TMC11H (Ver.D) Installation Guide(01)(PDF)-EN
TMC11H (Ver.D) Installation Guide(01)(PDF)-EN
D)
Installation Guide
Issue 01
Date 2020-01-20
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees
or representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Website: https://www.huawei.com
Email: [email protected]
Contents
Overview
This document provides the procedures for installing the cabinet, boards, modules,
and cables when the BBU is installed in a TMC11H (Ver.D). It also provides
checklists for hardware installation. The TMC11H (Ver.D) can be configured with
the BBU3910, BBU3900, or BBU5900.
The RF modules for distributed base stations in this document include RRUs and
AAUs. The application scenarios, power distribution principles, cable connections,
and cable installation of the RRUs and AAUs are the same. The following uses the
RRUs as an example.
The exteriors of components or cables in this document are for reference only. The
actual exteriors may be different.
NOTE
● Unless otherwise specified, in this document, LTE and eNodeB always include FDD, NB-IoT,
and TDD. In scenarios where they need to be distinguished, LTE FDD, LTE NB-IoT, and LTE
TDD are used. The same rules apply to eNodeB.
● Unless otherwise specified, in this document, NR and gNodeB always include FDD and TDD.
In scenarios where they need to be distinguished, NR FDD and NR TDD are used. The same
rules apply to gNodeB.
● In this document, "G" is short for GSM, "U" for UMTS, "L" for LTE FDD, "T" for LTE TDD, "M"
for LTE NB-IoT, and "N" for NR. In addition, "N (FDD)" is short for NR FDD and "N (TDD)" is
short for NR TDD.
● For details about the BBU in the LampSite solution, see this document. For details about the
RHUB and pRRU in the LampSite solution, see LampSite Installation Guide.
Product Versions
The following table lists the product versions related to this document.
3900 series base stations SRAN12.1 and later V100R012C10 and later
Intended Audience
This document is intended for base station installation engineers.
Organization
1.1 Changes in TMC11H (Ver.D) Installation Guide
This section describes the changes in TMC11H (Ver.D) Installation Guide.
1.2 Requirements for Site Selection
Sites provided by Huawei must be deployed in places that meet specified
requirements.
1.3 Installation Preparations
1.4 Installation Scenarios
This section describes the installation scenarios of the TMC11H (Ver.D).
1.5 Unpacking Check
This chapter describes how to unpack the delivered equipment, components, or
parts and check whether all the materials are included and intact.
1.6 Obtaining an ESN
The electronic serial number (ESN) is used to identify an NE. Record the ESN of
the base station before the installation for future commissioning.
1.7 Installation Clearance Requirements
This section describes the clearance requirements for installing a cabinet. The
clearances are reserved for cable layout and future maintenance.
1.8 Installation Process
The DBS site installation process includes installing cabinets, installing
components in the cabinets, installing cables, installation check, power-on check,
and subsequent operations.
01 (2020-01-20)
This is the first commercial release.
This document is separated from the DBS3900 Installation Guide document and its
content derives from the section "Outdoor DC Scenario Where the BBU Is Installed
in a TMC11H (Ver.D)."
Compared with the section "Outdoor DC Scenario Where the BBU Is Installed in a
TMC11H (Ver.D)" in DBS3900 Installation Guide of Issue 12 (2018-12-30), this
issue includes the following new topics:
Compared with the section "Outdoor DC Scenario Where the BBU Is Installed in a
TMC11H (Ver.D)" in DBS3900 Installation Guide of Issue 12 (2018-12-30), this
issue does not exclude any topics.
1.3.1 Documents
During the installation, familiarize yourself with related information in the
following documents:
● Safety Information
● Installation Reference
● 3900 & 5900 Series Base Station Model Description
● 3900 & 5900 Series Base Station Component Description
● 3900 & 5900 Series Base Station Cables
● RFU Hardware Description
● BBU5900 Hardware Description
● BBU5900A Hardware Description
● BBU3900 and BBU3910 Hardware Description
● BBU3910A Hardware Description
M2.5 to M6
M2.5 to M6
The following table lists the cabinet configurations of a single- or dual-mode base
station with different backup power requirements, requirements on space for
customer equipment, and carrier configurations.
NOTE
When APM30Hs and IBBS200Ds/IBBS200Ts are initially configured on a 1:1 ratio and more
than six RRUs are configured, ensure that two or more 100 Ah battery packs are configured
in each IBBS200D/IBBS200T to avoid overcurrent of a single battery pack.
When two BBUs are configured for a triple- or quadruple-mode base station, the
BBUs are installed as follows:
● If two BBUs are configured during initial deployment, both the BBUs are
installed in an APM30H, and transmission equipment is installed in a
TMC11H.
● If there is space for a second BBU in the APM30H during capacity expansion,
the BBU is installed in the APM30H. Otherwise, the BBU is installed in a
TMC11H.
When one BBU is configured for a triple- or quadruple-mode base station, the
position of the BBU is indicated by BBU0 in the following figure.
When backup power is not required in a triple- or quadruple-mode base station,
the cabinet configurations of the base station with different requirements on
space for customer equipment are shown in the following figure. In the following
figure, illustrations a and b show the scenarios of new site deployment and
illustration c shows a capacity expansion scenario.
Context
When transporting, moving, or installing the equipment, components, or parts,
you must:
● Package them for delivery before the base station deployment. Unpacked
delivery or package replacement for transferring is not allowed.
● Prevent them from colliding with doors, walls, shelves, or other objects.
● Wear clean gloves, and avoid touching the equipment, components, or parts
with bare hands, sweat-soaked gloves, or dirty gloves.
● Transport the base stations in an environment that meets requirements of
ETSI 300 019-1-2 Class 2.3. For the goods damage caused by non-standard
and violent transportation or non-human factors (such as natural disasters),
the transportation entity should take the responsibility.
NOTICE
● The gravity center of some cabinets is in the front, for example, the IBBS700T,
BTS3900AL, and IBBS300T. Therefore, avoid toppling of the cabinet when the
door of the cabinet is open, especially when you unpack the cabinet or before it
has been secured onto a base.
● After unpacking a cabinet or BBU, you must power on the cabinet or BBU
within seven days. Otherwise, the cabinet or BBU may be damaged.
● After unpacking an RRU, you must power on the RRU within 24 hours.
Otherwise, the RRU may be damaged.
● To protect the equipment from damage, you are advised to keep the unpacked
equipment and packing materials indoors, take photos of the storage
environment, packing case or carton, packing materials, and any rusted or
eroded equipment, and then file the photos.
Procedure
Step 1 Check the total number of articles in each case according to the packing list.
If... Then...
The total number is not consistent Find out the cause and report it to the
with the packing list local Huawei office.
If... Then...
The outer packing is severely Find out the cause and report it to the
damaged or soaked local Huawei office.
Step 3 Check the type and quantity of the equipment in the cases according to the
packing list.
If... Then...
The type and quantity are consistent Sign the Packing List with the customer.
with the packing list on each
packing case
If... Then...
There is any shortage, wrong Report the situation to the local Huawei
delivery, or damaged equipment office.
----End
Procedure
● Obtain the ESN on the BBU5900.
a. Record the ESN on the BBU5900. If there is a label on the FAN unit of the
BBU, the ESN is printed on the label and a mounting ear of the BBU, as
shown in Figure 1-9. Remove the label and record the base station
information on the label marked Site.
NOTE
The base station information includes the name, ID, and location of the base station.
For a base station configured with multiple BBUs, record the ESNs on all BBUs
and submit them to the personnel responsible for the base station
commissioning.
● Obtain the ESN on the BBU5900A.
a. Record the ESN on the BBU5900A. The following figure shows the
position of the ESN on the module.
For a base station configured with multiple BBUs, record the ESNs on all BBUs
and submit them to the personnel responsible for the base station
commissioning.
● Obtain the ESN on the BBU3900/BBU3910.
a. Record the ESN on the BBU.
▪ If there is no label on the FAN unit of the BBU, the ESN is printed on
a mounting ear of the BBU, as shown in Figure 1-11. Record the ESN
and base station information manually.
▪ If there is a label on the FAN unit of the BBU, the ESN is printed on
the label and a mounting ear of the BBU, as shown in Figure 1-12.
Remove the label and record the base station information on the
label marked Site.
NOTE
The base station information includes the name, ID, and location of the base station.
For a base station configured with multiple BBUs, record the ESNs on all BBUs
and submit them to the personnel responsible for the base station
commissioning.
● Obtain the ESN on the BBU3910A.
a. Record the ESN on the BBU3910A. The following figure shows the
position of the ESN on the module.
For a base station configured with multiple BBUs, record the ESNs on all BBUs
and submit them to the personnel responsible for the base station
commissioning.
● Obtain the ESN on the BBU3910C.
a. Remove the backup ESN label from the surface of the BBU3910C. The
following figure shows the position of the backup ESN label.
NOTE
NOTE
For a base station configured with multiple BBUs, record the ESNs on all BBUs
and submit them to the personnel responsible for the base station
commissioning.
----End
Figure 1-15 Clearance requirements for installing cabinets on a concrete floor (1)
The following figure shows the installation clearance requirements for cabinets
such as the APM30H, TMC11H, RFC, and IBBS300D/IBBS300T configured for the
DBS site.
Figure 1-16 Clearance requirements for installing cabinets on a concrete floor (2)
The following figure shows the installation clearance requirements for cabinets
such as the APM30H, TMC11H, RFC, and IBBS700D/IBBS700T configured for the
DBS site.
NOTE
When the IBBS700D or IBBS700T is configured, align the front doors of all cabinets when the
site has sufficient space or align the rear of the cabinets when the space is insufficient.
Figure 1-17 Clearance requirements for installing cabinets on a concrete floor (3)
NOTE
The recommended thickness of the pole wall is 3.5 mm (0.14 in.) or above.
The following figure shows the clearance requirements for installing a cabinet on
a pole.
The ODM06D can be installed on a pole of which the diameter ranges from 48
mm to 114 mm (1.89 in. to 4.49 in.).
The following figure shows the clearance requirements for installing an ODM06D
on a pole.
The OFD06 can be installed on a pole of which the diameter ranges from 48 mm
to 114 mm (1.89 in. to 4.49 in.).
The following figure shows the clearance requirements for installing an OFD06 on
a pole.
For details about how to install an RRU, see the related RRU installation guide.
Procedure
Step 1 Position the base for the cabinet.
1. Determine the position for installing the cabinet according to the engineering
drawing and 1.7 Installation Clearance Requirements.
2. Mark anchor points on the concrete pad, as shown by the circles in the
following figure, to determine the position for installing the base.
3. After drawing the lines between anchor points, use a measuring tape to
measure the distance between anchor points to ensure that the dimensions
are accurate.
Step 2 Drill holes at the anchor points and install expansion bolts in the holes, as shown
in the following figure.
CAUTION
Take proper safety measures to protect your eyes and respiratory tract against the
dust before drilling holes.
NOTE
Generally, the concrete floor is solid and smooth. Therefore, you can use the center punch
to help locate the drill bit. If the conditions of the floor allow direct drilling, skip this step.
(1) M12x60 bolt (2) Spring washer (3) Flat washer (4) Expansion tube
1. Use a hammer drill with a Φ16 drill bit to drill holes with a depth ranging
from 55 mm (2.17 in.) to 60 mm (2.36 in.).
2. Use a vacuum cleaner to wipe away any dust in and around the holes and
measure the spacing between holes. If any of the holes is beyond the
acceptable range, mark a new anchor point and drill a new hole.
3. Use a rubber mallet to pound each expansion bolt until the corresponding
expansion tube completely enters the hole.
4. Tighten an expansion bolt to 20 N·m (177 lbf·in.).
5. Remove the M12x60 bolt, spring washer, and flat washer in sequence by
turning them counterclockwise.
CAUTION
After dismantling the expansion bolts, ensure that the top of each expansion
tube is level with the concrete floor. Otherwise, the cabinet cannot be
installed on the concrete floor evenly and securely.
Step 4 Adjust the base until it is horizontally level, as shown in the following figure.
1. Place the level on the base and observe the position of the bubble.
2. The base is horizontal only when the bubble is in the center of the level. Add
spacers between the base and the concrete pad to adjust the levelness if
necessary.
Step 5 Use a torque wrench to tighten the M12x60 bolts diagonally to 45 N·m (398.28
lbf·in.), as shown in the following figure.
Step 6 Use a Phillips screwdriver to loosen the three M4 countersunk screws on the front
cover plate for the base, and remove the front cover plate, as shown in the
following figure.
NOTE
Do not lose the removed screws and cover plate. They are required during future installation.
Step 7 Remove the baffle plates from both sides and the rear of the base, as shown in
the following figure.
1. Use a Phillips screwdriver to loosen the M4 screw assemblies on both sides of
the base and remove the baffle plates.
2. Use a Phillips screwdriver to loosen the two M4 screw assemblies on the rear
left side of the base and slide the baffle plates to the left. Then, remove the
baffle plates on the right one by one.
Figure 1-29 Removing the baffle plates from both sides and the rear of the base
----End
Context
● The procedures for installing the APM30H, TMC11H, IBBS200D/IBBS200T/
BBC5200D-L/BBC5200T-L, and IBBS300D/IBBS300T are the same. This section
uses the APM30H as an example.
NOTICE
The APM30H (Ver.D) and APM30H (Ver.E) series cabinets are configured with air baffles.
The APM30H (Ver.B)/APM30H (Ver.C) series cabinets are configured with filler modules.
Procedure
Step 1 Place the APM30H onto the base and align the bolt holes in the cabinet with
those in the base, as shown in the following figure.
Step 2 Optional: Remove one to two air baffles or filler modules from the bottom of the
APM30H.
● Remove one or two air baffles from the bottom of an APM30H (Ver.D) or
APM30H (Ver.E) series cabinet, as shown in the following figure.
● Remove one or two filler modules from the bottom of an APM30H (Ver.B)/
APM30H (Ver.C) series cabinet, as shown in the following figure.
Step 3 Use four M12x35 bolts to secure the APM30H onto the base, and use a torque
wrench to tighten the bolts to 45 N·m (398.28 lbf·in.), as shown in the following
figure.
NOTE
The gasket with an oblong hole is not required when you install an IBBS300D/IBBS300T on a
base.
(1) M12x35 bolt (2) Spring washer (3) Flat washer (4) Waterproof (5) Gasket with
rubber washer an oblong hole
Step 4 Optional: Reinstall the removed air baffles or filler modules. Secure the air baffles
or filler modules to 2 N·m (17.70 lbf·in.).
----End
Context
● The cabinet can be installed at a maximum height of 10 m (32.81 ft).
● The procedures for installing the APM30H and TMC11H are the same. This
section uses the APM30H as an example.
NOTICE
The diameter of the pole ranges from 60 mm to 230 mm (2.36 in. to 9.06 in.). The
recommended wall thickness of the pole is 4 mm (0.16 in.) or higher. The
following figure shows the diameter of a pole.
Procedure
Step 1 At an appropriate height on the pole, use four M12x180 bolts to secure a ladder-
shaped bracket onto the pole, and tighten the bolts to 45 N·m (398.28 lbf·in.), as
shown in the following figure.
Step 2 Remove the two plastic bolts at the rear top of the cabinet, as shown in the
following figure.
Step 3 Install a bar at the top of the cabinet and use a socket wrench to tighten two
M12x35 bolts on the bar to 45 N·m (398.28 lbf·in.), as shown in the following
figure.
(1) Bar
Step 4 Optional: Remove one to two air baffles or filler modules from the bottom of the
APM30H.
● Remove one or two air baffles from the bottom of an APM30H (Ver.D) or
APM30H (Ver.E) series cabinet, as shown in the following figure.
● Remove one or two filler modules from the bottom of an APM30H (Ver.B)/
APM30H (Ver.C) series cabinet, as shown in the following figure.
Step 5 Place the cabinet onto the ladder-shaped bracket, use four M12x35 bolts to secure
the cabinet onto the ladder-shaped bracket, and use a torque wrench to tighten
the bolts to 45 N·m (398.28 lbf·in.), as shown in the following figure.
(1) M12x35 bolt (2) Spring washer (3) Flat washer (4) Waterproof (5) Gasket with
rubber washer an oblong hole
Step 6 Put a U-shaped bracket through the holes in the bar at the top of the cabinet, as
shown in the following figure.
Step 7 Optional: Reinstall the removed air baffles or filler modules. Secure the air baffles
or filler modules to 2 N·m (17.70 lbf·in.).
----End
Context
● The cabinet can be installed at a maximum height of 10 m (32.81 ft).
● The procedures for installing the APM30H and TMC11H are the same. This
section uses the APM30H as an example.
NOTICE
Procedure
Step 1 Place a marking-off template against the wall, use a level to ensure that the
marking-off template is placed horizontally, and then use a marker to mark six
anchor points, as shown in the following figure.
Step 2 Drill holes at the anchor points and insert expansion bolts into the holes, as shown
in the following figure.
1. Use a hammer drill with a Ф16 drill bit to drill holes at the anchor points with
a depth ranging from 55 mm to 60 mm (2.17 in. to 2.36 in.).
NOTICE
Take proper safety measures to protect eyes and respiratory tract against the
dust before drilling holes.
2. Tighten the expansion bolts slightly, and place each expansion bolt vertically
into each hole.
3. Use a rubber mallet to pound each expansion bolt until the corresponding
expansion tube completely enters the hole. Then, secure the bolts.
4. Remove the bolts, spring washers, and flat washers in sequence.
(1) Bolt (2) Spring washer (3) Flat washer (4) Expansion tube
Step 3 Align the ladder-shaped bracket with the four lower holes in the wall and use four
M12x60 bolts to tighten the ladder-shaped bracket with a torque of 45 N·m
(398.28 lbf·in.), as shown in the following figure.
Step 4 Remove the two plastic bolts at the rear top of the cabinet, as shown in the
following figure.
Step 5 Install a bar at the top of the cabinet and use a socket wrench to tighten two
M12x35 bolts on the bar to 45 N·m (398.28 lbf·in.), as shown in the following
figure.
(1) Bar
Step 6 Optional: Remove one to two air baffles or filler modules from the bottom of the
APM30H.
● Remove one or two air baffles from the bottom of an APM30H (Ver.D) or
APM30H (Ver.E) series cabinet, as shown in the following figure.
● Remove one or two filler modules from the bottom of an APM30H (Ver.B)/
APM30H (Ver.C) series cabinet, as shown in the following figure.
Step 7 Place the cabinet onto the ladder-shaped bracket, use four M12x35 bolts to secure
the cabinet onto the ladder-shaped bracket, and use a torque wrench to tighten
the bolts to 45 N·m (398.28 lbf·in.), as shown in the following figure.
(1) M12x35 bolt (2) Spring washer (3) Flat washer (4) Waterproof (5) Gasket with
rubber washer an oblong hole
Step 8 Use two bolts to secure the bar on the cabinet onto the wall, as shown in the
following figure.
Step 9 Optional: Reinstall the removed air baffles or filler modules. Secure the air baffles
or filler modules to 2 N·m (17.70 lbf·in.).
----End
Context
The following table lists the specifications of a PGND cable and an equipotential
cable in the TMC11H (Ver.B).
The following table lists the specifications of a PGND cable and an equipotential
cable in the TMC11H (Ver.C).
The following table lists the specifications of a PGND cable and an equipotential
cable in the TMC11H (Ver.D).
The following table lists the specifications of a PGND cable and an equipotential
cable in the TMC11H (Ver.E).
NOTE
The procedures for installing PGND and equipotential cables are the same for the TMC11H
(Ver.B)/TMC11H (Ver.C)/TMC11H (Ver.D)/TMC11H (Ver.E). This following uses a TMC11H
(Ver.D) as an example.
Procedure
Step 1 Prepare the PGND cable and equipotential cable.
1. Cut the cable to suit the actual cable route.
2. Add OT terminals to both ends of the cable by following the instructions in
Assembling the OT Terminal and the Power Cable.
When installing a PGND cable, tightly press the OT terminal in the correct direction, as
shown in Figure 1-51.
(1) Ground bar in the cabinet (2) PGND cable (3) Ground busbar
Step 3 Install the equipotential cable between two TMC11Hs, as shown in the following
figure.
Step 4 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 5 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the
pipe to the cable outlet on the cabinet.
Step 6 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
● A maximum of two BBUs can be installed in the APM30H/TMC11H of a
DBS3900 based on the onsite conditions.
● In a DBS3900 configured with an APM30H (Ver.D) or APM30H (Ver.E), when
two BBUs are installed during initial site deployment, both BBUs are installed
in the APM30H and the transmission equipment is installed in a TMC11H.
When a second BBU is installed during capacity expansion, the BBU is
installed in the APM30H if there is sufficient space. Otherwise, the BBU is
installed in a TMC11H. When two BBUs are installed in a cabinet, BBU 1 is
installed in the 2 U space below BBU 0. The two BBUs must be installed
adjacently. No vacant space or equipment is allowed between the two BBUs.
● In a DBS3900 configured with a TMC11H (Ver.D) or TMC11H (Ver.E), when
two BBUs are installed during initial site deployment, both BBUs are installed
in the TMC11H (with a built-in BBU3900 and –48 V DC power input) and the
transmission equipment is installed in a TMC11H (only providing transmission
space). When a second BBU is installed during capacity expansion, the BBU is
installed in the TMC11H (with a built-in BBU3900 and –48 V DC power input)
if there is sufficient space. Otherwise, the BBU is installed in a TMC11H (only
providing transmission space).
● The following figure shows the positions for installing BBUs in an APM30H
(Ver.D)/APM30H (Ver.E)/TMC11H (Ver.D)/TMC11H (Ver.E).
● The following figure shows the positions for installing BBUs in an APM30H
(Ver.B)/APM30H (Ver.C)/TMC11H (Ver.B)/TMC11H (Ver.C).
NOTE
● The BBU case has a left-in-right-out ventilation channel. It can be stacked with a device
using a left-in-right-out ventilation channel but cannot be stacked with a device using a
right-in-left-out ventilation channel.
● For an indoor application, the BBU case can be installed in a standardized indoor equipment
room but cannot be installed in an equipment room using direct ventilation.
● For an outdoor application, the BBU case can be installed in a cabinet using a heat
exchanger but cannot be installed in a cabinet using direct ventilation. For the specific
cabinet types, see the related hardware documentation.
Procedure
Step 1 If a BBU is installed in an OMB/indoor centralized rack (ICR), perform the
following operations to reinstall the BBU mounting ears in standard mode. Skip
this step if a BBU is installed in other cabinets.
1. Remove the mounting ears on the BBU, as shown in the following figure.
3. Reinstall the mounting ears in standard mode and tighten the four M6x12
screws on each of the mounting ears, with a torque of 2 N·m (17.7 lbf·in.), as
shown in the following figure.
Step 2 Optional: Install cable claws for the BBU in the APM30H or TMC11H.
Align cable claws with the holes on each side of the BBU. Then use two M4 screws
to secure the cable claws to the BBU and tighten the screws to 1.2 N·m (10.62
lbf·in.), as shown in the following figure.
Step 3 Slide the BBU into the cabinet, and tighten the four M6x16 screws on the BBU
panel to 2 N·m (17.70 lbf·in.), as shown in the following figure.
NOTICE
When installing a BBU equipped with boards, hold the bottom of the BBU with
your hands and slide it into the cabinet slowly to prevent it from falling.
----End
Context
The trunk signal protection unit is installed in the 1 U space below the fan
assembly at the top of the APM30H, TP48600A, or TMC11H cabinet.
Procedure
Step 1 Install the cable claws, as shown in the following figure.
1. Remove the four M4 screws from the mounting ear on each side of the SLPU.
2. Place a cable claw between the mounting ear and the SLPU on each side,
move the mounting ear backwards by one hole, and align the mounting holes
in the cable claw with those in the mounting ear and the SLPU.
3. Use two removed M4 screws to secure the mounting ear and cable claw to
the SLPU and tighten the screws to 1.2 N·m (10.62 lbf·in.).
Step 2 Slide the SLPU into the cabinet and use a torque screwdriver to tighten the two
M6x12 screws on the mounting ears to 2 N·m (17.7 lbf·in.), as shown in the
following figure.
----End
Context
When the site is configured with an APM30H, TMC11H, APM5930(AC), or
APM5930(DC), a maximum of two BBUs can be installed. The following figure
shows the positions for installing the two BBUs.
NOTE
NOTE
● The BBU case has a left-in-right-out ventilation channel. It can be stacked with a device
using a left-in-right-out ventilation channel but cannot be stacked with a device using a
right-in-left-out ventilation channel.
● For an indoor application, the BBU case can be installed in a standardized indoor equipment
room but cannot be installed in an equipment room using direct ventilation.
● For an outdoor application, the BBU case can be installed in a cabinet using a heat
exchanger but cannot be installed in a cabinet using direct ventilation. For the specific
cabinet types, see the related hardware documentation.
Procedure
Step 1 Optional: If there is an air baffle in the installation position, remove the air baffle,
as shown in the following figure.
NOTE
The removed air baffles must be installed in the vacant slots in the lower part of the cabinet
from top down. If vacant slots are all occupied with air baffles, other redundant air baffles are
discarded.
Step 2 Optional: When cable claws are not required onsite, align the BBU mounting ears
with the mounting holes, slide the BBU along the guide rails into the cabinet, and
tighten the four M6 screws to 4.8 N·m (42.48 lbf·in.), as shown in the following
figure.
NOTE
Cable claws for the BBU5900 are optional based on site requirements.
Step 3 Optional: When cable claws are required onsite, align the BBU mounting ears and
cable claws with the mounting holes, slide the BBU along the guide rails into the
cabinet, and tighten the four M6 screws to 4.8 N·m (42.48 lbf·in.), as shown in the
following figure.
Step 4 Optional: In most cases, an HDEPC connector has been added to one end of the
BBU power cables before delivery. Connectors must be added to the other end of
the cables on the power equipment side onsite. If an HDEPC connector needs to
be added onsite, see the instructions in Assembling the HDEPC Connector and
Power Cables.
Step 5 Connect the HDEPC connector at one end of the BBU power cables to the UPEU in
the BBU5900.
Step 6 Install the BBU power cables, as listed in the following table and shown in the
following figure.
CAUTION
When installing a BBU power cable for a running base station, connect the cable
to the BBU before connecting it to the power equipment. The operations in the
reverse sequence may cause component damage or personal injury.
NOTE
● In most regions except UK and China, the RTN(+) and NEG(-) wires are black and blue,
respectively.
● In UK, the RTN(+) and NEG(-) wires are blue and gray, respectively.
● In China, the RTN(+) and NEG(-) wires are red and blue, respectively.
EPU02D-02/ "LOAD0" or
EPU02B/EPU02S "LOAD1" port
DCDU16D "LOAD3" or
"LOAD4" port
EPU02D-02/ "LOAD0" or
EPU02B/EPU02S "LOAD1" port
DCDU16D "LOAD3" or
"LOAD4" port
EPU02D-02/ "LOAD0" or
EPU02B/EPU02S "LOAD1" port
DCDU16D "LOAD3" or
"LOAD4" port
If the LOAD8 and LOAD9 ports on the DCDU15D are occupied, install another DCDU to supply
power to the second BBU.
Figure 1-68 Installing BBU power cables when the BBU is installed in the
transmission cabinet
Figure 1-69 Position for installing the power cables of the second power board in
an APM30H (Ver.D)/TMC11H (Ver.D) cabinet
Step 7 Attach labels to the installed cables according to the instructions in Attaching an
L-Shaped Label.
NOTE
● Attach an engineering label to the positive and negative cables on the power equipment
side. And attach the engineering labels with the same content to the corresponding cables
on the BBU side.
● It is recommended that a label on the BBU side be attached 70 mm to 100 mm (2.76 in. to
3.94 in.) away from the HDEPC connector.
● PWR0 and PWR1 in the following figure are for illustration only.
----End
Context
The boards in the BBU to be installed include main control boards (UMPT), half-
width baseband processing units (UBBP), full-width baseband processing units
(UBBPfw1), and power boards (UPEU). The boards to be installed onsite depend
on the configuration requirements of a base station. The following part uses the
procedure for installing a UMPT as an example. The procedures for installing a
UMPT and a UBBP in the BBU are the same.
Operation Rules
● When moving a board, hold the board with both hands, as shown by the
correct operation in the following figure.
● When installing a board, hold the ejector lever side of the board with one
hand and hold another side of the board with the other hand to ensure that
the board is moving in the correct direction. Do not hold the board with only
one hand and never apply lateral forces to the board. The following figure
shows incorrect and correct operations of installing a board.
Figure 1-72 Incorrect and correct operations when installing a board (1)
● When installing a board, ensure that your hands are level so that the board
and the guide rails are on the same level. Do not apply lateral forces to the
board. Otherwise, the board will be distorted. The following figure shows
incorrect and correct operations of installing a board.
Figure 1-73 Incorrect and correct operations when installing a board (2)
NOTICE
● Handle the board with care and avoid collision. Do not pile or compress boards
after they are unpacked.
● When inserting a board into a subrack, prevent it from colliding with the
subrack and push it into the subrack until it snaps into place.
Procedure
Step 1 Put on a pair of ESD gloves.
NOTICE
Step 3 Optional: In an outdoor base station, you need to install a UELP or UFLP. The
following describes how to install a UELP in an SLPU as an example.
1. Loosen the screws on the filler panel in the slot to be used, and slowly
remove the filler panel.
2. Slowly insert the board into the slot until it snaps into place.
3. Use a torque screwdriver to tighten the two captive screws on the board
panel to 0.6 N·m (5.31 lbf·in.).
Step 4 Optional: Install a UBBPfw1. For detailed operations, see Installing a Full-Width
Board.
1. Loosen the screws on the filler panel or half-width board in the slot, and then
slowly remove the filler panel or half-width board from the slot.
2. Remove the guide rail between the left and right slots. Use a Phillips
screwdriver to loosen the M3 screw on the guide rail until it is detached from
the guide rail, and slowly pull out the guide rail.
3. Take the full-width board out of the ESD bag, and raise the ejector levers on
the panel of the board.
4. Insert the full-width board into the slot, and slowly push the board until it is
in contact with the backplane. Then, use both hands to push the ejector levers
and properly install the board.
5. Use a torque screwdriver to tighten the two captive screws on the board
panel to 0.6 N·m (5.31 lbf·in.).
NOTICE
● Use both hands to remove and install a full-width board. During the operations,
hold the bottom of the board with one hand. Do not apply main forces to the
ejector levers. Otherwise, the ejector levers or the board may be damaged.
● Pay attention to the position of the barcode label on the board when inserting
the full-width board into the slot. The barcode label must not be stuck between
the board and the guide rail.
● Store the removed guide rail in a proper place for future maintenance.
4. Add connectors to power cables on the power equipment side. Connect the
HDEPC connector at one end of each power cable to the new UPEU and the
connector at the other end to the corresponding port on the power
equipment. The power cable connections are illustrated in the following table
and figure.
NOTE
In most cases, an HDEPC connector has been added to one end of each BBU power cable
before delivery. Connectors must be added to the other ends of BBU power cables on the
power equipment onsite. If an HDEPC connector must be added onsite, see Assembling the
HDEPC Connector and Power Cables.
For the second BBU (if any) in the APM5930(AC), the power cables of the
BBU are connected to the "LOAD2" and "LOAD5" ports on the EPU05A-11/
EPU05A-12. For the second BBU (if any) in the APM5930(DC), the power
cables of the BBU are connected to the "LOAD8" and "LOAD9" ports on the
DCDU15D.
NOTE
Figure 1-79 Position for installing the power cables of the second power
board in a BTS5900 cabinet
Figure 1-80 Position for installing the power cables of the second power
board in a BTS5900L cabinet
Figure 1-81 Position for installing the power cables of the second power
board in an APM30H (Ver.E)/TMC11H (Ver.E) cabinet
Figure 1-82 Position for installing the power cables of the second power
board in an APM30H (Ver.D)/TMC11H (Ver.D) cabinet
Figure 1-83 Position for installing the power cables of the second BBU in an
APM5930(AC)/APM5930(DC)
----End
Context
● The following table lists the cable specifications of the SLPU.
Procedure
Step 1 Perform required operations according to the type of a cabinet.
If... Then...
Step 2 Optional: If there is a filler module in the installation position, remove the filler
module, as shown in the following figure.
1. Use a Phillips screwdriver to remove the two M6 screws from the mounting
ear on each side of the filler module.
2. Slide the filler module out of the cabinet.
NOTE
The removed filler modules must be installed in the vacant slots in the lower part of the cabinet
from top down. If vacant slots are all occupied with filler modules, other redundant filler
modules are discarded.
Step 3 Optional: If there is an air baffle in the installation position, remove the air baffle,
as shown in the following figure.
NOTE
The removed air baffles must be installed in the vacant slots in the lower part of the cabinet
from top down. If vacant slots are all occupied with air baffles, other redundant air baffles are
discarded.
Step 5 Slide the SLPU into the cabinet and use a torque screwdriver to tighten the two
M6x12 screws on the mounting ears to 2 N·m (17.7 lbf·in.), as shown in the
following figure.
Step 6 Install the surge protection transfer cable for the monitoring signals, as shown in
the following figure.
1. Connect one end of the cable to the OUT0 port on the USLP2 in slot 3 of the
SLPU.
2. Connect the other end of the cable to the EXT_ALM0 port on the UPEU in the
BBU.
Figure 1-88 Installing the surge protection transfer cable for the monitoring
signals
NOTE
The number of surge protection transfer cables for monitoring signals depends on the
actual number of customized alarms. A maximum of four such cables are supported, as
shown in the following figure. For details about the numbers of customized alarms and
cable connections, see section "Customized Alarm Input Principles" in the related hardware
description.
Figure 1-89 Connections of the surge protection transfer cable for the monitoring
signals
Step 7 Install an external dry contact monitoring signal cable, as shown in the following
figure.
1. Cut the external dry contact monitoring signal cable to the length suitable for
the actual cable route.
2. Strip an 8 mm (0.31 in) length of the jacket off the cable connected to the
USLP2 to expose the wires.
3. Use a screwdriver to press the IN0 port on the USLP, insert an external dry
contact monitoring signal cable into the port, and move the screwdriver away.
Then, repeat this procedure to insert external dry contact monitoring signal
cables into IN1 to IN3 ports.
Step 8 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 9 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Context
● The following figure shows the installation positions of DCDU-12Bs in
different cabinets.
In a TMC11H (Ver.D)
serving 7 to 12 RRUs
In a TMC11H (Ver.E)
serving 7 to 21 RRUs
Procedure
Step 1 Remove the four M6 screws from both sides of the slot housing the DCDU-12B.
Step 2 Stick a cable claw onto the right side of the DCDU-12B, as shown in the following
figure.
Figure 1-92 Sticking a cable claw onto the right side of a DCDU-12B
Step 5 Install the DCDU-12B power cables, as shown in the following figure.
1. Remove the protective cover for the terminals of the DC input power cable
from the DCDU-12B. Connect the OT terminals at one end of the power cable
to the DC input terminals on the DCDU-12B and tighten the screw on the OT
terminal to 4.8 N·m (42.48 lbf·in.).
2. Reinstall the protective cover, and use the screwdriver to tighten the screw on
the protective cover to 0.3 N·m (2.66 lbf·in.).
3. Connect the other end of the power cable to the corresponding port on the
power equipment, as described in the following table.
Step 6 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 7 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
NOTE
One DCDU16D can distribute power for three RRUs (power consumption per RRU ≤ 1400 W).
● APM30H (Ver.E)
● APM30H (Ver.E_B~D)
● APM30H (Ver.E)
● APM30H (Ver.E_B~D)
● TMC11H (Ver.D)
● TMC11H (Ver.D_B)
● TMC11H (Ver.D_C)
● APM30H (Ver.D)
● APM30H (Ver.D_B)
● APM30H (Ver.D_C)
(1) DCDU16D
NOTE
● In most regions except UK and China, the RTN(+) and NEG(-) wires are black and blue,
respectively.
● In UK, the RTN(+) and NEG(-) wires are blue and gray, respectively.
● In China, the RTN(+) and NEG(-) wires are red and blue, respectively.
Procedure
Step 1 Stick a cable claw onto the right side of the DCDU16D, as shown in the following
figure.
Figure 1-98 Sticking a cable claw onto the right side of the DCDU16D
Step 2 Put the DCDU16D into the installation position. Then, use a torque screwdriver to
tighten the four M6x12 screws of mounting ears on both sides of the DCDU16D
with the recommended torque of 3 N·m (26.55 lbf·in.), as shown in the following
figure.
4. Reinstall the protective cover on the DCDU16D, and use a torque screwdriver
to tighten the M3 screw on the protective cover to 0.3 N·m (2.66 lbf·in.).
5. Connect the other end of the power cables to the corresponding port on the
power equipment.
Step 4 Optional: Install the DCDU16D input power cables in an APM30H (Ver.D)/
APM30H (Ver.D_C)/APM30H (Ver.D_B).
1. Add OT terminals to both ends of the DCDU16D input power cables by
following the instructions in Assembling the OT Terminal and the Power
Cable.
2. Use a Phillips screwdriver to loosen one M3 screw on the protective cover for
the wiring terminal block on the DCDU16D, and then remove the protective
cover.
3. Connect the OT terminals at one end of the power cables to the "RTN(+)"
and "NEG(-)" terminals on the DCDU16D, and use a torque screwdriver to
tighten the M6 screws to 4.8 N·m (42.48 lbf in.).
4. Reinstall the protective cover on the DCDU16D, and use a torque screwdriver
to tighten the M3 screw on the protective cover to 0.3 N·m (2.66 lbf·in.).
5. Connect the other end of the DCDU16D input power cables to the RFC1 or
RFC2 power terminals on the EPU05A-02, EPU05A-03, EPU05A-04, or
EPU05A-05, and tighten the screws to 4.8 N·m (42.48 lbf in.), as shown in the
following figure.
Step 6 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 7 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
NOTE
● APM30H (Ver.E)
● APM30H (Ver.E_B~D)
● APM30H (Ver.D)
● APM30H (Ver.D_B)
● APM30H (Ver.D_C)
● TMC11H (Ver.D)
● TMC11H (Ver.D_B)
● TMC11H (Ver.D_C)
● APM30H (Ver.E)
● APM30H (Ver.E_B~D)
● TMC11H (Ver.D)
● TMC11H (Ver.D_B)
● TMC11H (Ver.D_C)
● APM30H (Ver.D)
● APM30H (Ver.D_B)
● APM30H (Ver.D_C)
NOTE
● In most regions except UK and China, the RTN(+) and NEG(-) wires are black and blue,
respectively.
● In UK, the RTN(+) and NEG(-) wires are blue and gray, respectively.
● In China, the RTN(+) and NEG(-) wires are red and blue, respectively.
Procedure
Step 1 Optional: After an EPU02D-02 is installed, remove the DCDU that is not in use.
1. Turn off the circuit breaker of the equipment supplying power for the DCDU.
2. Record all cable connections on the DCDU, and remove the cables.
3. Use a Phillips screwdriver to remove the four M6 screws from both sides of
the DCDU, and gently pull the DCDU out of the cabinet along the guide rails.
4. Place the removed DCDU in an ESD box or bag.
Step 2 Stick a cable claw onto the right side of the EPU02D-02, as shown in the following
figure.
Figure 1-105 Sticking a cable claw onto the right side of an EPU02D-02
Step 3 Put the EPU02D-02 into the installation position. Then, use a torque screwdriver to
tighten the four M6x12 screws of mounting ears on both sides of the EPU02D-02
with the recommended torque of 3 N·m (26.55 lbf·in.), as shown in the following
figure.
Step 4 Optional: Install the second BDU in slot 2 of the EPU02D-02 as required.
NOTE
An EPU02D-02 has been configured with two BDUs before delivery. Therefore, skip this step for
an EPU02D-02.
1. Remove the corresponding filler panel.
2. Release the buckle on the upper right corner of the BDU, and rotate the
handle outwards.
3. Gently slide the BDU into the corresponding slot along the guide rails.
4. Rotate the handle inwards, and fasten the buckle.
NOTE
– Add OT terminals to the power cables according to the instructions in Assembling the
OT Terminal and the Power Cable.
– The cable diagram on the top of the EPU02D/EPU02D-02 protection cover is used for
preparing an output power cable connected to an EPC4/EPC5/EPC11 connector.
Step 7 Optional: In the APM30H (Ver.E), configure the PDU01D-01 in slots 8 and 9 in the
EPU05A-06, EPU05A-07, EPU05A-08, or EPU05A-09 and connect the EPU02D input
power cables to the PDU01D-01, as shown in the following figure. Then, tighten
the OT terminals to 4.8 N·m (42.48 lbf·in.).
Step 8 Optional: Install the EPU02D-02 alarm cable, as shown in the following figure.
NOTE
The types and installation positions of the cables installed on the FAN02H are similar to
those of cables installed on the FAN 02E. The following figures use the FAN 02E as an
example.
Step 9 Optional: When the monitoring port on the fan assembly is occupied, connect the
RJ45 connector at one end of the cable to the "COM_IN" port on the EPU02D-02,
and the RJ45 connector at the other end to the "MON1" port on the BBU, as
shown in the following figure.
Step 10 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 11 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
● An EPU02B can be configured with a maximum of two BDU70-03s.
● An EPU02S can be configured with a maximum of two dynamic voltage
boosting SDU60-02s.
● One EPU02B can provide voltage boosting power distribution for six RRUs
(power consumption per RRU < 1200 W).
● One EPU02S can provide voltage boosting power distribution for three RRUs
(power consumption per RRU ≤ 1400 W).
NOTE
For the configuration principles of the EPU02B, see EPU02B. For the configuration
principles of the EPU02S, see EPU02S.
The following figure shows the installation positions of an EPU02B/EPU02S.
Figure 1-114 Installation positions of the power distribution box in 3900 series
base stations
Figure 1-115 Installation positions of the power distribution box in 5900 series
base stations
Table 1-28 Specifications of power cables for the power distribution box in 3900
series base stations
Base Cabinet Type Connector Power
Station Equipment
Type One End The Other
End
Table 1-29 Specifications of power cables for the power distribution box in 5900
series base stations
Base Cabinet Type Connector Power
Station Equipment
Type One End The Other
End
NOTE
● In most regions except the UK and China, the RTN(+) cable is black and the NEG(-)
cable is blue.
● In the UK, the RTN(+) cable is blue and the NEG(-) cable is gray.
● In China, the RTN(+) cable is red and the NEG(-) cable is blue.
Procedure
Step 1 After an EPU02B/EPU02S is installed, remove the DCDU that is not in use.
1. Turn off the circuit breaker of the equipment supplying power to the DCDU.
2. Record all cable connections on the DCDU, and remove the cables.
3. Use a Phillips screwdriver to remove the four M6 screws from both sides of
the DCDU, and gently pull the DCDU out of the cabinet along the guide rails.
4. Place the removed DCDU in an ESD box or bag.
Step 2 Stick a cable claw onto the right side of the EPU02B/EPU02S, as shown in the
following figure.
Figure 1-116 Sticking a cable claw onto the right side of the EPU02B
Figure 1-117 Sticking a cable claw onto the right side of the EPU02S
Step 3 Place the EPU02B/EPU02S at the installation position. Then, use a torque
screwdriver to tighten the four M6x12 screws of mounting ears on both sides with
the recommended torque of 2 N·m or 17.70 lbf·in. (EPU02B)/3 N·m or 26.55 lbf·in.
(EPU02S), as shown in the following figure.
Step 4 If a second BDU is required, install the second BDU in slot 2 of the EPU02B as
required.
1. Remove the filler panel from slot 2 of the EPU02B.
2. Release the buckle on the upper right corner of the BDU, and rotate the
handle outwards.
3. Gently slide the BDU into the corresponding slot along the guide rails.
4. Rotate the handle inwards, and fasten the buckle.
Step 7 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 8 Attach labels to the installed cables by following the instructions in Attaching a
Cable-Tying Label.
----End
Context
● An EPU02S-02 supports only one SDU60-02 and one SDU30-01. Both
SDU60-02 and SDU30-01 are dynamic voltage boosting modules.
● An EPU02S-02 can provide voltage boosting power distribution for three RRUs
(power consumption per RRU ≤ 1400 W).
For details about the configuration principles of the EPU02S-02, see EPU02S-02.
The following figure shows the installation positions of an EPU02S-02.
Figure 1-125 Installation positions of the power distribution boxes in 3900 series
base stations
Figure 1-126 Installation positions of the power distribution boxes in 5900 series
base stations
Table 1-30 Specifications of power cables for the power distribution box in 3900
series base stations
Base Cabinet Type Connector Power
Station Equipment
Type One End The Other
End
Table 1-31 Specifications of power cables for the power distribution box in 5900
series base stations
Base Cabinet Type Connector Power
Station Equipment
Type One End The Other
End
NOTE
● In most regions except the UK and China, the RTN(+) cable is black and the NEG(-)
cable is blue.
● In the UK, the RTN(+) cable is blue and the NEG(-) cable is gray.
● In China, the RTN(+) cable is red and the NEG(-) cable is blue.
Procedure
Step 1 After an EPU02S-02 is installed, remove the DCDU that is not in use.
1. Turn off the circuit breaker of the equipment supplying power for the DCDU.
2. Record all cable connections on the DCDU, and remove the cables.
3. Use a Phillips screwdriver to remove the four M6 screws from both sides of
the DCDU, and gently pull the DCDU out of the cabinet along the guide rails.
4. Place the removed DCDU in an ESD box or bag.
Step 2 Stick a cable claw onto the right side of the EPU02S-02, as shown in the following
figure.
Figure 1-127 Sticking a cable claw onto the right side of the EPU02S-02
Step 3 Put the EPU02S-02 into the installation position. Then, use a torque screwdriver to
tighten the four M6x12 screws of mounting ears on both sides with the
recommended torque of 3 N·m (26.55 lbf·in.), as shown in the following figure.
Step 6 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 7 Attach labels to the installed cables by following the instructions in Attaching a
Cable-Tying Label.
----End
Context
The procedures for installing an AC heater are the same in an APM30H or a
TMC11H of Ver.D, Ver.B, Ver.C, and Ver.E. This section illustrates how to install an
AC heater in an APM30H (Ver.E) and a TMC11H (Ver.E).
If a service outlet unit (SOU) is not installed in the cabinet, install the AC heater in
the 1 U space at the bottom of the cabinet, as shown in Figure 1-131. If an SOU
is installed in the cabinet, install the AC heater above the SOU, as shown in Figure
1-132.
Procedure
Step 1 Slide the AC heater into the installation position, and tighten the four M6x12
screws on the panel to 2 N·m (17.7 lbf·in.), as shown in the following figure.
If... Then...
2. Install the AC heater power cable in the TMC11H, as shown in Figure 1-135
and Figure 1-136.
a. Remove the cover plate of the AC junction box.
b. Connect the C13 connector at the other end of the AC heater power
cable to the power input port on the AC heater.
c. Connect the OT terminals at one end of the brown, blue, and green and
yellow wires of the AC heater power cable to the L0, N0, and PE
terminals in the AC junction box, respectively.
d. Install the power cables for the AC junction box in the TMC11H as
follows: Route the cables into the cabinet from the left side of the
cabinet, and then connect the OT terminals at one end of the cables to
the L and N terminals in the AC junction box in the TMC11H and the
other end of the cables to the external power equipment.
e. Install the cover plate of the AC junction box and tighten the screws on
the cover plate to 0.3 N·m (2.66 lbf·in.).
Figure 1-136 Installing power cables for the AC junction box in the TMC11H
Step 3 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 4 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
● An EMUA or EMUB is installed in a reserved slot in a cabinet. In normal cases,
it is installed in the 1 U space under the installed devices in a cabinet.
● The following table lists the specifications of EMUA or EMUB cables.
Most UK
Region
s
Procedure
Step 1 Perform required operations according to the type of a TMC11H.
If... Then...
Step 2 Optional: If there is a filler module in the installation position, remove the filler
module, as shown in the following figure.
1. Use a Phillips screwdriver to remove the two M6 screws from the mounting
ear on each side of the filler module.
2. Slide the filler module out of the cabinet.
NOTE
The removed filler modules must be installed in the vacant slots in the lower part of the cabinet
from top down. If vacant slots are all occupied with filler modules, other redundant filler
modules are discarded.
Step 3 Optional: If there is an air baffle in the installation position, remove the air baffle,
as shown in the following figure.
NOTE
The removed air baffles must be installed in the vacant slots in the lower part of the cabinet
from top down. If vacant slots are all occupied with air baffles, other redundant air baffles are
discarded.
Step 4 Optional: Align the holes on the cable claws with the holes on the mounting ears
on both sides of the EMUB, and stick the cable claws onto both sides of the
EMUB, as shown in the following figure. If an EMUA is to be installed, skip this
step.
----End
Context
A satellite card needs to be installed onsite only for a USCU that supports two
satellite cards. To install a satellite card, perform steps 1 to 3.
Procedure
Step 1 Optional: Loosen the two M3 screws on the panel of the USCU and pull it out, as
shown in the following figure.
Step 2 Optional: Install a satellite card on the USCU, as shown in the following figure.
1. Remove the three M1.6 screws on the USCU.
2. Place the satellite card on the USCU, aligning the mounting holes on the
satellite card with the bolts on the USCU.
3. Use the three M1.6 screws removed in step a to secure the satellite card, and
tighten the screws to 0.1 N·m (0.89 lbf·in.).
4. Connect one end of the RF jumper for the satellite card to the RF port on the
satellite card, and connect the other end to the "GPS" port on the USCU.
NOTE
There are six mounting holes on the satellite card. You only need to install the three screws
shown in the following figure.
Step 3 Optional: Install the USCU equipped with the satellite card into the BBU, and
tighten the captive screws on the USCU to 0.6 N·m (5.31 lbf·in.).
Step 4 Secure the GPS clock signal cable onto the support, and tighten the screws to 6.5
N·m (57.53 lbf in.), as shown in the following figure.
Figure 1-145 Securing the GPS clock signal cable onto the support
Step 5 Secure the support onto the inner left wall of the cabinet with a torque of 1.2 N·m
(10.62 lbf in.), as shown in the following figure.
Step 6 Optional: Connect the GPS clock signal cable to the "GPS" port on the USCU or
UMPT, as shown in the following figure.
Step 7 Use a torque wrench to secure the "Protect" port on the GPS surge protector onto
the type N50 straight female connector on one end of the GPS signal cable with a
torque of 4 N·m (35.40 lbf·in.), as shown in the following figure.
NOTE
● The UMPTg supports surge protection. Therefore, no GPS surge protector is required.
● The exterior of the GPS surge protector in this section is for reference only. The actual
exterior may be different.
Step 8 Use a torque wrench to secure the GPS jumper to the "Surge" port on the GPS
surge protector with a torque of 4 N·m (35.40 lbf·in.), as shown in the following
figure.
Step 9 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 10 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Context
● The DDF is installed in the 1 U space reserved in the cabinet.
● In the digital distribution module, a, b, and s have different meanings.
– a and b indicate signal cables.
– s indicates a PGND cable.
● Alarm cables are routed on the left side of the DDF, and E1/T1 cables are
routed on the right side of the DDF. All cables are routed from the top down.
● The following procedure uses a twisted pair cable as an example. When
installing an E1 coaxial cable, install an insulation pad between the wiring
terminal and the DDF.
Procedure
Step 1 Distribute the twisted pair cable on the DDF on the device side. This twisted pair
cable is connected to the BBU.
1. Insert the bare wires at one end of the twisted pair cable to the corresponding
digital distribution module according to the colors and labels of the wires.
2. Use an impact tool to seat the wires of the twisted pair cable into the
terminal blocks on the DDF, as shown in Figure 1-150.
Step 2 Distribute the twisted pair cable on the DDF on the cable side. This twisted pair
cable is connected to the peer equipment.
1. Insert the bare wires at one end of the twisted pair cable to the corresponding
digital distribution module according to the colors and labels of the wires.
2. Use an impact tool to seat the wires of the twisted pair cable into the
terminal blocks on the DDF, as shown in Figure 1-150.
Step 3 Arrange the wires on the DDF, as shown in the following figure.
NOTE
● After distributing cables on the DDF, ensure that no bare wire is exposed outside the
DDF.
● When interconnecting cables on both sides of the DDF, interconnect wires according to
actual situations. The colors of interconnected wires must be the same.
If... Then...
Step 5 Optional: If there is a filler module in the installation position, remove the filler
module, as shown in the following figure.
1. Use a Phillips screwdriver to remove the two M6 screws from the mounting
ear on each side of the filler module.
2. Slide the filler module out of the cabinet.
NOTE
The removed filler modules must be installed in the vacant slots in the lower part of the cabinet
from top down. If vacant slots are all occupied with filler modules, other redundant filler
modules are discarded.
Step 6 Optional: If there is an air baffle in the installation position, remove the air baffle,
as shown in the following figure.
NOTE
The removed air baffles must be installed in the vacant slots in the lower part of the cabinet
from top down. If vacant slots are all occupied with air baffles, other redundant air baffles are
discarded.
Step 7 Check whether floating nuts are installed on both sides of the 19-inch rack. If no,
install the floating nuts delivered with the DDF to both sides of the rack.
Step 8 Align the DDF with the cabinet, slide it into the cabinet, and use a screwdriver to
tighten four M6x12 screws on both sides of the DDF to 2 N·m (17.70 lbf in.), as
shown in the following figure.
----End
NOTE
If a cable listed below is not required, skip the cabling requirements of the cable.
Security requirements
● When routing cables, avoid sharp objects or sharp edges on the wall. If
necessary, use tubes to protect the cables.
● When routing cables, keep the cables away from heat sources and use heat
insulation materials to insulate the cables from the heat sources.
● Reserve a proper distance (0.1 m or 0.33 ft is recommended) between
equipment and cables, especially at the cable curves to protect the cables and
equipment.
● Reserve drip loops for all cables outside the feeder window before routing
them into the room. Ensure that the radiuses of the drip loops are greater
than or equal to the minimum bending radiuses of the cables.
● When routing a cable into the room, ensure that a person is assisting you in
the room.
● Apply waterproof treatment to the feeder window.
(1) Cable hole for a (2) Cable hole for a (3) Cable hole for a (4) Rubber tube
feeder CPRI/Ir optical fiber power cable
● After routing a DC power cable onto the platform on a tower, route it along
the shortest path to the rails surrounding the platform, and route it along the
inside of the rails.
● After routing a DC power cable close to the equipment on a tower, use clips
to secure the power cable onto a pole or the rails surrounding the platform.
Ensure the position where the power cable is secured is less than 1.5 m (4.92
ft) away from the equipment to which the power cable connects.
Cabling of PGND cables
● PGND cables for a base station must be connected to the same group of
ground bars.
● PGND cables cannot be routed overhead outdoors. All PGND cables must be
buried in the ground or laid out indoors.
● The external conductor of the coaxial wire and the shield layer of the shielded
cable must have proper electrical contact with the metal surface of the
equipment to which they are connected.
● PGND cables and signal cables must be installed with a certain distance
reserved between them to prevent interference from each other.
● Switches or fuses must not be installed on the PGND cables.
● Other devices must not be used for electrical connections of the PGND cables.
● All the metal parts in the housing of the equipment must be reliably
connected to the ground terminal.
Cabling of E1 cables
● E1 cables cannot be crossed with power cables, PGND cables, or RF cables
when being laid out. If transmission cables are routed with power cables,
PGND cables, or RF cables in parallel, the spacing between them must be
greater than 30 mm (1.18 in.).
● E1 cables are routed straightly and bound neatly with cable ties.
● Sufficient slack is provided in E1 cables at turns.
● E1 cables cannot be pressed by the cabinet door when routed through the
cabinet. The following figure shows both correct and incorrect ways of routing
the cables.
● When coiling optical fibers, apply even strength. Do not bend the optical
fibers with force.
● Unused optical connectors must be covered with dustproof caps.
● The optical fibers must not be pressed by the door of the cabinet when
routed, as shown in the following figures.
● After routing an optical fiber onto the platform on a tower, route it along the
shortest path to the rails surrounding the platform, and route it along the
inside of the rails.
● After routing an optical fiber near the equipment on a tower, use clips to
secure the optical fiber onto a pole or the rails surrounding the platform.
Ensure that the distance between the equipment and the position where the
optical fiber is secured is not too long.
● Coil the excess of the optical fibers near the equipment on the tower before
securing the cables onto the tower.
The following table describes the cable routing through the cable holes in an
APM30H.
Item Description
Left Used for routing the following cables: APM30H input power cables,
cable equipotential cables between cabinets, heating-film power cables for
hole the IBBS200D, power cables for the junction box in the TMC11H,
CPRI optical fibers, GPS clock signal cables, GPS jumpers, and
monitoring signal cables for storage battery cabinets.
Item Description
Right Used for routing the following cables: RRU power cables, power
cable cables for storage battery cabinets, TMC11H input power cables, fan
hole power cables for the IBBS200D, TEC power cables for the IBBS200T,
E1/T1 cables, FE/GE Ethernet cables, FE/GE optical fibers, and
CMUEA-BBU monitoring signal cables.
Cable bags are used in the cable holes of the APM30H to facilitate routing all
types of cables. The following figure shows the cable bags in an APM30H.
The following table describes the cable routing through the cable holes in a
TMC11H.
Left cable Used for routing the following cables: TMC11H input power cables,
hole DCDU-12B input power cables, power cables for the junction box
in the TMC11H, heating-film power cables for the IBBS200D,
equipotential cables between cabinets, monitoring signal cables
between cascaded CMUEAs (in different storage battery cabinets),
CPRI optical fibers, GPS clock signal cables, and GPS jumpers.
Right Used for routing the following cables: RRU power cables,
cable hole monitoring signal cables between cascaded CMUEAs, E1/T1 cables,
FE/GE Ethernet cables, FE/GE optical fibers, and CMUEA-BBU
monitoring signal cables.
Cable bags are used in the cable holes of the TMC11H to facilitate routing all
types of cables. The cable bags in a TMC11H are the same as those in an
APM30H.
The following table describes the cable routing through the cable holes in an
IBBS200D/IBBS200T.
Left cable Used for routing the following cables: input power cables, power
hole cables for the junction box, equipotential cables between cabinets,
monitoring signal cables between cascaded CMUEAs (in different
storage battery cabinets), CPRI optical fibers, GPS clock signal
cables, and GPS jumpers.
Right Used for routing the following cables: RRU power cables, power
cable hole cables for storage battery cabinets, input power cables, fan power
cables for the IBBS200D, TEC power cables for the IBBS200T,
monitoring signal cables between cascaded CMUEAs, E1/T1 cables,
FE/GE Ethernet cables, FE/GE optical fibers, and CMUEA-BBU
monitoring signal cables.
NOTE
There are two cable holes on the right of the upper IBBS200D. Route cables preferentially
through the rear cable hole (the one far away from the door). If the space in the rear cable hole
is insufficient, route cables through the front cable hole (the one close to the door).
Cable bags are used in the cable holes of the IBBS200D/IBBS200T to facilitate
routing all types of cables. The cable bags in an IBBS200D/IBBS200T are the same
as those in an APM30H, as shown in Figure 1-163.
The following table describes the cable routing through the cable holes in an
IBBS300D/IBBS300T.
Item Description
Left Used for routing the following cables: power cables for the junction
cable box in the TMC11H, equipotential cables between cabinets, heater
hole power cables for the IBBS300D, monitoring signal cables for storage
battery cabinets, and monitoring signal cables between cascaded
CCU01D-03 modules (in different storage battery cabinets).
Right Used for routing the following cables: TMC11H input power cables,
cable power cables for storage batteries, power cables for cascaded storage
hole batteries, TEC power cables for the IBBS300T, and fan power cables
for the IBBS300D.
Cable bags are used in the cable holes of the IBBS300D/IBBS300T to facilitate
routing all types of cables. The following figure shows the cable bags in an
IBBS300D/IBBS300T.
Figure 1-168 Top view for the cable outlets at the bottom of an IBBS700D/
IBBS700T
Cable bags are used in the cable outlets of an IBBS700D/IBBS700T. This facilitates
the routing of all types of cables. The following figure shows the cable bags in the
IBBS700D/IBBS700T.
The following table describes the cable routing through the cable outlets in an
IBBS700D/IBBS700T.
Left Cables routed through this cable outlet are as follows: PGND cable,
cable power cable for the junction box, power cable for the power distribution
outle box, CCU monitoring signal cable, and battery cabinet monitoring signal
t cable.
Right Cables routed through this cable outlet are as follows: power cable for
cable the temperature control system and power cable for the power
outle distribution box.
t
Context
Input power cables for the TMC11H refer to DCDU power cables. The following
table lists the specifications of the DCDU power cables.
NOTE
● Colors and exteriors of cables may vary with countries and regions.
● The cables are black and blue in most regions, whereas blue and gray in the UK and red and
blue in China.
Procedure
Step 1 Route the DCDU power cables into the cabinet through the cable bag or cable
outlet on the bottom left side of the cabinet.
Step 2 Prepare DCDU power cables.
1. Cut the cables to suit the actual cable routes.
2. Add a connector or OT terminals to each end of each power cable according
to Table 1-40Table 1-41. For detailed operations, see Assembling the OT
Terminal and the Power Cable.
Step 3 Install DCDU power cables, as shown in the following figure.
NOTE
The installation methods of DCDU-03B, DCDU-11B, and DCDU-12B power cables are the same.
The following figure uses the installation method of DCDU-12B power cables in a TMC11H
(Ver.D) as an example.
1. Use a Phillips screwdriver to remove an M3 screw from the protective cover
for the AC input terminals, and open the protective cover.
2. Connect the M6 OT terminals at one end of the DCDU power cables to the
RTN(+) and NEG(-) terminals on the DCDU in the TMC11H, and tighten the
screws to 4.8 N·m (42.48 lbf·in.).
3. Reinstall the protective cover, and use a torque screwdriver to tighten the
screw on the protective cover to 0.3 N·m (2.66 lbf·in.).
Step 4 Connect the other end of the DCDU power cables to the external power
equipment.
Step 5 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 6 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the
pipe to the cable outlet on the cabinet.
Step 7 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
The following table lists the specifications of BBU power cables.
NOTE
● Colors and exteriors of cables may vary with countries and regions.
● The cables are black and blue in most regions, whereas red and blue in China.
● In capacity expansion scenarios, two BBUs are configured. The installation of power
cables of the second BBU is the same as that of the first BBU.
Procedure
Step 1 Add a connector or OT terminals to the BBU power cable on the power equipment
side.
1. Cut the cable to suit the actual cable route.
2. Add a connector or OT terminals to one end of the cable, as listed in the
following table.
Cabinet Type Power Equipment Method of Adding a
Connector/Terminal
Step 2 Connect the 3V3 connector at one end of the BBU power cable to the "-48V" port
on the UPEU in the BBU, and tighten the screws on the connector to 0.25 N·m
(2.21 lbf·in.).
Step 3 Connect the other end of the BBU power cable to the corresponding power
equipment, as listed in the following table.
Cabinet Type Power Equipment Installation Position
NOTE
● When two UPEU boards are configured in a BBU, each UPEU requires one BBU power
cable. The 3V3 connector at one end of the second BBU power cable is connected to the
"-48V" port on the UPEU. The EPC4 connector, female fast connector (pressfit type), or
OT terminal at the other end is connected to the "LOAD7" port on the DCDU.
● The installation position of the DCDU16D is similar to that of the DCDU-12B in the
TMC11H (Ver.D)/TMC11H (Ver.E). The following uses the DCDU-12B as an example.
CAUTION
When installing a BBU power cable for a running base station, connect the cable
to the BBU before connecting it to the power equipment. The operations in the
reverse sequence may cause component damage or personal injury.
Figure 1-171 Installing a BBU power cable (when the DCDU-03B supplies power)
Figure 1-172 Installing a BBU power cable (when the DCDU-11B supplies power)
Figure 1-173 Installing BBU power cables (when the DCDU-12B supplies power)
Step 4 Optional: Install the power cable for the second BBU3900/BBU3910 in the
TMC11H (Ver.D)/TMC11H (Ver.E), as shown in Figure 1-173.
1. Prepare the BBU power cable by following the instructions in Step 1.
2. Connect the 3V3 connector at one end of the BBU power cable to the "-48V"
port on the UPEU in the BBU.
3. Connect the EPC4 connector at the other end of the BBU power cable to the
"LOAD8" port on the DCDU-12B.
Step 5 Install the power cable for the second BBU5900 in the TMC11H (Ver.D)/TMC11H
(Ver.E), as shown in the following figure.
1. Connect the HDEPC connector at one end of the BBU power cables to the
UPEU in the BBU5900.
2. Connect the EPC4 connectors at the other end of the BBU power cables to the
"LOAD6" and "LOAD7" ports on the DCDU-12B.
NOTE
When installing the second BBU5900, connect the EPC4 connectors at the other end of
the BBU power cables to the "LOAD3" and "LOAD4" ports on the DCDU16D.
Figure 1-174 Installing BBU5900 power cables (when the DCDU-12B supplies
power)
Step 6 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 7 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Context
RRU power cables feed DC power into RRUs.
NOTE
● In most regions except UK and China, the RTN(+) and NEG(-) wires are black and blue,
respectively.
● In UK, the RTN(+) and NEG(-) wires are blue and gray, respectively.
● In China, the RTN(+) and NEG(-) wires are red and blue, respectively.
Procedure
Step 1 Optional: When the APM30H is stacked on an IBBS200D/IBBS200T/BBC5200T-L,
relocate the ground clips in the APM30H to the IBBS200D/IBBS200T/BBC5200T-L,
as shown in the following figure.
1. Remove the three nuts that are used to secure the three ground clips onto the
three PGND cables from the inner right wall of the APM30H. Then remove
the three ground clips.
2. Secure the PGND cables with the ground clips to the two pivot screws on the
inner right wall of the IBBS200D/IBBS200T/BBC5200T-L. Then tighten the
screws on the ground clips to 1.2 N·m (10.62 lbf·in.).
NOTICE
5. Route the RRU power cables through the ground clip and ensure that the
shield layers securely contact the ground clip. Then tighten the M4 screw on
the ground clip to 1.2 N·m (10.62 lbf·in.).
NOTE
A ground clip can be used to secure a maximum of six RRU power cables.
NOTE
When installing a ground clip for the RRU power cables, comply with the following rules:
● When installing one to three RRU power cables, place all the power cables at one side of
the ground screw, as shown by illustration 1 in the following figure.
● When installing four or six RRU power cables, place the power cables evenly on two sides
of the ground screw, as shown by illustration 2 in the following figure.
● When installing five RRU power cables, use two ground clips, with three or four power
cables in one ground clip and the remaining power cables in the other ground clip, as
shown by illustration 3 in the following figure.
● When installing seven/eight/nine/ten/twelve RRU power cables, use two ground clips and
distribute the power cables by complying with the preceding rules.
● When installing eleven RRU power cables, use two ground clips, with five power cables in
one ground clip and six power cables in the other ground clip, as shown by illustration 4 in
the following figure.
● When installing thirteen or more RRU power cables, use three ground clips and distribute
the power cables by complying with the preceding rules.
Step 3 Connect one end of the RRU power cables to the RRUs. For the method of adding
connectors to the power cables on the RRU side, see the corresponding RRU
installation guide.
CAUTION
When installing an RRU power cable for a running base station, connect the cable
to the RRU before connecting it to the power system. An incorrect sequence or
reverse connection of the power cable will cause damage to the RRU or injuries to
the human body.
Step 4 Add EPC5 connectors or EPC11 connectors to the RRU power cables on the cabinet
side according to the instructions in Assembling an EPC5 Connector and the Power
Cable and Assembling an EPC11 Connector and the Power Cable.
Step 5 Install RRU power cables in the cabinet, as shown in the following figures.
Figure 1-182 Installing RRU power cables in an APM30H (Ver.D) (EPC5 connectors
used on the cabinet side)
NOTE
The RRU obtains power from the DCDU16D in the same way as obtaining power from the
DCDU-12B. The following figure uses the DCDU-12B as an example.
Figure 1-184 Installing RRU power cables in a TMC11H (Ver.E) (EPC5 connectors
used on the cabinet side)
Figure 1-185 Installing RRU power cables in a TMC11H (Ver.E) (EPC11 connectors
used on the cabinet side)
Figure 1-186 Installing RRU power cables in a TMC11H (Ver.D) (EPC5 connectors
used on the cabinet side)
Figure 1-187 Installing RRU power cables in a TMC11H (Ver.D) (EPC11 connectors
used on the cabinet side)
2. Strip the sheaths off cables based on the cable stripping ruler for the circuit
breaker. Figure 1-189 shows the inapplicable cable specifications. Figure
1-190 shows the cable stripping ruler.
3. Connect the connectors on the RRU power cables on the RRU side to the
power ports on the RRUs.
CAUTION
– Only 6 mm2 to 16 mm2 (0.009 in.2 to 0.025 in.2) power cables can be
connected to the LOAD0 to LOAD2 circuit breakers. 12 AWG (3.3 mm2 or
0.005 in.2), 10 AWG (5.3 mm2 or 0.008 in.2), 4 mm2 (0.006 in.2), or 2.5
mm2 (0.0039 in.2) power cables cannot be connected to the LOAD0 to
LOAD2 circuit breakers. The length of the stripped sheath must be between
17 mm (0.67 in.) and 19 mm (0.75 in.).
– When installing an RRU power cable in a base station that has been
deployed, first connect the connector on the RRU side, and then connect
the connector on the power equipment side. An incorrect sequence or
reverse connection of the power cable will cause damage to the RRU or
injuries to the human body.
4. Connect the RTN and NEG power cables to the LOAD0 to LOAD2 ports on the
DCDU16D.
a. Insert the Φ3 flat-head screwdriver into the "+" and "-" tool holes of the
circuit breaker obliquely in sequence, and insert the prepared power
cables into the "+" and "-" connection holes. Ensure that the core wires
contact the bottom of the connection hole and do not split. The following
figure shows the positions of the "+" and "-" tool holes and connection
holes.
b. Remove the flat-head screwdriver from the tool hole of the circuit
breaker.
c. Pull each power cable slightly to check whether it is securely connected. If
the power cable is pulled out a bit or the wires are exposed outside the
hole, remove the power cable, cut the split wires, and then strip the
sheath and install the power cable again.
5. After the cable connection, route the power cables through the cable claw
and secure the cables, as shown in the following figure.
6. Press the handle of the circuit breaker and turn on the circuit breaker to
supply power to loads. When the circuit breaker is turned on, the handle is
pressed and the indicator is red, as shown in the following figure.
Step 7 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 8 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the
pipe to the cable outlet on the cabinet.
Step 9 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
● Each ODM06D supplies power for six RRUs.
● For the ODM06D configuration principles, see Table 1-43.
● An ODM06D transfers power from the power equipment to RRUs.
Procedure
Step 1 Route the ODM06D power cables out of the cabinet from top down through the
cable bag on the inner right side of the cabinet.
NOTICE
● When the cable bag is already full of cables, do not route cables through the
cable bag from bottom up. Otherwise, the bottom of the cable bag may be
dragged and broken.
● Before routing the ODM06D power cables from top down, bind all other cables
so that they are not affected by the ODM06D power cables.
Step 2 Install the ground clip for the ODM06D power cable.
1. Strip a length of jacket off the ODM06D power cables at the position 300 mm
(11.81 in.) away from the cable bag to expose the shield layer.
2. Strip the shield layer while reserving a 70 mm (2.76 in.) length of it and
expose two core wires.
3. Reserve the shield layer of 50 mm (1.97 in.) and wrap two layers of insulation
tape around the upper part of the shield layer to ensure secure attachment of
the shield layer.
NOTICE
4. Open the ground clip that secures three RRU power cables on the right side of
the cabinet.
NOTE
Step 3 Add the cord end terminal to the ODM06D power cable on the ODM side
according to the instructions in Assembling the Cord End Terminal and the Power
Cable.
Step 4 Open the cover for the ODM06D, as shown in the following figure.
1. Use a T20 Torx screwdriver to loosen the six screws on the cover for the
ODM06D, and then open the cover.
Step 5 Prepare the cable according to the cabling label on the protective cover.
Step 6 Install the RRU power cables and ODM06D power cable, as shown in the
following figure.
1. Use a Phillips screwdriver to loosen the screw on the cable clip.
NOTE
The screw on the cable clip can be adjusted to adapt to cables with different cross-
sectional areas.
2. Partially loosen the PG connector to route the cable through the PG
connector.
3. Route the RRU power cables and ODM06D power cable through the PG
connector.
4. Use an M4 Phillips screwdriver to secure the cord end terminal onto the
terminal block to 1.4 N·m (12.39 lbf·in.), which is a recommended torque.
5. Use the cable clip to secure the cable and tighten the M4 screw on the cable
clip to 1.4 N·m (12.39 lbf·in.) to ensure that the cable clip closely contacts
with the shield layer of the cable. The 1.4 N·m (12.39 lbf·in.) value is a
recommended torque.
6. Secure the PG connector of the cable.
NOTICE
Figure 1-196 Installing the RRU power cables and ODM06D power cable
Step 7 Close the cover for the ODM06D, as shown in the following figure.
1. Close the protective cover and use an M4 flat-head screwdriver to secure the
screw on the protective cover.
2. Close the cover and use a T20 Torx screwdriver to secure the six screws on the
cover.
Step 8 Install RRU power cables according to instructions in the corresponding RRU
installation guide.
Step 9 Install the ODM06D power cable.
● Optional: When the ODM06D is installed in an APM30H (Ver.E), connect the
ODM06D power cable to the PDU01D-01.
– Add the OT terminal to the ODM06D power cable on the cabinet side by
following the instructions in Assembling the OT Terminal and the Power
Cable.
– Ensure that the circuit breakers on the RRUs connecting to the ODM06D
are turned off.
– Connect the OT terminals at the other end of the power cables to the
"RTN(+)" and "NEG(-)" terminals on the PDU01D-01 in the APM30H.
Then tighten the screws on the OT terminals to 4.8 N·m (42.48 lbf·in.).
Step 10 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 11 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the
pipe to the cable outlet on the cabinet.
Step 12 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
When an RRU requires voltage boosting power distribution in a -57 V scenario, an
EPU02D/EPU02D-02/EPU02B/EPU02S/BDU70-03/SDU60-02/EPU02S-02 needs to
be configured. The following figures show installation positions.
NOTE
NOTE
● In most regions except UK and China, the RTN(+) and NEG(-) wires are black and blue,
respectively.
● In UK, the RTN(+) and NEG(-) wires are blue and gray, respectively.
● In China, the RTN(+) and NEG(-) wires are red and blue, respectively.
Procedure
Step 1 Optional: When the APM30H is stacked on an IBBS200D/IBBS200T/BBC5200T-L,
relocate the ground clips in the APM30H to the IBBS200D/IBBS200T/BBC5200T-L,
as shown in the following figure.
1. Remove the three nuts that are used to secure the three ground clips onto the
three PGND cables from the inner right wall of the APM30H. Then remove
the three ground clips.
2. Secure the PGND cables with the ground clips to the two pivot screws on the
inner right wall of the IBBS200D/IBBS200T/BBC5200T-L. Then tighten the
screws on the ground clips to 1.2 N·m (10.62 lbf·in.).
NOTICE
5. Route the RRU power cables through the ground clip and ensure that the
shield layers securely contact the ground clip. Then tighten the M4 screw on
the ground clip to 1.2 N·m (10.62 lbf·in.).
NOTE
A ground clip can be used to secure a maximum of six RRU power cables.
NOTE
When installing a ground clip for the RRU power cables, comply with the following rules:
● When installing one to three RRU power cables, place all the power cables at one side of
the ground screw, as shown by illustration 1 in the following figure.
● When installing four or six RRU power cables, place the power cables evenly on two sides
of the ground screw, as shown by illustration 2 in the following figure.
● When installing five RRU power cables, use two ground clips, with three or four power
cables in one ground clip and the remaining power cables in the other ground clip, as
shown by illustration 3 in the following figure.
● When installing seven/eight/nine/ten/twelve RRU power cables, use two ground clips and
distribute the power cables by complying with the preceding rules.
● When installing eleven RRU power cables, use two ground clips, with five power cables in
one ground clip and six power cables in the other ground clip, as shown by illustration 4 in
the following figure.
● When installing thirteen or more RRU power cables, use three ground clips and distribute
the power cables by complying with the preceding rules.
Step 3 Connect one end of the RRU power cables to the RRUs. For the method of adding
connectors to the power cables on the RRU side, see the corresponding RRU
installation guide.
CAUTION
When installing an RRU power cable for a running base station, connect the cable
to the RRU before connecting it to the power system. An incorrect sequence or
reverse connection of the power cable will cause damage to the RRU or injuries to
the human body.
Figure 1-205 Installing RRU power cables (EPU02D for power supply and EPC5
connectors used on the cabinet side)
Figure 1-206 Installing RRU power cables (EPU02D for power supply and EPC11
connectors used on the cabinet side)
Figure 1-207 Installing RRU power cables (EPU02D-02 for power supply and EPC5
connectors used on the cabinet side)
Figure 1-208 Installing RRU power cables (EPU02D-02 for power supply and
EPC11 connectors used on the cabinet side)
Figure 1-209 Installing RRU power cables (EPU02B for power supply and EPC5
connectors used on the cabinet side)
Figure 1-210 Installing RRU power cables (EPU02B for power supply and EPC11
connectors used on the cabinet side)
Figure 1-211 Installing RRU power cables (EPU02S for power supply and SPC1
connectors used on the cabinet side)
Figure 1-212 Installing RRU power cables (EPU02S-02 for power supply and SPC1
connectors used on the cabinet side)
Figure 1-213 Installing RRU power cables (BDU70-03 for power supply and
EPC5 connectors used on the cabinet side)
Figure 1-214 Installing RRU power cables (BDU70-03 for power supply and
EPC11 connectors used on the cabinet side)
Figure 1-215 Installing RRU power cables (SDU60-02 for power supply and
SPC1 connectors used on the cabinet side)
Step 7 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 8 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the
pipe to the cable outlet on the cabinet.
Step 9 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
1.14.3.3.4 Installing RRU Power Cables (RRU Power Consumption > 800 W, with an
ODM03D)
When the power consumption per RRU is greater than 800 W, an ODM03D needs
to be configured.
Context
To supply power for high-power RRUs (power consumption per RRU > 800 W), an
ODM03D needs to be configured.
NOTE
● In most regions except UK and China, the RTN(+) and NEG(-) wires are black and blue,
respectively.
● In UK, the RTN(+) and NEG(-) wires are blue and gray, respectively.
● In China, the RTN(+) and NEG(-) wires are red and blue, respectively.
Procedure
Step 1 Install ODM03D-RRU power cables according to the instructions in ODM03D User
Guide.
Step 2 Route the ODM03D input power cables through a cable bag into the cabinet.
Step 3 Install the ground clip according to the sections "Installing RRU Power Cables."
NOTE
Two adjacent power output ports on the power equipment are used to supply power for an
ODM03D.
Step 7 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 8 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the
pipe to the cable outlet on the cabinet.
Step 9 Attach labels to the cables by following the instructions in Attaching a Cable-Tying
Label.
----End
Context
● The following shows how to install E1/T1 surge protection transfer cables in a
GU base station using the independent transmission mode. For the E1/T1
surge protection transfer cable connections in other configuration scenarios,
see Transmission Cable Connections in 3900 & 5900 Series Base Station
Cables.
● The connection positions and routing of the E1/T1 surge protection transfer
cables are the same in the TMC11H (Ver.C), TMC11H (Ver.B), and TMC11H
(Ver.D). This section uses the TMC11H (Ver.D) as an example.
Procedure
Step 1 Connect the DB26 connectors at one end of the E1/T1 surge protection transfer
cables to the "E1/T1" ports on the main control processing boards (such as GTMU)
in the BBU, and then tighten the plastic screws on the connectors to 0.25 N·m
(2.21 lbf·in.), as shown in the following figure.
Step 2 Connect the DB25 connectors at the other end of the E1/T1 surge protection
transfer cables to the "INSIDE" ports on the UELP in the SLPU, and then tighten
the plastic screws on the connectors to 0.25 N·m (2.21 lbf·in.), as shown in the
preceding figure.
Step 3 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 4 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Prerequisites
NOTICE
Ensure that connectors are added to both ends of an E1/T1 cable before cable
connections. Ensure that both ends of the E1/T1 cable are disconnected from any
equipment when the connectors are added.
Context
● The following shows how to install E1/T1 cables in a GU base station using
the independent transmission mode. For the E1/T1 cable connections in other
configuration scenarios, see Transmission Cable Connections in 3900 & 5900
Series Base Station Cables.
● The connection positions and routing of the E1/T1 cables are the same in the
TMC11H (Ver.C), TMC11H (Ver.B), and TMC11H (Ver.D). This section uses the
TMC11H (Ver.D) as an example.
● The E1/T1 cables on the SLPU side are routed along the left side of the
cabinet interior.
Procedure
Step 1 Connect the DB26 male connector on each E1/T1 cable to the "OUTSIDE" port on
the UELP, and tighten the plastic screws on the connector to 0.25 N·m (2.21
lbf·in.), as shown in the following figure.
Step 2 Route the other end of the E1/T1 cable out of the cabinet through the cable bag
on the bottom left of the cabinet, and then connect the cable to the external
transmission equipment.
Step 3 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 4 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Context
● The following shows how to install FE/GE surge protection transfer cables in a
GL base station using the independent transmission mode. For the FE/GE
Procedure
Step 1 Connect the RJ45 connector at one end of each FE/GE surge protection transfer
cable to an FE electrical port on the main control board (such as GTMU), as
shown in the following figure.
Step 2 Connect the other end of the FE/GE surge protection transfer cable to the "FE0" or
"FE1" port near the "INSIDE" silkscreen on the UFLP, as shown in the preceding
figure.
Step 3 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 4 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Context
● An FE/GE Ethernet cable is a shielded straight-through cable.
● When the TMC11H is stacked on an IBBS200D/IBBS200T, ensure that the
ground clip has been moved from the TMC11H to the IBBS200D/IBBS200T
before installing the FE/GE Ethernet cable.
● The following shows how to install FE/GE Ethernet cables in a GL base station
using the independent transmission mode. For the FE/GE Ethernet cable
connections in other configuration scenarios, see Transmission Cable
Connections in 3900 & 5900 Series Base Station Cables.
● The connection positions and routing of the FE/GE Ethernet cables are the
same in the TMC11H (Ver.C), TMC11H (Ver.B), and TMC11H (Ver.D). This
section uses the TMC11H (Ver.D) as an example.
Procedure
Step 1 Route the FE/GE Ethernet cables through a cable bag or a cable outlet module
into the cabinet.
Step 2 Install the ground clip, as shown in the following figure.
1. At a position 300 mm (11.81 in.) away from the cable bag (TMC11H (Ver.D))
or within 1 m (3.28 ft.) away from the cable hole on the cabinet (TMC11H
(Ver.C) or TMC11H (Ver.B)), strip a length of 50 mm (1.97 in.) jacket off an
FE/GE Ethernet cable to expose the shield layer.
2. Route the FE/GE Ethernet cable through the ground clip and ensure that the
shield layer securely contacts the ground clip. Then tighten the M4 screw to
1.2 N·m (10.62 lbf·in.).
For details about FE/GE Ethernet cable connections in different base stations, see Transmission
Cable Connections in 3900 & 5900 Series Base Station Cables.
● If a UMPTe/GTMUc is installed, connect one end of the FE/GE Ethernet cables
to the "FE/GE0" or "FE/GE2" ports on the UMPTe/GTMUc, as shown in the
following figure.
Step 4 Connect the other end of the FE/GE Ethernet cables to the external transmission
equipment.
Step 5 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 6 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Context
● Single-mode optical modules are labeled SM and multimode optical modules
are labeled MM.
● The puller of a single-mode optical module is blue. The puller of a multimode
optical module is black or gray.
● An FE/GE optical fiber has an LC connector at one end and an FC, SC, or LC
connector at the other end.
● The SFP0 and FE/GE0 ports on an LMPT are used for one GE input. Therefore,
the two ports cannot be used simultaneously.
● The SFP1 and FE/GE1 ports on the LMPT are used for another GE input.
Therefore, the two ports cannot be used simultaneously.
● The connections and routing of FE/GE optical fibers in the TMC11H (Ver.B),
TMC11H (Ver.C), TMC11H (Ver.D), and TMC11H (Ver.E) are the same. This
section uses the TMC11H (Ver.D) as an example.
NOTICE
NOTICE
Optical modules to be installed must match the rates of their corresponding ports.
For example, the FE1 port (optical transmission port) on a GTMU/GTMUb/GTMUc
supports only the 100 Mbit/s transmission rate and therefore can only use an
optical module that supports hundreds of megabits per second. In this scenario, an
optical module that supports thousands of megabits per second may cause the
transmission link to be disconnected.
Procedure
Step 1 Install an optical module into the FE/GE, FE, SFP, or XGE port on the main control
board or transmission board, as shown in Figure 1-223 and Figure 1-224.
1. Remove the dustproof cap from the corresponding optical port on the
corresponding board in the BBU.
NOTICE
After removing dustproof caps from the optical module and optical fiber
connector, insert the optical fiber into the optical module immediately (within
one minute) to avoid pollution of the optical module or optical fiber
connector, which may cause an optical module alarm.
Step 2 Install optical fibers, as shown in Figure 1-225 and Figure 1-226.
1. Remove the dustproof caps from the connectors at the end labeled "2A" and
"2B" of the optical fibers, and insert the connectors into the optical module
on the BBU side.
2. Route the optical fibers out of the cable bag on the bottom right side of the
cabinet.
3. Connect the other end of the optical fibers to the external transmission
equipment.
NOTICE
The "TX" and "RX" ports (FE/GE optical ports) on the BBU must be connected
to the "RX" and "TX" ports on the transmission equipment, respectively.
Step 3 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 4 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Prerequisites
● A BBU (which is optional) has been installed.
● Optical modules, optical fibers, and electrical cables meeting the following
requirements are available:
– The optical modules and optical fibers must be of the multimode type.
– Multimode optical modules on a UMPT or UCIU must meet the following
requirements:
● Single-mode optical modules are labeled "SM" and multimode optical modules are
labeled "MM".
● The puller of a single-mode optical module is blue and the puller of a multimode
optical module is black or gray.
● The following figure shows the label on an optical module.
Context
The following table lists scenarios supporting the BBU interconnection and the
positions to which BBU interconnection signal cables are connected. For details
about scenarios supporting the BBU interconnection, see BBU Interconnection
Signal Cable Connections.
Table 1-49 Positions to which BBU interconnection signal cables are connected
NOTICE
NOTE
Procedure
● Install one or two BBU interconnection signal cables connecting the UCIU and
the UMPT.
a. Remove the dustproof caps from the corresponding ports on the BBUs
and install the optical modules in BBU 0 and BBU 1, as shown in the
following figure.
i. Lower the puller of the optical module.
ii. Insert the optical module into the port.
iii. Raise the puller of the optical module.
Figure 1-229 Removing the dustproof caps from the optical fiber
c. Install one or two BBU interconnection signal cables connecting the UCIU
and the UMPT. The following figure shows the installation of two BBU
interconnection signal cables.
NOTE
● You need to install two BBU interconnection signal cables connecting the UCIU
and the UMPT in GU+UL mode.
● You need to install only one BBU interconnection signal cable connecting the UCIU
and the UMPT in GU+L or GL+U mode.
i. Connect one end of the cables to the "M0" and "M1" ports on the
UCIU in BBU 0.
ii. Connect the other end of the cables to the "CI" ports on the UMPT_U
and UMPT_L in BBU 1.
● Install the interconnection signal cables between the UMPTs in BBU 0 and the
UMPTs in BBU 1.
– (Optional) Install SFP+ cables.
i. Connect the end with the "Master" color-coding label of each cable
to the "CI" port on BBU 0 and connect the other end of each cable to
the "CI" port on BBU 1.
– (Optional) Install CPRI single-fiber bidirectional optical fibers.
i. Install optical modules, as shown in Figure 1-230 and Figure 1-231.
○ Remove the dustproof caps from the "CI" ports on the main
control boards in BBU 0. Lower the pullers of the optical
modules with the blue puller. Insert the optical modules into the
"CI" ports on the main control boards in BBU 0, and raise the
pullers of the optical modules.
○ Remove the dustproof caps from the "CI" ports on the main
control boards in BBU 1. Lower the pullers of the optical
modules with the purple puller. Insert the optical modules into
the ports on the main control boards in BBU 1, and raise the
pullers of the optical modules.
ii. Remove the dustproof cap from the LC connector labeled 2A.
iii. Separate the DLC connector into two LC connectors. Insert the LC
connector labeled 2A into the optical module on the UMPT board in
one BBU, as shown in the following figure. Insert the LC connector
labeled 1A into the optical module on the UMPT board in the other
BBU.
----End
Context
NOTE
● When a base station is configured with one TMC11H, one monitoring signal cable must
be installed onsite.
● If this base station is expanded to two TMC11Hs, as shown in Figure 1-238, another
monitoring signal cable must be installed onsite.
● A triple- or quadruple-mode base station is configured with two BBUs, and the second
BBU is installed in the TMC11H. This BBU does not perform the monitoring function.
Procedure
Step 1 Install a CMUEA-BBU monitoring signal cable, as shown in the following figure.
1. Connect one end of the CMUEA-BBU monitoring signal cable to the
"COM_IN" port on the CMUEA in the fan assembly.
2. Connect the other end of the CMUEA-BBU monitoring signal cable to the
"MON1" port on the UPEU in the BBU.
Step 2 If this base station is expanded to two TMC11Hs, another CMUEA-BBU monitoring
signal cable must be installed, as shown in the following figure.
1. Connect one end of the CMUEA-BBU monitoring signal cable to the
"COM_IN" port on the CMUEA in the added TMC11H.
2. Connect the other end of the CMUEA-BBU monitoring signal cable to the
"MON0" port on the UPEU in the BBU of the original TMC11H.
Step 3 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 4 Use a PVC corrugated pipe to protect the cables outside the cabinet, and tie the
pipe to the cable outlet on the cabinet.
Step 5 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Procedure
Step 1 Install the BBU alarm cable, as shown in the following figure.
1. Connect the RJ45 connector at one end of the BBU alarm cable to the "EXT-
ALM0" or "EXT-ALM1" port on the UPEU in the BBU.
2. Connect the RJ45 connector at the other end of the BBU alarm cable to the
external alarm equipment.
Step 2 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 3 Attach labels to the cables by following the instructions in Attaching an L-Shaped
Label.
----End
Context
NOTE
● Single-mode optical modules are labeled "SM" and multimode optical modules are
labeled "MM".
● The puller of a single-mode optical module is blue and the puller of a multimode
optical module is black or gray.
● Optical modules to be installed must match the rates of their corresponding ports.
● For details about the CPRI optical fiber connections, see section "CPRI Cable
Connections" in 3900 Series Base Station Cables.
● A large quantity of optical fibers are required in certain scenarios, so you are advised to
adopt the solution for routing 1-to-12 fiber optic bundles using LC connectors when an
ODF is used. Figure 1-242 shows the detailed routes.
a. Traditional solution for routing optical fibers b. Solution for routing 1-to-12 fiber optic
bundles using LC connectors
NOTICE
NOTICE
Procedure
Step 1 Install an optical module on the BBU side, as shown in Figure 1-243 and Figure
1-244.
1. Remove the dustproof cap from the "CPRI" port on the main control board
(for example, GTMU) or baseband processing unit (for example, WBBP) in the
BBU.
2. Remove the dustproof cap from the optical module.
3. (Optional) For the optical module with a puller, lower the puller. For the
optical module with a handle, skip this step.
4. Insert the optical module into the "CPRI" port on the main control board (for
example, GTMU) or baseband processing unit (for example, WBBP).
5. (Optional) For the optical module with a puller, raise the puller. For the
optical module with a handle, skip this step.
Step 2 Optional: Install a CPRI optical fiber for a two-fiber bidirectional optical module.
NOTICE
● When a CPRI optical fiber connects a BBU and an RRU, the breakout cables on
the BBU side are 0.34 m (1.12 ft) long and the breakout cables on the RRU side
are 0.03 m (0.098 ft) long, respectively.
● If an LC-LC optical fiber is used, the "TX" port on the BBU must be connected to
the "RX" port on the RRU and the "RX" port on the BBU must be connected to
the "TX" port on the RRU.
Step 3 Optional: Install a CPRI optical fiber for a single-fiber bidirectional optical module.
1. Remove the dustproof cap from the LC connector labeled 2A.
2. Split the DLC connector into two LC connectors, as shown in the following
figure.
Step 4 Route the CPRI optical fibers along the left side of the cabinet through the cable
bag on the bottom left side of the cabinet, and connect the cables to the
corresponding RRUs.
Step 5 Route the cables by following the instructions in 1.14.1 Cabling Requirements.
Step 6 Attach labels to the cables by following the instructions in Attaching a Sign Plate
Label.
----End
No. Item
3 All the bolts, especially those for electrical connections, are tightened.
No flat washer or spring washer is missing, and flat washers and
spring washers are installed in the correct sequence.
4 The cabinet is clean, and dust and dirt are cleaned in a timely
manner.
NOTICE
Filler panels must be correctly installed in vacant BBU slots to ensure proper heat
dissipation. Otherwise, normal operation and service life of boards will be affected.
No. Item
2 No tapes, tails of cable ties, paper, or packing bags are left around
the cabinet.
No. Item
No. Item
2 The ground cable is securely connected and the AC lead-in cable and
cables in the cabinet are correctly connected according to the
electrical design of the power system. The screws are tightened. The
input and output cables are not short-circuited.
3 The redundant part of the power cable or PGND cable is cut off
instead of coiled up.
4 The terminals at both ends of the power cable or PGND cable are
securely soldered or crimped.
5 The bare wires and the terminal handles of the wiring terminals are
coated with heat shrink tubings.
6 The flat washers and spring washers are well mounted on all OT
terminals. The contact surfaces on the OT terminals are not
deformed. The OT terminals are securely and properly connected.
No. Item
14 Before powering on the DCDU, ensure that the two sides of the
power cable for a load such as an RRU or a BBU are correctly
connected to the positive and negative terminals on the modules.
Reverse connections or short circuits may trigger the upper-level
protector for the DCDU after the DCDU is powered on.
2 All cables are neatly and tightly bound. The cable ties are evenly
spaced and face the same direction.
4 The layout of all cables must facilitate the maintenance and capacity
expansion. For example, the local maintenance adapter must be
bound to a BBU cable claw and oriented outwards, as shown in the
following figure.
5 The labels at both ends of a cable are legible (labels are attached).
6 The extra length of the indoor cable ties is cut off, and the cut
surfaces are smooth without sharp edges. The extra length of 3 mm
to 5 mm (0.11 in. to 0.19 in.) of the outdoor cable ties is reserved
when the cable ties are cut.
7 All vacant ports are properly protected. For example, unused CPRI
ports on BBU boards are protected using dust-proof caps.
NOTICE
Prerequisites
● Input power cables for the DBS3900 are correctly connected.
● The power supply to the DBS3900 meets the requirements of the power
system.
● External power supply to the DBS3900 has been shut off.
● All circuit breakers (if any) on the DCDU in the TMC11H are turned off.
● The power circuit breaker on the BBU is turned off.
● Boards, modules, and cables have been installed in the cabinet.
Context
NOTICE
Process
The following figure shows the power-on check process.
Procedure
Step 1 Use a multimeter to measure the resistance between the input/output terminal
and the ground, and ensure that there is no short circuit.
Step 2 Turn on the external power circuit breaker to power on the TMC11H.
Step 3 Optional: Turn on all circuit breakers with loads on each DCDU in the TMC11H.
Skip this step if there is no circuit breaker on the DCDU, such as the DCDU-12B/
12C.
Step 4 Turn on the power circuit breaker on the UPEU in the BBU.
Step 5 Check the power supply to each component according to the following figure.
DANGER
● Before the power-on operation, check that all power cables are correctly
connected. Any reverse power cable connection or short circuit of the positive
and negative poles may cause damage to equipment or unexpected injuries of
human body.
● Exercise caution when performing a power-on check, which involves high
voltage operations. Direct contact with the input voltage or indirect contact
with the input voltage using a damp object may be fatal.
TMC11H Fan ● The RUN indicator is blinking (on for 0.125s and
assembly off for 0.125s or on for 1s and off for 1s).
● The ALM indicator is steady off.
Step 6 Optional: If the power supply to a component fails after the cabinet is powered
on, handle the fault according to the instructions in the following table.
Failure in the power Check whether the power cables are connected correctly:
supply to all ● If the cables are incorrectly connected, turn off all
components in the circuit breakers, and then reconnect the power cables.
cabinet
● If the cables are connected correctly, replace the
power device.
----End
Procedure
● Sealing cable outlets of a cabinet
a. Route cables through the cable bags and pull the drawstrings to fasten
the bags around the cables, as shown in the following figure.
NOTE
● All cables must be bound to the cable bridges on one side of the cabinet.
● You can put your hands in the cable bag to route cables through the bag.
● The following figure describes the method of fastening cable bags in an
APM30H. The same method is used for fastening the cable bags in other
types of cabinets.
a. Use a baffle plate to block the redundant space in the cable outlet and
tighten the two screws and two butterfly nuts on each baffle plate to 1.2
N·m (10.62 lbf·in.), as shown in the following figure.
(1) Baffle plate on the left (2) Baffle plate on the right (3) Baffle plate at the rear
b. Use fireproof mud to seal the cable outlets on the base, as shown in the
following figure.
NOTE
If the ambient temperature is low, use a heat gun to heat the fireproof mud for
convenient sealing.
Figure 1-253 Using fireproof mud to seal the cable outlets on the base
c. Tighten the three screws on the front cover plate of the base to 1.2 N·m
(10.62 lbf·in.) and close the front cover plate.
● Sealing cable outlets on a base for an IBBS300D/IBBS300T
a. Use a baffle plate to block the redundant space in the cable outlet and
tighten the two screws and two butterfly nuts on each baffle plate to 4.8
N·m (42.48 lbf·in.), as shown in the following figure.
(1) Baffle plate on the right (2) Baffle plate at the rear (3) Baffle plate on the left
b. Use fireproof mud to seal the cable outlets on the base, as shown in the
following figure.
NOTE
If the ambient temperature is low, use a heat gun to heat the fireproof mud for
convenient sealing.
Figure 1-255 Using fireproof mud to seal the cable outlets on the base
c. Tighten the three screws on the front cover plate of the base to 4.8 N·m
(42.48 lbf·in.) and close the front cover plate.
● Sealing cable outlets on a base for an IBBS700D/IBBS700T
a. Use baffle plates to block the redundant space in the cable outlets, as
shown in the following figure.
b. Install the front cover plate for the base. Tighten the three M6
countersunk screws on the front cover plate to 3 N·m (26.55 lbf·in.).
Figure 1-256 Sealing the cable outlets on the base for an IBBS700D/
IBBS700T
(1) PVC corrugated pipe (2) Baffle plate (3) Front cover plate
----End
1.17.2 Repainting
The paint on the surface of the cabinet should be kept intact. Any damaged paint
must be repaired to prevent corrosion.
Prerequisites
Before repainting the cabinet, select the paint of the same color according to the
following table.
Procedure
Step 1 If the area where the paint is damaged is dirty or the material is rusted, slightly
rub the area with sandpaper to remove the dirt or rust, as shown in the following
figure.
Step 2 Use anhydrous alcohol to dampen a cloth and use the wet cloth to remove dirt or
dust from the rubbed area or the area to be repaired. Then dry the area with
another clean cloth, as shown in the following figure.
Step 3 Paint the surface of the cabinet with paint of the same color.
Step 4 Shake the bottle of the paint, open the bottle, and saturate the brush with the
paint. Then apply the paint evenly to the damaged area until no scar can be
observed, as shown in the following figure.
NOTICE
Ensure that the paint coating is thin and even and paint drops are prohibited on
the coating to keep the surface smooth.
Step 5 Perform the subsequent operations after the repaired paint coating has been
exposed in the air for about 30 minutes.
NOTE
The color of the repaired paint coating area should be consistent with that of the
surrounding areas, without obvious edges and bulges, and the original damage should no
longer be distinguishable. In addition, there should be no paint peeled off.
----End