Large-scale-generator-technical-requirements
Large-scale-generator-technical-requirements
PERFORMANCE
REQUIREMENTS FOR
CONNECTION OF LARGE
SCALE EMBEDDED
GENERATORS TO THE
EVOENERGY NETWORK
1.1 Purpose
The purpose of this document is to outline Evoenergy’s technical requirements for the connection to, and
parallel operation with, Evoenergy’s high voltage (HV) and sub-transmission networks to the proponents of
large scale embedded generation systems.
1.2 Scope
This document applies to any Registered Generator which operate in parallel with the Evoenergy network for
more than 400 milliseconds (ms). It also covers any customer choosing to comply with Part A of National
Electricity Rules (NER) Chapter 5 in developing a Generator Connection Agreement.
This document provides guidance on the interpretation of NER technical requirements in the context of
Evoenergy’s network. This document does not address connection process details. Proponents should refer
to Evoenergy’s embedded generation requirement documents available at the Evoenergy website for
information on the connection process and Network Technical Study (NTS).
1.3 Background
Evoenergy has conducted a review of several key documents that describe the technical requirements for
large scale embedded generator connections to a distribution network, and has formulated a grid code which
outlines the requirements for connection of large scale embedded generators to Evoenergy’s network. The
following process was considered during the formation of the Grid Code.
1. Review, analysis and production of a summarised version of Chapter 5 of the NER 1 requirements;
2. Determination of the applicability of schedules S5.2.5.1 to S5.2.8 of the NER; fault ride through,
frequency and voltage stabilisation, power quality and reactive power control aspects as required by
Evoenergy;
3. Determination of other requirements of that may be applicable;
4. Determination of requirements of other applicable Australian and overseas standards;
5. Requirements for connection;
6. Determination of network support that can be provided by such installation and risks associated with
providing this support; and
7. Determination of impact to the network and how these impacts can be managed.
1.4 Disclaimer
This document has been developed to assist Generators with understanding technical requirements. It is not
possible to maintain and update this document each time the NER changes, it is therefore a guide only and
must not be relied upon to be current at all times. This document cannot be controlled when printed and
users should ensure they are using the most recent version from the Evoenergy website.
It is the document user’s responsibility to satisfy themselves of compliance with the NER. If there is any
inconsistency between this document and NER requirements, the NER will prevail. This document must not
be used as a substitute to the NER.
1 National Electricity Rules (NER) AEMO Guidelines for Assessment of Generator Proposed Performance Standards
2020 • PO07391 • V1.0 4
Evoenergy does not make any representations as to the accuracy or currency of this document. Evoenergy
will not accept liability for any loss or damage arising from reliance on this document. Proponents should
seek their own professional and technical advice in respect of their compliance with the NER requirements
and the otherwise in relation to the subject matter of this document.
3.4 Maintenance
To ensure the electrical installation is maintained in a safe condition, the proponent shall develop a
maintenance plan that specifies the maintenance schedule for all equipment and details the frequency and
types of maintenance. The generator shall ensure the following maintenance requirements are met:
Records of all maintenance activities are retained for all equipment.
Changes to the electrical installation are performed by suitably qualified personnel and the generator
holds a certificate of compliance issued in respect of any of the changes.
Approval is obtained from Evoenergy prior to altering the connection for any addition, upgrade,
extension, expansion, augmentation or any other kind of alteration, including changing inverter
settings.
Protection systems are to be tested by suitably qualified personnel at an interval no greater than five
years after commissioning.
In the event a system is deemed to be non-compliant, Evoenergy will contact the generator to request that
the system is rectified within a specified timeframe. If the generator fails to adequately address the non-
compliance within the timeframe, Evoenergy will take steps to have the system disconnected from the
network to ensure its obligations regarding the safe and reliable operation of the distribution network are met.
This process may vary depending on the severity of the risk posed by the system.
4. ACCESS STANDARDS
2 Between the proponent and the NSP with advice from AEMO if it is an AEMO related matter
2020 • PO07391 • V1.0 6
4.4 Performance Standard
A performance standard is an access standard that forms part of the terms and conditions of a Generator
Connection Agreement. Where a Generator proposes a performance standard it will be referred to as a
proposed performance standard until such time as both Evoenergy and AEMO have reviewed and accepted
it, it will then become an agreed performance standard.
The agreed performance standards become part of the terms and conditions of a Generator Connection
Agreement with the Generator and Evoenergy. If the Generator is applying to become a registered
participant, a copy of the Generator Connection Agreement (with the commercial terms removed) can be
submitted to AEMO.
Evoenergy may consider a negotiated standard in cases where the connection point is in a lightly loaded
area and compliance with voltage standards will be achieved; or where the active power output may improve
reactive power margins on the network without additional reactive power capability. Any such negotiation is
dependent on the network at the connection point.
If the generating system is used to provide support to the network Evoenergy may require the Generator to
provide additional reactive power capability but this will depend on the circumstances of each connection.
The Generator, NSP and AEMO may negotiate a range of reactive power absorption and supply for the point
of connection within which the plant must operate or a negotiate a limit which describes how the reactive
power capability will vary depending on the active power output based on the plant’s design characteristic.
In the case that the generating system is not able to perform at the level established, under reasonable
circumstances the Generator must provide for the deficit of reactive power (supply and absorption) in one or
more of the following ways:
Pay the NSP a compensation to provide for the deficit;
Install additional equipment connecting at the generating system’s point of connection or at another
location, such equipment is classified to be part of the generating system;
Reach a commercial arrangement with a Registered Participant;
If there are specific operating conditions under which the performance level cannot be met, the Generator
may document this as a constituent of the negotiated access standard and agree to operational
arrangements which allow the plant to meet the agreed performance levels in those specific conditions.
General – The agreed rated active power must be recorded in a performance standard and if deemed
relevant also it’s associated method of calculation. When the Generator is not supplying or absorbing
reactive power, the performance standard for consumption of energy under an ancillary services
arrangement must be established under NER’s clause S5.3.5 in which the Generator shall be treated as a
Market Customer.
Study results will need to assume power factor control of generation reactive dispatch, the facility will need to
comply with voltage flicker thresholds assigned by Evoenergy.
If Evoenergy accepts a negotiated access standard the Generator may be required to upgrade to the
automatic access standard where Evoenergy connects new customers to its network. This is required for
Evoenergy to comply with the access standards defined in the NER.
Minimum – Continuous uninterrupted operation within the given ranges with reduced timing and
performance, as per Figure 3, unless the rate of change of frequency is outside the range of -2Hz to 2 Hz per
second for more than 0.25 seconds, -1Hz to 1Hz per second for more than one second, or such a range as
determined time to time by the Reliability Panel.
Negotiated – Operation as close to the Automatic requirement without impacting on quality of supply.
The Generator must provide details of the over and under frequency protection, steady state frequency
range operating capability and maximum rate of change of frequency operating capability.
FIGURE 5. RESPONSE TO VOLTAGE DISTURBANCES UNDER 110 PERCENT, AUTOMATIC ACCESS STANDARD
The ranges detailed above are also subject to the requirement that the Generator does not cause nearby LV
networks to be outside the range of ±6 per cent.
Minimum – Continuous uninterrupted operation within a range of ±10 per cent of normal voltage provided
the voltage to frequency ratio is above specified limits.
FIGURE 6. RESPONSE TO VOLTAGE DISTURBANCES OVER 110 PERCENT, MINIMUM ACCESS STANDARD
Negotiated – Operation as close to the Automatic requirement without impacting on plant safety, loss of
generated power not greater than 100MW if the automatic access standard were applied, and no adverse
impact on the quality of supply or power system security.
The Generator must provide:
Details of over and under voltage protection and their settings/limits; a curve (similar to Figure S5.1a.1
of the NER) which shows the range of voltages the Generator can ride through and remain connected
for that range; and
Details of the Generator’s voltage operating capability. The generating units must be capable of
continuous uninterrupted operation for the range of voltages specified in the automatic access
standard, except where AEMO and the Network Service Provider agree that the total reduction of
generation in the power system as a result of any voltage excursion within levels specified by the
automatic access standard would not exceed 100 MW, or a greater limit based on what AEMO and the
Network Service Provider both consider to be reasonable in the circumstances.
Evoenergy requires protection in place to trip the generating system where all three line to line voltages are
below 0.85 pu and the plant is absorbing inductive reactive power. This is to prevent the Generator from
impeding network voltage recovery after a fault.
The generating unit or generating system will have facilities to regulate voltage or reactive power or power
factor in a manner that does not prevent the Network Service Provider from achieving the requirements of
clause S5.1a.3 and S5.1a.4; and sufficient to achieve the performance of agreed in respect of clauses
S5.2.51, S5.2.5.2, S5.2.5.3, S5.2.5.4, S5.2.5.5, S5.2.5.6 and S5.2.5.12.
GLOSSARY OF TERMS
TERM DEFINITION
AEMO The Australian Energy Market Operator.
Registered Generator A person or legal entity registered with the AEMO as a Registered
Participant as per Chapter 5 of the NER.
Generating system The plant and equipment used for generating electricity.
Other Capitalised words used in this document have the same meaning as given to them in the NER.
DOCUMENT CONTROL