Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
Authorities to submit to Parliament a 2025 budget
consistent with overall revenue, grants and
spending projections in the program that includes
a comprehensive roads budget with information end-
on total cost, variations, allocations in FY2025, November
and expected funding needs for FY2026 and 2024
FY2027.
3
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
fiscal costs.
4
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
5
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
information on taxpayer registration, on-
time filing, payment rates, tax audits, and
tax arrears recovery.
6 Revenue measures
Initiate audits of at least one of the largest
mining companies.
Expenditure measures
Maintain wages and salaries at around 3.5
percent of GDP over the program period
supported by a wage bill strategy and Continuous
commit to impose stricter controls on the
recruitment and compensation of
consultants and sub-vented agencies staff
while protecting essential services.
Fully implement the National Public
Investment Management Policy (NPIMP) Continuous
from 2025.
6
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
Re-appraise and reselect investment
projects that are longstanding or that have
gone through variations that exceed the Continuous
regulatory threshold of 25 percent of
original cost.
7
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
Share with IMF staff, quarterly IFMIS starting with
reports with information on budget the fourth
allocations, commitments made, quarter of
completed payments, and outstanding 2024 (by end-
payments. January 2025)
8
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
The Expanded Cash and Debt
Management Committee (ECDMC) will
prepare cash flow projections at [bi-
Continuous
weekly] meeting and will establish a
monthly-rolling cash forecasting system
with approved guidelines.
Debt management
Terminate the use of domestic FX linked
securities.
MEFP
Continuous
Lengthen the maturity profile of the commitment
domestic debt portfolio; undertake other
market development initiatives identified
in paragraph 17 of MEFP.
Monetary Policy Continuous MEFP
Terminate the securitization of the Ways commitment
and Means advances beginning with the
outstanding stock at end December 2024.
9
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
inflation objective in our monetary policy
statements
FX market development -
publish the BSL FX reference rate on the
day it is compiled;
10
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
End-June MEFP
2025 commitment
A. Fiscal Policies and PFM
Authorities to submit to Parliament a 2026
Finance bill with measures projected to deliver at
least 1 percent of GDP in additional annual tax end-
revenues. November
2025
11
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
Install an additional 1,710 large
consumers with smart meters, for a total
of 3000 EDSA’s larger consumers with
smart meters;
12
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
November)
13
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
We will work with FAD and AFW2 to develop an Part of the
action plan to implement baseline budgeting. In 2025 Budget
that process, the MoF will develop costing Process (by
templates and provide support to MDAs on the end-
estimation of baseline costs’ November)
A pilot baseline budget for the [seven] MDAs Part of the
with largest historical budget overruns will be 2025 Budget
published alongside the 2025 Fiscal Strategy Process (by
Statement as well as detailed measures to contain end-
spending within these MDAs. November)
14
Table. Sierra Leone: List of commitments for the ECF Arrangement
Update at Action Point/Next Steps
List of commitments/issues TIMING STATUS
May 30, 2024
publishing the FIU AML/CFT national risk
assessment report, making beneficial ownership
of companies available, and strengthening 2025 commitment
AML/CFT risk-based supervision.
15