Maximum Level of Stock
Maximum Level of Stock
The maximum level of stock is the level above which a business does not or cannot hold
stock on its premises.
The maximum level of inventory could be described as the maximum capacity of a business
to stock goods (inventory or raw material) in its store, which may be due to reasons like
demand limitation of goods (in production or sales), the storage capacity of business,
rationed funds etc. The ‘maximum level of stock’ is usually achieved when those goods
arrive that were ordered at the ‘re-order level’ of the stock. This stock is then used in the
production process (in case of raw materials) or sold (in case of finished goods) and then
re-ordered again at the re-order level which again fills up the stock to the ‘maximum level’.
This is an ongoing process.
Formula:
Maximum Level = Re-order level + Re-order quantity – (Minimum usage × Minimum lead
time)
Reorder level of stock (also known as reorder point or ordering point) in a business is a
preset level of stock or inventory at which the business places a new order with its suppliers
to obtain the delivery of raw materials or finished goods inventory. Every business has to
maintain a certain level of raw materials or finished goods in its store. This is done in order
to sustain the continuity of production in case of raw materials and the continuity of sales
in case of finished goods. For this purpose, the business must set a specific level at which
it should place a new order with the suppliers of inventory.
Formula:
The two formulas used to calculate the re-order level are given below:
Maximum demand or usage (in days, weeks or months) × Maximum lead time (in days,
weeks or months)
[Maximum demand or usage (in days, weeks or months) × Maximum lead time (in days,
weeks or months)] + Safety stock\
The timing difference between placing an order with the supplier and arrival of the goods
is known as the lead time.
What is safety stock (also known as buffer stock)?
In some scenarios, it may be unlikely that the reorder level could be estimated accurately.
This is because the demand and the lead time of the goods could differ than the usual trends
and in that case the business may run out of stock. So, a level of safety stock is set to avoid
such a condition. It is also known as buffer stock.
The David IT Store sells 500 laptops on average in a week. The maximum demand in a
week is 523 laptops. If, the lead time is 4.5 weeks then the reorder level would be:
= 2,354 units
It means that every time the number of laptops decreases to 2,354, the David IT Store must
place a new order.
A business manufactures tire. The average demand for the business is 645 tires/week and
the maximum demand is 670 tires/week. To manufacture one tire 3 kilos of rubber is
required as raw material. So, the production department of the business requires a
maximum of 2,010 (= 670 × 3) kilos of rubber per week. If the lead time to get rubber from
the supplier is 1.5 weeks, then the re-order level would be:
= 3,015 kilos
The production department must place a new order when the raw material (rubber) reaches
3,015 kilos.
Usage or demand
Minimum demand: 390 sweaters per month
Average demand:420 sweaters per month
Maximum demand:435 sweaters per month
Safety stock: 120 sweaters
Lead time
Minimum lead time: 1.2 months
Solution
= 881 units
Example 3
The Maha Cutlery Outlet sells dinner sets. It provides you the following information:
Required: Compute the maximum level of stock of Maha Cutlery Outlet using above
information.
Solution
Example 4
A company manufactures wooden chairs. To manufacture one chairs the company needs 2
square feet of wood.
Demand:
Stock levels:
Solution
= *3,350 sq. ft. + 496 sq. ft. – (970 sq. ft. × 1.75 days)
= 3,350 sq. ft. + 496 sq. ft. – 1,698 sq. ft.
= 3,846 sq. ft. – 1,698 sq. ft.
= 2,148 sq. ft.
So, the maximum level of wood as raw material that can be stored is 2,148 square feet per
month.