015_JH_1910
015_JH_1910
Engineering Group
Specificstion Number
015-JH-1910
Mechanical Completion of Instrument Systems
CONTENTS I
6 . 0 PERFORMANCE REQUIREMENTS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 8
6.1 Mechanical Completion Test Equipment . . . . . . . . . . . . . . . . . . . . . 8
6 . 2 Documentation Record of Completion Tests . . . . . . . . . . . . . . . . . . 9
6 . 3 Report . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
6.4 Completion Tests . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 9
6.5 Witnessed Mechanical Completion Testing . . . . . . . . . . . . . . . . . . . 1 3
1.0 SCOPE
1.2 The plant instrumentation shall fully comply with all relevant contractual
requirements specified in the Scope of Work and Technical Specification of
the Contract.
2.1 Instruments, systems, equipment and testing shall conform in design, supply,
materials and performance, except where otherwise specified, with the
current issue and amendments of the applicable codes and standards
prevailing on the effective date of the Contract.
2.2 Compliance with this specification shall not relieve the Contractor of its
responsibility to supply equipment suited to meet the specified service
conditions and applicable regulations.
2.3 Where conflicts exist between this specification and other Drawings,
standards, codes and specifications, the most stringent shall be applied.
3.1 The equipment shall be suitable for continuous operation at a desert location
under high ambient temperatures and humidity. The atmosphere at the
Facility is generally dusty and corrosive and may contain traces of hydrogen
sulphide.
Project Number Specification Number Rev Date Sheet
3.2 The plant instrumentation systems shall in all respects be suitable for
continuous operation in the service conditions stated in the Engineering Group
Specification entitled "Basic Design Criteria" (Number 015-AH-1001).
4.2 Quarantine
4.5.3 Company may wish to witness part or all of the testing and will
advise requirements to Contractor's as part of the document review,
or on the review of the Contractor's submitted quality (test and
inspection) plan, which shall be submitted for approval 3 months
before testing is scheduled to start.
Apart from the tests for specific items covered by the test procedures, the
construction requirements for the plant in general shall be verified and
confirmed on checklists. These lists shall be prepared by Contractor for all
systems and shall typically include:
f. Cabling and other items are suitably protected from the direct
sun.
Pneumatic System
g. Tag number on the air supply isolation valve agrees with the
served instrument.
old. This period shall be shorter for fragile testing instruments. The
calibration certificate shall be available for verification and approval
by the Company during the tests.
6.2.3 Where witnessing by Company has been requested for any item, the
Contractor must coordinate the testing to suit Company availability.
This Witnessing is not to be confused with the "Witnessed
Mechanical Completion Testing" noted later within this specification.
6.2.4 The Contractor shall take due note of those items marked as HOLD
points on the quality plan.
6.4 Comoletion T e a
1. Failure mode.
2. Direction of operation.
3. Smoothness of action.
5. Speed of response.
a. General Examination
a. DCS Communication
When all I10 interfaces have been proved, the system shall
be powered down and the 110s connected to the DCS input
cards. The Contractor shall prove by simulation (from the
instrument in the field, wherever possible) the operation of
the control loops, alarm functions, line break and signal
viability functions, recording and printer functions, failure
modes, trending, paging up and down and updating, soft and
hardware redundancy and all other features of the system
and graphics configuration.
The total electrical load and power factor shall be measured for
the complete system and the various isolated subsystems. All
values shall be recorded and checked against the relevant
fuseIMCB. The fuses shall be checked that they are of the
correct rating for the service. It shall be confirmed that only the
correct sections of the plant are isolated when the fuseIMCB is
withdrawn, and that fuseIMCB failure on redundant items does
not cause loss of plant operations.
The Contractor shall make available for use during the test two
complete copies of all relevant Drawings and documents. It is
preferred that one copy is in roll-file format for ease of access.
These shall include:
a. lnstrument schedule/list.
c. Cable Schedule.
d. Loop diagram.
e. Loop schedules,