transformer methode of statement
transformer methode of statement
TABLE OF CONTENTS
1. SCOPE
2. DEFINITIONS
4. OPERATION
1.SCOPE
This procedure to clear the method of the supply, installations of
Transformer for the project.
This document details Transformer Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.
2. DEFINITIONS
PQP : Project Quality Plan
MS : Method Statement
4. OPERATION
Storage and Protection:
Pre-Installation:
Installation:
Before the transformer will be delivered to site, ensure that the transformer
railing is fixed as per approved drawings.
prior start of installation Check civil work of transformer room according to
civil check list and record any comments by official mail or report.
Make visual inspection for panels (MDB , PF , RMU) according to packing
list ( housing, selectors , fuses ,voltage indicators and indication lamps
internal cable status ,internal cable labels , energy meters ,
heaters ,panels labels) and make sure that there is no damage in its body.
Move the transformers from the designated off-loading area or storage
area using forklift and set them in position near to the transformer room.
Make sure that the orientation of the transformer with regards to the
position of cable entries is correct.
Set work permit to start work.
Push in the transformers inside the transformer room. Set the transformer
on their final positions and make sure that they are properly secured and
protected.
Check wheels and its locking after locating the transformer.
Install RMU, MDB and P.F panels according to approved arrangement
and adjust its level.
Fix panels with anchor bolts and start cable termination for the
transformer, RMU and bus way for MDB.
Ask for manufacturer's site visit to check installation of bus way as its ready for
commissioning and energize.
Raise Request for Inspection of equipment’s Installation to QC.
Conduct on site test for the transformer.
Test shall include winding insulation resistance test and shall conform to
manufacturer’s recommendation and specification.
All tests must be recorded and conducted in the presence of Consultant
by manufacturer testing engineer.
Dress and terminate the incoming and outgoing cables on the
transformers.
Ensure that the cables were supported properly.
Cable glands, lugs and termination kits shall be approved type.
After termination works has been completed, clean the transformer cable
box and ensure that it is free from foreign materials and excess openings
must be sealed off and ensure that all the connections are properly tight
and torque.