transformer methode of statement

Uploaded by

KAREEM NADER
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
16 views

transformer methode of statement

Uploaded by

KAREEM NADER
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Construction department (madkour projects)

Transformer Room Method of statement

 TABLE OF CONTENTS

1. SCOPE

2. DEFINITIONS

3. HEALTH AND SAFETY

4. OPERATION

5. INSTALLATION AND FIXATION

1.SCOPE
 This procedure to clear the method of the supply, installations of
Transformer for the project.
 This document details Transformer Installation:
1. Preparation of work.
2. Delivery and inspection upon arrival of material at site.
3. Installation of the system.

2. DEFINITIONS
PQP : Project Quality Plan

PSP : Project Safety Plan

QCP : Quality Control Procedure

HSE : Health, Safety and Environment

MS : Method Statement

ITP : Inspection Test Plan


Construction department (madkour projects)

QA/QC : Quality Assurance / Quality Control

WIR : Work Inspection Request

MIR : Material Inspection Request

3. HEALTH AND SAFETY


 Strictly followed as per the manufacturer's Health and Safety
recommendations for handling and use of the materials.
 Ensure all involved personnel shall be aware of the risks and the steps to be
taken to mitigate any hazards or unsafe situations.
 Specific safety measures must follow as applicable, and all the safety
measures are covered separately in the project safety plan.

4. OPERATION
 Storage and Protection:

 Deliver components to site, completely identified in accordance approved


Drawings prepared for this work.
 Store in accordance with the manufacturer’s instructions, above ground,
properly protected from the weather and construction activities.

5. INSTALLATION AND FIXATION


 Off-Loading:
 Use Forklifts or Mobile Crane to off-load the transformers.
 Make sure that the capacity of the forklifts or mobile crane can carry the
weight of the transformers.
 Off load the transformer on the designated offloading area.
 Proper care must be observed during offloading to prevent unnecessary
damage or dents on the transformers.
 Ensure that the transformers are properly protected and covered with
tarpaulin.

 Pre-Installation:

 All consumable materials, documentation, manuals and drawings relevant


to this section of works shall be checked by the Construction Department
prior to the begin of works ensuring that these are correct and approved
type.
 Before any permanent works will continue, pre-inspection on all materials,
tools and access for installation to be carried out.
Construction department (madkour projects)

 Installation:

 Before the transformer will be delivered to site, ensure that the transformer
railing is fixed as per approved drawings.
 prior start of installation Check civil work of transformer room according to
civil check list and record any comments by official mail or report.
 Make visual inspection for panels (MDB , PF , RMU) according to packing
list ( housing, selectors , fuses ,voltage indicators and indication lamps
internal cable status ,internal cable labels , energy meters ,
heaters ,panels labels) and make sure that there is no damage in its body.
 Move the transformers from the designated off-loading area or storage
area using forklift and set them in position near to the transformer room.
 Make sure that the orientation of the transformer with regards to the
position of cable entries is correct.
 Set work permit to start work.
 Push in the transformers inside the transformer room. Set the transformer
on their final positions and make sure that they are properly secured and
protected.
 Check wheels and its locking after locating the transformer.
 Install RMU, MDB and P.F panels according to approved arrangement
and adjust its level.
 Fix panels with anchor bolts and start cable termination for the
transformer, RMU and bus way for MDB.
 Ask for manufacturer's site visit to check installation of bus way as its ready for
commissioning and energize.
 Raise Request for Inspection of equipment’s Installation to QC.
 Conduct on site test for the transformer.
 Test shall include winding insulation resistance test and shall conform to
manufacturer’s recommendation and specification.
 All tests must be recorded and conducted in the presence of Consultant
by manufacturer testing engineer.
 Dress and terminate the incoming and outgoing cables on the
transformers.
 Ensure that the cables were supported properly.
 Cable glands, lugs and termination kits shall be approved type.
 After termination works has been completed, clean the transformer cable
box and ensure that it is free from foreign materials and excess openings
must be sealed off and ensure that all the connections are properly tight
and torque.