Chapter 8 Network Analysis 2023 Solutions
Chapter 8 Network Analysis 2023 Solutions
Chapter 8
NETWORK ANALYSIS
1
Operations Research | Richa Saxena
Activity A B C D E F G H
IP - A A B C D E F, G
Construct the network.
Network 2: The following list of activities must be accomplished in order to complete a construction project:
Activity A B C D E F G H
IP - - A B C D E F, G
Construct the network.
2
Operations Research | Richa Saxena
Network 3: The following are the activities involved in a project.
Activity A B C D E F G H
IP - - - A A A B, D C, E
Construct the network for this project.
3
Operations Research | Richa Saxena
4
Operations Research | Richa Saxena
Network 7: Construct the network using the following list of activities:
Activity A B C D E F G H I J
IP - A B B B C C F, G D, E, H I
5
Operations Research | Richa Saxena
Network 9: Construct the network diagram for a maintenance job:
Activity A B C D E F G H I J K
IP - - A B A B C, D G, F E H, I J
Network 10: Construct the network using the following list of activities:
Activity A B C D E F G H I J
IP - - A A B, C B, C E E D, G F, H, I
6
Operations Research | Richa Saxena
Network 11: Construct the network diagram for a maintenance job:
Activity A B C D E F G H I J K
IP - A A B C C, D C, D E F G I, J
7
Operations Research | Richa Saxena
Critical Path Method (CPM)
8
Operations Research | Richa Saxena
9
Operations Research | Richa Saxena
10
Operations Research | Richa Saxena
11
Operations Research | Richa Saxena
12
Operations Research | Richa Saxena
13
Operations Research | Richa Saxena
14
Operations Research | Richa Saxena
Crashing
15
Operations Research | Richa Saxena
16
Operations Research | Richa Saxena
17
Operations Research | Richa Saxena
18
Operations Research | Richa Saxena
19
Operations Research | Richa Saxena
PERT
20
Operations Research | Richa Saxena
21
Operations Research | Richa Saxena
22
Operations Research | Richa Saxena
23
Operations Research | Richa Saxena
24