding one
psig/ hour.
For direct mounted instrument such as level gauges, level transmitters (displacer
type), level switches etc. the instrument loop shall be pressurized to maximum
operating pressure slowly and steadily with the instruments on line. The installations
shall then be isolated from main pressure source. The pressure shall not fall at a rate
exceeding one psig/hr.
Document Number Rev.
INSTRUMENT DESIGN BASIS 9658-09-DB-001 1
Triune Energy Services Pvt. Ltd.
New Delhi Sheet 45 of 51
16-QMP-05-3C
Wiring
a) The Contractor shall calibrate instruments in-situ also, when possible. Otherwise,
calibration shall be done prior to installation or removal. The Contractor shall
submit written calibration record in prescribed format for Company‟s approval.
The status/ progress of testing calibration for each loop shall be reported to the
Company.
d) All analog instruments shall be calibrated minimum for 0%, 25%, 50%, 75% and
100% upscale and downscale.
e) All Control Valves prior to stroke checking shall be internally and externally
cleaned thoroughly. The full stroke of valve shall be checked for opening and
closing, in the range of 0%, 25%, 50%, 75% and 100%. Any adjustments
required for obtaining full stroke and reducing hysteresis shall be carried out.
f) Cv testing certificates for each tag of control valve shall be provided to Owner
(ONGC). Software shall be provided to store and access the as-built plant data.
g) All test instruments shall have proper certificates and traceability of valid
calibration to national or international standard without which installation shall
not be acceptable.
a) The Contractor shall provide records of all above tests and provide reasonable
evidence of the satisfactory condition of test equipment. All errors of faulty
workmanship discovered during the testing shall be corrected to the satisfaction
of the Client.
c) All required checks prior to start-up are to be completed in all respect, result
recorded and approval of EIC for ensuring readiness of plant and all safety
aspects adherence for start-up is to be obtained by contractor. During the plant
start-up all the instruments calibration, controller alignment, trip point settings
shall be trimmed/ checked and confirmed so as to meet the operation
requirement.
d) Prior to guarantee run of any package unit, the vital instruments shall be
recalibrated and the results shall be recorded and submitted.
e) All the required testing equipments - duly certified by reputed national lab/
agency, tools and tackles, equipments etc., for calibrating, testing and
commissioning shall be brought by contractor.
Name plates and identification tags shall be provided to properly identify each
piece of instrumentation equipment.
All instruments shall have SS tag or nameplate of a permanent type with
identification number and service description.
All panel instrument nameplates shall be constructed of white laminated plastic
plates with black engraved lettering and securely fastened with 316 SS screws.
All front panel mounted equipment shall also be identified with a metal or plastic
nameplate attached to the rear of the device, and easily visible via the rear access
doors.
ANNEXURE-1: ONGC provided specification for Fire & Gas detection devices.
SECTION – 2
S.
No. Standard / Code Descriptions
AGA American Gas Association, Gas Measurement Committee
Natural Gas Fluid Measurement- Orifice Metering Of Natural
Report No.3 Gas
1 Compressibility and super compressibility for Natural Gas
Report No.8 and other Hydrocarbons
Report No.9 Measurement of gas by multipoint Ultrasonic meters
Report No.11 Measurement of Gas by Coriolis flowmeters
ASME American National Standards Institute/ American Society of Mechanical
Engineers
B 1.20.1 Pipe Threads
B 16.34 Valves Flanged, Threaded and Welding End
B 16.36 Orifice Flanges
2 B 16.37 Hydrostatic Testing of Control valves
B 16.5 Steel Pipe Flanges and Flanged Fittings Steel
B 16.20 Ring Joint Gaskets and grooves for Steel Pipe Flanges.
B 16.104 Control Valve Leakage
B 40.1 Gauges-Pressure Indicating Dial Type- Elastic element
PTC 19.3 Performance test code temperature measurement
ANSI/FCI American National Standards Institute/ Fluids Control Institute
3
70.2 Control Valve Seat Leakage Classification
API American Petroleum Institute
6A Specification for Wellhead and Christmas Tree Equipment.
6D Specification for pipeline valves
6FA Fire test for valves
Analysis, Design, Installation and Testing of Safety Systems
RP 14 C for Off-shore
Sizing, Selection and installation of pressure relieving system
in refineries
RP 520
Part-I –Sizing and selection
Part-II-Installation
RP 521 Guide for pressure relieving and depressurising systems.
4
RP 526 Flanged Steel Safety relief valves
RP 527 Seat tightness of pressure relief valves
RP 551 Process Measurement Instrumentation
RP 552 Transmission systems
RP 554 Process Instruments and control
RP 555 Process Analysers
Overfilling Protection for Storage Tanks in Petroleum
2350 Industries
607 Fire Safe Test
608 Metal Ball Valves- Flanged, Threaded and Welding Ends
S 2000 Venting Atmospheric and low pressure storage tanks
Document Number Rev.
INSTRUMENT DESIGN BASIS 9658-09-DB-001 1
Triune Energy Services Pvt. Ltd.
New Delhi Sheet 49 of 51
16-QMP-05-3C
S.
No. Standard / Code Descriptions
Vibration, Axial-Position and Bearing- Temperature
S 670 Monitoring Systems
API/MPMS American Petroleum Institute-Manual of petroleum Measurement standards
Measurement of Petroleum Liquids Hydrocarbons by Positive
Chapter 5.2 Displacement Meters
5 Chapter 5.6 Measurement of Liquid Hydrocarbons by Coriolis Meters
Natural Gas Fluids Measurement-Concentric Square Edged
Chapter 14.3 orifice meters
Chapter 21.2 Flow measurement Using Electronic Metering Systems
BS British Standards
1042 Measurement of fluid flow in closed conduits.
Flame arrestors- Performance Requirements, Test Methods
12874 and Limits for use.
6
5351 Specification for Steel Ball Valve.
EN 50288 Instrumentation Cables
6755-1 Specification for production pressure testing requirements
6755-2 Specification for fire type-testing requirements
IEC International Electro-Technical Commission
60079 Electrical Apparatus for Explosive Gas Atmosphere
Polyvinyl chloride insulated cables of rated voltages upto and
60227 including 440/750 V
60331 Fire resistant characteristics of Electrical cables.
60332 Test on bunched wires or cables, Part 3 Cat.A
60529 Classification of degree of protection provided by enclosures.
60534-2 Industrial process control valves-Flow Capacity
7
60584-2 Thermocouples-Tolerances
Thermocouples extension and compensating cables,
60584-3 tolerances and identification systems
60751 Industrial Platinum Resistance Thermometer Sensors
Electromagnetic compatibility for Industrial Process
61000-4 measurement and control equipment
Functional Safety of electrical/ Electronic/ Programmable
61508 Electronic Safety Related Systems
61131 Programmable Controller language
Industrial Communication Networks- Fieldbus Specifications-
61158-2
Part 2
ISA Instrumentation, System & Automation society
S-5.1 Instrument Symbols
S-5.2 Binary Logic Diagrams for process operations
8 S-7.3 Quality Standard for Instrument Air
S-20 Specification forms for instruments
S-75.01 Flow equations for sizing control valves.
S-75.03 Face to Face dimensions for Flanged Globe Style Control
Valves
S-12.13 Part I-Performance Requirements, Combustible Gas detectors
S.
No. Standard / Code Descriptions
Part II- Installation, Operation and Maintenance of
S-12.13 Combustible Gas Detectors
S-96.1 Temperature Measurement Thermocouples
ISO International Organization for Standardization
9 Measurement of fluid flow by means of orifice plates, nozzles
5167
and venturi tubes inserted in circular cross-section conduits.
NACE National Association of Corrosion Engineers
MR-01-75 Standard Material Requirements-Sulfide Stress Cracking
10 Resistant Metallic Materials for Oil field Equipment.
MR-01-03 Materials Resistant to Sulfide Stress Cracking in Corrosive
Petroleum Refining Envinronments.
NFPA National Fire Protection Association
11 496 Purged and pressurised enclosures for electrical equipment
72E Automatic Fire Detectors
IS Indian Standards
IS 8945 Electric measuring instruments for explosive atmosphere
Zener Barrier for Intrinsically Safe Process Control
IS 10398 Instruments
IS 3624 Pressure and Vacuum Gauges
IS 2848 Industrial Platinum Resistance Thermometer Sensor
IS 7358 Thermocouples
Ceramic Components for Thermocouples and Resistance
IS 8495: Part 1 Thermometers Part 1 : Terminal Blocks
IS 8784 Thermocouple Compensating Cables
12 IS 8935 Electric solenoid operated actuators
IS 9334 Electric motor operated actuators
IS 10189 Industrial Process Control Valves
IS / IEC 60534
Part 2 Industrial Process Control Valves - Flow Capacity
Specification of Thermal Evaluation and Classification of
IS 1271 Electric Insulation
Cable Trunking and Ducting Systems for Electrical
IS 14927 Part 1 Installations : Part 1 : General Requirements
Cable Trunking and Ducting Systems for Electrical
IS 14927 Part 2 Installations : Part 2 : for Mounting on Walls or Ceiling
Other Bodies
NEC National Electric Code
13
OSHA Occupational Safety and Health Authority
OISD Oil Industry Safety Directive
3. Suitable for Hazardous area Zone 1, Group IIC, T4/T5 for field MCP
4. Switch Type/Rating Double Changeover / 2 Amps, 24VDC resistive.
5. Protection for hazardous area IP 66 or Better.
6. Body Material Aluminum Alloy LM6
7. Colour Red Epoxy Paint Finish.
8. Entry 2 Numbers, Vendor to specify the size.
9. Power Consumption VTA
10. Approvals ATEX/FM/UL/CSA/CENELEC/BASEEFA/PTB/ATC/ CCOE
11. Make VTA.
12. Model VTA.
Volume
ONSHORE ENGINEERING Specification for F&G detection devices Section
SERVICES
DELHI Rev.
Annexure- I
Page : 7 of 10