CGPS User Guide(01)(PDF)-EN
CGPS User Guide(01)(PDF)-EN
User Guide
Issue 01
Date 2019-06-06
and other Huawei trademarks are trademarks of Huawei Technologies Co., Ltd.
All other trademarks and trade names mentioned in this document are the property of their respective
holders.
Notice
The purchased products, services and features are stipulated by the contract made between Huawei and
the customer. All or part of the products, services and features described in this document may not be
within the purchase scope or the usage scope. Unless otherwise specified in the contract, all statements,
information, and recommendations in this document are provided "AS IS" without warranties, guarantees
or representations of any kind, either express or implied.
The information in this document is subject to change without notice. Every effort has been made in the
preparation of this document to ensure accuracy of the contents, but all statements, information, and
recommendations in this document do not constitute a warranty of any kind, express or implied.
Website: https://www.huawei.com
Email: [email protected]
Contents
Overview
A CPRI Global Positioning System (CGPS) converts GPS analog signals into digital
signals and transmits the signals to the BBU using optical cables. The CGPS
resolves the problem that cable layout is not allowed in the equipment room and
the GPS remote deployment problem.
This document describes the appearance, functions, and interfaces of a DC blade
CGPS and the process of installing it.
Version Requirement
The following table lists the version requirement.
Intended Audience
This document is intended for:
● Base station installation engineers
● System engineers
● Site maintenance engineers
1.1 Change History
This section describes the changes in CGPS Installation Guide.
1.2 Introduction to CGPS
This chapter describes the appearance, functions, interfaces, technical
specifications, and indicators of the CGPS.
1.3 CGPS Cable
This section describes CGPS cables.
1.4 Installing a CGPS
01 (2019-06-06)
This is the first official release.
Compared with Draft A (2019-05-10), this issue does not include any modification.
Draft A (2019-05-10)
This is a draft.
CGPS exterior
Figure 1-1 shows the exterior of a CGPS.
CGPS Dimensions
Figure 1-2 shows CGPS dimensions.
The CGPS module name and power supply information can be queried on the
cabling cavity nameplate, as shown in Figure 1-3.
NOTE
The actual nameplate may differ from what is shown in the figure.
● Receives GPS signals using GPS antennas, and obtains timing signals and
position information.
● Reports timing information and position information to the BBU from CPRI
ports.
A CGPS is a CPRI-based GPS clock unit. GPS antennas obtain timing and position
information and send the information to the BBU from CPRI ports.
A CGPS is connected to a BBU directly . Figure 1-5 shows the position of a CGPS
in the system.
A CGPS consists of a high-speed interface unit, GPS signal processing unit, CPU,
clock unit, and power supply unit, as shown in Figure 1-6.
Figure 1-7
Weight 6 kg
Table 1-2 describes the ports on the CGPS bottom panel and cabling cavity panel
and indicators.
ACT
VSWR
CPRI0
CPRI1
Optical modules of various types must be used in pairs on both ends of an optical
fiber. The following table describes the mapping.
NOTICE
● Each type of optical module has its own mapping. If different types of optical
modules are used, performance risks may arise, for example, alarms, bit errors,
and interrupted links.
● To ensure that optical modules are connected and working properly, Huawei
equipment must be used with the original optical modules. As the compatibility
and quality of third-party optical modules cannot be guaranteed, using such
modules may cause connection exceptions or even damage to the main
equipment.
SFP duplex (two-fiber SFP duplex optical modules with the same
bidirectional, duplex for specifications
short) optical module
SFP BIDI (single-fiber SFP BIDI optical modules are used on both sides.
bidirectional, BIDI for ● The receive and transmit wavelengths of
short) optical module optical modules on both sides have the
mapping relationship. For example, if the
receive and transmit wavelengths of the optical
module on the BBU side are 1270TX/1330RX,
those on the RRU side are 1330TX/1270RX.
● Except for wavelengths, the specifications of
optical modules are the same.
QSFP BIDI optical module QSFP BIDI optical modules are used on both sides.
● The receive and transmit wavelengths of
optical modules on both sides have the
mapping relationship. For example, if the
receive and transmit wavelengths of the optical
module on the BBU side are 1270TX/1330RX,
those on the RRU side are 1330TX/1270RX.
● Except for wavelengths, the specifications of
optical modules are the same.
QSFP duplex optical QSFP duplex optical modules with the same
module specifications
QSFP SR4 (short distance, QSFP SR4 optical modules with the same
SR4 for short) optical specifications
module
DSFP optical module/SFP The DSFP optical module is used on the BBU side
BIDI optical module and the SFP BIDI optical module is used on the
RRU side.
● The receive and transmit wavelengths of
optical modules on both sides have the
mapping relationship. For example, if the
receive and transmit wavelengths of the optical
module on the BBU side are 1270TX/1330RX,
those on the RRU side are 1330TX/1270RX.
● Except for wavelengths, the specifications of
optical modules are the same.
NOTE
● The exterior and label on an optical module in this section are for reference only.
● Optical modules to be installed must match the rates of their corresponding ports.
● Only Huawei-certified optical modules meeting the following requirements can be used
for Huawei wireless devices:
● Requirements of devices on which optical modules are to be installed
● Laser safety requirements in the IEC 60825-1 standard
● General safety requirements in the IEC 60950-1 standard
● The supported maximum remote distance varies depending on the optical module. For
details, see section "CPRI Optical Fiber" in 3900 & 5900 Series Base Station Cables. CPRI
optical fibers are configured based on application scenarios.
There is a label on each optical module that provides information such as the rate,
wavelength, and transmission mode, as shown in the following figure.
A 100G SR4 optical module provides an MPO connector, as shown in the following
figure.
There is a label on each QSFP optical module, which provides information such as
the rate, wavelength, and transmission mode, as shown in the following figure.
NOTE
NOTE
NOTE
A PGND cable is yellow and green or green with a cross-sectional area of 16 mm2.
Both ends of the cable are OT terminals, as shown in Figure 1-19.
(1) OT terminal (16 mm2, M6) (2) OT terminal (16 mm2, M8)
NOTE
If you use your own power supply equipment, the 20 A to 30 A circuit breaker is recommended.
(1) DC round waterproof connector (2) Female fast connector (pressfit type)
NOTE
(1) DC round waterproof connector (2) Female fast connector (pressfit type)
NOTE
CGPS power cables are two-core cables with the specification of 3.3 mm2 to 8.2
mm2, and the outer diameter ranges from 9.9 mm to 14.4 mm.
Table 1-6 describes the pin assignment for CGPS power cables.
NOTE
Cable color and appearance differ by country and region. If cables are purchased in the
local area, the cables (subject to cables delivered) must meet Huawei cable requirements.
CPRI Optical cables are used to connect a CGPS and RRU and with a default length of 2 m
(78.74 in.) are used for CGPS and RRU cascading. If the distance between a CGPS and RRU
exceeds 2 m (78.74 in.), contact Huawei technical support.
Exterior
Two ends are DLC connectors, as shown in Figure 1-22.
(1) DLC connector (2) Breakout cable (3) Breakout cable label
Pin Assignment
Table 1-7 describes the labels on CPRI optical cables and recommended
connections.
The two ends of a GPS jumper are type N connectors, which need to be prepared
on site.
Torque wrench
Capacity: 16 mm or 22
mm (0.63 in. or 0.87 in.)
Combination wrench
Capacity:16 mm or 22
mm (0.63 in. or 0.87 in.)
5 mm or 0.2 in.
5 mm or 0.2 in.
(M3 to M6)
(M3 to M6)
Hydraulic pliers - -
NOTE
● Application scenarios
To ensure proper heat dissipation of the CGPS, the following requirements
must be met:
– The CGPS cannot be installed in an enclosed cabinet without a cooling
system.
– The CGPS cannot be installed in an enclosed camouflage box.
– The CGPS cannot be installed in an enclosed equipment room without a
cooling system.
– The CGPS must be installed near the RRU when being independently
installed.
NOTICE
If the CGPS is improperly installed, heat dissipation of the CGPS deteriorates
and the CGPS may not work properly, as shown in Figure 1-24.
● Mounting mode
NOTE
The installation supports' specifications are based only on the exterior and dimensions
of the mounting kits. Before installing equipment, assess the strength and reliability of
the installation support to determine whether it can bear the weight of the
equipment.
– To ensure the heat dissipation of the CGPS and waterproofing of the
ports at the bottom of the CGPS, the vertical deviation angle of a CGPS
must be less than or equal to 10 degrees, as shown in Figure 1-25.
– When the CGPS is installed on the tower, it can be installed with the RRU
on the pole or wall. Alternatively, it can be independently installed on the
pole, U-steel, angle steel, or wall.
NOTE
NOTICE
● The diameter of a pole for installing a CGPS ranges from 60 mm (2.36 in.) to
114 mm (4.49 in.). The recommended diameter is 80 mm (3.15 in.).
● The recommended thickness of the pole wall is 3.5 mm (0.14 in.) or above.
Figure 1-27 and Figure 1-28 show how to install a CGPS on the pole.
NOTICE
The mounting kits cannot be combined when the RRUs and CGPSs are installed on
a wall in side-mounted mode, as shown in Figure 1-29.
Figure 1-29 Correct installation of mounting kits for RRUs installed on the wall in
side-mounted mode
Figure 1-30 and Figure 1-31 show the RRU and CGPS installation on the wall.
NOTE
The wall for installing the CGPS must meet the following requirements:
● For each RRU and CGPS, the wall must be able to bear a weight four times as heavy as the
RRU and CGPS's weight and the bolts' pulling force of 1.25 kN vertical to the wall.
● When the RRU and CGPS are installed on the wall, expansion bolts must be tightened with a
torque of 30 N·m to ensure the bolts work properly and the wall remains intact without
cracks in it.
Figure 1-30 Installing the RRU and CGPS on the wall (1)
NOTE
When a CGPS is independently installed, the distance between the CGPS and RRU must be
less than or equal to 2 m.
NOTICE
● The diameter of a pole for installing a CGPS ranges from 60 mm (2.36 in.) to
114 mm (4.49 in.). The recommended diameter is 80 mm (3.15 in.).
● The recommended thickness of the pole wall is 3.5 mm (0.14 in.) or above.
NOTICE
The CGPS must be installed in standard mode when being independently installed.
NOTICE
U-steel only supports the standard installation of a single CGPS.
Figure 1-37 shows how to independently install a CGPS on the angle steel.
NOTICE
Angle steel only supports the standard installation of a single CGPS.
NOTE
● The recommended clearance ensures normal running and provides an appropriate space
for operation and maintenance (O&M). If there is sufficient space, leave the
recommended clearance after installing the equipment.
● The minimum installation clearance ensures proper equipment running and heat
dissipation. However, O&M activities, such as checking indicator status and opening the
cabling cavity cannot be properly performed. If the installation space is restricted, leave
the minimum clearance after installing the equipment.
● When a CGPS is installed in side-mounted mode, space requirements for installing RRUs
must be met.
If a CGPS is installed on the bitumen ground, the CGPS bottom must be at least
500 mm away (700 mm recommended) from the bitumen ground. The following
describes the space requirements for installing a CGPS on the non-bitumen
ground.
Figure 1-39 shows the clearance for installing a CGPS in standard mode.
Context
NOTE
When transporting, moving, or installing the equipment, components, or parts, you must:
● The base stations need to be transported to the site before they are installed. Do not
unpack them or change the packages of them before transportation.
● Prevent them from colliding with doors, walls, shelves, or other objects.
● Wear clean gloves, and avoid touching the equipment, components, or parts with bare
hands, sweat-soaked gloves, or dirty gloves.
● Transportation of the base stations must comply with requirements of ETSI 300
019-1-2 class 2.3. For the goods damage caused by non-standard and violent
transportation or non-human factors (such as natural disasters), the transportation
entity should take the responsibility.
NOTICE
Procedure
Step 1 Check the total number of articles in each case according to the packing list.
The total number does not tally with Find out the cause and report any
the packing list missing articles to the local Huawei
office.
The outer packing is severely Find out the cause and report it to the
damaged or soaked local Huawei office.
Step 3 Check the type and quantity of the equipment in the cases according to the
packing list.
Types and quantity of the article Sign the Packing List with the customer.
tally with those on the packing list
CAUTION
● To protect the equipment and prevent damage to the equipment, you are
advised to keep the unpacked equipment and packing materials indoors, take
photos of the stocking environment, packing case or carton, packing materials,
and any rusted or eroded equipment, and then file the photos.
● Verify that the insulation layers of all CGPS cables are intact. If the insulation
layers are damaged or broken, water will penetrate into the cables, which may
cause damages to CGPS or human injury.
----End
Context
NOTE
● Do not stand a CGPS upright because the CGPS bottom cannot support the weight of the
CGPS.
● Place a foam pad or cardboard under a CGPS to protect the CGPS housing from damage
during the installation.
● When a CGPS is installed with an RRU, they can only be installed on a pole.
● This section describes how to install a CGPS with a blade RRU.
Procedure
Step 1 Install the CGPS with the RRU by following the steps provided in 1.4.8.2 Installing
Blade RRU and CGPS.
Step 2 After climbing up to the tower, installation engineer A secures the fixed pulley to
the tower platform support and leads the lifting sling through the fixed pulley.
Step 3 Installation engineer C on the ground binds the RRU mounting kits using lifting
sling and traction sling, as shown in Figure 1-41. Installation engineer B pulls the
lifting sling downwards, and installation engineer C pulls the traction sling
outwards to protect the RRU mounting kits from colliding with the tower.
Step 4 Installation engineer A catches the RRU and mounting kits and then unties the
lifting sling and traction sling.
Step 5 Install the mounting kits by seeing RRU Installation Guide.
Step 6 After installing mounting kits, installation engineer C binds the CGPS and RRU
using lifting sling and traction sling, as shown in Figure 1-42.
(1) RRU hander (2) Lifting sling (3) RRU traction (4) Traction sling
eye
Step 7 Hoist the bound CGPS and RRU onto the tower, as shown in Figure 1-43.
Installation engineer B pulls the lifting sling downwards, and installation engineer
C pulls the traction sling outwards to protect the CGPS and RRU from colliding
with the tower.
Figure 1-43 Hoisting the CGPS and RRU onto the tower
NOTICE
● The lifting sling or traction sling must bear a weight of 200 kg (441 lb), and the
diameter must be less than 25 mm (0.98 in.).
● When hoisting the CGPS and mounting kits onto the tower, protect them from
colliding with the tower.
● The CGPS and RRU cannot be installed on the pole before being hoisted onto
the tower.
● Do not use the traction eye to hoist other objects.
Step 9 Installation engineer A installs the RRU on the main bracket. For details, see the
corresponding RRU Installation Guide.
Step 11 If the RRU has been installed on the tower, hoist the mounting kits onto the tower.
1. Hoist the mounting kits onto the tower by seeing Step 2, Step 3, and Step 4,
as shown in Figure 1-44.
2. Hoist the CGPS onto the tower by seeing steps 5, 6, and 7 in 1.4.6.2 Hoisting
a CGPS onto a Tower in Independent Installation Scenarios. Then, install
the CGPS with the RRU using the mounting kits. For details, see 1.4.8.1
Installing Non-Blade RRU and CGPS and 1.4.8.2 Installing Blade RRU and
CGPS.
----End
NOTE
● Do not stand a CGPS upright because the CGPS bottom cannot support the weight of the
CGPS.
● Place a foam pad or cardboard under a CGPS to protect the CGPS housing from damage
during the installation.
● A CGPS can be independently installed on the pole, angle steel, and U-steel.
Procedure
Step 1 After climbing up to the tower, installation engineer A secures the fixed pulley to
the tower platform support and leads the lifting sling through the fixed pulley.
Step 2 Installation engineer C on the ground binds the CGPS mounting kits using lifting
sling and traction sling, as shown in Figure 1-45. Installation engineer B pulls the
lifting sling downwards, and installation engineer C pulls the traction sling
outwards to protect the RRU mounting kits from colliding with the tower.
Step 3 Installation engineer A catches the CGPS mounting kits and then unties the lifting
sling and traction sling.
Step 4 Install the mounting kits. For details, see 1.4.9 Installing a CGPS in Independent
Installation Scenarios.
Step 5 After installing mounting kits, installation engineer C binds the CGPS using lifting
sling and traction sling, as shown in Figure 1-46. Do not bind the CGPS using the
methods shown in Figure 1-47 and Figure 1-48.
(1) Handle (2) Lifting sling (3) Traction eye (4) Traction sling
Figure 1-48 Incorrect binding method – hoisting the traction eye only
Step 6 Hoist the bound CGPS onto the tower, as shown in Figure 1-49. Installation
engineer B pulls the lifting sling downwards, and installation engineer C pulls the
traction sling outwards to protect the CGPS from colliding with the tower.
NOTICE
● The lifting sling or traction sling must bear a weight of 200 kg (441 lb), and the
diameter must be less than 25 mm (0.98 in.).
● When hoisting the CGPS and mounting kits onto the tower, protect them from
colliding with the tower.
● Hoist the CGPS onto the tower before it is installed on a pole, angle steel, or U-
steel.
● Do not use the traction eye to hoist other objects.
NOTE
----End
Prerequisites
A CGPS and RRU have been hoisted onto the tower.
NOTE
If an RRU has been installed on the tower, use the original RRU optical cables.
Context
Cabling requirements for optical cables are met. For details, see 1.4.10.1 Cabling
Requirements.
Procedure
Step 1 Hoist the optical cables onto the tower, as shown in Figure 1-50.
NOTICE
Before hoisting optical cables onto the tower, connect the optical cables to the
BBU based on the labels on both ends of the cables and determine the hoisting
direction.
1. After climbing up to the tower, installation engineer A secures the fixed pulley
to the tower platform support and leads the lifting sling through the fixed
pulley.
2. Installation engineer B places the optical cable coiler for coiling optical cables
on the optical cable spools, and installation engineer D leads the lifting sling
through the stretch sling of the optical cables and uses the other sling as a
traction sling to secure the cables 4 m (13.12 ft) away from the lifting sling,
as shown in Figure 1-51.
NOTE
Do not remove the stretch sling and protection pipe or bind optical cables using one sling,
as shown in Figure 1-52.
Step 2 Secure the optical cables to the tower vertically using cable clips.
Step 3 Remove the lifting sling, traction sling, and protection pipe.
NOTE
----End
Prerequisites
A CGPS and RRU have been hoisted onto the tower.
NOTE
If an RRU has been installed on the tower, use the original RRU power cables. In this case, the
connector on the CGPS side needs to be prepared.
Context
● Cabling requirements for power cables are met. For details, see 1.4.10.1
Cabling Requirements.
● The procedure for adding a connector to the CGPS power cable on the CGPS
side is done under the tower.
Procedure
Step 1 Hoist the power cables onto the tower, as shown in Figure 1-53.
1. After climbing up to the tower, installation engineer A secures the fixed pulley
to the tower platform support and leads the lifting sling through the fixed
pulley.
2. Installation engineer B secures three cable ties to the power cable connector,
and then secures the power cable to the lifting sling, as shown in Figure 1-54.
NOTE
The connector on the power cable in the figure is only an example. The actual connector
may vary according to the situation.
3. Installation engineer B wraps the power cable connector with a layer of PVC
insulation tape, as shown in Figure 1-55.
NOTE
Wrap the PVC insulation tape from 30 mm (1.18 in.) away from one end of the connector
until it reaches the other end of the connector. The total length of the wrapped connector
is 150 mm (3.94 in.).
----End
NOTE
When the operator faces the CGPS whose handle and cabling cavity are on the right-hand
side, the side facing the operator is the front of the CGPS.
(1) Plastic screw cap (2) Standard nut M10 (3) Spring washer
(4) Thick flat washer (5) Square-neck bolt (6) Hoist clamp on the
main bracket
(7) Main bracket (8) Hex socket screw (9) Pole mounting kit
NOTICE
● Do not stand a CGPS upright because the radio frequency (RF) port on the
CGPS bottom cannot support the weight of the CGPS.
● Place a foam pad or cardboard under a CGPS to protect the CGPS housing from
damage during the installation.
Procedure
Step 1 Install the two washers in the fitting bag on the CGPS mounting kits, and use an
M4 torque screwdriver to tighten the four captive screws on the conversion
bracket washers to 1.2 N•m, as shown in Figure 1-59.
Step 2 Use an M6 inner hexagon torque screwdriver to remove the conversion bracket at
the rear of the RRU, and install the CGPS mounting kits at the rear of the RRU.
Use an M6 inner hexagon torque screwdriver to tighten the captive screws on the
CGPS mounting kits to 5 N·m (44.25 lbf·in.), as shown in Figure 1-60.
(1) Label
Step 3 Use an M6 Phillips screwdriver to remove the RRU cover plate and install the RRU
conversion bracket at the side of the RRU. Use an M6 inner hexagon torque
screwdriver to tighten the four screws to 5 N·m (44.25 lbf·in.), as shown in Figure
1-61.
Figure 1-61 Installing the RRU conversion bracket on the side of the RRU
Step 4 Removing the rubber plugs in the mounting holes on the mounting kits, as shown
in Figure 1-62.
Figure 1-62 Removing the rubber plugs in the mounting holes on the mounting
kits
Step 5 Install the CGPS at the rear of the RRU and fasten the drawbars on the CGPS
cabinet to the card slots, as shown in Figure 1-63.
Figure 1-63 Fastening the drawbars on the CGPS cabinet to the card slots
Step 6 Use an M6 inner hexagon torque screwdriver to tighten the four captive screws on
the CGPS to 5 N·m (44.25 lbf·in.), as shown in Figure 1-64.
Step 7 Install the CGPS and RRU on the pole or wall. For details, see the corresponding
RRU Installation Guide.
----End
Procedure
Step 1 Install the CGPS mounting kits at the rear of the RRU and use an M6 inner
hexagon torque screwdriver to tighten the captive screws on the conversion
bracket to 5 N·m (44.25 lbf·in.), as shown in Figure 1-65.
Figure 1-65 Installing the CGPS mounting kits at the rear of the RRU
(1) Label
Step 2 Removing the rubber plugs in the mounting holes on the mounting kits, as shown
in Figure 1-66.
Figure 1-66 Removing the rubber plugs in the mounting holes on the mounting
kits
Step 3 Install the CGPS at the rear of the RRU and fasten the drawbars on the CGPS
cabinet to the card slots, as shown in Figure 1-67.
Figure 1-67 Fastening the drawbars on the CGPS cabinet to the card slots
Step 4 Use an M6 inner hexagon torque screwdriver to tighten the captive screws on the
CGPS to 5 N·m (44.25 lbf·in.), as shown in Figure 1-68.
Step 5 Install the CGPS and RRU on the pole or wall. For details, see the corresponding
RRU Installation Guide.
----End
Context
NOTE
The procedure for installing a non-blade RRU is the same as for installing a blade RRU. This
section uses a blade RRU as an example.
Procedure
Step 1 Install the CGPS mounting kits at the rear of the RRU and use an M6 inner
hexagon torque screwdriver to tighten the captive screws on the conversion
bracket to 5 N·m (44.25 lbf·in.), as shown in Figure 1-69.
Figure 1-69 Installing the CGPS mounting kits at the rear of the RRU
(1) Label
Step 2 Removing the rubber plugs in the mounting holes on the mounting kits, as shown
in Figure 1-70.
Figure 1-70 Removing the rubber plugs in the mounting holes on the mounting
kits
Step 3 Install the CGPS at the rear of the RRU and fasten the drawbars on the CGPS
cabinet to the card slots, as shown in Figure 1-71.
Figure 1-71 Fastening the drawbars on the CGPS cabinet to the card slots
Step 4 Use an M6 inner hexagon torque screwdriver to tighten the captive screws on the
CGPS to 5 N·m (44.25 lbf·in.), as shown in Figure 1-72.
Step 5 Install the OPM15M at the rear of the CGPS and use an M6 inner hexagon torque
screwdriver to tighten the captive screws on the conversion bracket to 5 N·m
(44.25 lbf·in.), as shown in Figure 1-73.
Figure 1-73 Installing the OPM15M conversion bracket at the rear of the CGPS
(1) Label
Step 6 Install the OPM15M at the rear of the CGPS and use an M6 inner hexagon torque
screwdriver to tighten the captive screws on the OPM15M to 5 N·m (44.25 lbf·in.),
as shown in Figure 1-74.
Step 7 Install the CGPS and RRU on the pole or wall. For details, see the corresponding
RRU Installation Guide.
----End
NOTICE
● Do not stand a CGPS upright because the radio frequency (RF) port on the
CGPS bottom cannot support the weight of the CGPS.
● Place a foam pad or cardboard under a CGPS to protect the CGPS housing from
damage during the installation.
Prerequisites
● Before you install a CGPS on a tower, the CGPS and its mounting kits are
hoisted onto the tower. For details, see 1.4.6.2 Hoisting a CGPS onto a
Tower in Independent Installation Scenarios.
● The hoist clamp on the main bracket is secured properly.
Procedure
Step 1 Determine a position for installing the mounting kits.
NOTE
Ensure that the arrows on the mounting kits are pointing up.
● Adjust the position of the nut and remove the square-neck bolt at the open end from
the slot on the auxiliary bracket.
● Slide the mounting kits onto the pole horizontally and insert the square-neck bolt into
the slot.
Step 3 Use a 16 mm (0.63 in.) M10 torque wrench to tighten the nuts to 40 N•m (354.03
lbf•in.) so that the mounting kits are secured onto the pole, as shown in Figure
1-76.
NOTICE
Tighten the nuts on the two square-neck bolts synchronously. After the main and
auxiliary brackets are secured properly, measure the spacing between the brackets
on both sides and ensure that the spacing is the same on the two sides.
Step 4 Install the CGPS onto the main bracket, as shown in Figure 1-77.
NOTE
Only the installation in standard mode is supported.
Step 5 Use an inner hexagon torque screwdriver to tighten the captive screws into the
connection eyes on the top of the CGPS conversion bracket and main bracket to 5
N•m (44.25 lbf·in.), as shown in Figure 1-78.
Figure 1-78 Securing the captive screws into the connection eyes
----End
Prerequisites
● Before you install a CGPS on a tower, the CGPS and its mounting kits are
hoisted onto the tower. For details, see 1.4.6.2 Hoisting a CGPS onto a
Tower in Independent Installation Scenarios.
● The hoist clamp on the main bracket is secured properly.
Context
Figure 1-79 shows the top view of the CGPS installed on the angle steel.
NOTICE
When the width of the narrower edges of the U-steel is less than 40 mm (1.57
in.), only the a and b modes are supported.
(1) U-steel
Procedure
Step 1 Determine a position for installing the mounting kits.
● If the CGPS is installed on a tower, determine a position for installing the
mounting kits according to the instructions in 1.4.3 CGPS Installation
Clearance Requirements.
● If the CGPS is installed on the ground, install the CGPS near the RRU. The
distance between the CGPS and ground must meet the requirements in 1.4.3
CGPS Installation Clearance Requirements.
NOTE
Ensure that the arrows on the mounting kits are pointing up.
● Adjust the position of the nut and remove the square-neck bolt at the open end from
the slot on the auxiliary bracket.
● Slide the mounting kits onto the U-steel horizontally and insert the square-neck bolt
into the slot.
Step 3 Use a 16 mm (0.63 in.) M10 torque wrench to tighten the nuts to 40 N•m so that
the mounting brackets are secured onto the U-steel, as shown in Figure 1-81.
NOTICE
Tighten the nuts on the two square-neck bolts simultaneously. After the main and
auxiliary brackets are secured properly, measure the spacing between the brackets
on both sides and ensure that the spacing is the same on the two sides.
Step 4 Install the CGPS onto the main bracket, as shown in Figure 1-82.
Step 5 Use an inner hexagon torque screwdriver to tighten the captive screws into the
connection eyes on the top of the CGPS conversion bracket and main bracket to 5
N•m (44.25 lbf·in.), as shown in Figure 1-83.
Figure 1-83 Securing the captive screws into the connection eyes
----End
Prerequisites
● Before you install a CGPS on a tower, the CGPS and its mounting kits are
hoisted onto the tower. For details, see 1.4.6.2 Hoisting a CGPS onto a
Tower in Independent Installation Scenarios.
● The hoist clamp on the main bracket is secured properly.
Context
Figure 1-84 shows the top view of the CGPS installed on the angle steel.
Procedure
Step 1 Determine a position for installing the mounting kits.
● If the CGPS is installed on a tower, determine a position for installing the
mounting kits according to the instructions in 1.4.3 CGPS Installation
Clearance Requirements.
● If the CGPS is installed on the ground, install the CGPS near the RRU. The
distance between the CGPS and ground must meet the requirements in 1.4.3
CGPS Installation Clearance Requirements.
Step 2 Install the CGPS mounting kits, as shown in Figure 1-85.
NOTE
Ensure that the arrows on the mounting kits are pointing up.
● Adjust the position of the nut and remove the square-neck bolt at the open end from
the slot on the auxiliary bracket.
● Put the CGPS mounting kits horizontally in the angle steel and insert the square-neck
bolt into the slot.
Step 3 Use a 16 mm (0.63 in.) M10 torque wrench to tighten the nuts to 40 N m
(354.03) so that the mounting kits are secured onto the angle steel, as shown in
Figure 1-86.
NOTICE
Tighten the nuts on the two square-neck bolts synchronously. After the main and
auxiliary brackets are secured properly, measure the spacing between the brackets
on both sides and ensure that the spacing is the same on the two sides.
Step 4 Install the CGPS onto the main bracket, as shown in Figure 1-87.
Step 5 Use an inner hexagon torque screwdriver to tighten the captive screws into the
connection eyes on the top of the CGPS conversion bracket and main bracket to 5
N·m (44.25 lbf·in.), as shown in Figure 1-88.
Figure 1-88 Securing the captive screws into the connection eyes
----End
Prerequisites
The hoist clamp on the main bracket is secured properly.
Procedure
Step 1 Disassemble the CGPS independent mounting kits, as shown in Figure 1-89.
(1) Main bracket (2) Square-neck bolt (3) Pole mounting kit
NOTE
The recommended height of the pole mounting kits to the ground is 1200 mm (47.24 in.)
to 1600 mm (62.99 in.). When the installation space is limited, only the following
requirement needs to be met: 1.4.3 CGPS Installation Clearance Requirements
Step 3 Drill holes at the anchor points, and insert expansion anchor bolts, as shown in
Figure 1-91.
1. Use a hammer drill with a Ф12 bit to drill holes vertically at the marked
anchor points. Ensure that the depth of each hole ranges from 55 mm (2.17
in.) to 60 mm (2.36 in.). Use a vacuum cleaner to clear the dust out from
inside and around the holes, and measure the distances between holes. If any
of the holes is beyond the acceptable range, mark a new anchor point and
drill a new hole.
NOTICE
Take proper safety measures to protect your eyes and respiratory tract against
the dust before drilling holes.
2. Tighten the expansion anchor bolts slightly and place one vertically into each
hole.
3. Use a rubber mallet to pound the expansion anchor bolts until they go into
the hole completely.
4. Tighten and then loosen the expansion anchor bolts, and remove the M10
bolt, spring washer, and flat washer in sequence.
NOTICE
After dismantling an expansion bolt, ensure that the top of the expansion
sleeve is on the same level as the wall. Otherwise, the device cannot be
installed on the wall evenly and securely.
Step 4 Install the pole mounting kits on the expansion anchor bolts, place the flat
washers, spring washers, and nuts through the expansion anchor bolts in
sequence, and then use a 16 mm (0.63 in.) torque socket to tighten the nuts to 30
N m (265.52 lbf·in.), as shown in Figure 1-92.
Figure 1-92 Installing the pole mounting kits on the expansion anchor bolts
NOTICE
Verify that the arrows on the pole mounting kits are pointing up.
Step 5 Install the main bracket onto the pole mounting kits using four M6x16 inner
hexagon screws, and use an inner hexagon torque screwdriver to tighten the inner
hexagon screws to 5 N m (44.25 lbf·in.), as shown in Figure 1-93.
Step 6 Install the CGPS onto the main bracket, as shown in Figure 1-94.
Step 7 Use an inner hexagon torque screwdriver to tighten the captive screws into the
connection eyes on the top of the CGPS conversion bracket and main bracket to 5
N m (44.25 lbf·in.), as shown in Figure 1-95.
Figure 1-95 Securing the captive screws into the connection eyes
----End
NOTE
There are two types of clips: 3-hole clip and 6-hole clip, which are described as follows:
● A 3-hole clip is shown by illustration a in the following figure. It is often used to fasten
feeders.
● A 6-hole clip is shown by illustration b in the following figure. It is often used to fasten
power cables and CPRI fiber optic cables.
(1) Cable hole for feeders (2) Cable hole for fiber optic (3) Cable hole for power
cables cables
● Cables can only be laid out under well-planned instructions. The cabling
activities of fiber optic cables are allowed only when qualified personnel and
communication facilities are available.
● Do not circle and twist cables.
● After routing a DC power cable onto the platform on a tower, route it along
the shortest path to the rails surrounding the platform, and route it along the
inside of the rails.
● After routing a DC power cable close to the equipment on a tower, use clips
to secure the power cable onto a pole or the rails surrounding the platform.
Ensure that there is no excessively long distance between the equipment and
the position where the power cable is secured.
Cabling of PGND cables
● PGND cables for a base station must be connected to the same group of
ground bars.
● PGND cables must be buried in the ground or routed indoors.
● The external conductor of the coaxial wire and the shield layer of the shielded
cable must have proper electrical contact with the metal surface of the
equipment to which they are connected.
● PGND cables and signal cables must be installed separately. A certain distance
must be reserved between them to prevent interference from each other.
● Switches or fuses must not be installed on the PGND cables.
● Other devices must not be used for electrical connections of the PGND cables.
● All the metal parts in the housing of the equipment must be reliably
connected to the ground terminal.
Cabling of E1 cables
● E1 cables must not cross power cables, PGND cables, or RF cables when laid
out. If transmission cables are laid out with power cables, PGND cables, or RF
cables in parallel, the spacing between them must be greater than 30 mm
(1.18 in.).
● E1 cables are lined up straight and bound neatly with cable ties.
● Sufficient slack is provided for E1 cables at turns.
● E1 cables must not be pressed by the door of the cabinet when routed, as
shown in the following figure.
● When coiling fiber optic cables, apply even strength. Do not bend the fiber
optic cables with force.
● Unused optical connectors must be covered with dustproof caps.
● The fiber optic cables must not be pressed by the door of the cabinet when
routed, as shown in the following figures.
Figure 1-101 CPRI fiber optic cables routed in the cabinet (1)
Figure 1-102 CPRI fiber optic cables routed in the cabinet (2)
● After routing a fiber optic cable onto the platform on a tower, route it along
the shortest path to the rails surrounding the platform, and route it along the
inside of the rails.
● After routing a fiber optic cable close to the equipment on a tower, use clips
to secure the fiber optic cable onto a pole or the rails surrounding the
platform. Ensure that there is no excessively long distance between the
equipment and the position where the cable is secured.
● Coil the excess of the fiber optic cables near the equipment on the tower
before securing the cables on the tower.
Figure 1-105
(1) PGND cable (2) CPRI optical cable (3) CGPS input power
cable
Context
The cross-sectional area of a CGPS PGND cable is 16 mm2 (0.025 in.2). The cable
has an M6 OT terminal at one end and an M8 terminal at the other end.
Procedure
Step 1 According to the actual cable route, cut the PGND cable into a proper length to
prepare a CGPS PGND cable. Then add an OT terminal at each end of the cable
according to the instructions in Assembling the OT Terminal and the Power Cable.
Step 2 Connect the M6 OT terminal at one end of the PGND cable to the ground
terminal at the CGPS bottom and the M8 OT terminal at the other end to the
external ground bar, as shown in Figure 1-107.
NOTE
When installing the PGND cable, tightly press the OT terminal in the correct direction, as
shown in Figure 1-108.
Step 3 (Mandatory in RRU, CGPS, and OPM15M mounted installation scenarios) Connect
the M6 OT terminal at the other end of the OPM15M equipotential cable to the
ground terminal at the bottom of the CGPS, as shown in Figure 1-109.
NOTE
Figure 1-109 Installing the equipotential cable and the PGND cable
----End
Prerequisites
GPS antennas have been installed according to the instructions in 1.7.1 Installing
GPS Antennas.
The 1/2 super-flexible jumper connectors on the GPS jumper for connecting to the
CGPS have been prepared according to the instructions in 1.7.3 Adding a 1/2
Super-Flexible Jumper Connector to a GPS Jumper on the CGPS Side.
Procedure
Step 1 Connect the type N connector of the GPS RF jumper to the CGPS antenna port,
and use a torque wrench to tighten the connector to 1 N·m (8.85 lbf·in.), as
shown in Figure 1-110.
Step 2 Connect the other end of the GPS jumper to the GPS antenna port.
Step 3 Waterproof the connectors of the GPS jumper, as shown in Figure 1-111.
NOTE
● Before wrapping waterproof tape, stretch the tape evenly until the length of the tape is
twice its original length.
● Do not stretch the PVC insulation tape when wrapping it.
● Wrap each layer of tape tightly and neatly, ensuring that each layer of tape overlaps more
than 50% of the preceding layer.
● Ensure that the adhesive surface of the tape overlaps the lower layer.
● When cutting off the cable tie, reserve a surplus length of 3 mm (0.012 in.) to 5 mm (0.20
in.).
1. Wrap three layers of PVC waterproof tape. Start wrapping the connector at a
position 50 mm (1.97 in.) away below the bottom of the connector to the top
of the connector, first from bottom up, then from top down, and finally from
bottom up. Cut off the redundant tape after three layers are wrapped. Wrap
each layer of tape around the connector tightly.
2. Wrap three layers of PVC insulation tape. Start the wrapping at a position 30
mm (1.18 in.) away below the bottom of the waterproof tape to the top of
the connector, first from bottom up, then from top down, and finally from
bottom up. Cut off the redundant tape after three layers are wrapped. Wrap
each layer of tape around the connector tightly.
3. Start binding cable ties to the cable at a position 3 mm (0.12 in.) to 5 mm
(0.20 in.) away from one end of the PVC insulation tape.
Step 4 Route the cable according to the instructions in 1.4.10.1 Cabling Requirements.
Step 5 Label the installed cables.
Step 6 Label the color-coding according to instructions in Attaching a Color-coding Label.
----End
Procedure
Step 1 Wear a pair of ESD gloves.
NOTICE
Take proper ESD protection measures, for example, wear ESD gloves, to prevent
electrostatic damage to the boards or electronic components.
Step 2 Use an M4 Phillips screwdriver to rotate the locking screw on the cover plate of
the cabling cavity 90 degrees counterclockwise to unlock the cover plate. Then,
pull the handle outwards to open the cabling cavity, as shown in the following
figure.
NOTICE
Do not use the electric screwdriver to rotate the locking screw. Otherwise, the
cross recess may be scratched.
(1) Cover plate of the (2) Cabling cavity (3) Cable clip
cabling cavity
----End
Prerequisites
Before the installation, single-mode optical modules can be distinguished from
multimode optical modules in either of the following ways:
● SM and MM labels on an optical module: SM indicates a single-mode
optical module, and MM indicates a multimode optical module.
● Color of the puller on an optical module: Blue indicates a single-mode
optical module, and black or gray indicates a multimode optical module.
NOTICE
The rate of the optical module to be installed must match the rate of the CPRI
port.
Context
A CPRI optical cable transmits CPRI signals between a CGPS and an BBU.
Procedure
Step 1 Lower the pullers of the optical modules, insert one optical module into CPRI 0
port on the CGPS and the other optical module into CPRI 1 port on the RRU, and
raise the pullers, as shown in Figure 1-114.
NOTICE
Step 2 Remove the caps from the CPRI optical cables. Connect the ends labeled 1A and
1B of the optical cable to the optical module on the CGPS side, as shown in Figure
1-115. Then, connect the DLC connectors labeled 2A and 2B to the CPRI port on
the BBU.
NOTICE
● Ensure that CPRI optical cables are correctly connected before powering on the
CGPS. Otherwise, the CGPS may become faulty.
● To avoid any damage to optical cables, the cables must be installed according
to the installation in 1.4.10.1 Cabling Requirements.
Figure 1-115 Installing CPRI optical cables for dual-fiber bidirectional optical
modules
Step 3 Route the cable according to the instructions in 1.4.10.1 Cabling Requirements.
Step 4 Label the installed cables according to instructions in Attaching an L-Shaped Label.
----End
Prerequisites
The DC round waterproof connectors on the CGPS power cables for connecting to
the CGPSs have been prepared according to the instructions in 1.7.2 Adding a DC
Round Waterproof Connector to a CGPS Power Cable.
CAUTION
● Before installing CGPS power cables, ensure that the upper-level circuit breaker
is disconnected, and no voltage is detected on the power cables.
● Connect the CGPS power cable to the CGPS first and then to the power
equipment. Connections in a reverse sequence or polarity reverse connections
may cause damages to CGPSs and body injuries.
Procedure
● When a CGPS is powered by an external device, the CGPS power cable
connects the external power supply device and the CGPS.
a. Align the red flag on the DC round waterproof connector on the CGPS
power cable with the red flag on the DC_IN port on the CGPS, and push
the DC round waterproof connector upwards, as shown in Figure 1-116.
The connector is properly installed when you hear click.
b. Connect the connector at the other end of the CGPS power cable to the
corresponding position on the power supply device.
c. Route the cable according to the instructions in 1.4.10.1 Cabling
Requirements.
d. Label the installed cable according to instructions in Attaching an L-
Shaped Label.
● When an RRU is powered by a CGPS, the CGPS output power cable connects
the RRU and CGPS.
a. Align the red flag on the DC round waterproof connector on the CGPS
power cable with the red flag on the DC_OUT port on the CGPS, and
push the DC round waterproof connector upwards, as shown in Figure
1-117. The connector is properly installed when you hear click.
NOTE
● Before wrapping waterproof tape, stretch the tape evenly until the length of the
tape is twice its original length.
● Do not stretch the PVC insulation tape when wrapping it.
● Wrap each layer of tape tightly and neatly, ensuring that each layer of tape
overlaps more than 50% of the preceding layer.
● Ensure that the adhesive surface of the tape overlaps the lower layer.
● When cutting off the cable tie, reserve a surplus length of 3 mm (0.012 in.) to 5
mm (0.20 in.).
c. Connect the female fast connector (pressfit type) at one end of the CGPS
power cable to the PWR port on the RRU.
d. Route the cable according to the instructions in 1.4.10.1 Cabling
Requirements.
e. Label the installed cable according to instructions in Attaching an L-
Shaped Label.
----End
Procedure
Step 1 Fasten the cables using clips, as shown in Figure 1-119.
Step 2 Insert waterproof blocks into vacant cable troughs in the cabling cavity, as shown
in Figure 1-120.
NOTICE
Ensure that cables and waterproof blocks are properly inserted into troughs.
Step 3 Push the handle to close the cover plate of the cabling cavity. Then, use an M4
Phillips screwdriver to rotate the locking screw on the cover plate of the cabling
cavity 90 degrees clockwise shown in the following figure to lock the cover plate
of the cabling cavity, as shown in the following figure.
NOTICE
● Do not use the electric screwdriver to rotate the locking screw. Otherwise, the
cross recess may be scratched.
● Tighten the cover plate of the CGPS cabling cavity to prevent water entering.
Step 4 Take off the ESD gloves and pack up the tools.
----End
8 Power cables and PGND cables are separately bound from other
cables.
10 The connectors of each signal cable are intact and securely linked,
and these cables are not damaged or broken.
NOTICE
After unpacking the CGPS, power on it within 24 hours. The power-off time for
maintenance cannot exceed 24 hours.
Figure 1-122 shows the process for checking the power-on status of the CGPS.
NOTE
For details on powering on and powering off the CGPS, see 1.6.2.1 Powering on a CGPS
and 1.6.2.2 Powering off a CGPS, respectively.
(a) The normal input voltage of a CGPS is –48 V DC. The voltage must range
from –36 V DC to –57 V DC.
(b) The RUN indicator on the CGPS is on for 1s and off for 1s. The ALM indicator
is steady off.
Context
● Only the CGPS clock source for NR can be directly connected to a UBBPfw or
UBBPg.
● In a separate-MPT scenario, the CGPS clock source cannot be shared with a
GTMUb, or GTMUc.
● If a multimode RF module is connected to two interconnected BBUs, the
mode that is configured with the CGPS clock source must be configured in the
root BBU.
Operation Procedure
NOTE
Users can configure a CGPS using by running MML commands. This section describes how
to configure the CGPS by running MML commands.
2. Run ADD CXU to add a CGPS. In this step, set parameters according to Table
1-10.
3. Run ADD GNSS to add a GPS clock link. In this step, set parameters according
to Table 1-11.
4. Run SET CLKMODE to set the reference clock work mode. You are advised to
set Clock Working Mode to AUTO(Auto).
5. Run SET CLKSYNCMODE to set the clock synchronization mode as required.
For TDD base stations, set Clock Synchronization Mode to TIME(TIME).
Follow-up Procedure
After the CGPS is deployed, perform the following operations to check whether
the CGPS is working properly:
1. Run DSP BRD to check whether the CGPS status is normal. If Availability
Status is Normal, the CGPS is normal. If Availability Status is
Communication Lost, and the CGPS is installed at the rear side of the RRU,
the CPRI rate of the CGPS may be inconsistent with that of the upper-level
RRU. In this case, you are advised to run STR CPRILBRNEG to perform a CPRI
rate negotiation.
2. Run DSP GPS with GNSS Clock No. set to that specified when the GPS clock
link is created. If GPS Card State is Normal, the CGPS satellite card is normal.
3. About 10 minutes after the base station starts, run DSP CLKSTAT to query the
clock source status. If PLL Status is Locked, the CGPS clock source is normal.
DANGER
Be cautions about falling objects if there are someone working at heights. Always
wear a helmet and avoid standing in danger area.
The items in Table 1-12 for CGPS preventive maintenance are not mandatory but
strongly recommended.
3 All GPS jumpers are free from wear, cuts, cracks, or other damage.
6 All power cables are free from wear, cuts, cracks, or other damage.
11 All CPRI optical cables are free from wear, cuts, cracks, or other
damage.
If any of the statements in the checklist cannot be complied with, perform the
following actions:
Prerequisites
● The CGPS hardware is installed and CGPS cable connections are secure.
● The input voltage of the CGPS ranges from –36 V DC to –57 V DC.
NOTICE
After unpacking the CGPS, power on it within 24 hours. The power-off time for
maintenance cannot exceed 24 hours.
Procedure
Step 1 Set the corresponding circuit breaker on the power distribution equipment for the
CGPS to ON to power on the CGPS.
DANGER
After powering on the CGPS, do not look into the optical modules without eye
protection.
Step 2 Keep the CGPS running for three to five minutes to check the status of CGPS
indicators. For details, see 1.2.5 CGPS Indicators.
NOTE
If CGPS and RRU modules are cascaded, check the status of CGPS indicators.
If... Then...
----End
Procedure
● Normal power-off
NOTE
If RRU modules are cascaded, services carried on lower-level RRUs and CGPS power supply
to RRUs may be interrupted during the power-off.
Set the corresponding circuit breaker on the power distribution equipment for
the CGPS to OFF.
● Emergency power-off
NOTICE
Power-off in an emergency may damage the CGPS, and do not use it in
normal situations.
a. Turn off the external power input equipment of the CGPS power
distribution equipment.
b. Set the corresponding circuit breaker on the power distribution
equipment for the CGPS to OFF.
----End
Prerequisites
● The type of the faulty CGPS has been confirmed using the following method:
– If the CGPS can be queried online, log in to the LMT and run DSP
BRDMFRINFO to query the CGPS electronic labels. The type of the CGPS
to be replaced can be determined according to the values of "Type" and
"Description" fields in the command output.
– If the CGPS cannot be queried online, the information about the CGPS
can be queried offline on the M2000/U2000.
● The following tools and materials are available: ESD gloves, M5 Phillips
screwdriver, M6 inner hexagon torque screwdriver, waterproof tape, and PVC
insulation tape.
● The quantity of faulty CGPSs has been determined, and the same quantity of
new CGPSs are ready.
NOTE
Procedure
Step 1 Power off the CGPS. For details, see 1.6.2.2 Powering off a CGPS.
NOTICE
During a replacement, take proper ESD protection measures. For example, wear a
pair of ESD gloves to prevent boards, modules, or electronic components from ESD
damage.
Step 3 Record connection positions of all cables between the CGPS and RRU.
Step 4 Remove all cables in the CGPS cabling cavity and at the CGPS bottom in the
sequence of power cables first and ground cables at last.
NOTE
Remove cables in the following sequence: input power cable, output power cable, GPS cable,
optical cable, and ground cable.
Step 5 Use an M6 inner hexagon screwdriver to loosen the four captive screws on the
CGPS, as shown in Figure 1-123.
Step 6 Hold the CGPS upwards to enable the CGPS to be removed from the conversion
bracket, as shown in Figure 1-124.
NOTICE
When removing the CGPS, hold the CGPS handle with one hand and hold the
CGPS upwards with the other hand.
Step 7 Install a new CGPS according to instructions provided in 1.4.8.2 Installing Blade
RRU and CGPS.
Step 8 Connect all CGPS related cables, waterproof the ports connected to the CGPS, and
verify that vacant cable troughs in the cabling cavity are equipped by waterproof
blocks.
Step 9 Close the CGPS cabling cavity. For details, see 1.4.10.9 Closing the CGPS Cabling
Cavity.
----End
Follow-up Procedure
● Put the removed CGPS in an ESD bag. Then, put the ESD bag in a carton
padded with foam or in the packing box of the new CGPS.
● Record the information about the faulty component in the fault card.
● Contact the local Huawei office to deal with the faulty components.
Prerequisites
● The type of the faulty CGPS has been confirmed using the following method:
– If the CGPS can be queried online, log in to the LMT and run DSP
BRDMFRINFO to query the CGPS electronic labels. The type of the CGPS
to be replaced can be determined according to the values of "Type" and
"Description" fields in the command output.
– If the CGPS cannot be queried online, the information about the CGPS
can be queried offline on the M2000/U2000.
● The following tools and materials are available: ESD gloves, M5 Phillips
screwdriver, M6 inner hexagon torque screwdriver, waterproof tape, and PVC
insulation tape.
● The quantity of faulty CGPSs has been determined, and the same quantity of
new CGPSs are ready.
NOTE
Procedure
Step 1 Power off the CGPS. For details, see 1.6.2.2 Powering off a CGPS.
NOTICE
During a replacement, take proper ESD protection measures. For example, wear a
pair of ESD gloves to prevent boards, modules, or electronic components from ESD
damage.
Step 3 Record connection positions of all cables between the CGPS and RRU.
Step 4 Remove all cables in the CGPS cabling cavity and at the CGPS bottom in the
sequence of power cables first and ground cables at last.
NOTE
Remove cables in the following sequence: input power cable, output power cable, GPS cable,
optical cable, and ground cable.
Step 5 Use an M6 inner hexagon screwdriver to loosen the captive screws on the
connection eyes on the top of the CGPS conversion bracket and main bracket, as
shown in Figure 1-125.
Step 6 Hold the CGPS upwards to remove the CGPS, as shown in Figure 1-126.
NOTICE
When removing the CGPS, hold the CGPS handle with one hand and hold the
CGPS upwards with the other hand.
Step 7 Install a new CGPS according to instructions provided in 1.4.9 Installing a CGPS
in Independent Installation Scenarios.
Step 8 Connect all CGPS related cables, waterproof the ports connected to the CGPS, and
verify that vacant cable troughs in the cabling cavity are equipped by waterproof
blocks.
Step 9 Close the CGPS cabling cavity. For details, see 1.4.10.9 Closing the CGPS Cabling
Cavity.
----End
Follow-up Procedure
● Put the removed CGPS in an ESD bag. Then, put the ESD bag in a carton
padded with foam or in the packing box of the new CGPS.
● Record the information about the faulty component in the fault card.
● Contact the local Huawei office to deal with the faulty components.
1.7 Appendix
This section describes procedures for installing GPS and adding a female fast
connector (pressfit type).
Context
Table 1-13 describes CGPS power cables.
NOTE
Cable color and appearance differ by country and region. If cables are purchased in the
local area, the cables are subject to goods delivered.
Procedure
Step 1 Determine the diameter of the cable to be installed. If it is greater than 14 mm
(0.55 in.), replace the clamping jaw, as shown in Figure 1-128.
● Clamping jaw 1 supports the following power cable: 2 x 12 AWG, 2 x 4 mm2,
2 x 6 mm2
NOTICE
When replacing the clamping jaw, align the boss of the clamping jaw with the
groove inside the socket to ensure that the clamping jaw is completely in the
socket, as shown in Figure 1-129.
Step 2 Maintain sufficient length in the power cable, install plastic cable ties, route the
nut, clamping jaw (with waterproof ring), and socket through the power cable,
and partially tighten them, as shown in Figure 1-130.
Figure 1-130 Routing the nut, clamping jaw, waterproof ring, and socket through
the power cable
Step 3 Strip the sheaths off the power cable with 48 mm (1.89 in.) and each core wire
with 17 mm (0.67 in.), and twist the shield layers as one, as shown in Figure
1-131.
NOTE
NOTICE
Step 4 Connect the blue (global) or gray (UK) core wire labeled NEG(-) to the "-" port on
the connector and the black/brown (global) or blue (UK) core wire labeled RTN(+)
to the "+" port on the connector. Use a Phillips screwdriver to tighten the screws
to 1.4 N·m (12.39 lbf·in.), as shown in Figure 1-132.
Figure 1-132 Connecting the core wires to the connector and tightening the core
wires
Step 5 After core wires are installed, slightly pull each cable to check whether the
connections are secure. If the cables are pulled out a bit or exposed outside the
holes, remove and cut the split wires, and then strip the sheaths and install the
cables again.
Step 6 Twist the shield layers as one, insert them in the shield layer trough, and tighten
the shield layers to 0.6 N m (5.31 lbf·in.), as shown in Figure 1-133.
NOTE
Use a pair of diagonal pliers to cut off extra part of the shield layer.
Step 7 Screw the socket and the enclosure until the red line on the socket cannot be
seen, as shown in Figure 1-134.
Step 8 Partially tighten the nut and the socket, and then use a torque wrench with an
open end of 28 mm (1.10 in.) to tighten the nut, as shown in Figure 1-135.
Step 9 Use a multimeter to test the reliability of the cable components, as shown in
Figure 1-136.
NOTICE
Step 10 If the device is installed outdoors, the connector must be wrapped with three
layers of insulation tape, as shown in Figure 1-137.
NOTICE
Do not wrap the connector with more than three layers of insulation tape.
----End
Context
NOTE
The method for making type N connectors differs by manufacturer. Make type N
connectors based on instructions.
(1) Forward socket (2) Backward socket (3) Sealing plastic ring
Procedure
Step 1 Cut feeders.
NOTE
● After cutting the feeders, ensure that the cross-section of the outer conductor is smooth,
intact, and round.
● The inner conductor of the feeder must be beveled.
Step 2 Install the heat shrink tubing and sealing plastic ring.
NOTE
----End