Earthwork Data
Earthwork Data
(BLKD-CSTN-2-2)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output : 240.00 cum
a) Labour
Mazdoor ( Unskilled) 8.32 Nos. 575.00 1 No. 4784.00
Add for MA @ 20% 0.20 4784.00 956.80
b) Machinery
Shovel 0.85 cum 110hp (Part I (I&CAD
Works)) 6.00 hours 3204.10 1 Hour 19224.60
Crew charges (Part I (I&CAD Works)) 6.00 hours 353.60 1 Hour 2121.60
Add MA on crew charges 0.20 2121.60 424.32
Conveyance for 3 Kms 240 cum 163.00 1 cum 39120.00
(Unloading at open area 3 Kms &
unloading at Site 3 Kms)
66631.32
Overheads & Contractors Profit @
13.615% 0.13615 66631.32 9071.85
Cost for 240 cum ( a+b+c+d) 75703.17
Rate per 1 cum (a+b+c+d) / 240 Total Rs. 315.43
Or Say 315.00