Mus Report 2924 Night Report
Mus Report 2924 Night Report
Staged up flow rate to 400 gpm/500 psi, while rotating string with 20 rpm, observed increase in
pressure from 500 psi to 700 psi @ 2863 m.
06:15-07:00
Dry back reaming from 2866 m to 2852 m with 20-50 rpm, 6-20 klb. Ft torque. Circulate @ 2852 m
with 50-100 gpm/60-100 psi, 22 rpm, 8 klb. Ft torque for 15 mins. Resumed dry back reamed 2852 m
to 2832 m and reamed down to 2842 m with 50 rpm, 7-19 klbs. ft torque.
07:00-08:00
Staged up flow rate to 900 gpm/1700 psi, 20-22 rpm, 5-18 klbs. Ft torque. No losses. Staged up
rotation at 900 gpm from 30 rpm to 70 rpm. @ 900 gpm/1700 psi, 70 rpm,10 klb. Ft, observed
pressure increase to 1830 psi. Immediately stopped pump, rotation and work string to 2842 m.
08:00-10:45
Staged up flow rate to 900 gpm/1700 psi, 20 rpm, 8-12 klb.ft torque. No losses. Continue back
reamed f/-2842 m t/-2841 m. Observed pressure increase to 1800 psi. Immediately stopped pump
and work string, staged up flow rate to 800 gpm/1450 psi, 20 rpm, 8 klb.ft torque. Observed
pressure increase to 1580 psi. Again stopped pump and work string, to 2852 m staged up flow rate
while back reamed to 2842 m, 600 gpm/920 psi, 22 rpm, 9 klb.ft torque. Observed pressure increase
to 940 psi. Worked string to 5852 m Observed pressure increase to 1000 psi. Stopped pump work
string with 550 gpm/ 1020 psi, 20 rpm, 6-16 klb. Ft.
10:45-11:30
Circulated @ 2850 m by staged up flow rate to 400 gpm/440 psi, 22 rpm, 8 klb. Ft torque. Observed
pressure increase to 500 psi. Stopped pump and work the string, back reamed f/-2580 m t/-2840 m
with 50 gpm/50 psi, 22 rpm, 7-13 klb. Ft torque.
11:30-12:00
@ 2842 m, break 3 single stand of # 72 make up TIW and side entry sub with same stand. Line up
cemet unit to string and trough to kill line for LOT..