0% found this document useful (0 votes)
5 views

work program plan

work program main builder

Uploaded by

Jazlan Omar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views

work program plan

work program main builder

Uploaded by

Jazlan Omar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 24

ID Task

Task Name Duration Start Finish % Complete


Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
1 MAXIM RISEN - Electrical, LPS & TEL Services 888 days Mon 1/5/23 Sat 28/2/26 14%

2 SITE POSSESION 2 days Mon 1/5/23 Tue 2/5/23 100%

3 MOBILIZATION 21 days Tue 1/8/23 Thu 24/8/23 100%

4 Project Start 1 day Tue 1/8/23 Tue 1/8/23 100%

5 Project finish 1 day Sat 28/2/26 Sat 28/2/26 0%

6 Electrical Service 809 days Tue 1/8/23 Sat 28/2/26 15%

7 LV System 822 days Mon 17/7/23 Sat 28/2/26 9%

8 Main Switch Board 233 days Wed 7/5/25 Mon 2/2/26 0%

9 FAT 1 day Wed 7/5/25 Wed 7/5/25 0%

10 Delivery to Site 1 day Wed 14/5/25 Wed 14/5/25 0%

11 Positioning, Installation of MSB 7 days Thu 15/5/25 Thu 22/5/25 0%

12 Termination cable work 120 days Fri 23/5/25 Thu 9/10/25 0%

13 Testing & Commisioning 60 days Tue 25/11/25 Mon 2/2/26 0%

14 Sub-Switch Board 114 days Tue 15/7/25 Mon 24/11/250%

15 Delivery to Site patch 1 14 days Tue 15/7/25 Wed 30/7/25 0%

16 Delivery to Site patch 2 14 days Thu 31/7/25 Fri 15/8/25 0%

17 Cable Termination Work 60 days Tue 16/9/25 Mon 24/11/250%

18 Distribution Board 192 days Tue 8/4/25 Mon 17/11/250%

19 Delivery to Site patch 1 14 days Tue 8/4/25 Wed 23/4/25 0%

20 Delivery to Site patch 2 14 days Wed 4/6/25 Thu 19/6/25 0%

21 Delivery to Site patch 3 14 days Tue 5/8/25 Wed 20/8/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 1
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
22 Cable Termination Work 120 days Tue 1/7/25 Mon 17/11/250%

23 Generator 277 days Wed 4/12/24 Wed 22/10/250%

24 FAT 1 day Wed 4/12/24 Wed 4/12/24 0%

25 Delivery to Site 1 day Thu 5/12/24 Thu 5/12/24 0%

26 Installation of Ascoutic System and Genset 21 days Mon 6/1/25 Wed 29/1/25 0%

27 Termination cable work 7 days Fri 10/10/25 Fri 17/10/25 0%

28 Testing & Commisioning 4 days Sat 18/10/25 Wed 22/10/250%

29 Cast Resin Transfomer 207 days Tue 18/2/25 Thu 16/10/25 0%

30 FAT 1 day Tue 18/2/25 Tue 18/2/25 0%

31 Delivery to Site 1 day Fri 21/2/25 Fri 21/2/25 0%

32 Installation of Transformer Unit 14 days Mon 24/2/25 Tue 11/3/25 0%

33 Termination cable work 7 days Wed 1/10/25 Wed 8/10/25 0%

34 Testing & Commisioning 4 days Mon 13/10/25Thu 16/10/25 0%

35 HT Switchgear 243 days Wed 5/3/25 Fri 12/12/25 0%

36 FAT 1 day Wed 5/3/25 Wed 5/3/25 0%

37 Delivery to Site 1 day Sat 8/3/25 Sat 8/3/25 0%

38 Installation of Switchgear Unit 14 days Tue 11/3/25 Wed 26/3/25 0%

39 Termination cable work 7 days Wed 8/10/25 Wed 15/10/250%

40 Testing & Commisioning 4 days Tue 9/12/25 Fri 12/12/25 0%

41 External TNB Infra Work 41 days Fri 1/8/25 Wed 17/9/25 0%

42 To Lay PN-10 for TNB incoming 14 days Fri 1/8/25 Sat 16/8/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 2
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
43 To Install Manhole 10 days Mon 18/8/25 Thu 28/8/25 0%

44 To Lay Underground Ducting 14 days Fri 29/8/25 Sat 13/9/25 0%

45 Testing & Commisioning 3 days Mon 15/9/25 Wed 17/9/25 0%

46 External Street Lighting 71 days Wed 1/10/25 Mon 22/12/250%

47 To Install Ducting Laying 17 days Wed 1/10/25 Mon 20/10/250%

48 To Install street light footing 18 days Thu 23/10/25 Wed 12/11/250%

49 To Install Street Lighting Pole 17 days Mon 17/11/25Fri 5/12/25 0%

50 Testing & Commisioning 10 days Sat 6/12/25 Wed 17/12/250%

51 To Install Cabling & termination 4 days Thu 18/12/25 Mon 22/12/250%

52 TNB Sub-station 52 days Fri 1/3/24 Tue 30/4/24 100%

53 1st Fix ( Exposedl Conduit) 10 days Fri 1/3/24 Tue 12/3/24 100%

54 2nd Fix ( Wiring Work) 5 days Wed 13/3/24 Mon 18/3/24 100%

55 3rd Fix ( Switches, Light Fitting & DB ) 5 days Tue 19/3/24 Sat 23/3/24 100%

56 To interlinking copper tape and earth chamber 5 days Mon 18/3/24 Fri 22/3/24 100%
installation.
57 Testing & commissioning 3 days Tue 26/3/24 Thu 28/3/24 100%

58 TNB sub-station handing over 26 days Mon 1/4/24 Tue 30/4/24 100%

59 Submain cable Installation 395 days Wed 5/6/24 Mon 8/9/25 0%

60 Podium Floor 150 days Tue 18/3/25 Mon 8/9/25 0%


61 Basement to Level 9 150 days Tue 18/3/25 Mon 8/9/25 0%

62 Tower A 350 days Wed 5/6/24 Thu 17/7/25 0%

63 Level 10 to LMR 350 days Wed 5/6/24 Thu 17/7/25 0%

64 Tower B 300 days Wed 19/6/24 Tue 3/6/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 3
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
65 Level 10 to LMR 300 days Wed 19/6/24 Tue 3/6/25 0%

66 Earthing & Lightning Sytem 765 days Mon 17/7/23 Wed 24/12/2521%

67 Structure Floor- Block A & B 765 days Mon 17/7/23 Wed 24/12/2522%

68 To install earth work connection with 60 days Mon 17/7/23 Sat 23/9/23 100%
exothermiix weld onto structure rebar and
interlinking cabling work ( Sub-structure)
69 To install down conductor with Aluminium 574 days Tue 1/8/23 Fri 30/5/25 18%
Tape run on surface mounted ( Supper
Structure )
70 To install Air Terminal & Aluminium Tape run60 days Mon 9/6/25 Sat 16/8/25 0%
on perimeters at roof
71 To install earth chamber & earth Rod on 45 days Mon 3/11/25 Wed 0%
Ground Floor 24/12/25
72 LIGHT FITTING 135 days Tue 3/6/25 Thu 6/11/25 0%

73 1st Batch Delivery 14 days Tue 3/6/25 Wed 18/6/25 0%

74 2nd Batch Delivery 14 days Wed 2/7/25 Thu 17/7/25 0%

75 3rd Batch Delivery 14 days Wed 20/8/25 Thu 4/9/25 0%

76 4th Batch Delivery 14 days Wed 22/10/25Thu 6/11/25 0%

77 Testing & Commissioning 120 days Mon 13/10/25Sat 28/2/26 0%

78 Lighting, Small Power & Telephone 731 days Wed 19/7/23 Mon 17/11/2519%

79 Block A, Podium/Car Park RC Works 731 days Wed 19/7/23 Mon 17/11/2519%

80 B1, Basement 507 days Wed 19/7/23 Fri 28/2/25 20%

81 1st Fix ( Conceal Conduit, All ) 9 days Wed 19/7/23 Fri 28/7/23 100%
82 2nd Fix ( Wiring Work, All) 14 days Wed 5/2/25 Thu 20/2/25 0%

83 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Wed 5/2/25 Fri 28/2/25 0%

84 Ground 520 days Fri 28/7/23 Tue 25/3/25 26%

85 1st Fix ( Conceal Conduit, All ) 12 days Fri 28/7/23 Thu 10/8/23 100%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 4
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
86 2nd Fix ( Wiring Work, All) 14 days Thu 20/2/25 Fri 7/3/25 0%

87 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Sat 1/3/25 Tue 25/3/25 0%

88 Mezzanine 524 days Tue 15/8/23 Wed 16/4/25 26%

89 1st Fix ( Conceal Conduit, All ) 12 days Tue 15/8/23 Mon 28/8/23 100%
90 2nd Fix ( Wiring Work, All) 14 days Fri 7/3/25 Sat 22/3/25 0%

91 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Mon 24/3/25 Wed 16/4/25 0%

92 Level 1 524 days Thu 7/9/23 Fri 9/5/25 55%

93 1st Fix ( Conceal Conduit, All ) 12 days Thu 7/9/23 Wed 20/9/23 100%
94 2nd Fix ( Wiring Work, All) 14 days Sat 22/3/25 Mon 7/4/25 100%

95 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Wed 16/4/25 Fri 9/5/25 0%

96 Level 2 546 days Sat 30/9/23 Fri 27/6/25 26%

97 1st Fix ( Conceal Conduit, All ) 12 days Sat 30/9/23 Fri 13/10/23 100%

98 2nd Fix ( Wiring Work, All) 14 days Mon 7/4/25 Tue 22/4/25 0%

99 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Fri 9/5/25 Fri 27/6/25 0%

100 Level 3 546 days Tue 24/10/23 Mon 21/7/25 26%

101 1st Fix ( Conceal Conduit, All ) 12 days Tue 24/10/23 Mon 6/11/23 100%

102 2nd Fix ( Wiring Work, All) 14 days Tue 22/4/25 Wed 7/5/25 0%

103 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Fri 27/6/25 Mon 21/7/25 0%

104 Level 4 546 days Thu 16/11/23 Wed 13/8/25 26%

105 1st Fix ( Conceal Conduit, All ) 12 days Thu 16/11/23 Wed 29/11/23100%

106 2nd Fix ( Wiring Work, All) 14 days Wed 7/5/25 Thu 22/5/25 0%

107 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Mon 21/7/25 Wed 13/8/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 5
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
108 Level 5 546 days Sat 9/12/23 Fri 5/9/25 26%

109 1st Fix ( Conceal Conduit, All ) 12 days Sat 9/12/23 Fri 22/12/23 100%

110 2nd Fix ( Wiring Work, All) 14 days Thu 22/5/25 Fri 6/6/25 0%

111 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Wed 13/8/25 Fri 5/9/25 0%

112 Level 6 546 days Tue 2/1/24 Mon 29/9/25 26%

113 1st Fix ( Conceal Conduit, All ) 12 days Tue 2/1/24 Mon 15/1/24 100%

114 2nd Fix ( Wiring Work, All) 14 days Fri 6/6/25 Sat 21/6/25 0%

115 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 21 days Fri 5/9/25 Mon 29/9/25 0%

116 Level 7 537 days Thu 25/1/24 Sat 11/10/25 32%

117 1st Fix ( Conceal Conduit, All ) 12 days Thu 25/1/24 Wed 7/2/24 100%

118 2nd Fix ( Wiring Work, All) 14 days Sat 21/6/25 Mon 7/7/25 0%

119 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 12 days Mon 29/9/25 Sat 11/10/25 0%

120 Level 8 519 days Wed 28/2/24 Fri 24/10/25 56%

121 1st Fix ( Conceal Conduit, All ) 33 days Wed 28/2/24 Fri 5/4/24 100%

122 2nd Fix ( Wiring Work, All) 14 days Mon 7/7/25 Tue 22/7/25 0%

123 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 12 days Sat 11/10/25 Fri 24/10/25 0%

124 Level 9 528 days Wed 28/2/24 Tue 4/11/25 51%

125 1st Fix ( Conceal Conduit, All ) 44 days Wed 28/2/24 Thu 18/4/24 100%

126 2nd Fix ( Wiring Work, All) 12 days Tue 22/7/25 Mon 4/8/25 0%

127 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 30 days Wed 1/10/25 Tue 4/11/25 0%

128 Level 10 (Typical Floor) 97 days Mon 22/4/24 Mon 12/8/24 62%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 6
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
129 1st Fix ( Conceal Conduit, All ) 8 days Mon 22/4/24 Tue 30/4/24 100%

130 2nd Fix ( Wiring Work, All) 8 days Fri 7/6/24 Sat 15/6/24 100%

131 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 1/8/24 Mon 12/8/24 0%

132 Level 11 101 days Sat 27/4/24 Thu 22/8/24 62%

133 1st Fix ( Conceal Conduit, All ) 8 days Sat 27/4/24 Mon 6/5/24 100%

134 2nd Fix ( Wiring Work, All) 8 days Sat 15/6/24 Mon 24/6/24 100%

135 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 12/8/24 Thu 22/8/24 0%

136 Level 12 103 days Mon 6/5/24 Mon 2/9/24 62%

137 1st Fix ( Conceal Conduit, All ) 8 days Mon 6/5/24 Tue 14/5/24 100%

138 2nd Fix ( Wiring Work, All) 8 days Mon 24/6/24 Tue 2/7/24 100%

139 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 22/8/24 Mon 2/9/24 0%

140 Level 13 105 days Tue 14/5/24 Thu 12/9/24 62%

141 1st Fix ( Conceal Conduit, All ) 8 days Tue 14/5/24 Wed 22/5/24 100%

142 2nd Fix ( Wiring Work, All) 8 days Wed 3/7/24 Thu 11/7/24 100%

143 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 2/9/24 Thu 12/9/24 0%

144 Level 13A 107 days Wed 22/5/24 Mon 23/9/24 62%

145 1st Fix ( Conceal Conduit, All ) 8 days Wed 22/5/24 Thu 30/5/24 100%

146 2nd Fix ( Wiring Work, All) 8 days Fri 12/7/24 Sat 20/7/24 100%

147 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 12/9/24 Mon 23/9/24 0%

148 Level 15 109 days Thu 30/5/24 Thu 3/10/24 62%

149 1st Fix ( Conceal Conduit, All ) 8 days Thu 30/5/24 Fri 7/6/24 100%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 7
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
150 2nd Fix ( Wiring Work, All) 8 days Sat 20/7/24 Mon 29/7/24 100%

151 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 23/9/24 Thu 3/10/24 0%

152 Level 16 111 days Fri 7/6/24 Mon 14/10/2462%


153 1st Fix ( Conceal Conduit, All ) 8 days Fri 7/6/24 Sat 15/6/24 100%

154 2nd Fix ( Wiring Work, All) 8 days Tue 30/7/24 Wed 7/8/24 100%

155 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 3/10/24 Mon 14/10/240%

156 Level 17 113 days Sat 15/6/24 Thu 24/10/24 62%

157 1st Fix ( Conceal Conduit, All ) 8 days Sat 15/6/24 Mon 24/6/24 100%

158 2nd Fix ( Wiring Work, All) 8 days Thu 8/8/24 Fri 16/8/24 100%

159 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 14/10/24Thu 24/10/24 0%

160 Level 18 115 days Mon 24/6/24 Mon 4/11/24 62%

161 1st Fix ( Conceal Conduit, All ) 8 days Mon 24/6/24 Tue 2/7/24 100%

162 2nd Fix ( Wiring Work, All) 8 days Sat 17/8/24 Mon 26/8/24 100%

163 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 24/10/24 Mon 4/11/24 0%

164 Level 19 117 days Tue 2/7/24 Thu 14/11/24 62%

165 1st Fix ( Conceal Conduit, All ) 8 days Tue 2/7/24 Wed 10/7/24 100%

166 2nd Fix ( Wiring Work, All) 8 days Tue 27/8/24 Wed 4/9/24 100%

167 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 4/11/24 Thu 14/11/24 0%

168 Level 20 121 days Mon 8/7/24 Mon 25/11/240%

169 1st Fix ( Conceal Conduit, All ) 8 days Mon 8/7/24 Tue 16/7/24 0%

170 2nd Fix ( Wiring Work, All) 8 days Tue 3/9/24 Wed 11/9/24 0%

171 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 14/11/24 Mon 25/11/240%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 8
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
172 Level 21 121 days Thu 18/7/24 Thu 5/12/24 0%

173 1st Fix ( Conceal Conduit, All ) 8 days Thu 18/7/24 Fri 26/7/24 0%

174 2nd Fix ( Wiring Work, All) 8 days Thu 12/9/24 Fri 20/9/24 0%

175 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 25/11/24Thu 5/12/24 0%

176 Level 22 123 days Fri 26/7/24 Mon 16/12/240%

177 1st Fix ( Conceal Conduit, All ) 8 days Fri 26/7/24 Sat 3/8/24 0%

178 2nd Fix ( Wiring Work, All) 8 days Sat 21/9/24 Mon 30/9/24 0%

179 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 5/12/24 Mon 16/12/240%

180 Level 23 125 days Sat 3/8/24 Thu 26/12/24 0%

181 1st Fix ( Conceal Conduit, All ) 8 days Sat 3/8/24 Mon 12/8/24 0%

182 2nd Fix ( Wiring Work, All) 8 days Tue 1/10/24 Wed 9/10/24 0%

183 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 16/12/24Thu 26/12/24 0%

184 Level 24 127 days Mon 12/8/24 Mon 6/1/25 0%

185 1st Fix ( Conceal Conduit, All ) 8 days Mon 12/8/24 Tue 20/8/24 0%

186 2nd Fix ( Wiring Work, All) 8 days Thu 10/10/24 Fri 18/10/24 0%

187 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 26/12/24 Mon 6/1/25 0%

188 Level 25 129 days Tue 20/8/24 Thu 16/1/25 0%

189 1st Fix ( Conceal Conduit, All ) 8 days Tue 20/8/24 Wed 28/8/24 0%

190 2nd Fix ( Wiring Work, All) 8 days Thu 19/9/24 Fri 27/9/24 0%

191 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 6/1/25 Thu 16/1/25 0%

192 Level 26 131 days Wed 28/8/24 Mon 27/1/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 9
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
193 1st Fix ( Conceal Conduit, All ) 8 days Wed 28/8/24 Thu 5/9/24 0%

194 2nd Fix ( Wiring Work, All) 8 days Sat 28/9/24 Mon 7/10/24 0%

195 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 16/1/25 Mon 27/1/25 0%

196 Level 27 133 days Thu 5/9/24 Thu 6/2/25 0%

197 1st Fix ( Conceal Conduit, All ) 8 days Thu 5/9/24 Fri 13/9/24 0%

198 2nd Fix ( Wiring Work, All) 8 days Tue 8/10/24 Wed 16/10/240%

199 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 27/1/25 Thu 6/2/25 0%

200 Level 28 135 days Fri 13/9/24 Mon 17/2/25 0%

201 1st Fix ( Conceal Conduit, All ) 8 days Fri 13/9/24 Sat 21/9/24 0%

202 2nd Fix ( Wiring Work, All) 8 days Wed 16/10/24Thu 24/10/24 0%

203 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 6/2/25 Mon 17/2/25 0%

204 Level 29 137 days Sat 21/9/24 Thu 27/2/25 0%

205 1st Fix ( Conceal Conduit, All ) 8 days Sat 21/9/24 Mon 30/9/24 0%

206 2nd Fix ( Wiring Work, All) 8 days Thu 24/10/24 Fri 1/11/24 0%

207 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 17/2/25 Thu 27/2/25 0%

208 Level 30 139 days Mon 30/9/24 Mon 10/3/25 0%

209 1st Fix ( Conceal Conduit, All ) 8 days Mon 30/9/24 Tue 8/10/24 0%

210 2nd Fix ( Wiring Work, All) 8 days Fri 1/11/24 Sat 9/11/24 0%

211 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 27/2/25 Mon 10/3/25 0%

212 Level 31 141 days Tue 8/10/24 Thu 20/3/25 0%

213 1st Fix ( Conceal Conduit, All ) 8 days Tue 8/10/24 Wed 16/10/240%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 10
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
214 2nd Fix ( Wiring Work, All) 8 days Sat 9/11/24 Mon 18/11/240%

215 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 10/3/25 Thu 20/3/25 0%

216 Level 32 143 days Wed 16/10/24Mon 31/3/25 0%

217 1st Fix ( Conceal Conduit, All ) 8 days Wed 16/10/24Thu 24/10/24 0%

218 2nd Fix ( Wiring Work, All) 8 days Mon 18/11/24Tue 26/11/24 0%

219 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 20/3/25 Mon 31/3/25 0%

220 Level 33 145 days Thu 24/10/24 Thu 10/4/25 0%

221 1st Fix ( Conceal Conduit, All ) 8 days Thu 24/10/24 Fri 1/11/24 0%

222 2nd Fix ( Wiring Work, All) 8 days Tue 26/11/24 Wed 4/12/24 0%

223 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 31/3/25 Thu 10/4/25 0%

224 Level 34 147 days Fri 1/11/24 Mon 21/4/25 0%

225 1st Fix ( Conceal Conduit, All ) 8 days Fri 1/11/24 Sat 9/11/24 0%

226 2nd Fix ( Wiring Work, All) 8 days Wed 4/12/24 Thu 12/12/24 0%

227 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 10/4/25 Mon 21/4/25 0%

228 Level 35 149 days Sat 9/11/24 Thu 1/5/25 0%

229 1st Fix ( Conceal Conduit, All ) 8 days Sat 9/11/24 Mon 18/11/240%

230 2nd Fix ( Wiring Work, All) 8 days Thu 12/12/24 Fri 20/12/24 0%

231 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 21/4/25 Thu 1/5/25 0%

232 Level 36 151 days Mon 18/11/24Mon 12/5/25 0%

233 1st Fix ( Conceal Conduit, All ) 8 days Mon 18/11/24Tue 26/11/24 0%

234 2nd Fix ( Wiring Work, All) 8 days Fri 20/12/24 Sat 28/12/24 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 11
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
235 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 1/5/25 Mon 12/5/25 0%

236 Level 37 153 days Tue 26/11/24 Thu 22/5/25 0%

237 1st Fix ( Conceal Conduit, All ) 8 days Tue 26/11/24 Wed 4/12/24 0%

238 2nd Fix ( Wiring Work, All) 8 days Sat 28/12/24 Mon 6/1/25 0%

239 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 12/5/25 Thu 22/5/25 0%

240 Level 38 155 days Wed 4/12/24 Mon 2/6/25 0%

241 1st Fix ( Conceal Conduit, All ) 8 days Wed 4/12/24 Thu 12/12/24 0%

242 2nd Fix ( Wiring Work, All) 8 days Mon 6/1/25 Tue 14/1/25 0%

243 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 22/5/25 Mon 2/6/25 0%

244 Level 39 157 days Thu 12/12/24 Thu 12/6/25 0%

245 1st Fix ( Conceal Conduit, All ) 8 days Thu 12/12/24 Fri 20/12/24 0%

246 2nd Fix ( Wiring Work, All) 8 days Tue 14/1/25 Wed 22/1/25 0%

247 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 2/6/25 Thu 12/6/25 0%

248 Level 40 159 days Fri 20/12/24 Mon 23/6/25 0%

249 1st Fix ( Conceal Conduit, All ) 8 days Fri 20/12/24 Sat 28/12/24 0%

250 2nd Fix ( Wiring Work, All) 8 days Wed 22/1/25 Thu 30/1/25 0%

251 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 12/6/25 Mon 23/6/25 0%

252 Level 41 161 days Sat 28/12/24 Thu 3/7/25 0%

253 1st Fix ( Conceal Conduit, All ) 8 days Sat 28/12/24 Mon 6/1/25 0%

254 2nd Fix ( Wiring Work, All) 8 days Thu 30/1/25 Fri 7/2/25 0%

255 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 23/6/25 Thu 3/7/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 12
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
256 Level 42 163 days Mon 6/1/25 Mon 14/7/25 0%

257 1st Fix ( Conceal Conduit, All ) 8 days Mon 6/1/25 Tue 14/1/25 0%

258 2nd Fix ( Wiring Work, All) 8 days Fri 7/2/25 Sat 15/2/25 0%

259 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 3/7/25 Mon 14/7/25 0%

260 Level 43 165 days Tue 14/1/25 Thu 24/7/25 0%

261 1st Fix ( Conceal Conduit, All ) 8 days Tue 14/1/25 Wed 22/1/25 0%

262 2nd Fix ( Wiring Work, All) 8 days Sat 15/2/25 Mon 24/2/25 0%

263 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 14/7/25 Thu 24/7/25 0%

264 Level 44 167 days Wed 22/1/25 Mon 4/8/25 0%

265 1st Fix ( Conceal Conduit, All ) 8 days Wed 22/1/25 Thu 30/1/25 0%

266 2nd Fix ( Wiring Work, All) 8 days Mon 24/2/25 Tue 4/3/25 0%

267 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 24/7/25 Mon 4/8/25 0%

268 Level 45 169 days Thu 30/1/25 Thu 14/8/25 0%

269 1st Fix ( Conceal Conduit, All ) 8 days Thu 30/1/25 Fri 7/2/25 0%

270 2nd Fix ( Wiring Work, All) 8 days Tue 4/3/25 Wed 12/3/25 0%

271 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 4/8/25 Thu 14/8/25 0%

272 Level 46 171 days Fri 7/2/25 Mon 25/8/25 0%

273 1st Fix ( Conceal Conduit, All ) 8 days Fri 7/2/25 Sat 15/2/25 0%

274 2nd Fix ( Wiring Work, All) 8 days Wed 12/3/25 Thu 20/3/25 0%

275 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 14/8/25 Mon 25/8/25 0%

276 Level 47 173 days Sat 15/2/25 Thu 4/9/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 13
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
277 1st Fix ( Conceal Conduit, All ) 8 days Sat 15/2/25 Mon 24/2/25 0%

278 2nd Fix ( Wiring Work, All) 8 days Fri 21/3/25 Sat 29/3/25 0%

279 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 25/8/25 Thu 4/9/25 0%

280 Level 48 175 days Mon 24/2/25 Mon 15/9/25 0%

281 1st Fix ( Conceal Conduit, All ) 8 days Mon 24/2/25 Tue 4/3/25 0%

282 2nd Fix ( Wiring Work, All) 8 days Sat 29/3/25 Mon 7/4/25 0%

283 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 4/9/25 Mon 15/9/25 0%

284 Level 49 177 days Tue 4/3/25 Thu 25/9/25 0%

285 1st Fix ( Conceal Conduit, All ) 8 days Tue 4/3/25 Wed 12/3/25 0%

286 2nd Fix ( Wiring Work, All) 8 days Mon 7/4/25 Tue 15/4/25 0%

287 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 15/9/25 Thu 25/9/25 0%

288 Level 50 179 days Wed 12/3/25 Mon 6/10/25 0%

289 1st Fix ( Conceal Conduit, All ) 8 days Wed 12/3/25 Thu 20/3/25 0%

290 2nd Fix ( Wiring Work, All) 8 days Tue 15/4/25 Wed 23/4/25 0%

291 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 25/9/25 Mon 6/10/25 0%

292 Level 51 181 days Thu 20/3/25 Thu 16/10/25 0%

293 1st Fix ( Conceal Conduit, All ) 8 days Thu 20/3/25 Fri 28/3/25 0%

294 2nd Fix ( Wiring Work, All) 8 days Wed 23/4/25 Thu 1/5/25 0%

295 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 6/10/25 Thu 16/10/25 0%

296 Level 52 183 days Fri 28/3/25 Mon 27/10/250%

297 1st Fix ( Conceal Conduit, All ) 8 days Fri 28/3/25 Sat 5/4/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 14
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
298 2nd Fix ( Wiring Work, All) 8 days Thu 1/5/25 Fri 9/5/25 0%

299 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 16/10/25 Mon 27/10/250%

300 Level 53 185 days Sat 5/4/25 Thu 6/11/25 0%

301 1st Fix ( Conceal Conduit, All ) 8 days Sat 5/4/25 Mon 14/4/25 0%

302 2nd Fix ( Wiring Work, All) 8 days Fri 9/5/25 Sat 17/5/25 0%

303 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Mon 27/10/25Thu 6/11/25 0%

304 Level 54 191 days Wed 9/4/25 Mon 17/11/250%

305 1st Fix ( Conceal Conduit, All ) 21 days Wed 9/4/25 Fri 2/5/25 0%

306 2nd Fix ( Wiring Work, All) 8 days Sat 17/5/25 Mon 26/5/25 0%

307 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Thu 6/11/25 Mon 17/11/250%

308 Level Water Tank 157 days Sat 3/5/25 Sat 1/11/25 0%

309 1st Fix ( Conceal Conduit, All ) 38 days Sat 3/5/25 Mon 16/6/25 0%

310 2nd Fix ( Wiring Work, All) 30 days Mon 26/5/25 Sat 28/6/25 0%

311 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 11 days Tue 21/10/25 Sat 1/11/25 0%

312 Level LMR 106 days Fri 6/6/25 Tue 7/10/25 0%

313 1st Fix ( Conceal Conduit, All ) 40 days Fri 6/6/25 Tue 22/7/25 0%

314 2nd Fix ( Wiring Work, All) 14 days Fri 8/8/25 Sat 23/8/25 0%

315 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 14 days Mon 22/9/25 Tue 7/10/25 0%

316 Lighting, Power & Telephone 436 days Mon 6/5/24 Thu 25/9/25 19%

317 Block B 436 days Mon 6/5/24 Thu 25/9/25 19%


318 Level 10 (Typical Floor) 83 days Thu 16/5/24 Tue 20/8/24 62%

319 1st Fix ( Conceal Conduit, All ) 8 days Thu 16/5/24 Fri 24/5/24 100%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 15
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
320 2nd Fix ( Wiring Work, All) 8 days Fri 14/6/24 Sat 22/6/24 100%

321 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 9/8/24 Tue 20/8/24 0%

322 Level 11 101 days Mon 6/5/24 Fri 30/8/24 62%

323 1st Fix ( Conceal Conduit, All ) 8 days Mon 6/5/24 Tue 14/5/24 100%

324 2nd Fix ( Wiring Work, All) 8 days Sat 22/6/24 Mon 1/7/24 100%

325 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 20/8/24 Fri 30/8/24 0%

326 Level 12 103 days Tue 14/5/24 Tue 10/9/24 62%

327 1st Fix ( Conceal Conduit, All ) 8 days Tue 14/5/24 Wed 22/5/24 100%

328 2nd Fix ( Wiring Work, All) 8 days Mon 1/7/24 Tue 9/7/24 100%

329 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 30/8/24 Tue 10/9/24 0%

330 Level 13 105 days Wed 22/5/24 Fri 20/9/24 62%

331 1st Fix ( Conceal Conduit, All ) 8 days Wed 22/5/24 Thu 30/5/24 100%

332 2nd Fix ( Wiring Work, All) 8 days Tue 9/7/24 Wed 17/7/24 100%

333 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 10/9/24 Fri 20/9/24 0%

334 Level 13A 107 days Thu 30/5/24 Tue 1/10/24 62%

335 1st Fix ( Conceal Conduit, All ) 8 days Thu 30/5/24 Fri 7/6/24 100%

336 2nd Fix ( Wiring Work, All) 8 days Wed 17/7/24 Thu 25/7/24 100%

337 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 20/9/24 Tue 1/10/24 0%

338 Level 15 110 days Thu 6/6/24 Fri 11/10/24 62%

339 1st Fix ( Conceal Conduit, All ) 8 days Thu 6/6/24 Fri 14/6/24 100%

340 2nd Fix ( Wiring Work, All) 8 days Thu 25/7/24 Fri 2/8/24 100%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 16
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
341 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 1/10/24 Fri 11/10/24 0%

342 Level 16 112 days Fri 14/6/24 Tue 22/10/24 62%

343 1st Fix ( Conceal Conduit, All ) 8 days Fri 14/6/24 Sat 22/6/24 100%

344 2nd Fix ( Wiring Work, All) 8 days Fri 2/8/24 Sat 10/8/24 100%

345 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 11/10/24 Tue 22/10/24 0%

346 Level 17 114 days Sat 22/6/24 Fri 1/11/24 62%

347 1st Fix ( Conceal Conduit, All ) 8 days Sat 22/6/24 Mon 1/7/24 100%

348 2nd Fix ( Wiring Work, All) 8 days Sat 10/8/24 Mon 19/8/24 100%

349 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 22/10/24 Fri 1/11/24 0%

350 Level 18 116 days Mon 1/7/24 Tue 12/11/24 62%

351 1st Fix ( Conceal Conduit, All ) 8 days Mon 1/7/24 Tue 9/7/24 100%

352 2nd Fix ( Wiring Work, All) 8 days Mon 19/8/24 Tue 27/8/24 100%

353 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 1/11/24 Tue 12/11/24 0%

354 Level 19 118 days Tue 9/7/24 Fri 22/11/24 62%

355 1st Fix ( Conceal Conduit, All ) 8 days Tue 9/7/24 Wed 17/7/24 100%

356 2nd Fix ( Wiring Work, All) 8 days Tue 27/8/24 Wed 4/9/24 100%

357 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 12/11/24 Fri 22/11/24 0%

358 Level 20 120 days Wed 17/7/24 Tue 3/12/24 31%

359 1st Fix ( Conceal Conduit, All ) 8 days Wed 17/7/24 Thu 25/7/24 100%

360 2nd Fix ( Wiring Work, All) 8 days Wed 4/9/24 Thu 12/9/24 0%

361 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 22/11/24 Tue 3/12/24 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 17
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
362 Level 21 122 days Thu 25/7/24 Fri 13/12/24 31%

363 1st Fix ( Conceal Conduit, All ) 8 days Thu 25/7/24 Fri 2/8/24 100%

364 2nd Fix ( Wiring Work, All) 8 days Thu 12/9/24 Fri 20/9/24 0%

365 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 3/12/24 Fri 13/12/24 0%

366 Level 22 124 days Fri 2/8/24 Tue 24/12/24 31%

367 1st Fix ( Conceal Conduit, All ) 8 days Fri 2/8/24 Sat 10/8/24 100%

368 2nd Fix ( Wiring Work, All) 8 days Fri 20/9/24 Sat 28/9/24 0%

369 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 13/12/24 Tue 24/12/24 0%

370 Level 23 126 days Sat 10/8/24 Fri 3/1/25 31%

371 1st Fix ( Conceal Conduit, All ) 8 days Sat 10/8/24 Mon 19/8/24 100%

372 2nd Fix ( Wiring Work, All) 8 days Sat 28/9/24 Mon 7/10/24 0%

373 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 24/12/24 Fri 3/1/25 0%

374 Level 24 128 days Mon 19/8/24 Tue 14/1/25 31%

375 1st Fix ( Conceal Conduit, All ) 8 days Mon 19/8/24 Tue 27/8/24 100%

376 2nd Fix ( Wiring Work, All) 8 days Mon 7/10/24 Tue 15/10/24 0%

377 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 3/1/25 Tue 14/1/25 0%

378 Level 25 130 days Tue 27/8/24 Fri 24/1/25 31%

379 1st Fix ( Conceal Conduit, All ) 8 days Tue 27/8/24 Wed 4/9/24 100%

380 2nd Fix ( Wiring Work, All) 8 days Tue 15/10/24 Wed 23/10/240%

381 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 14/1/25 Fri 24/1/25 0%

382 Level 26 132 days Wed 4/9/24 Tue 4/2/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 18
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
383 1st Fix ( Conceal Conduit, All ) 8 days Wed 4/9/24 Thu 12/9/24 0%

384 2nd Fix ( Wiring Work, All) 8 days Wed 23/10/24Thu 31/10/24 0%

385 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 24/1/25 Tue 4/2/25 0%

386 Level 27 134 days Thu 12/9/24 Fri 14/2/25 0%

387 1st Fix ( Conceal Conduit, All ) 8 days Thu 12/9/24 Fri 20/9/24 0%

388 2nd Fix ( Wiring Work, All) 8 days Thu 31/10/24 Fri 8/11/24 0%

389 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 4/2/25 Fri 14/2/25 0%

390 Level 28 136 days Fri 20/9/24 Tue 25/2/25 0%

391 1st Fix ( Conceal Conduit, All ) 8 days Fri 20/9/24 Sat 28/9/24 0%

392 2nd Fix ( Wiring Work, All) 8 days Fri 8/11/24 Sat 16/11/24 0%

393 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Fri 14/2/25 Tue 25/2/25 0%

394 Level 29 138 days Sat 28/9/24 Fri 7/3/25 0%

395 1st Fix ( Conceal Conduit, All ) 8 days Sat 28/9/24 Mon 7/10/24 0%

396 2nd Fix ( Wiring Work, All) 8 days Sat 16/11/24 Mon 25/11/240%

397 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Tue 25/2/25 Fri 7/3/25 0%

398 Level 30 141 days Mon 7/10/24 Wed 19/3/25 0%

399 1st Fix ( Conceal Conduit, All ) 8 days Mon 7/10/24 Tue 15/10/24 0%

400 2nd Fix ( Wiring Work, All) 8 days Mon 25/11/24Tue 3/12/24 0%

401 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 11 days Fri 7/3/25 Wed 19/3/25 0%

402 Level 31 143 days Tue 15/10/24 Sat 29/3/25 0%

403 1st Fix ( Conceal Conduit, All ) 8 days Tue 15/10/24 Wed 23/10/240%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 19
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
404 2nd Fix ( Wiring Work, All) 8 days Tue 3/12/24 Wed 11/12/240%

405 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 19/3/25 Sat 29/3/25 0%

406 Level 32 145 days Wed 23/10/24Wed 9/4/25 0%

407 1st Fix ( Conceal Conduit, All ) 8 days Wed 23/10/24Thu 31/10/24 0%

408 2nd Fix ( Wiring Work, All) 8 days Wed 11/12/24Thu 19/12/24 0%

409 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 29/3/25 Wed 9/4/25 0%

410 Level 33 147 days Thu 31/10/24 Sat 19/4/25 0%

411 1st Fix ( Conceal Conduit, All ) 8 days Thu 31/10/24 Fri 8/11/24 0%

412 2nd Fix ( Wiring Work, All) 8 days Thu 19/12/24 Fri 27/12/24 0%

413 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 9/4/25 Sat 19/4/25 0%

414 Level 34 149 days Fri 8/11/24 Wed 30/4/25 0%

415 1st Fix ( Conceal Conduit, All ) 8 days Fri 8/11/24 Sat 16/11/24 0%

416 2nd Fix ( Wiring Work, All) 8 days Fri 27/12/24 Sat 4/1/25 0%

417 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 19/4/25 Wed 30/4/25 0%

418 Level 35 151 days Sat 16/11/24 Sat 10/5/25 0%

419 1st Fix ( Conceal Conduit, All ) 8 days Sat 16/11/24 Mon 25/11/240%

420 2nd Fix ( Wiring Work, All) 8 days Sat 4/1/25 Mon 13/1/25 0%

421 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 30/4/25 Sat 10/5/25 0%

422 Level 36 153 days Mon 25/11/24Wed 21/5/25 0%

423 1st Fix ( Conceal Conduit, All ) 8 days Mon 25/11/24Tue 3/12/24 0%

424 2nd Fix ( Wiring Work, All) 8 days Mon 13/1/25 Tue 21/1/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 20
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
425 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 10/5/25 Wed 21/5/25 0%

426 Level 37 155 days Tue 3/12/24 Sat 31/5/25 0%

427 1st Fix ( Conceal Conduit, All ) 8 days Tue 3/12/24 Wed 11/12/240%

428 2nd Fix ( Wiring Work, All) 8 days Tue 21/1/25 Wed 29/1/25 0%

429 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 21/5/25 Sat 31/5/25 0%

430 Level 38 157 days Wed 11/12/24Wed 11/6/25 0%

431 1st Fix ( Conceal Conduit, All ) 8 days Wed 11/12/24Thu 19/12/24 0%

432 2nd Fix ( Wiring Work, All) 8 days Wed 29/1/25 Thu 6/2/25 0%

433 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 31/5/25 Wed 11/6/25 0%

434 Level 39 159 days Thu 19/12/24 Sat 21/6/25 0%

435 1st Fix ( Conceal Conduit, All ) 8 days Thu 19/12/24 Fri 27/12/24 0%

436 2nd Fix ( Wiring Work, All) 8 days Thu 6/2/25 Fri 14/2/25 0%

437 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 11/6/25 Sat 21/6/25 0%

438 Level 40 161 days Fri 27/12/24 Wed 2/7/25 0%

439 1st Fix ( Conceal Conduit, All ) 8 days Fri 27/12/24 Sat 4/1/25 0%

440 2nd Fix ( Wiring Work, All) 8 days Fri 14/2/25 Sat 22/2/25 0%

441 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 21/6/25 Wed 2/7/25 0%

442 Level 41 163 days Sat 4/1/25 Sat 12/7/25 0%

443 1st Fix ( Conceal Conduit, All ) 8 days Sat 4/1/25 Mon 13/1/25 0%

444 2nd Fix ( Wiring Work, All) 8 days Sat 22/2/25 Mon 3/3/25 0%

445 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 2/7/25 Sat 12/7/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 21
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
446 Level 42 165 days Mon 13/1/25 Wed 23/7/25 0%

447 1st Fix ( Conceal Conduit, All ) 8 days Mon 13/1/25 Tue 21/1/25 0%

448 2nd Fix ( Wiring Work, All) 8 days Mon 3/3/25 Tue 11/3/25 0%

449 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 12/7/25 Wed 23/7/25 0%

450 Level 43 167 days Tue 21/1/25 Sat 2/8/25 0%

451 1st Fix ( Conceal Conduit, All ) 8 days Tue 21/1/25 Wed 29/1/25 0%

452 2nd Fix ( Wiring Work, All) 8 days Tue 11/3/25 Wed 19/3/25 0%

453 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 23/7/25 Sat 2/8/25 0%

454 Level 44 169 days Wed 29/1/25 Wed 13/8/25 0%

455 1st Fix ( Conceal Conduit, All ) 8 days Wed 29/1/25 Thu 6/2/25 0%

456 2nd Fix ( Wiring Work, All) 8 days Wed 19/3/25 Thu 27/3/25 0%

457 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 2/8/25 Wed 13/8/25 0%

458 Level 45 171 days Thu 6/2/25 Sat 23/8/25 0%

459 1st Fix ( Conceal Conduit, All ) 8 days Thu 6/2/25 Fri 14/2/25 0%

460 2nd Fix ( Wiring Work, All) 8 days Thu 27/3/25 Fri 4/4/25 0%

461 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 13/8/25 Sat 23/8/25 0%

462 Level 46 173 days Fri 14/2/25 Wed 3/9/25 0%

463 1st Fix ( Conceal Conduit, All ) 8 days Fri 14/2/25 Sat 22/2/25 0%

464 2nd Fix ( Wiring Work, All) 8 days Fri 4/4/25 Sat 12/4/25 0%

465 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Sat 23/8/25 Wed 3/9/25 0%

466 Level 47 175 days Sat 22/2/25 Sat 13/9/25 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 22
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
467 1st Fix ( Conceal Conduit, All ) 8 days Sat 22/2/25 Mon 3/3/25 0%

468 2nd Fix ( Wiring Work, All) 1 day Sat 12/4/25 Sat 12/4/25 0%

469 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 10 days Wed 3/9/25 Sat 13/9/25 0%

470 Level Water Tank 178 days Mon 3/3/25 Thu 25/9/25 0%

471 1st Fix ( Conceal Conduit, All ) 41 days Mon 3/3/25 Fri 18/4/25 0%

472 2nd Fix ( Wiring Work, All) 21 days Tue 8/7/25 Thu 31/7/25 0%

473 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 11 days Sat 13/9/25 Thu 25/9/25 0%

474 Level LMR 158 days Wed 26/3/25 Thu 25/9/25 0%

475 1st Fix ( Conceal Conduit, All ) 37 days Wed 26/3/25 Wed 7/5/25 0%

476 2nd Fix ( Wiring Work, All) 14 days Sat 24/5/25 Mon 9/6/25 0%

477 3rd Fix ( Switches, Light Fitting, Tel Outlet ) 14 days Wed 10/9/25 Thu 25/9/25 0%

478 MAXIM RISEN - Telephone 809 days Tue 1/8/23 Sat 28/2/26 0%

479 Project Start 1 day Tue 1/8/23 Tue 1/8/23 0%

480 Project finish 1 day Sat 28/2/26 Sat 28/2/26 0%

481 External Telephone Services 48 days Wed 1/10/25 Tue 25/11/25 0%

482 To Lay TMB ducting 14 days Wed 1/10/25 Thu 16/10/25 0%

483 To Install TMB Manhole 10 days Fri 17/10/25 Tue 28/10/25 0%

484 Testing & Commissioning 10 days Wed 29/10/25Sat 8/11/25 0%

485 Handing Over To TMB 14 days Mon 10/11/25Tue 25/11/25 0%

486 FTTH System - Block A & B 189 days Mon 9/6/25 Wed 14/1/26 0%

487 Internal Telecommunication System 189 days Mon 9/6/25 Wed 14/1/26 0%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 23
ID Task
Task Name Duration Start Finish % Complete
Mode

Half 1, 2023 Half 2, 2023 Half 1, 2024 Half 2, 2024 Half 1, 2025 Half 2, 2025 Half 1, 2026
M J J A S O N D J F M A M J J A S O N D J F M A M J J A S O N D J F M
488 Telephone Backbone Cabling Installation At 90 days Mon 9/6/25 Sat 20/9/25 0%
Riser
489 Equipment Installation 14 days Wed 26/11/25Thu 11/12/25 0%

490 Programming Operator Console Software 7 days Tue 2/12/25 Tue 9/12/25 0%

491 Testing & Commissioning 30 days Thu 11/12/25 Wed 14/1/26 0%


492 SDF ROOM 224 days Tue 1/4/25 Wed 17/12/250%

493 1st Fix ( Exposedl Conduit) 10 days Tue 5/8/25 Fri 15/8/25 0%

494 2nd Fix ( Wiring Work) 10 days Wed 20/8/25 Sat 30/8/25 0%

495 3rd Fix ( Switches, Light Fitting & DB ) 7 days Wed 10/9/25 Wed 17/9/25 0%

496 To interlinking copper tape and earth chamber 7 days Mon 8/9/25 Mon 15/9/25 0%
installation.
497 Cabling Work Installation 180 days Tue 1/4/25 Mon 27/10/250%

498 Testing & commissioning 14 days Mon 3/11/25 Tue 18/11/25 0%

499 TMB/TIME SDF Room handing over 14 days Tue 2/12/25 Wed 17/12/250%

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline

Project: MAXIM RISEN CHERAS Split External Tasks Inactive Summary Manual Summary Progress
Date: 19/08/2023 Milestone External Milestone Manual Task Start-only Manual Progress
Summary Inactive Task Duration-only Finish-only

Page 24

You might also like