PIERRE MOSTERT
PIERRE MOSTERT
Ref: CSOS5016/WC/23
and
ADJUDICATION ORDER
EXECUTIVE SUMMARY
Section 39(2) In respect of behavioural issues- (a) “an order that particular behaviour or
default constitutes a nuisance and requiring the relevant person to act, or refrain from acting,
in a specified way.”
Section 39(6) In respect of works pertaining to private areas and common areas-
Page 1 of 7
CSOS5016/WC/23
(b) “an order requiring the relevant person- (i) to carry out specified repairs, or have specified
repairs made.
• Order:
(a) The relief sought by the Applicant in terms of section 39(2)(a) and 39(6) (b) of the
CSOS Act, is dismissed in terms of Section 53(1) (b) of the CSOS Act.
(b) No order is made as to costs.
INTRODUCTION
1. The Applicant is PIERRE MOSTERT, the registered owner of unit 35 Olive Grove, Klip
Road, Grassy Park, Cape Town, Western Cape Province.
2. The Respondent is JAYSON EATON, the registered owner of unit 60 Olive Grove,
Klip Road, Grassy Park, Cape Town, Western Cape Province.
4. The application seeking relief in terms of section 39(2) of the CSOS Act, is in respect
of behavioural issues and section 39(6) of the CSOS Act in respect of works
pertaining to private areas and common areas.
5. A letter requesting final submissions was sent to the parties confirming that due to the
current situation regarding the Covid-19 pandemic, the CSOS is taking the appropriate
precautions against the further spread of COVID-19 (Coronavirus) and is
Page 2 of 7
CSOS5016/WC/23
adjudicating disputes on documents submitted, without the need to meet parties face
to face.
6. This matter is adjudicated in terms of the CSOS Act and Practice Directive on Dispute
Resolution, 2019 as amended and more specifically the amended Practice Directive
dated 23 June 2020 which provides under paragraph 8.2:- “Adjudications will be
conducted on the papers filed by the parties and any further written submissions, documents
and information as requested by the appointed Adjudicator”. Parties were requested to
make written submissions. The adjudication was conducted on the 29th of September
2023 and an order is now determined.
PRELIMINARY ISSUES
15. Accordingly, a direct referral was done in terms of Section 48(1) of the CSOS Act. The
Ombud referred the application together with any submissions and responses thereto
to an adjudicator on the 22nd of September 2023.
Page 4 of 7
CSOS5016/WC/23
Applicant’s Submissions
16. The Applicant avers that the Respondent is engaging in disruptive conduct at night by
knocking and drilling till the early hours of the morning.
17. The Applicant further submitted that there is water ingress in his unit which emanates
from the Respondent’s unit, and that as a result both his kitchen and bathroom are
affected by the water leakage, which the Respondent refuses to fix.
18. According to the Applicant, the Respondent has ignored his attempt to engage him for
the purposes of resolving the matter, as he did not respond to his emails.
Respondent’s Submissions
20. The Respondent failed to file written submissions despite the request for the same
issue by CSOS Compliance officer on the 13th of September 2023.
22. In evaluating the evidence and information submitted, the probabilities of the case
together with the reliability and credibility of the witnesses must be considered.
23. The general rule is that only evidence, which is relevant, should be considered.
Relevance is determined with reference to the issues in dispute. The degree or extent
of proof required is a balance of probabilities. This means that once all the evidence
has been tendered, it must be weighed up and determined whether the Applicant’s
version is probable. It involves findings of facts based on an assessment of credibility
and probabilities.
Page 5 of 7
CSOS5016/WC/23
24. Acting in accordance with section 51(1)(a)(i) of the CSOS Act which provides, “An
adjudicator may require the applicant, managing agent or relevant person to give to the
adjudicator further information or documentation.”, on the 22nd of September 2023 a
request for additional information was sent to the Applicant, for the scheme’s Conduct
Rules and expert’s report confirming that the source of water ingress is the
Respondent’s unit, to which no response was received.
25. Section 38 of the CSOS Act, under the heading ‘Applications’ states as follows, (2) “An
application must be- (a) Made in the prescribed manner and as may be required by practice
directives; (b) Lodged with an ombud; and (c) ….”
26. The above provision should be read together with the CSOS Practice Directive on
Dispute Resolution which states, “5.3. The Applicant bears the onus of ensuring that
all relevant information has been submitted to ‘make their case,’ in other words, to ensure
their application form is correctly completed and meets legislative requirements.” (My own
emphasis)
27. The Applicant’s failure to submit the required information has rendered the adjudicator
unable to evaluate and make a finding relating to the relief sought.
28. Accordingly, the Applicant’s prayers for relief against the Respondent is dismissed in
terms of section 53 (1) (b) of the CSOS Act.
COSTS
ADJUDICATION ORDER
RIGHT OF APPEAL
Page 6 of 7
CSOS5016/WC/23
31. Section 57 of the CSOS Act, provides for the right of appeal-
(1) An applicant, the association or any affected person who is dissatisfied by an adjudicator's
order, may appeal to the High Court, but only on a question of law.
(2) An appeal against an order must be lodged within 30 days after the date of delivery of the
order of the adjudicator.
(3) A person who appeals against an order, may also apply to the High Court to stay the
operation of the order appealed against to secure the effectiveness of the appeal.
_______________
N. FOCA
ADJUDICATOR
Page 7 of 7