SPEC. CIB
SPEC. CIB
TECHNICAL.SPECIFICATIONS
I
!
i l_.:,.
,---
I\
{ 1,,_...
r·
I
I
I
\.... ...
1··-..
I· -
,,..-,,.,,
,·
I
l....
I
t
[ ..
,, , .,
r
\
SCOPE OF WORK
,J
TABLE OF CONTENTS
1. Location
3. Breasting Dolphins
4. Platforms
...
DESIGN PHILOSOPHY
...
r-:
i
L.,
,·""'"'"'-,
'.
I
I
l- DESIGN PHILOSOPHY
r-
j ,1. LOCATION
The location of the crude unloading facilities .is at the
I northern shore of the island of Nusa Kambangan just op
I ·- posite the town of Cilacap and the nearby refinery on the
main land.
This location is favoure·d due to the following .reasons .:
- The location is sheltered from wave attack from the Indian
Ocean by the island. - •
- The prevailing Wil}9J3 are such that they push the ships
against the breasting dolphins. ·
- S !_,1=£;i.ent..:..§2.! d i§:...a:v:. .il.§,J?.!..:., and tim\e requil"ed to make
further studies·does not affect execution time.
The length of piles of platforms .and dolphins is rather
short, and increases in northerly direction (Java site),
becaus e the bed r9_:_ls- J;l.o - -" dip of 2 1".
1
.
A location on the Java site requires extensive time con
suming hy.q;rographical studies, in particular if a protec
tive JgJ?.:!:E..,fu. s considered, because of the disturbance of
natural hydrolog;ical .balance...
1-. ALIGNMENT OF ACCESS CHANNEL
.
The existing water depths of the approach channel to the pro
L1 jected Crude Island .Berths do not allow the passage of tankers
o;f 135.000 tons.As a consequence the existing fairway channel
,-· l S"o:i,·rcY\
t acapb.as to beadjusted.,
i'--'
Various alignments of this channel have been _studie , having
r- regard to naJ:i.tJca.l requirements on the one hand and to mini-
I-: •mizing :th.e...:.. ost-·ofdredging-of .soft and hard material o the
otne:t hand. -----·- >-- · ----·•···--«-
C
,,..,..11-, ,\
3. BREASTING DOLPHINS
The solution of a rubber fender mounted on a fixed structure
·: has been chosen because :
- The available soil data show .a vast variation in the_J:ied,+
rock levels , and it reaches levels up to 5 metres t<f
his,. affects the slender ratio of flexible fender piles.
•
2/ ....
L
\I
2 -
4. PLATFORMS
,} - They have been designed as small as possible to facilitate
the required equipment and piping.
•- The position of the .location, makes it impossible to connect
the berth to the mainland with an approach jetty; accessi
bility canonly be obtained with launchefs.
- The inner breasting dolphins are c nnecte <w±'th the platform 1
v±th-catwa3:e. by' c.o::hjo.(k"? ·f.o b
\,>
5.1. Flushing
V The requirement of Pertamina to unload both domestic, and
light Arabian .crude through all 30" diam. pipelines,
made it necessary to
.incorporate :i.n the design a f'lushing
system.
- It i.·s designed to tl:ush the 3O J2. l!ges with 1!. !;t · •·.J·
1
Arabian crude through a 18" diam. pipe3:_ine.
/ • ,..,e~"• •<' S' -,,,_,,., ,a,<,w,>M o _ »,M>-<o<W"'0N', - • - "'""M'='-""' ••" f' )
_ ,
• V • .,.
V
;·{,"':. !.',:)- "' I :.!1., ,--·; , , { ,'h"/J/;'_,l.. p, C..1,\,,,t.>-- ,,.,,··{ C H-<-\..1 ,\ V /[) i /1
Furthermore· it is advisable ..that. the domestic crude ,,, t
lines hould oe·dreifii°a''"p ;,:operly#and 11-s_ d. in C9ntractor' s /
0
I
design are p g launchers and receivers for ich op ,;i.on§..l
prices have 'been quotedffi • •
Fire Fighting
a. In accordance with the NFPA code one extra diesel
driven fire fighting pump per platformwill be install
ed. This pump is connected to the fire fighting system
and will start automatically in the event that the / i
electrical pump fails. .I
r }"' \
r7 ...
The supply and installations of the two diesel driven \;1,.Ji\
pumps have been included in Contractor's price. (c.;,t,:-'J •••
3/ .... \) \
b. It is advisable to install a f'oam/water :f'ire f'ighting
installation, therefor on• tlQ:t;_m one f.Q.11m-..llt}.i:t
and one _fggr1;i./wt:1_ter mq!'l,;i.tor has been designed: :y<5:f.•this
item an optional--estimate has been previously
indicated but is not at_prese included._in..,the
_conti- _c.t price.
, c. For the pr.oteC.E_ QL.:t e. ]2i §_Jmg,er......t.h.e.... J,at!Qll!l a·
foam/water screen and a sprinkler system around the
outer piles can be designed.
For this item an o Aonal estimate has been previously
indicated, but is not--at pres,ei;it
included in the Contract Price. ---------------------•
,.-
.,..,.----··
/
5. 3, Berthing Aid System
It is advisable to install a bertM.ng aid system, the
results of the recordings can be of great help in case
of damages atter a collision, when insurance claims
ha.veto be s<':!ttled between Pertamina and ship owners.·
For this item an. optional estimate has been previously (•
_ .. ---· ... •
.:q;1? . ! =: !: tc_;;: !; - --
r-"" •
SCOPE OF WORK
The new facilities will be of the island berth type, which will
be connected with the refinery by sub-marine pipelines across
the channel between the island of Nusa Kambangan and the main
land.
The new.terminal will have a lay::_out employing.two _crude oil
unl o a d i n g -
platforms
.. ·
protected by--·-
four
- breasting
.. ..
dolphins
. - -- · - - ---, ""'""'"- .... . """"-•- , .,,,,_,. ,,- ,-·, ,.
each ,_
_ and J;>rovided with s- y run.e>p;r::irig c:lal hins Jfl the :11?0: I:e\.!- 11 s.
The pipelines will..:r.un first to the shore tii ;:r r·;;om, . ,
there run further as a sub-marine pipeline to.Java.site, and on
land to the tankfarm south of the city of Cilacap.
The existing access channel wliich can reach the new location
has to be deepened, lengthened and its lay-out improved.
The design has been based on the available data regarding
soil-, wave- and wind conditions.., in particular on :
"Geological investigations in the Crude Island Berth area,
Cilaca.p, Indonesia", for Fluor Engineers and Constructo.rs
,Inc. by Geotechnical Consultants and Survey B.V. "Fugro-
Cesco", The Netherlands, Report no. S 0005-1 31st January
--- ·~· ,,_ ••••• ··----.,.,--------
1975.
'
L
DESCRIPTION OF THE WbRKS
TABLE OF CONTENTS
if:
1. . General Description
Geographic co-ordinat s
3. Meteomarine conditions
4. Water .Depth in Access
5. Channel Ship's dimensions
,---
6. Subsoil cond:itions3 rock conditions
7. Seismic
8. Plat.forms
9.• Breasting dolphins
10. Mooring dolphins
11. Piping
12. Unloading crude oil .facility
13. Fluslil.i;n.g.system·
14. Bunker fuel system
15. Mechanical.·installa:tions
15.1. Fire fighting system
15.2 Gangway tower •
15.3 Flushin pump·
15.'4 Loading ,arms
15.5 -
16. Q.R. hooks and caps-t;ans
16.l. Electrical installations
16.2. General
16.3. Cables
J.'.7.. ,. Cathodic protection
Requirements and exclusions
17.1. Metering unit crude oil
_17. Booster pump
2.
17,3. Velocity unloaded crude oil
17.4. Fresh water
18. Dredging·
18.1. Channel and turningbasin
18.2. Dumping area
18.3. Maintenance dreding
l
Long span cat walks link the inner breasting dolphins with
the loading platforms..
Each platform is provided with ::e.'?.'l:'1: r,....op rij:t <:i. lQ Q:!. E:L. ;:!0-S,
fire f' £;!J;t::LJ:1g }!.l:fl;J.itors; gangway tower, berth control room...
and 1:ullding H·;· • ' ~-----····· •• :' • ·: •••••• "
Geographic·Co-ordinates
,
E 281 645,00
, ...-,
, ..Berth 2 N 9141 612,48
.
E 281 983,58
2/ ....
II
2
/
/
- Currents :
Maximum .2 knots
Sea table 18
In the Cilacap channel there is an outgoing - and
.ingoing current o:f the semi diur.nal type.
Ships' dimensions
3/
Subsoil Condition, especially Rock·
II:° , _,
bearing capacity of. the b,edrock has been. given a.s 5 times .•··
compressivE? strength:.of :the_;bedrock.'
top iof 'the beclt'ock .range .,1';6rii_·:5:o#:: to 26,5 metres .•.
'.'\ < '.,:,:.< :.; ),,::\tt-:\·j::\,i·::<·.<··- •·:·¥: \. ::·i, \) .:.\?:; ' ---{..:- i..,;,. .,/
',,·F"f/ .. .>",- ; ,.- '.
4 / ....
Se i·s m
A sumei : S ismic
8. Platforms.
J The dimensions o:f' the platforms .are 23,0 .x 23,0 metres. -
-;----;-:--- ··. "> ., ··• .. ·: - ... ·-:-7'--".. ' -· -
- Two types -of breasting dolphins .,,, inner and outer - will b_e
provided. • .- -- - ._ - - ---
' Plans and typical section a.re shown: on_ drawing No. 105.
---- .:,.,--- ' - ' -
Only. the _g:u,t_fil: breasting dolphins will be described as the-
inner dolphins a r e- similar but s:n.a.l.ler. -
The breasting·dolphins are of-the so-called fixed type that
means a concrete superstructure founded on a group of raker
piles._The absorption of the berthing energy .is effected .by
'=--- • i:ubber( J fJ/i -'.t th:?front: f- he dolphin. •
- The raker• piles·-will cater :for the. horizonta-l .forces :result
. • ing f'rom the .ship's,:impact..:;:f}J ,: \:>•'.··- ·'···-·- •·--;...<
v
The inner bre s:ting dolphins will be provided with a double_/
g_uickrelease hook _75 tons capacity.and capstan.
10. / 1
-
Mooring dolphins, •
11
The raker piles of the dolphins must be anchored into the rock
adequately.
5/ ....
'.'t'':''
•.· ··'
Coaltar ena:melfv
glass· filter_ •
.• .. . ,:l_it•t :. :
-
- r·
6/
>:· ·.. ,>:<..• '."."_;:•.,; ,•,,-·:>·, - • : _•· :_": .:,'.',<: '--- >/·1·_-.-/, .::·...",_:"·,'-, ,, y : ..-::,; _ch it;), : ;•••:• :,l,_¾ - z ·. :.,•;1-:•,•:{:
..''.f
•
!
' . \ - •
:, y.:: <
:t'lushmg ..lme ,diam. f ¢ .18,....i. · .. • .
j Btmk.r fuel
·
14. ii •.
• ••• .. One:riiel - :i.1 pipeline diam( will run from the refinery
to•i;;he loading facilities of the·tankers situated on both
platforms. Therefore·each platform will be connected to the
mentioned. ;f'uel oil pipeline. ,:§;. c::E:,.J?,;!:,!!; J,2m;will be provided
;;·. tl !n!it af! ::%at:rs. ! ; 1
:ni \r t ormal ••.
printer ·wil.l 1:>e .located on each.,J?lat]'oriii"as·shown on the •
•· d:rawings:of Fluor ..••
7/ ....
Mechanical Installations.
• i5 · 1/Fi!e· :fighting' :syst m:•·
·J The basic price 'of the quota.ti;n has been based on the
• mentioned drawings of Messrs.· Fluor. 4
Flushing Pl.m!J2•
pupplY,:,,c.o.sts of j;ll pump a.re in,c;Lude.d in Contractor's
price, installati.oh·costs are.excluded-.
Loading arms.
• f'\ / )
_(!s·..t·l·ch·.•·,·1.·cks_a_n
loading arms type MD or equivalent size (12"''
<,i 60 feet, complete with power pack and control
equip- ment.
a;· ....
, 1 .
· - The control• desk-to the loading arms
into 'the contror room of ·the gangway ;tower. •· ·
,,;
': ·,:
;·.· • "' • ,
10 / .........." ..
I ••
There has not b a.de 'EWY provi ion for installation of
a,,,.l!le e:e;IJ.g.....YJ:lit . on . the .. plat:forms .•as it has been as
smned that these one( s) :should be located in the tankfa.rm
.of the
refinery.· :,,.·•.. : • • · -·- ·.,··- ··-·-··
It has been assumed that:: the .flow rate of the crude oil vrill
not exceed ·a, value :-of 3000 litres 1>er second in the 30II.
- -- f •"' · ··''"'1" 1•
pipeline to ·the. ref ine e y . . '. . • · .. . ·
> ; , . ---- - --- . . "''"•' '''"''''·""""'"' f
11/ .. •·• ..
On awing no.3578;.;81..;oo.;.003 a: general outlay is
dredging works;:c·hannelaJ.ignment: .tur:q.ingbasin
. The \ottom; {' of·•th;;. annel -vill be [email protected]!l. · the clepth v1il · ·
be 14. 5 m', 15. 5 :iii.. . ,(J:6.5 Jil1 /and l. 7. 0 m' - L.L.W.s ...for .the·,
;\f?f? :t
outei::·: s '.'': 't'?;;:'. :i::··7:zo;s: : .• ··.•· ...• •'. .. <: •.
'.,:./ c:.:::••,;,:_ ...•f·\:<i /}y;,, ;. .:t·/ )':'.:;:/i.·· '. -:.:/,,,;, -::.;::', • •.•. ••• .d:.:,?: ::t :: )?:.'.'•t,\
_Besides··we ;have•;c:onstilted :well-known coastalengineers., owho •. -·• -- _/>·••· /)
• -also ·came ;,to :the! conc1usion;: based :on .current data, ·:to dump ·,:<
.• • the soil on<approximately:four ,miles•,from the .entrance. Through : :,
• the _governi:ng,.S.E. winds from·over·the .. ocean .during •the monsoon... .c:· <.>,:
. <period;; :.:with an extremely :long1ifetch, substantial swell ,occurs ••
i:n.'.the _area in,, front o:f:,the •channel .entrance. C ntinuous.../Ei!:Uld
transport :exists. in directi·on bay of -Cilacap during ,this period.
,,._:.,,,.:-;\'"i'' <·:: ·':·:· : . "j' -··:? ·. \:··,;;' ,-.:·- ;•<1:·f/'' ,...,,, ·"·••' -,·· ,, ,,,,/,"""'·"'' "'"'""•
12/.........
After completion :!of·the,'cap1.ta.ldredging in •1975 several hydro
graphical ,surveys. were executed during .the successive years.
• .• < . • • •
,:,/'.
. .··•·.
.-..,.,... -,i.
From the differ nce...:eh ts it was .made clear that siltation .in.
; the .newJ.y·.·dredged charinel·was remarkably ·1ow..
• . It could be concluded :f'r m the pa.st yea.rs,. that the r.iver Kali
•••• · f& iii {l'i:; l yt : f t/rt · :m f-;f:t ;
quite'in a situatiori'of equilibrium with the environment con
cerning movements.iof sand ,f'rom the bay of' Cilacap.
Our considered !ppinion would··be; :.that the · future·.depth.· of' 14. 5
.m•/.t.L.W,.$;,·alsotwill.:not:..be .'effected and :will turn out to
·be ..stable. ,. ,f: ::;? :'•\t\·,:: :'<;'hf .· :_ ·;':·••···• . ..
In orde:r to'be/safe.it'W1.y.be advised.not to deviate from the
original ideas and:again:project· ·the• dump;i,ng..area.,:for soft
. , ir '·· ' soils· on at .least ,4 nautical miles :from the channel entrance
"'. ,.(;:t'{,i •
.. S?rF as indi t n ,..ru:- ;;1 , · ''
18. . Deposit of -Ro k-: >; : ,''.'.:;:: ;;-,; ;<ir \·
_ --.·-.-.·.\:_.?}
n_i_s_.-· _;.. .
. -
r:/'.,:_::_>.\f\_:(:\r.t:_i,,,}·Jit\,·,:•
. - - . ;,';>···\.''•'.
- wind,
,. .,...,.
waves and
, ,' .,,.,.,,,,..,,_
current.
J
5.2. Loa.ding Platforms<.
deadload + live
normal-- working stress
load+
safety factor for pile
r;v{/ q , /iek -· is capaci y 2, .
--
'---, ,;,.•
I
'"
5,i. Soft Soil.
.3. Navigation.
5,4. Conclusion.
1. Civil Works.
P;ile Driving
Each platform consists of a reinforced concrete deck support
ed by concrete beams The whole superstructure is founded
on a group of vertical piles,. driven down to the load bear
ing strata, and A-frames anchored into the. rock, which great
ly stiffen the structure against horizontal movement.
2. Anchoring of Piles. ,
' ' '
drill
points mentioned above ·Contractor has; used.this
technique recently in· similar conditions. For thi.s present
operation two drilling rigs are envisaged.
Upon completion of the drilling the anchor ( a H-profile)
will be lowered into the hole and grouted up to form a·
point capable of resisting the design loads.
2/ .... ·8 ••••
=• -'-"''U. ·a.c.u.u..1....rectangular
dredged On the shore or. on the island •
a heavy winch is situated'and the complete string is pulled
with a special pulling head at the end of the pipe •either
direct by "Winch on· islan1L,or via a dead. man and winch on Java
::ng stresses
stren6: h t}he
?l::
pip ·)J/fjt{(::-: ft·•. 7,·- ..
: ce:/ ;- 0pecific 7ield-
> --•.,\··,,: •
5/ • • • e • • •
- 5 -
" /•• -:::;/In. --· y;en.t...J:t. xaule,:f'tt. into the overall time schedule,
1·i1 • .i Con_:tr.§._Q_t.or.:rna...o.ei::;;i.c;\e to use tqt2 l:l9pper p.:r;t;q,g ,,. which f0r
( the opportunity will be modified by adding a ri,:,per onto the
I suction-heads, the s:poil also to be dumpi;q._ QP. 39Q.m' .
.,•. I
11
,I The·working method ana. the pri(! ..r .."E,!:. d on the assu:mpti.on,
,:t ) l ;:n ?'W' = : '{: t l 1!' Ei :fr,f; t.:. !_! t if so required'!l• cie::,
5 ,i3. Navigation
\/ The choice of the hopperdredger Johanna Jacoba does also comply
with the requirements of·other shipping traffic to and from
the harbour of Cilacap.
Contractor's ship being of not too big a size (3000-4000 m3)
supplied with "bow-thrusters" will not hamper the normal traffic,,
and can turn very fast, when after it returns empty from
I the dumping area, it has to manoeuvre again into position to
\
\,/
/ restart dredging-a tivities.
.5,4. Conclusion
From above mentioned follows that the choice of the
hopper dredger Johanna Jacoba is based on.
- Excellent for hard sand as well as stiff clay-layers,
be cause provided with the so-called "active heads:.
- Ships of 3.000/4.000 m3 provided with "bowthrusters"
are well manoeuvrable and will not form an obstacle in
the normal traffic.
-.Well able to work under the prevailing conditions of
swell in the area of more than 5 ft.
- Suitable to work in "hard-material" area's when modified
1
"j JJ---= by adding a "ripper" onto the suction head.
7 "'-1, i.-t,,.l-
_
, Plant List ( Subject to modification with respect to availability etc.)
Nos. Description
1. Piling Work
J
2.
1
1
Tugboat 400 HP
Small Service Boat.
Drilling- and Grouting Work
l Barge 36 x 12 mtrs.
1 Crane RB 22
1 Concrete Mixer Cap. 500 lt.
4. Concrete vibrators.
G e n e r a 1
1 Crane Grove RT 60
l Tractor Ford 55 HP
1 Flat Trailer 10 ton
l Welding pontoon 8 x 4 mtrs.
4 Welding generators.
l Serviceboat ..
l Tugboat 400 HP.
5,j Specifications Hopperdredger Johanna Jacoba
Width 17,50 m.
Depth 6,95 m.
Maximum draught 6,23 m.
Suctiondepth 30 m.
Accomodation 42 persons
T. Dredging.·
;, 2. Civil Works
,k.
3, Piping - Su1:imar.ine
5. Utilities
a). Berthing aid system
b) Fire fighting system
c) . Communication cable
a.) Cathodic protection
e) water·
1. DREDGINGWORKS
1.1 General
'
c)· Wherechanges in depth of the accesschannel are indicated,
those changes shall be effected with a slope of one
vertical to ten horizontal (1:10).
.,,· ••,--------------------;.,,.,
,./,.,. . )
d) A tolerance
'
tered in the dredging l'l.;t: i:i ,which have tcL,.be removed, then
'•,... ,.,._ ,.. ,· .. -•-"'''·•>•,;,o.-\1\.. -·" "'·'-""''""" " - • ' ' •
1.8 Radioconnection
a) The
autca:rmming soft m... t r.i.§.J.. J;'t1 !. . be evenly deposited
sea at at· a distance ol{ nautical mil s)f'rom the 17 m
\ --·· ._.,_.,..........,.....
depthcontour.
b) The 6,;tc fu -; k\shall be deposited alongside the
Acces - : i-- -;· distance of at least/"300
\
0 ·
"---·· .. ,,·/
r
2. CIVIL WORKS
2.1. GENERAL
to
t_!? top ·.of pile: •••
•' .-•--• <·•·••► •"'"•... • •• ,, c"
Pile Type
Dimensions of Butt, Tip, Length
Elevation of Cutt-Off level seabed level, toe level
Location and Identification
Time and Date
...
\
\
2. 7. TIMBER
a. All timber for the permanent works will be of the best g_ual.ity.
It will be free from sap, clei'ts radial cracks, long loose
or dead knots, or other imper:rections..
d. Assumed environmental
data: Current 2 knots .at
surface.
Wave during installation maximum l roete:r,per:iPd 7 seconds.
TotaLcurrent near bottom ..is assumed to be:l m/s.
' '
As a guidance:
Rules for the Design, Construction and Inspection of
Submarine Pipelines and Pipeline Risers.
(Det Norske Veritas DNV).
I
b) inclusive..
b) Diameter inclusive.
4a.2. FLANGES
-
API Std. 605 class. 150 lbs WN RF suitable for
wel- ding onto line pipe to API 5LX Grade,X52, bcrred
-
to ,• suit wall thickness of pipe.
Material, carbon steel according to ASTM A-105 or
equivalent, with max C 0,25 .%.
4a,3. FITTINGS
•'
The pipe nipples shall be•.cut from seamlesi:3 pipe
according to ASTM A-53 Schedule f6: )
0-#'"v
with
automatic vent upstream of the meter, will be provided.
4a.8. TRANSPORTING UNLOADED CRUDE OIL
of of 40 m we.
4b LOADING ARM SPECIFICATION
4b.l.
SCOPE OF SPECIFICATION
b. Berth no. 2
SITE DATA
b.
console.
4b. 8. CONTROLS
4b,9,5, MATERIALS
4b.10. LUBRICATION
4b.ll. CONSTRUCTION
4b.13. INSPECTION
,.,,,,,·
/.------- · •
'
Cod.es:
ASTM - American Society for Testing Materials
AISC - American Institute of Steelconstruction
ASME - American Soc.iety of Mechanical
Engineers NEC - National Electric
Code·(U.S.A..)
API American Petroleum Institute
ANSI - American National Standard Institute
AWS - American Welding Society
IEEC - Pref. 141 & 142.
4c. GANGWAY TOWER
.
stairways giving access at a .suitable le vel to a gangway
assembly arranged to travel vertically up and also to
swing
through both vertical and horizontal :planes.
Data
Platform decklevel
... 4,oo above MSL
.m
. Max!, tanker deck height 18,00 m above MSL .
Min, tanker deck height . 2,50 m above
MSL Distance of berthing line to platform edge 3,00 m
Max. outward drif't 3,00 m
Longitudinal dri.ft 3,00 m to
Floodlights
4c.3.3. Materials
a,. Steel
b. Aluminium
Minimum yield strength will be 31,,,000 psi. - a safety
factor of 1.7 will be applied.
• 4c.3.4. Gangway
, self-contained.J;tY-
draul.ic be provided consisting of an electro
hydraulic necessary fittings,
gauges, strainers, safety devices etc. An over-ride control
system will be provided, preventing damage to the system
'i,"
All controls for the vertical and horizontal swing and for
the sliding of the gangway as well a.s the controls for the
stores crane and the loading arms.will be located in the
elevated control cabin.
4c.,3.8. Protection
L
)
All brakes, switches, interlocks, etc. will be suitable
protected against the weather.
a. General
All structural steel. wi.11 be manufactured by the
"open hearth11 or electrical furnace pr.ocess o:r
alternatively by an,approved oxygen top blown
process.
b. Tubular Sections
C,
Electrical Equipment
4.c.4.6.
Hydraulic System
.
Hydraulic lines will be steelpipe or tubing flexible hoses
,t•;,w0>W·""
)
electrical isolation.
General
A control panel for the gangway and the stores crane will be
installed in the cabin, whereas ample space will be
available for the installation of the loading arms control
panel
( by others ).
From the control room platform a fixed cage ladder leads to the
stores crane platform.
4.c.6.0. PROTECTIVE COATING & PAINTING
a. Coating Systems
The supplier will submit for approval full details of
the coating systems he proposes to use, including the
manufacturer, the number of coats to be applied, the.
brand name and 'Colour of each coat, the dry film
thickness of the completed coating.
b.
Tie coat
An intermediate coat of colturiet Epicoat, minimum dry
film thickness l50.microns.
Finish
One or more··coats of vinyl acrylate, minimum dry
\
film
thickness 50 icrons - colour to be standard ·grey.
l
</
b. Aluminium parts.
4d.l.O. GENERAL
4d.Ll. Scope
4d.2.l. General
c,
The effort in releasing the hook shall not be more than
35 lbs even under full proof designed load of the
hooks. The hook will also release effectively with only
minimum tension on the hawsers of the ship.
lfd.3. 4. Capstans
Starting.pull
30.KN
Running· pull • :
15 KN
Rope spee(;l(max.
.20 m/min
): Electric power
5 .KW - 380
Pedal operated switch.
4d.3.5. Control.Equipment
4d.4.0. MATERIALS.
4d.4 1. General
a. General
c.
All mild steel plates and plate for structural
fabrica tion will conform to ASTM A36.
approved equivalent.
4a.4.4. Welding
5a.l.l. - One sonar control unit type DS 120, providing speed and
distance indication through two separate channels..
Speed range from Oto 99 ems/sec.
Distance range fro, 0 to 99 metres.
For mounting in a non-hazardous area.
(Office on platform).
5a. l. 5. The units area FLP/WP and basicly certified for use in zone
1 hazardous areas and will be supplied complete with support
gearbox and drive for manual rotation.
5c.
/0