Program of Work Pitogo
Program of Work Pitogo
Date:
DOTS #:
EXECUTIVE SUMMARY
3 Area: : 18 x 24 = 432 m2
SUBMITTED BY:
BENILDA V. BANQUE
Chief, Planning and Design Section
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGWAYS
NEGROS ORIENTAL
1st DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
Tinaogan, Bindoy, Negros Oriental
Project : Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of
Multi-Purpose Buildings (Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental Net Length :
AS SUBMITTED AS EVALUATED
DESCRIPTION OF WORKS TO BE DONE QUANTITY UNIT
% TOTAL TOTAL DIRECT COST % TOTAL TOTAL DIRECT COST
PART B: OTHER GENERAL REQUIREMENTS 1.37% 54,983.74
PART A: EARTHWORK (PLS. SEE FORM POW-2015-01C-00) 3.09% 123,536.69
PART B: PLAIN AND REINFORCED CONCRETE WORK 24.54% 981,468.18
PART C: FINISHINGS AND OTHER CIVIL WORKS 68.52% 2,740,718.42
PART D: ELECTRICAL WORKS 2.48% 99,032.05
Total 100.0% 3,999,739.08
Prepared by: Checked/Submitted by: Reviewed asto Unit Cost: Recommending Approval: Approved:
GARNEN HUBERT Y. TURA BENILDA V. BANQUE FELICIANO R. ESPINA JESSIE C. PAQUIBO JOEL MELCHOR R. BOCO
Engineer II Chief, Planning and Design Section Chief, Construction Section OIC-Assistant District Engineer District Engineer
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of Multi-Purpose Buildings
(Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
FORM POW-2019-01B-00
MINIMUM EQUIPMENT REQUIREMENT
No. Equipment Description Capacity Number of No. Equipment Description Capacity Number of
Equipment Equipment
1 Backhoe SE 130 LC-2 (0.80 m³) 0.80 m³ 1 31
2 Bar Bender, 25 mm Maximum Rebar 1 32
3 Bar Cutter, Single Phase, 25 mm 1 33
4 Cargo/Service Truck (9-10mt) 9-10mt 1 34
5 High and Lowbed Trailer with Prime Mover 4-6 ft3/min 1 35
6 Plate Compactor (5 hp) 36
7 Water Truck/Pump (16000 L) 16000 L 1 37
8 Welding Machine w/ Generator 1 38
9 1 39
10 40
11 41
12 42
13 43
14 44
15 45
16 46
17 47
18 48
19 49
20 50
21 51
22 52
23 53
24 54
25 55
26 56
27 57
28 58
29 59
30 60
SUB-TOTAL SUB-TOTAL
TOTAL 8 TOTAL
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of
Multi-Purpose Buildings (Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
0
DETAILED UNIT PRICE ANALYSIS (DUPA)
F.1 Materials
FORM POW-2019-01A-00
ITEMIZED BREAKDOWN
DIRECT COST TOTAL UNIT COST
QUANTITY (DIRECT+INDIRECT) % DIRECT COST
ITEM NO. DESCRIPTION UNIT TOTAL UNIT COST
AS SUBMITTED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED AS SUBMITTED AS EVALUATED
PART B OTHER GENERAL REQUIREMENTS
B.3(1) Permits and Clearances 1.00 LS 5,250.00 5,250.00 5,512.50 0.13%
B.5(1) Project Billboard/Signboard 2.00 each 10,171.66 5,085.83 6,301.35 0.25%
B.7(1) Occupational Safety and Health 1.00 LS 26,597.72 26,597.72 30,720.37 0.66%
B.9(1) Mobilization / Demobilization 1.00 LS 12,964.36 12,964.36 13,612.58 0.32%
TOTAL OF PART B 54,983.74 1.37%
PART A EARTHWORK
803(1)a Structure Excavation (Common Soil) 105.65 m3 27,754.00 262.70 325.49 0.69%
804(1)a Embankment (from roadway/structure excavation) 70.97 m3 14,296.82 201.46 249.60 0.36%
804(7) Gravel fill 53.85 m3 81,485.87 1,513.31 1,875.00 2.04%
TOTAL OF PART A 123,536.69 3.09%
PART B PLAIN AND REINFORCED CONCRETE WORK
900(1)c Structural Concrete (3000psi, Class A, 28 Days) 75.98 m3 517,973.81 6,817.16 8,446.46 12.95%
902(1)a Reinforcing Steel (Deformed, Grade 40) 5,539.18 kg 423,633.97 76.48 94.76 10.59%
903 (1) Formworks and Falseworks 1.00 LS 39,860.40 39,860.40 49,387.04 1.00%
TOTAL OF PART B 981,468.18 24.54%
PART C FINISHINGS AND OTHER CIVIL WORKS
1013(2)a Fabricated Metal Roofing Accessory (Gauge 26, 0.551mm, Ridge/Hip Roll) 26.00 lm 6,980.34 268.47 332.64 0.17%
1013(2)b Fabricated Metal Roofing Accessory (Gauge 26, 0.551mm, Flashings) 44.44 lm 9,720.18 218.73 271.00 0.24%
1014(1)b2 Prepainted Metal Sheets (Rib Type ,Long Span,above 0.427mm) 577.72 m2 369,788.83 640.08 793.06 9.25%
1032(1)a Painting Works (Masonry/Concrete) 28.60 m2 7,010.98 245.14 303.73 0.18%
1032(1)c Painting Works (Steel) 509.21 m2 167,108.58 328.17 406.61 4.18%
1047(3) Metal Structure Accessories 1.00 LS 270,725.40 270,725.40 335,428.77 6.77%
1047(8)a Structural Steel, Trusses 16,076.87 kg 1,511,690.52 94.03 116.50 37.79%
1047(8)b Structural Steel, Purlins 3,861.00 kg 374,484.17 96.99 120.17 9.36%
TOTAL OF PART C 2,740,718.42 68.52%
PART D ELECTRICAL WORKS
1100(10) Conduits, Boxes & Fittings (Conduit Works/ Conduit Rough-ins) 1.00 l.s. 25,972.62 25,972.62 32,180.07 0.65%
1101(33) Wires and Wiring Devices 1.00 l.s. 30,935.71 30,935.71 38,329.35 0.77%
1102(1) Panel Board With Main & Branch Breakers 1.00 l.s. 16,285.24 16,285.24 20,177.41 0.41%
1103(1) Lighting Fixtures 1.00 l.s 25,838.48 25,838.48 32,013.88 0.65%
TOTAL OF PART D 99,032.05 2.48%
GRAND TOTAL 3,999,739.08 100.00%
PROJECT NAME:
Basic Infrastructure Program: Evacuation Centers/ Quarantine Facilities/
Public Health Facilities - Construction of Evacuation Centers / Covered
Court, Hibaiyo, Guihulngan City, Negros Oriental
STATION LIMITS: 10.271473333333335N, 123.32047666666668E
DISTANCE FROM NEGROS ORIENTAL 1ST DISTRICT ENGINEERING OFFICE TO SITE: 66 KM
FORM POW-2019-01C-00
DETAILED BREAKDOWN OF COMPONENT COST FOR EACH ITEM
DIRECT COST TOTAL MARK-UP
COLUMN/TOP/BOTTOM
1 CHORDS 2 <s - 75 x 75 x 8 6 90 54.18
2 WEB MEMBERS 2 <s - 63 x 63 x 8 6 80 44.81
STRUT
3 TOP/BOTTOM CHORDS 1< - 63 X 63 X 6 6 79 34.33
4 WEB MEMBERS 1< - 50 X 50 X 6 6 79 26.79
1< - 25 X 25 X 3 6 20 6.72
TOTAL
5 PURLINS LC 150 x 50 x 20 x 20 x 2 6 100 25.74
TOTAL
18X30 MPB
LENGTH
TRUSS MEMBER SIZE (mm) QTY WEIGHT per
(m) LENGTH
MAIN FRAME
1 TOP/BOTTOM CHORDS 2 <s - 75 x 75 x 8 6 108 54.18
2 WEB MEMBERS 2 <s - 63 x 63 x 8 6 115 44.81
STRUT
3 TOP/BOTTOM CHORDS 2< - 63 X 63 X 6 6 80 34.33
4 WEB MEMBERS 2< - 50 X 50 X 6 6 79 26.79
1< - 25 X 25 X 3 6 32 6.72
TOTAL
5 PURLINS LC 150 x 50 x 20 x 20 x 2 6 150 25.74
TOTAL
18X24 MPB
SIZE LENGTH
TRUSS MEMBER
(mm) (m)
MAIN FRAME
TOP/
BOTTOM
1 CHORDS
2 <s - 75 x 75 x 8 6
2 WEB MEMBERS
2 <s - 63 x 63 x 8 6
STRUT
TOP/
BOTTOM
2< - 63 X 63 X 6
3 CHORDS 6
4 2< - 50 X 50 X 6
WEB MEMBERS 6
5 LC 150 x 50 x 20 x 20 x 26
PURLINS
LOUVERS 14 X 24
a. Pre-painted Plain Sht Z -profile louver above 0.427m.
SQUARE TUBE 2mm x 50mm x 50mm
WEIGHT PER FRAME
(kg)
MAIN FRAME
5,000,000.00
148
68 11.333333333
WEIGHT
(kg)
2746.08 4862.49 96
2116.41 87
215.04
16076.87304 6.72
3861 136
3861.00
4 MPB WEIGHT
QTY per WEIGHT (kg)
LENGTH
fing Width 16 m.
9.81
26
510.12
PURLINS 22 578
1< - 25 X 25 X 3 12 24
RAMP RAILINGS 8.2 1.366667
106
32
34
32
31
16
14
80
79
96
4
2
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
NEGROS ORIENTAL
1st DISTRICT ENGINEERING OFFICE
REGIONAL OFFICE VII
Tinaogan, Bindoy, Negros Oriental
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of Multi-Purpose Buildings (Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
FORM ABC-2015-02-00
APPROVED BUDGET FOR THE CONTRACT
Contract Duration : 140 C.D.
TOTAL MARK-UP TOTAL INDIRECT
ITEM NO. DESCRIPTION QUANTITY UNIT ESTIMATED DIRECT COST VAT COST TOTAL COST UNIT COST
% VALUE
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED 1.00 LS 5,250.00 0% - 262.50 262.50 5,512.50 5,512.50
B.3(1) Permits and Clearances
AS EVALUATED
AS SUBMITTED 2.00 each 10,171.66 18% 1,830.90 600.13 2,431.03 12,602.69 6,301.35
B.5(1) Project Billboard/Signboard
AS EVALUATED
AS SUBMITTED 1.00 LS 26,597.72 10% 2,659.77 1,462.87 4,122.65 30,720.37 30,720.37
B.7(1) Occupational Safety and Health
AS EVALUATED
AS SUBMITTED 1.00 LS 12,964.36 0% - 648.22 648.22 13,612.58 13,612.58
B.9(1) Mobilization/Demobilization
AS EVALUATED
AS SUBMITTED 54,983.74 4,490.67 2,973.72 7,464.39 62,448.14
TOTAL OF PART B
AS EVALUATED
PART A EARTHWORK
AS SUBMITTED 105.65 m3 27,754.00 18% 4,995.72 1,637.49 6,633.21 34,387.21 325.49
803(1)a Structure Excavation (Common Soil)
AS EVALUATED
AS SUBMITTED 70.97 m³ 14,296.82 18% 2,573.43 843.51 3,416.94 17,713.76 249.60
804(1)a Embankment (from roadway/structure excavation)
AS EVALUATED
AS SUBMITTED 53.85 m3 81,485.87 18% 14,667.46 4,807.67 19,475.12 100,961.00 1,875.00
804(7) Gravel fill AS EVALUATED
AS SUBMITTED 123,536.69 22,236.60 7,288.66 29,525.27 153,061.97
TOTAL OF PART A
AS EVALUATED
PART B PLAIN AND REINFORCED CONCRETE WORK
AS SUBMITTED 75.98 m3 517,973.81 18% 93,235.29 30,560.45 123,795.74 641,769.55 8,446.46
900(1)c Structural Concrete (3000psi, Class A, 28 Days)
AS EVALUATED
AS SUBMITTED 5,539.18 kg 423,633.97 18% 76,254.11 24,994.40 101,248.52 524,882.49 94.76
902(1)a Reinforcing Steel (Deformed, Grade 40)
AS EVALUATED
AS SUBMITTED 1.00 LS 39,860.40 18% 7,174.87 2,351.76 9,526.64 49,387.04 49,387.04
903 (1) Formworks and Falseworks
AS EVALUATED
AS SUBMITTED 981,468.18 176,664.27 57,906.62 234,570.89 1,216,039.08
TOTAL OF PART B
AS EVALUATED
PART C FINISHINGS AND OTHER CIVIL WORKS
Fabricated Metal Roofing Accessory (Gauge 26, 0.551mm, Ridge/Hip AS SUBMITTED 26.00 lm 6,980.34 18% 1,256.46 411.84 1,668.30 8,648.64 332.64
1013(2)a Roll) AS EVALUATED
AS SUBMITTED 44.44 lm 9,720.18 18% 1,749.63 573.49 2,323.12 12,043.30 271.00
1013(2)b Fabricated Metal Roofing Accessory (Gauge 26, 0.551mm, Flashings)
AS EVALUATED
AS SUBMITTED 52.00 lm 23,209.42 18% 4,177.69 1,369.36 5,547.05 28,756.47 553.01
1013(2)c Fabricated Metal Roofing Accessory (Gauge 24, 0.701mm, Gutters)
AS EVALUATED
AS SUBMITTED 577.72 m2 369,788.83 18% 66,561.99 21,817.54 88,379.53 458,168.36 793.06
1014(1)b2 Prepainted Metal Sheets (Rib Type ,Long Span,above 0.427mm)
AS EVALUATED
AS SUBMITTED 28.60 m2 7,010.98 18% 1,261.98 413.65 1,675.62 8,686.60 303.73
1032(1)a Painting Works (Masonry/Concrete)
AS EVALUATED
AS SUBMITTED 509.21 m2 167,108.58 18% 30,079.54 9,859.41 39,938.95 207,047.53 406.61
1032(1)c Painting Works (Steel)
AS EVALUATED
AS SUBMITTED 1.00 LS 270,725.40 18% 48,730.57 15,972.80 64,703.37 335,428.76 335,428.76
1047(3) Metal Structure Accessories
AS EVALUATED
AS SUBMITTED 16,076.87 kg 1,511,690.52 18% 272,104.29 89,189.74 361,294.03 1,872,984.55 116.50
1047(8)a Structural Steel, Trusses
AS EVALUATED
AS SUBMITTED 3,861.00 kg 374,484.17 18% 67,407.15 22,094.57 89,501.72 463,985.89 120.17
1047(8)b Structural Steel, Purlins
AS EVALUATED
AS SUBMITTED 2,740,718.42 493,329.32 161,702.39 655,031.70 3,395,750.10
TOTAL OF PART C
AS EVALUATED
PART D ELECTRICAL WORKS
AS SUBMITTED 1.00 l.s. 25,972.62 18% 4,675.07 1,532.38 6,207.46 32,180.07 32,180.07
1100(10) Conduits, Boxes & Fittings (Conduit Works/ Conduit Rough-ins)
AS EVALUATED
AS SUBMITTED 1.00 l.s. 30,935.71 18% 5,568.43 1,825.21 7,393.64 38,329.35 38,329.35
1101(33) Wires and Wiring Devices
AS EVALUATED
AS SUBMITTED 1.00 l.s. 16,285.24 18% 2,931.34 960.83 3,892.17 20,177.41 20,177.41
1102(1) Panel Board With Main & Branch Breakers
1102(1) Panel Board With Main & Branch Breakers
AS EVALUATED
AS SUBMITTED 1.00 l.s 25,838.48 18% 4,650.93 1,524.47 6,175.40 32,013.88 32,013.88
1103(1) Lighting Fixtures
AS EVALUATED
AS SUBMITTED 99,032.05 17,825.77 5,842.89 23,668.66 122,700.71
TOTAL OF PART D
AS EVALUATED
AS SUBMITTED 3,999,739.09 714,546.63 235,714.29 950,260.92 4,950,000.00
GRAND TOTAL
AS EVALUATED
Preparation and Submission: Evaluation:
Prepared by: Checked/Submitted by: Reviewed as to Unit Cost:
47 94 140
ITEM NO. DESCRIPTION CONTRACT AMOUNT WEIGHT (%) S1 D1 S0 D0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113 114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136 137 138 139 140
47 94 140
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of Multi-Purpose Buildings (Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
FORM ABC-2015-02-00
SUMMARY OF APPROVED BUDGET FOR THE CONTRACT
Contract Duration : 140 C.D.
TOTAL MARK-UP
ITEM NO. DESCRIPTION ESTIMATED DIRECT COST VAT TOTAL INDIRECT COST TOTAL COST
% VALUE
AS SUBMITTED 54,983.74 8.17% 4,490.67 2,973.72 7,464.39 62,448.14
PART B OTHER GENERAL REQUIREMENTS
AS SUBMITTED
AS SUBMITTED 123,536.69 18.00% 22,236.60 7,288.66 29,525.27 153,061.97
PART A: EARTHWORK
AS EVALUATED
AS SUBMITTED 981,468.18 18.00% 176,664.27 57,906.62 234,570.89 1,216,039.08
PART B: PLAIN AND REINFORCED CONCRETE WORK
AS EVALUATED
AS SUBMITTED 2,740,718.42 18.00% 493,329.32 161,702.39 655,031.70 3,395,750.10
PART C: FINISHINGS AND OTHER CIVIL WORKS
AS EVALUATED
AS SUBMITTED 99,032.05 18.00% 17,825.77 5,842.89 23,668.66 122,700.71
PART D: ELECTRICAL WORKS
AS EVALUATED
AS SUBMITTED 3,999,739.08 714,546.63 235,714.29 950,260.92 4,950,000.00
TOTAL
AS EVALUATED
GARNEN HUBERT Y. TURA BENILDA V. BANQUE FELICIANO R. ESPINA JESSIE C. PAQUIBO JOEL MELCHOR R. BOCO
Engineer II Chief, Planning and Design Section Chief, Construction Section OIC-Assistant District Engineer District Engineer
PROJECT NAME : Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of Multi-Purpose Buildings (Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
LOCATION OF CONTRACT : La Libertad, Negros Oriental
47 94 140
ITEM NO. DESCRIPTION CONTRACT AMOUNT WEIGHT (%) S1 D1 S0 D0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43 44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65 66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89 90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105
35 70 105
HOURLY
Equipment RATE/UNIT
COST
Backhoe SE 130 LC-2 (0.80 m³) ₱ 2,096.00 x 8 =
Bar Bender, 25 mm Maximum Rebar ₱ 168.75 x 8 =
Bar Cutter, Single Phase, 25 mm ₱ 105.47 x 8 =
Cargo/Service Truck (9-10mt) ₱ 1,212.00 x 8 =
Concrete Vibrator ₱ 57.12 x 8 =
Dump Truck (12.0 yd3) ₱ 1,420.00 x 8 =
High and Lowbed Trailer with Prime Mover ₱ 2,720.00 x 8 =
One Bagger Mixer ₱ 172.00 x 8 =
Payloader, LX80-2C (1.50 m3) ₱ 1,733.00 x 8 =
Plate Compactor (5 hp) ₱ 123.00 x 8 =
Water Truck/Pump (16000 L) ₱ 2,450.00 x 8 =
Welding Machine w/ Generator ₱ 371.00 x 8 =
Cutting Outfit ₱ 45.45 x 8 =
DAILY RATE
₱ 865.84
₱ 625.92
₱ 482.48
DAILY RATE
₱ 16,768.00
₱ 1,350.00
₱ 843.76
₱ 9,696.00
₱ 456.96
₱ 11,360.00
₱ 21,760.00
₱ 1,376.00
₱ 13,864.00
₱ 984.00
₱ 19,600.00
₱ 2,968.00
₱ 363.60
EXCAVATION
COLUMN/FOOTINGS L/S R/S
C1/F1 VOL. 10.469 10.469 m3
C1/F1 VOL. 10.469 10.469 m3
C1/F1 VOL. 10.469 10.469 m3
C1/F1 VOL. 10.469 10.469 m3
C1/F1 VOL. 10.469 10.469 m3
m3
TOTAL 52.344 52.344 m3
104.688
SEPTIC TANK
W m
L m
D m
VOL m3
WALL FOOTING+CHB
L/S R/S front rear
A 0.06 0.06 0.06 0.06
L
VOL 0 0 0 0
0
FOOTINGS
(MPB) (CR) (STAGE)
W 2.5 m
L 2.5 m
D 0.4 m
NO. 10
VOL. 25.00 m3
COLUMNS/PEDESTAL
(MPB) (STAGE)
W 0.5 0.5 m
L 0.8 0.8 m
D 2.275 2.275 m
NO. 5 5
VOL. 4.55 4.55 m3
TIE BEAM
W 0.3 m
D 0.4 m
L 44 m
VOL. 5.28 m3
SLAB ON GRADE
W 18.8 m
L 24.5 m
D 0.075 m **4" thk
VOL. 34.545 m3
WALL FOOTING
W 0.1 m
L 40 m
D 0.2 m
NO.
VOL. 0 m3
BEAMS
W m
D m
L m
VOL. m3
RAMP
W 1.2 m
L 1.8 m
H 1.9036 m
VOL 2.055888 m3
REINFORCEMENT
FOOTING
(MPB) GATE CR
W 2.5 1 m
W 2.5 1 m
No. 48 19
No. 48 19
Total 16mmø 96.00 38.00 m
Total 16mmø @ 6m 16.00 7.00 pcs
Total 16mmø 151.52 66.29 kg
No. of Footings 10 0
Total 16mmø 1515.20 0.00 kg
COLUMN/PEDESTAL
(MPB) GATE CR
L/S R/S
H 2.775 3.08 4.9
No. 10 10 10
Total 20mmø 27.75 30.8 49 0
Total 20mmø @ 6m 5.00 6.00 9.00 0.00
Total 20mmø 74.00 88.8 133.20 0.00
NO. 5 5 0
Total 20mmø 370.00000 444.00000 0.00000 0.00000
TIES PEDESTAL
(MPB) GATE CR
L/S R/S
H 2.475 2.78 4.6
L 2.8 2.8 1.4
No. 9 10 16 0
Total 10mmø 25.20 28.00 22.40 0.00
Total 10mmø @ 6m 5.00 5.00 4.00 0.00
Total 10mmø 18.50 18.50 14.80 0.00
No. of Footings 5 5 0
Total 10mmø 92.50000 92.50000 0.00000 0.00000
I PAINTING
B. PEDESTAL (C1)
W 0.5 m
H 1.1 m
X2 2
AREA 1.1
L 0.8 m
H 1.1 m
X2 2
AREA 1.76
TOTAL 2.86
No. 10 m
FOR GATE
W 0.3
L 0.3
D 3
No. 0
AREA 0 m2
TOTAL AREA 28.60000 m2
EMBANKMENT
(MPB) (CR) (STAGE)
FOOTINGS
L/S R/S
STA. 0+002.87 VOL. 2.5 2.5 m3
STA. 0+008.87 VOL. 2.5 2.5 m3
STA. 0+0014.87 VOL. 2.5 2.5 m3
STA. 0+0020.87 VOL. 2.5 2.5 m3
STA. 0+0026.87 VOL. 2.5 2.5 m3
STA. 0+0032.87 VOL. m3
TOTAL 12.5 12.5 m3
25
WALL FOOTING
(FRONT) (REAR)
A m2
L m
VOL.
SEPTIC TANK
L m
W m
D m
VOL. m3
VOL. 34.6800 m3
H 48 m
No. 6m
Total 20mmø 288.00 m
Total 20mmø @ 6m 48.00 pcs
Total 20mmø 710.40 kg
No. of Footings 1
Total 20mmø 710.40000 kg
m
m
m
pcs
kg
kg
TOAL WEIGHT 5539.17556 kg
FILL
STAGE
A m2
H m
VOL. m3
ADDITIONAL FILL
ADDITIONAL FILL
12mm THK.
AREA m2
CEMENT bags
SAND m3
FLOORING WALL FOOTING
L 80
H 18.8 m NO. OF BA 2
L 24.5 m
No. 62.66666667 13.33333
81.66666667 6m x 10mm26.66667
255.88888889
255.88888889 wt. 98.66667
Total 10mmø 511.78 pcs
Total 10mmø 1893.58 kg
1
Total 10mmø 1893.57778 kg
RAMP
H 1.2036
SPACING 0.3
W 1.5
NO. OF BARS ALONG H 5.012
NO. OF BARS ALONG W 6
10mmø X 6m 3
wt 9.270007
GRAVEL BED
COLUMN/FOOTINGS
(MPB) (CR) (STAGE)
W 2.5 m
L 2.5 m
D 0.1 m
NO. 10
VOL. 6.25 m3
TIE BEAM
W 0.3 m
L 44 m
D 0.1 m
VOL 1.32 m3
SOG
AREA 460.6 m
D 0.1 m
VOL. 46.06 m3
RAMP
W 1.2 m
L 1.8 m
D 0.1 m
VOL 0.216 m3
WALL FOOTING
(FRONT) (REAR) left right
W m
L 16 16 24 24 m
D 0.6 0.6 0.6 0.6 m
VOL. 0 0 0 0 m3
SEPTIC TANK
W m
L m
D m
VOL. m3
6m x 10mm44.61111
kg WT. 165.0611
263.7278 KG
ITEM 506
ITEM 505
m3
m3
m3
m3
m3
m3
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of Multi-Purpose Buildings
(Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
DETAILED UNIT PRICE ANALYSIS (DUPA)
5,000.00
a. Fine Tax 0.1% (Construction Cost)
Bureau of Fire 250.00
98.71
Minor Tools (10% of labor cost)
12,964.36
a. Mobilization/ Demobilization
No. of
Designation No. of Days Hourly Rate Amount
Person
A.1 Labor
719,953.03
4,950,000.00
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of Multi-Purpose Buildings
(Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 900(1)c2 Structural Concrete (Footings and Slab on Fill, Class A, 28 days)
Unit of Measurement : m3
Output per hour : 0.357
Page 23
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of Multi-Purpose Buildings
(Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
DETAILED UNIT PRICE ANALYSIS (DUPA)
Item No./Description : 900(1)c3 Structural Concrete (Footing Tie Beams, Class A, 28 Days)
Unit of Measurement : m3
Output per hour : 0.270
Item No./Description : 1013(2)a Fabricated Metal Roofing Accessory (Gauge 26, 0.551mm, Ridge/Hip Roll)
Unit of Measurement : lm
Output per hour : 10
Item No./Description : 1013(2)b Fabricated Metal Roofing Accessory (Gauge 26, 0.551mm, Flashings)
Unit of Measurement : lm
Output per hour : 10
Item No./Description : 1013(2)c Fabricated Metal Roofing Accessory (Gauge 24, 0.701mm, Gutters)
Unit of Measurement : lm
Output per hour : 11.8
Item No./Description : 1014(1)b2 Prepainted Metal Sheets (Rib Type ,Long Span,above 0.427mm)
Unit of Measurement : m2
Output per hour : 2.769
Fabrication
a. Construction Foreman 1 15 865.84 12,987.60
b. Skilled Laborer 2 15 625.92 18,777.60
c. Unskilled Laborer 4 15 482.48 28,948.80
Fabrication
a. Construction Foreman 1 1.00 108.23 108.23
b. Skilled Laborer 2 1.00 78.24 156.48
c. Unskilled Laborer 2 1.00 60.31 120.62
Erection
a. Skilled Laborer 3 0.49 78.24 115.01
b. Unskilled Laborer 3 0.49 60.31 88.66
Item No./ Description : 1046(2)aCHB Non Load Bearing Wall (including Reinforcing Steel,100mm)
Unit of Measurement : m2
Output per hour - As Submitted : 3.83
Output per hour - As Evaluated :
Item No./Description 1100(10) Conduits, Boxes & Fittings (Conduit Works/ Conduit Rough-ins)
Unit of Measurement LS
No.of
No. of
Designation Hourly Rate Amount
Hours
Person
1. Labor
MPB
a. 15 mm dia PVC Conduit pcs 58.00 137 7,946.00
b. 20 mm dia RSC Conduit pc 1.00 521 521.00
c. C Clamp for 15 mm dia PVC pcs 10.00 30 300.00
d. C Clamp for 20 mm dia RSC pcs 2.00 50 100.00
e. Elbow for 15 mm dia PVC Conduit pcs 10.00 150 1,500.00
f. Elbow for 20 mm dia RSC Conduit pcs 2.00 197 394.00
g. Junction Box 4" x 4" (Deep Type) pcs 5.00 39 195.00
h. Utility Box (Deep Type) pcs 3.00 39 117.00
i. Entrance Cap 1" dia pc 1.00 62 62.00
j. Convenience Outlet, Weatherproof pcs 3.00 366 1,098.00
k. Three-gang Switch, 1-way pcs 1.00 176 176.00
-
Sub-Total for 3 12,409.00
Unit Direct Cost 25,972.62
Overhead, Contingencies & Miscellaneous (OCM) 8% 2,077.81
Contractor's Profit (CP) 10% 2,597.26
Vat 5% 1,532.38
Total Unit Cost 32,180.07
Prepared by: Checked/Reviewed by:
LOCATION :
Item No./Description 1101(33) Wires and Wiring Devices
Unit of Measurement l.s.
No.of
Designation No. of Hours Hourly Rate Amount
Person
1. Labor
MPB
a. 3.5 mmsq THHN Stranded Wire mtrs 348.00 36.00 12,528.00
b. 3.5 mmsq TW(G) Stranded Wire mtrs 179.00 36.00 6,444.00
c. 5.5 mmsq THHN Stranded Wire mtrs 20.00 57.00 1,140.00
d. Electrical Tape pcs 5.00 31.00 155.00
e. Tie Wire kg 2.00 78.00 156.00
f. Cable Tie packs 2.00 170.00 340.00
Item No./Description 1102(1) Panel Board With Main & Branch Breakers
Unit of Measurement l.s.
Output per hour 1
No.of
No. of
Designation Hourly Rate Amount
Hours
Person
1. Labor
3. Materials
No.of
No. of
Designation Hourly Rate Amount
Hours
Person
1. Labor
3. Materials
MPB
a. 100W LED Flood Light sets 12.00 1,950.00 23,400.00
3. Excavation
Generally excavation is carried out for the construction of wall foundations.
Excavation should be carried out as per the drawings defined lengths & widths.
Suitable machines are used to excavate the the earth for the making of foundation.
4. Foundation Work
Foundation work consists of many sub works which are as follows,
4.1 Compacting the ground
The excavation pits are trimmed and dressed as per the requirement and the
bottom is compacted using hand
compactors.
4.2 Plain Cement Concrete
To form a solid bases on which the reinforcement can be tied and footing can be
placed. Plain cement concrete of the mix 1:2:4 is laid on the compacted soil in
varying depth as required.
4.3. Footing Reinforcement
Reinforcement steel bars are tied together and placed on the PCC to form a
skeleton in which the concrete is poured and the column rods are taken from them.
4.5. Footing Concrete
It is very necessary to check the levels of foundation before concrete work. There
are patches where excavated depth slightly exceeds and vice versa. Concrete is
poured as per drawing specs. Footing shall rest at least 1500mm below natural
grade line unless otherwise indicated in plans. No footing shall rest on fill.
4.5. Pedestal Column Casting
Casting of pedestal columns is made by fixing the shuttering framework and
concrete is poured in the formwork. The shuttering is usually removed after 24hr of
casting and curing is done.
5.0 Structural Steel
After all the reinforced concrete works, structural steel will start. Structural steel to be used for
fabrication and erection of this structure shall comply will all the pertinent provision of AISC
specification for the design, fabrication, and erection of structural steel for building latest edition.
structural members shall be joined by welding. The welds shall be of the size and type
indicated and shall be made by competent operators. Shop welding shall conform in all details
Society.
5.1 Roofing
After all the reinforced concrete works,roofing will start. Roofings installation starts with
trusses, purlins, sagrods, cross-bracing and lastly the long-span rib type roof.
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social
Services - Construction of Multi-Purpose Buildings (Covered Court/Evacuation
Center), Barangay Pitogo, La Libertad, Negros Oriental
La Libertad, Negros Oriental
Scope of Works
2. Embankment
- embankment for footings for the covered court
3. Structural Excavation
- excavation for footings for the covered court
4. Reinforced Concrete
- for footings and columns of Covered court
- for tie beam for covered court
- for concrete pavement of covered court (entire area) and ramp
6 Painting Works
- Painting on pedestals
- Painting on Steel Trusses
- Painting on Steel Purlins
- Painting on Steel Columns
- Painting on Steel Struts
- Painting on gutter
- Painting on ramp handrails
7 Electrical Works
Republic of the Philippines
Department of Public Works and Highways
NEGROS ORIENTAL 1st DISTRICT ENGINEERING OFFICE
Tinaogan, Bindoy, Negros Oriental
Basic Infrastructure Program: Multi-Purpose Buildings/Facilities to support Social Services - Construction of
Multi-Purpose Buildings (Covered Court/Evacuation Center), Barangay Pitogo, La Libertad, Negros Oriental
DERIVATION OF HAULING COST PER KILOMETER
(Aggregates)
Say, 32 km
Say, 27 km
Total Rate of Cargo Truck for One Cycle = P 1,212.00 per hour x 1.15 hrs = ###
Say, 27 km
Total Rate of Cargo Truck for One Cycle = P 1,212.00 per hour x 1.15 hrs = ###
Say, 6 km
Total Rate of Cargo Truck for One Cycle = P 1,212.00 per hour x 0.07 hrs = ###
Say, 27 km
Total Rate of Cargo Truck for One Cycle = P 1,212.00 per hour x 1.15 hrs = ###
Say, 27 km
Total Rate of Cargo Truck for One Cycle = P 1,212.00 per hour x 1.15 hrs = ###