Operating_Manual_APL-4
Operating_Manual_APL-4
Contents
1. General ................................................................................................................. 3
6. Installation ............................................................................................................ 6
6.1. Mounting bracket ....................................................................................... 6
6.2. Mounting limit switch box ........................................................................... 6
6.3. Cam setting ................................................................................................ 6
6.4. Wiring ........................................................................................................ 7
6.5. Setting Position Transmitter Unit (APL- 4*6) ............................................. 10
7. Maintenance ....................................................................................................... 10
8. Inspection ........................................................................................................... 11
9. Storage ............................................................................................................... 11
11. Tools................................................................................................................... 11
1. General
1.1. HKC APL-4 series limit switch boxes are designed to provide accurate and reliable valve
position signalling and indicating of most valves or actuators manufactured.
1.2. APL-4 limit switch boxes consist of a visual position indicator, quick-set cam ass’y, terminal
strip, switch ass’y and easy mounting bracket. Quick-set cam allows for a quick and simple
hand operation in the setting of switches.
2. Ordering Information
APL - 4 1 0 N
① ② ③
① Enclosure type of explosion proof is based on IECEx :
Ex d IIB T6 Gb
Enclosure type of explosion proof is based on ATEX :
II 2 G Ex d IIB T6 Gb
Enclosure type of explosion proof is based on KCs :
Ex d IIB T6 Gb
Enclosure type of explosion proof is based on CSA :
Cl I, Div 1, Gr C & D T6
Cl I, Zone 1, AEx d IIB T6
Ex d IIB T6
② Switch type
Mechanical switch
10 : 2-SPDT (Wonwoo : SZM-V16-5FA-61)
11 : 3-SPDT (Wonwoo : SZM-V16-5FA-61)
12 : 4-SPDT (Wonwoo : SZM-V16-5FA-61)
13 : 2-SPST (Wonwoo : SZM-V16-5FA)
14 : 2-DPDT (Omron : DZ-10GW-1B)
15 : 2-SPDT + Potentiometer (Wonwoo : SZM-V16-5FA-61)
16 : 2-SPDT + Signal Unit(4~20mA) (Wonwoo : SZM-V16-5FA-61)
Proximity switch
20 : Proximity sensor (P&F : NJ2-V3-N)
21 : Proximity sensor (Autonics : PS17-5DNU) (Except CSA)
22 : Proximity sensor (P&F : NJ4-12GM-N)
23 : Proximity sensor (P&F : NBB2-V3)
25 : Proximity sensor + Potentiometer (P&F : NJ2-V3-N)
26 : Proximity sensor + Signal Unit(4~20mA) (P&F : NJ2-V3-N)
30 : Reed type Proximity sensor (MS-B 301)
③ Enclosure material
N : Aluminium
3. Standard specification
Model APL-4**N
Enclosure Rating Please refer to “2. Ordering Information, ① Enclosure type”
Enclosure High grade aluminium alloy
Ambient Temperature -20°C ≤ Ta ≤ +60 °C
Cable Entries Standard : Two NPT 3/4”, or M25 for Ex type
(Option for Non-Ex : NPT1/2”, PT3/4”, PT1./2”, PF3/4”, PF1/2”, M20)
Travel Angle 90 degree +/- 10%
Position Indicator Open : Yellow, Close : Red
Language : English (option : French, German)
Mechanical Switch SZM-V16-5FA-61 (Wonwoo Starion)
16A 1/2HP 125/250Vac, 0.6A 125Vdc, 0.3A 250Vdc, 5A 125Vac
Warning : Read this installation and maintenance manual carefully and completely before
attempting to install, operate, or troubleshoot the HKC product
4.2.1. Cable Connection
① Sealing devices must be used and shall be fitted directly at enclosure wall when using
conduit.
② Cable glands shall be suitable for the environment and shall be certified as flameproof if
used in Zone 1 application of IECEx scheme in order to connect outside electric wire.
③ Cable glands and conduit to be installed minimum 8 full threads and the length of thread
is minimum 8mm.
④ “Warning” : Please be sure that user should select the appropriate cable glands and
minimum 2SQ of wire for fear that the proper using temperature of cable entry and wire
way exceed 70 ℃ or the blanching point is over 80 ℃.
⑤ When cable entries or conduit entries are not used, user or installer shall close by certified
blanking elements(stopping plugs) so that the flameproof properties of the enclosure are
maintained.
4.2.2. Groundings
① Always ground the enclosure in accordance with local electric codes. The most effective
enclosure grounding method is a direct connection to earth ground with minimal
impedance. Methods for grounding the enclosure include:
Internal ground connection : The internal ground is located inside the body .
External ground connection : The ground bracket is located on the side of body.
(Min 2SQ wire required)
4.2.3. Special Condition for safe use (“X” marking)
① Electrostatic discharge from window(over 1GΩ) may cause the ignition on the explosive
gas atmosphere. By adapting the conducting window bolts make reduce the risk from
electrostatic discharge.
② Before installation or maintenance products, shut off incoming power and grounding
should be connected.
③ The window must only be cleaned with a damp cloth in order to avoid ignition hazard
caused by static electricity.
4.3. Initial inspection
When the user receipts the product, inspect the condition of the product and ensure the name
plate comparing with order sheet.
4.3.1. Remove packing wrap or wooden box carefully. Inspect the product for any physical
damage that may have occurred during shipment.
4.3.2. Check the product specification with product ordered. If a wrong product has been shipped,
immediately notify our coordinator.
5. Standard Features
5
1 6
7
2
8
9
3
10
4 11
6. Installation
6.1. Mounting bracket
Caution ; Where limit switch box or one of parts are to be moved, installed, disassembled, reassembled
by a hand, care must not be taken to cause injury by the harmful sharp edges of corners or rough
surfaces or residual electricity.
6.1.1. HKC shall supply a NAMUR VDI/VDE standards’ bracket and a fixing stuff for mounting on actuator.
Brackets are able to applied any type of valves; manual valve, linear valve, pneumatic rotary valve.
① Insure valve actuator alignment (fully open or closed).
② Place the mounting bracket on a horizontal plane of actuator
③ Tighten the bolts enclosed in a box using a proper tool.
6.3.2. Loose the captive cover bolts with an applicable tool. (L-Hex. Wrench
recommended)
6.3.3. Turn the cover counter clockwise to open carefully.
6.3.4. Open cam setting
① Electric power or air supply of valve actuator on to operate the actuator fully
open
② Lift the bottom yellow cam up and rotate it until the switch is activated.
③ And then release it. Cam shall be back into a stable position by itself.
6.4. Wiring
Danger ; HAZARDOUS VOLTAGE. No electrical power should be connected until all
wiring and limit switch adjustments have been completely.
6.4.1. Open circuit before removing cover, and seal required within 450mm (18 inch) of the enclosure by
CSA.
6.4.2. APL limit switch box enclosure feature prewired switches. All user connections are made at a
numbered terminal strip. A wiring diagram, located inside the cover, indicates which terminal
numbers correspond to switch contacts, such as normally open (NO), normally closed (NC), etc.
Follow the wiring diagram and electrical code to connect the switches to your system.
6.4.3. Solenoid valve may also can be wired through the APL enclosure. Two auxiliary terminals are
included as standard.
6.4.4. APL limit switch box has two cable entries on the body and supply a blanking plug not a cable gland
which meet the type of protection. Cable gland shall be applied by installer or user.
Note ;
Grounding should be connected until all wiring had been completely.
Internal/External grounding wire square shall be min. 2SQ recommended.
7. Maintenance
Caution ;
- Shut off incoming power or air supply on the valve actuator before maintenance limit switch box.
- Be sure that the area is clean before disassemble and maintenance limit switch box. Clean all parts
and housing before re-assemble.
- Refer to the part list when ordering replacement or spare parts.
7.1. Maintenance, under normal conditions at six month intervals or 10,000 cycle operation. But when
conditions are more severe, more frequent inspections may be required.
7.1.1. Insure valve actuator alignment
7.1.2. Insure wiring is insulated, connected and terminated properly
7.1.3. Insure all screws are present and tight
7.1.4. Insure cleanliness of internal electrical devices
7.1.5. Insure conduit connections are installed properly and are dry
7.1.6. Check internal devices for condensation
7.1.7. Check enclosure O rings seals and verify that the O ring is not pinched between housing
7.1.8. Visually inspect during open/close cycle
7.1.9. Inspect identification labels for wear and replace if necessary
Warning ;
Flameproof enclosure! Before opening, ensure the absence of gas and voltage.
Treat cover with care. Gap surfaces must not be damaged or dirtied in any way.
8. Inspection
8.1. The limit switch box should be inspected upon receipt to ensure that no damage has been sustained on
transit.
8.2. Check the item and quantity of products with packing list or related documents.
8.3. Check the limit switch box o-ring. Where damage on it, it caused the corrosion of internal parts.
8.4. Check the adjustment of cams. Cams shall be released when those have been used for a long period of
operating. If do so, they don’t work correctly with switches.
9. Storage
The products must be stored in a clean, cool and dry area. The unit shall be stored with the cover installed and
the conduit openings sealed. Storage must be off the floor, covered with a sealed dust protector.
11. Tools
① 1 Set Metric Allen Key (Hex Wrench)
② Set Screw Drivers
③ 1 Set Metric Spanner
④ 1 Wire Stripper long Nose
⑤ 1 Needle nose plier
⑥ 1 Multi Meter (AC, DC, Resistance)
⑦ 1 ohm Meter (0~25mA) : if applicable 16 adapted
Caution :
ü A regular inspection and maintenance performed by qualified and trained personnel
ü When working in potentially explosive areas, observe the standard EN 60079-14 “Electrical
Installations in Hazardous Areas”.
ü Work at the open actuator under voltage must only be performed if it is assured that for the duration of
the work there is no danger of explosion.
ü Observe additional national regulations.
12.1. Check the limit switch box visually. Ensure that no outside damage or changes are visible. The electric
connecting cables must be without damage and wired correctly.
12.2. Cable entries, cable glands, plugs etc. have to be checked for correct tightness and sealing.
12.3. Check whether Ex-connections are fastened correctly.
12.4. Take care of possible discolouration of the terminals and wires.
12.5. Check the flame path gaps of flameproof enclosures for dirt and corrosion. Since the dimensions of all Ex
gaps are strictly defined and inspected, no mechanical work shall be performed on them.
12.6. Ensure that all housing covers are handled carefully and that the seals are checked.
12.7. All cables have to be checked.
12.8. If defects which affect the safety are detected during maintenance, repair measures have to be taken
immediately.
12.9. Any kind of surface coating for the gap surface is not permitted.
12.10. When exchanging parts, seals etc. only original spare parts shall be used.
Warning ;
Flameproof enclosure! Before opening, ensure the absence of gas and voltage.