work program plan
work program plan
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
1 MAXIM RISEN - Electrical, LPS & TEL Services 888 days Mon 1/5/23 Sat 28/2/26 14%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 1
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
22 Cable Termination Work 120 days Tue 1/7/25 Mon 17/11/250%
26 Installation of Ascoutic System and Genset 21 days Mon 6/1/25 Wed 29/1/25 0%
42 To Lay PN-10 for TNB incoming 14 days Fri 1/8/25 Sat 16/8/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 2
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
43 To Install Manhole 10 days Mon 18/8/25 Thu 28/8/25 0%
53 1st Fix ( Exposedl Conduit) 10 days Fri 1/3/24 Tue 12/3/24 100%
54 2nd Fix ( Wiring Work) 5 days Wed 13/3/24 Mon 18/3/24 100%
55 3rd Fix ( Switches, Light Fitting & DB ) 5 days Tue 19/3/24 Sat 23/3/24 100%
56 To interlinking copper tape and earth chamber 5 days Mon 18/3/24 Fri 22/3/24 100%
installation.
57 Testing & commissioning 3 days Tue 26/3/24 Thu 28/3/24 100%
58 TNB sub-station handing over 26 days Mon 1/4/24 Tue 30/4/24 100%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 3
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
65 Level 10 to LMR 300 days Wed 19/6/24 Tue 3/6/25 0%
66 Earthing & Lightning Sytem 765 days Mon 17/7/23 Wed 24/12/2521%
67 Structure Floor- Block A & B 765 days Mon 17/7/23 Wed 24/12/2522%
68 To install earth work connection with 60 days Mon 17/7/23 Sat 23/9/23 100%
exothermiix weld onto structure rebar and
interlinking cabling work ( Sub-structure)
69 To install down conductor with Aluminium 574 days Tue 1/8/23 Fri 30/5/25 18%
Tape run on surface mounted ( Supper
Structure )
70 To install Air Terminal & Aluminium Tape run60 days Mon 9/6/25 Sat 16/8/25 0%
on perimeters at roof
71 To install earth chamber & earth Rod on 45 days Mon 3/11/25 Wed 0%
Ground Floor 24/12/25
72 LIGHT FITTING 135 days Tue 3/6/25 Thu 6/11/25 0%
78 Lighting, Small Power & Telephone 731 days Wed 19/7/23 Mon 17/11/2519%
79 Block A, Podium/Car Park RC Works 731 days Wed 19/7/23 Mon 17/11/2519%
81 1st Fix ( Conceal Conduit, All ) 9 days Wed 19/7/23 Fri 28/7/23 100%
82 2nd Fix ( Wiring Work, All) 14 days Wed 5/2/25 Thu 20/2/25 0%
83 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Wed 5/2/25 Fri 28/2/25 0%
85 1st Fix ( Conceal Conduit, All ) 12 days Fri 28/7/23 Thu 10/8/23 100%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 4
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
86 2nd Fix ( Wiring Work, All) 14 days Thu 20/2/25 Fri 7/3/25 0%
87 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Sat 1/3/25 Tue 25/3/25 0%
89 1st Fix ( Conceal Conduit, All ) 12 days Tue 15/8/23 Mon 28/8/23 100%
90 2nd Fix ( Wiring Work, All) 14 days Fri 7/3/25 Sat 22/3/25 0%
91 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Mon 24/3/25 Wed 16/4/25 0%
93 1st Fix ( Conceal Conduit, All ) 12 days Thu 7/9/23 Wed 20/9/23 100%
94 2nd Fix ( Wiring Work, All) 14 days Sat 22/3/25 Mon 7/4/25 100%
95 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Wed 16/4/25 Fri 9/5/25 0%
97 1st Fix ( Conceal Conduit, All ) 12 days Sat 30/9/23 Fri 13/10/23 100%
98 2nd Fix ( Wiring Work, All) 14 days Mon 7/4/25 Tue 22/4/25 0%
99 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Fri 9/5/25 Fri 27/6/25 0%
101 1st Fix ( Conceal Conduit, All ) 12 days Tue 24/10/23 Mon 6/11/23 100%
102 2nd Fix ( Wiring Work, All) 14 days Tue 22/4/25 Wed 7/5/25 0%
103 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Fri 27/6/25 Mon 21/7/25 0%
105 1st Fix ( Conceal Conduit, All ) 12 days Thu 16/11/23 Wed 29/11/23100%
106 2nd Fix ( Wiring Work, All) 14 days Wed 7/5/25 Thu 22/5/25 0%
107 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Mon 21/7/25 Wed 13/8/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 5
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
108 Level 5 546 days Sat 9/12/23 Fri 5/9/25 26%
109 1st Fix ( Conceal Conduit, All ) 12 days Sat 9/12/23 Fri 22/12/23 100%
110 2nd Fix ( Wiring Work, All) 14 days Thu 22/5/25 Fri 6/6/25 0%
111 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Wed 13/8/25 Fri 5/9/25 0%
113 1st Fix ( Conceal Conduit, All ) 12 days Tue 2/1/24 Mon 15/1/24 100%
114 2nd Fix ( Wiring Work, All) 14 days Fri 6/6/25 Sat 21/6/25 0%
115 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Fri 5/9/25 Mon 29/9/25 0%
117 1st Fix ( Conceal Conduit, All ) 12 days Thu 25/1/24 Wed 7/2/24 100%
118 2nd Fix ( Wiring Work, All) 14 days Sat 21/6/25 Mon 7/7/25 0%
119 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 12 days Mon 29/9/25 Sat 11/10/25 0%
121 1st Fix ( Conceal Conduit, All ) 33 days Wed 28/2/24 Fri 5/4/24 100%
122 2nd Fix ( Wiring Work, All) 14 days Mon 7/7/25 Tue 22/7/25 0%
123 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 12 days Sat 11/10/25 Fri 24/10/25 0%
125 1st Fix ( Conceal Conduit, All ) 44 days Wed 28/2/24 Thu 18/4/24 100%
126 2nd Fix ( Wiring Work, All) 12 days Tue 22/7/25 Mon 4/8/25 0%
127 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 30 days Wed 1/10/25 Tue 4/11/25 0%
128 Level 10 (Typical Floor) 97 days Mon 22/4/24 Mon 12/8/24 62%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 6
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
129 1st Fix ( Conceal Conduit, All ) 8 days Mon 22/4/24 Tue 30/4/24 100%
130 2nd Fix ( Wiring Work, All) 8 days Fri 7/6/24 Sat 15/6/24 100%
131 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 1/8/24 Mon 12/8/24 0%
133 1st Fix ( Conceal Conduit, All ) 8 days Sat 27/4/24 Mon 6/5/24 100%
134 2nd Fix ( Wiring Work, All) 8 days Sat 15/6/24 Mon 24/6/24 100%
135 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 12/8/24 Thu 22/8/24 0%
137 1st Fix ( Conceal Conduit, All ) 8 days Mon 6/5/24 Tue 14/5/24 100%
138 2nd Fix ( Wiring Work, All) 8 days Mon 24/6/24 Tue 2/7/24 100%
139 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 22/8/24 Mon 2/9/24 0%
141 1st Fix ( Conceal Conduit, All ) 8 days Tue 14/5/24 Wed 22/5/24 100%
142 2nd Fix ( Wiring Work, All) 8 days Wed 3/7/24 Thu 11/7/24 100%
143 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 2/9/24 Thu 12/9/24 0%
144 Level 13A 107 days Wed 22/5/24 Mon 23/9/24 62%
145 1st Fix ( Conceal Conduit, All ) 8 days Wed 22/5/24 Thu 30/5/24 100%
146 2nd Fix ( Wiring Work, All) 8 days Fri 12/7/24 Sat 20/7/24 100%
147 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 12/9/24 Mon 23/9/24 0%
149 1st Fix ( Conceal Conduit, All ) 8 days Thu 30/5/24 Fri 7/6/24 100%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 7
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
150 2nd Fix ( Wiring Work, All) 8 days Sat 20/7/24 Mon 29/7/24 100%
151 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 23/9/24 Thu 3/10/24 0%
154 2nd Fix ( Wiring Work, All) 8 days Tue 30/7/24 Wed 7/8/24 100%
155 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 3/10/24 Mon 14/10/240%
157 1st Fix ( Conceal Conduit, All ) 8 days Sat 15/6/24 Mon 24/6/24 100%
158 2nd Fix ( Wiring Work, All) 8 days Thu 8/8/24 Fri 16/8/24 100%
159 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 14/10/24Thu 24/10/24 0%
161 1st Fix ( Conceal Conduit, All ) 8 days Mon 24/6/24 Tue 2/7/24 100%
162 2nd Fix ( Wiring Work, All) 8 days Sat 17/8/24 Mon 26/8/24 100%
163 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 24/10/24 Mon 4/11/24 0%
165 1st Fix ( Conceal Conduit, All ) 8 days Tue 2/7/24 Wed 10/7/24 100%
166 2nd Fix ( Wiring Work, All) 8 days Tue 27/8/24 Wed 4/9/24 100%
167 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 4/11/24 Thu 14/11/24 0%
169 1st Fix ( Conceal Conduit, All ) 8 days Mon 8/7/24 Tue 16/7/24 0%
170 2nd Fix ( Wiring Work, All) 8 days Tue 3/9/24 Wed 11/9/24 0%
171 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 14/11/24 Mon 25/11/240%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 8
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
172 Level 21 121 days Thu 18/7/24 Thu 5/12/24 0%
173 1st Fix ( Conceal Conduit, All ) 8 days Thu 18/7/24 Fri 26/7/24 0%
174 2nd Fix ( Wiring Work, All) 8 days Thu 12/9/24 Fri 20/9/24 0%
175 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 25/11/24Thu 5/12/24 0%
177 1st Fix ( Conceal Conduit, All ) 8 days Fri 26/7/24 Sat 3/8/24 0%
178 2nd Fix ( Wiring Work, All) 8 days Sat 21/9/24 Mon 30/9/24 0%
179 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 5/12/24 Mon 16/12/240%
181 1st Fix ( Conceal Conduit, All ) 8 days Sat 3/8/24 Mon 12/8/24 0%
182 2nd Fix ( Wiring Work, All) 8 days Tue 1/10/24 Wed 9/10/24 0%
183 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 16/12/24Thu 26/12/24 0%
185 1st Fix ( Conceal Conduit, All ) 8 days Mon 12/8/24 Tue 20/8/24 0%
186 2nd Fix ( Wiring Work, All) 8 days Thu 10/10/24 Fri 18/10/24 0%
187 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 26/12/24 Mon 6/1/25 0%
189 1st Fix ( Conceal Conduit, All ) 8 days Tue 20/8/24 Wed 28/8/24 0%
190 2nd Fix ( Wiring Work, All) 8 days Thu 19/9/24 Fri 27/9/24 0%
191 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 6/1/25 Thu 16/1/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 9
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
193 1st Fix ( Conceal Conduit, All ) 8 days Wed 28/8/24 Thu 5/9/24 0%
194 2nd Fix ( Wiring Work, All) 8 days Sat 28/9/24 Mon 7/10/24 0%
195 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 16/1/25 Mon 27/1/25 0%
197 1st Fix ( Conceal Conduit, All ) 8 days Thu 5/9/24 Fri 13/9/24 0%
198 2nd Fix ( Wiring Work, All) 8 days Tue 8/10/24 Wed 16/10/240%
199 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 27/1/25 Thu 6/2/25 0%
201 1st Fix ( Conceal Conduit, All ) 8 days Fri 13/9/24 Sat 21/9/24 0%
202 2nd Fix ( Wiring Work, All) 8 days Wed 16/10/24Thu 24/10/24 0%
203 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 6/2/25 Mon 17/2/25 0%
205 1st Fix ( Conceal Conduit, All ) 8 days Sat 21/9/24 Mon 30/9/24 0%
206 2nd Fix ( Wiring Work, All) 8 days Thu 24/10/24 Fri 1/11/24 0%
207 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 17/2/25 Thu 27/2/25 0%
209 1st Fix ( Conceal Conduit, All ) 8 days Mon 30/9/24 Tue 8/10/24 0%
210 2nd Fix ( Wiring Work, All) 8 days Fri 1/11/24 Sat 9/11/24 0%
211 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 27/2/25 Mon 10/3/25 0%
213 1st Fix ( Conceal Conduit, All ) 8 days Tue 8/10/24 Wed 16/10/240%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 10
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
214 2nd Fix ( Wiring Work, All) 8 days Sat 9/11/24 Mon 18/11/240%
215 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 10/3/25 Thu 20/3/25 0%
217 1st Fix ( Conceal Conduit, All ) 8 days Wed 16/10/24Thu 24/10/24 0%
218 2nd Fix ( Wiring Work, All) 8 days Mon 18/11/24Tue 26/11/24 0%
219 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 20/3/25 Mon 31/3/25 0%
221 1st Fix ( Conceal Conduit, All ) 8 days Thu 24/10/24 Fri 1/11/24 0%
222 2nd Fix ( Wiring Work, All) 8 days Tue 26/11/24 Wed 4/12/24 0%
223 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 31/3/25 Thu 10/4/25 0%
225 1st Fix ( Conceal Conduit, All ) 8 days Fri 1/11/24 Sat 9/11/24 0%
226 2nd Fix ( Wiring Work, All) 8 days Wed 4/12/24 Thu 12/12/24 0%
227 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 10/4/25 Mon 21/4/25 0%
229 1st Fix ( Conceal Conduit, All ) 8 days Sat 9/11/24 Mon 18/11/240%
230 2nd Fix ( Wiring Work, All) 8 days Thu 12/12/24 Fri 20/12/24 0%
231 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 21/4/25 Thu 1/5/25 0%
233 1st Fix ( Conceal Conduit, All ) 8 days Mon 18/11/24Tue 26/11/24 0%
234 2nd Fix ( Wiring Work, All) 8 days Fri 20/12/24 Sat 28/12/24 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 11
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
235 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 1/5/25 Mon 12/5/25 0%
237 1st Fix ( Conceal Conduit, All ) 8 days Tue 26/11/24 Wed 4/12/24 0%
238 2nd Fix ( Wiring Work, All) 8 days Sat 28/12/24 Mon 6/1/25 0%
239 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 12/5/25 Thu 22/5/25 0%
241 1st Fix ( Conceal Conduit, All ) 8 days Wed 4/12/24 Thu 12/12/24 0%
242 2nd Fix ( Wiring Work, All) 8 days Mon 6/1/25 Tue 14/1/25 0%
243 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 22/5/25 Mon 2/6/25 0%
245 1st Fix ( Conceal Conduit, All ) 8 days Thu 12/12/24 Fri 20/12/24 0%
246 2nd Fix ( Wiring Work, All) 8 days Tue 14/1/25 Wed 22/1/25 0%
247 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 2/6/25 Thu 12/6/25 0%
249 1st Fix ( Conceal Conduit, All ) 8 days Fri 20/12/24 Sat 28/12/24 0%
250 2nd Fix ( Wiring Work, All) 8 days Wed 22/1/25 Thu 30/1/25 0%
251 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 12/6/25 Mon 23/6/25 0%
253 1st Fix ( Conceal Conduit, All ) 8 days Sat 28/12/24 Mon 6/1/25 0%
254 2nd Fix ( Wiring Work, All) 8 days Thu 30/1/25 Fri 7/2/25 0%
255 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 23/6/25 Thu 3/7/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 12
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
256 Level 42 163 days Mon 6/1/25 Mon 14/7/25 0%
257 1st Fix ( Conceal Conduit, All ) 8 days Mon 6/1/25 Tue 14/1/25 0%
258 2nd Fix ( Wiring Work, All) 8 days Fri 7/2/25 Sat 15/2/25 0%
259 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 3/7/25 Mon 14/7/25 0%
261 1st Fix ( Conceal Conduit, All ) 8 days Tue 14/1/25 Wed 22/1/25 0%
262 2nd Fix ( Wiring Work, All) 8 days Sat 15/2/25 Mon 24/2/25 0%
263 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 14/7/25 Thu 24/7/25 0%
265 1st Fix ( Conceal Conduit, All ) 8 days Wed 22/1/25 Thu 30/1/25 0%
266 2nd Fix ( Wiring Work, All) 8 days Mon 24/2/25 Tue 4/3/25 0%
267 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 24/7/25 Mon 4/8/25 0%
269 1st Fix ( Conceal Conduit, All ) 8 days Thu 30/1/25 Fri 7/2/25 0%
270 2nd Fix ( Wiring Work, All) 8 days Tue 4/3/25 Wed 12/3/25 0%
271 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 4/8/25 Thu 14/8/25 0%
273 1st Fix ( Conceal Conduit, All ) 8 days Fri 7/2/25 Sat 15/2/25 0%
274 2nd Fix ( Wiring Work, All) 8 days Wed 12/3/25 Thu 20/3/25 0%
275 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 14/8/25 Mon 25/8/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 13
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
277 1st Fix ( Conceal Conduit, All ) 8 days Sat 15/2/25 Mon 24/2/25 0%
278 2nd Fix ( Wiring Work, All) 8 days Fri 21/3/25 Sat 29/3/25 0%
279 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 25/8/25 Thu 4/9/25 0%
281 1st Fix ( Conceal Conduit, All ) 8 days Mon 24/2/25 Tue 4/3/25 0%
282 2nd Fix ( Wiring Work, All) 8 days Sat 29/3/25 Mon 7/4/25 0%
283 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 4/9/25 Mon 15/9/25 0%
285 1st Fix ( Conceal Conduit, All ) 8 days Tue 4/3/25 Wed 12/3/25 0%
286 2nd Fix ( Wiring Work, All) 8 days Mon 7/4/25 Tue 15/4/25 0%
287 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 15/9/25 Thu 25/9/25 0%
289 1st Fix ( Conceal Conduit, All ) 8 days Wed 12/3/25 Thu 20/3/25 0%
290 2nd Fix ( Wiring Work, All) 8 days Tue 15/4/25 Wed 23/4/25 0%
291 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 25/9/25 Mon 6/10/25 0%
293 1st Fix ( Conceal Conduit, All ) 8 days Thu 20/3/25 Fri 28/3/25 0%
294 2nd Fix ( Wiring Work, All) 8 days Wed 23/4/25 Thu 1/5/25 0%
295 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 6/10/25 Thu 16/10/25 0%
297 1st Fix ( Conceal Conduit, All ) 8 days Fri 28/3/25 Sat 5/4/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 14
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
298 2nd Fix ( Wiring Work, All) 8 days Thu 1/5/25 Fri 9/5/25 0%
299 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 16/10/25 Mon 27/10/250%
301 1st Fix ( Conceal Conduit, All ) 8 days Sat 5/4/25 Mon 14/4/25 0%
302 2nd Fix ( Wiring Work, All) 8 days Fri 9/5/25 Sat 17/5/25 0%
303 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 27/10/25Thu 6/11/25 0%
305 1st Fix ( Conceal Conduit, All ) 21 days Wed 9/4/25 Fri 2/5/25 0%
306 2nd Fix ( Wiring Work, All) 8 days Sat 17/5/25 Mon 26/5/25 0%
307 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 6/11/25 Mon 17/11/250%
308 Level Water Tank 157 days Sat 3/5/25 Sat 1/11/25 0%
309 1st Fix ( Conceal Conduit, All ) 38 days Sat 3/5/25 Mon 16/6/25 0%
310 2nd Fix ( Wiring Work, All) 30 days Mon 26/5/25 Sat 28/6/25 0%
311 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 11 days Tue 21/10/25 Sat 1/11/25 0%
313 1st Fix ( Conceal Conduit, All ) 40 days Fri 6/6/25 Tue 22/7/25 0%
314 2nd Fix ( Wiring Work, All) 14 days Fri 8/8/25 Sat 23/8/25 0%
315 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 14 days Mon 22/9/25 Tue 7/10/25 0%
316 Lighting, Power & Telephone 436 days Mon 6/5/24 Thu 25/9/25 19%
319 1st Fix ( Conceal Conduit, All ) 8 days Thu 16/5/24 Fri 24/5/24 100%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 15
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
320 2nd Fix ( Wiring Work, All) 8 days Fri 14/6/24 Sat 22/6/24 100%
321 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 9/8/24 Tue 20/8/24 0%
323 1st Fix ( Conceal Conduit, All ) 8 days Mon 6/5/24 Tue 14/5/24 100%
324 2nd Fix ( Wiring Work, All) 8 days Sat 22/6/24 Mon 1/7/24 100%
325 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 20/8/24 Fri 30/8/24 0%
327 1st Fix ( Conceal Conduit, All ) 8 days Tue 14/5/24 Wed 22/5/24 100%
328 2nd Fix ( Wiring Work, All) 8 days Mon 1/7/24 Tue 9/7/24 100%
329 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 30/8/24 Tue 10/9/24 0%
331 1st Fix ( Conceal Conduit, All ) 8 days Wed 22/5/24 Thu 30/5/24 100%
332 2nd Fix ( Wiring Work, All) 8 days Tue 9/7/24 Wed 17/7/24 100%
333 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 10/9/24 Fri 20/9/24 0%
334 Level 13A 107 days Thu 30/5/24 Tue 1/10/24 62%
335 1st Fix ( Conceal Conduit, All ) 8 days Thu 30/5/24 Fri 7/6/24 100%
336 2nd Fix ( Wiring Work, All) 8 days Wed 17/7/24 Thu 25/7/24 100%
337 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 20/9/24 Tue 1/10/24 0%
339 1st Fix ( Conceal Conduit, All ) 8 days Thu 6/6/24 Fri 14/6/24 100%
340 2nd Fix ( Wiring Work, All) 8 days Thu 25/7/24 Fri 2/8/24 100%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 16
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
341 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 1/10/24 Fri 11/10/24 0%
343 1st Fix ( Conceal Conduit, All ) 8 days Fri 14/6/24 Sat 22/6/24 100%
344 2nd Fix ( Wiring Work, All) 8 days Fri 2/8/24 Sat 10/8/24 100%
345 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 11/10/24 Tue 22/10/24 0%
347 1st Fix ( Conceal Conduit, All ) 8 days Sat 22/6/24 Mon 1/7/24 100%
348 2nd Fix ( Wiring Work, All) 8 days Sat 10/8/24 Mon 19/8/24 100%
349 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 22/10/24 Fri 1/11/24 0%
351 1st Fix ( Conceal Conduit, All ) 8 days Mon 1/7/24 Tue 9/7/24 100%
352 2nd Fix ( Wiring Work, All) 8 days Mon 19/8/24 Tue 27/8/24 100%
353 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 1/11/24 Tue 12/11/24 0%
355 1st Fix ( Conceal Conduit, All ) 8 days Tue 9/7/24 Wed 17/7/24 100%
356 2nd Fix ( Wiring Work, All) 8 days Tue 27/8/24 Wed 4/9/24 100%
357 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 12/11/24 Fri 22/11/24 0%
359 1st Fix ( Conceal Conduit, All ) 8 days Wed 17/7/24 Thu 25/7/24 100%
360 2nd Fix ( Wiring Work, All) 8 days Wed 4/9/24 Thu 12/9/24 0%
361 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 22/11/24 Tue 3/12/24 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 17
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
362 Level 21 122 days Thu 25/7/24 Fri 13/12/24 31%
363 1st Fix ( Conceal Conduit, All ) 8 days Thu 25/7/24 Fri 2/8/24 100%
364 2nd Fix ( Wiring Work, All) 8 days Thu 12/9/24 Fri 20/9/24 0%
365 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 3/12/24 Fri 13/12/24 0%
367 1st Fix ( Conceal Conduit, All ) 8 days Fri 2/8/24 Sat 10/8/24 100%
368 2nd Fix ( Wiring Work, All) 8 days Fri 20/9/24 Sat 28/9/24 0%
369 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 13/12/24 Tue 24/12/24 0%
371 1st Fix ( Conceal Conduit, All ) 8 days Sat 10/8/24 Mon 19/8/24 100%
372 2nd Fix ( Wiring Work, All) 8 days Sat 28/9/24 Mon 7/10/24 0%
373 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 24/12/24 Fri 3/1/25 0%
375 1st Fix ( Conceal Conduit, All ) 8 days Mon 19/8/24 Tue 27/8/24 100%
376 2nd Fix ( Wiring Work, All) 8 days Mon 7/10/24 Tue 15/10/24 0%
377 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 3/1/25 Tue 14/1/25 0%
379 1st Fix ( Conceal Conduit, All ) 8 days Tue 27/8/24 Wed 4/9/24 100%
380 2nd Fix ( Wiring Work, All) 8 days Tue 15/10/24 Wed 23/10/240%
381 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 14/1/25 Fri 24/1/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 18
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
383 1st Fix ( Conceal Conduit, All ) 8 days Wed 4/9/24 Thu 12/9/24 0%
384 2nd Fix ( Wiring Work, All) 8 days Wed 23/10/24Thu 31/10/24 0%
385 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 24/1/25 Tue 4/2/25 0%
387 1st Fix ( Conceal Conduit, All ) 8 days Thu 12/9/24 Fri 20/9/24 0%
388 2nd Fix ( Wiring Work, All) 8 days Thu 31/10/24 Fri 8/11/24 0%
389 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 4/2/25 Fri 14/2/25 0%
391 1st Fix ( Conceal Conduit, All ) 8 days Fri 20/9/24 Sat 28/9/24 0%
392 2nd Fix ( Wiring Work, All) 8 days Fri 8/11/24 Sat 16/11/24 0%
393 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 14/2/25 Tue 25/2/25 0%
395 1st Fix ( Conceal Conduit, All ) 8 days Sat 28/9/24 Mon 7/10/24 0%
396 2nd Fix ( Wiring Work, All) 8 days Sat 16/11/24 Mon 25/11/240%
397 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 25/2/25 Fri 7/3/25 0%
399 1st Fix ( Conceal Conduit, All ) 8 days Mon 7/10/24 Tue 15/10/24 0%
400 2nd Fix ( Wiring Work, All) 8 days Mon 25/11/24Tue 3/12/24 0%
401 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 11 days Fri 7/3/25 Wed 19/3/25 0%
403 1st Fix ( Conceal Conduit, All ) 8 days Tue 15/10/24 Wed 23/10/240%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 19
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
404 2nd Fix ( Wiring Work, All) 8 days Tue 3/12/24 Wed 11/12/240%
405 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 19/3/25 Sat 29/3/25 0%
407 1st Fix ( Conceal Conduit, All ) 8 days Wed 23/10/24Thu 31/10/24 0%
408 2nd Fix ( Wiring Work, All) 8 days Wed 11/12/24Thu 19/12/24 0%
409 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 29/3/25 Wed 9/4/25 0%
411 1st Fix ( Conceal Conduit, All ) 8 days Thu 31/10/24 Fri 8/11/24 0%
412 2nd Fix ( Wiring Work, All) 8 days Thu 19/12/24 Fri 27/12/24 0%
413 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 9/4/25 Sat 19/4/25 0%
415 1st Fix ( Conceal Conduit, All ) 8 days Fri 8/11/24 Sat 16/11/24 0%
416 2nd Fix ( Wiring Work, All) 8 days Fri 27/12/24 Sat 4/1/25 0%
417 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 19/4/25 Wed 30/4/25 0%
419 1st Fix ( Conceal Conduit, All ) 8 days Sat 16/11/24 Mon 25/11/240%
420 2nd Fix ( Wiring Work, All) 8 days Sat 4/1/25 Mon 13/1/25 0%
421 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 30/4/25 Sat 10/5/25 0%
423 1st Fix ( Conceal Conduit, All ) 8 days Mon 25/11/24Tue 3/12/24 0%
424 2nd Fix ( Wiring Work, All) 8 days Mon 13/1/25 Tue 21/1/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 20
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
425 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 10/5/25 Wed 21/5/25 0%
427 1st Fix ( Conceal Conduit, All ) 8 days Tue 3/12/24 Wed 11/12/240%
428 2nd Fix ( Wiring Work, All) 8 days Tue 21/1/25 Wed 29/1/25 0%
429 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 21/5/25 Sat 31/5/25 0%
431 1st Fix ( Conceal Conduit, All ) 8 days Wed 11/12/24Thu 19/12/24 0%
432 2nd Fix ( Wiring Work, All) 8 days Wed 29/1/25 Thu 6/2/25 0%
433 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 31/5/25 Wed 11/6/25 0%
435 1st Fix ( Conceal Conduit, All ) 8 days Thu 19/12/24 Fri 27/12/24 0%
436 2nd Fix ( Wiring Work, All) 8 days Thu 6/2/25 Fri 14/2/25 0%
437 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 11/6/25 Sat 21/6/25 0%
439 1st Fix ( Conceal Conduit, All ) 8 days Fri 27/12/24 Sat 4/1/25 0%
440 2nd Fix ( Wiring Work, All) 8 days Fri 14/2/25 Sat 22/2/25 0%
441 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 21/6/25 Wed 2/7/25 0%
443 1st Fix ( Conceal Conduit, All ) 8 days Sat 4/1/25 Mon 13/1/25 0%
444 2nd Fix ( Wiring Work, All) 8 days Sat 22/2/25 Mon 3/3/25 0%
445 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 2/7/25 Sat 12/7/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 21
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
446 Level 42 165 days Mon 13/1/25 Wed 23/7/25 0%
447 1st Fix ( Conceal Conduit, All ) 8 days Mon 13/1/25 Tue 21/1/25 0%
448 2nd Fix ( Wiring Work, All) 8 days Mon 3/3/25 Tue 11/3/25 0%
449 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 12/7/25 Wed 23/7/25 0%
451 1st Fix ( Conceal Conduit, All ) 8 days Tue 21/1/25 Wed 29/1/25 0%
452 2nd Fix ( Wiring Work, All) 8 days Tue 11/3/25 Wed 19/3/25 0%
453 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 23/7/25 Sat 2/8/25 0%
455 1st Fix ( Conceal Conduit, All ) 8 days Wed 29/1/25 Thu 6/2/25 0%
456 2nd Fix ( Wiring Work, All) 8 days Wed 19/3/25 Thu 27/3/25 0%
457 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 2/8/25 Wed 13/8/25 0%
459 1st Fix ( Conceal Conduit, All ) 8 days Thu 6/2/25 Fri 14/2/25 0%
460 2nd Fix ( Wiring Work, All) 8 days Thu 27/3/25 Fri 4/4/25 0%
461 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 13/8/25 Sat 23/8/25 0%
463 1st Fix ( Conceal Conduit, All ) 8 days Fri 14/2/25 Sat 22/2/25 0%
464 2nd Fix ( Wiring Work, All) 8 days Fri 4/4/25 Sat 12/4/25 0%
465 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 23/8/25 Wed 3/9/25 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 22
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
467 1st Fix ( Conceal Conduit, All ) 8 days Sat 22/2/25 Mon 3/3/25 0%
468 2nd Fix ( Wiring Work, All) 1 day Sat 12/4/25 Sat 12/4/25 0%
469 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 3/9/25 Sat 13/9/25 0%
470 Level Water Tank 178 days Mon 3/3/25 Thu 25/9/25 0%
471 1st Fix ( Conceal Conduit, All ) 41 days Mon 3/3/25 Fri 18/4/25 0%
472 2nd Fix ( Wiring Work, All) 21 days Tue 8/7/25 Thu 31/7/25 0%
473 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 11 days Sat 13/9/25 Thu 25/9/25 0%
475 1st Fix ( Conceal Conduit, All ) 37 days Wed 26/3/25 Wed 7/5/25 0%
476 2nd Fix ( Wiring Work, All) 14 days Sat 24/5/25 Mon 9/6/25 0%
477 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 14 days Wed 10/9/25 Thu 25/9/25 0%
478 MAXIM RISEN - Telephone 809 days Tue 1/8/23 Sat 28/2/26 0%
486 FTTH System - Block A & B 189 days Mon 9/6/25 Wed 14/1/26 0%
487 Internal Telecommunication System 189 days Mon 9/6/25 Wed 14/1/26 0%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 23
ID Task
Task Name Duration Start Finish % Complete
Mode
Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
488 Telephone Backbone Cabling Installation At 90 days Mon 9/6/25 Sat 20/9/25 0%
Riser
489 Equipment Installation 14 days Wed 26/11/25Thu 11/12/25 0%
490 Programming Operator Console Software 7 days Tue 2/12/25 Tue 9/12/25 0%
493 1st Fix ( Exposedl Conduit) 10 days Tue 5/8/25 Fri 15/8/25 0%
494 2nd Fix ( Wiring Work) 10 days Wed 20/8/25 Sat 30/8/25 0%
495 3rd Fix ( Switches, Light Fitting & DB ) 7 days Wed 10/9/25 Wed 17/9/25 0%
496 To interlinking copper tape and earth chamber 7 days Mon 8/9/25 Mon 15/9/25 0%
installation.
497 Cabling Work Installation 180 days Tue 1/4/25 Mon 27/10/250%
499 TMB/TIME SDF Room handing over 14 days Tue 2/12/25 Wed 17/12/250%
Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only
Page 24