Network Problem Objection (1)
Network Problem Objection (1)
R:Sweeks R 5 weeks
UPdatec
S=2 week5 aT:6weeks Netuok 5=2 weeks
T =6weeks
WITH
PERT
AND
CPM
Dr. B.C.PUNMIA
K.K.KHANDELWAL
PROJECT PLANNING AND CONTROL
WITH
PERT
AND
CPM
By
Dr. B.C. PUNMIA
B.E. (Hons.), M.E. (Hons.), Ph.D.
Formerly,
DEAN FACULTY OF ENGINEERING
M.B.M. ENGINEERING COLLEGE,
JODHPUR
AND
KK, KBANDELWAL
B.E. (Hons.), I.A.S.
The critical path for the network of Fig. 8.6 is shown by thick
lines in Fig. 8.16, along with the activities start and finish times
marked.
T¹= 10
=8 KEY
Description (EST ;EFT),
Duration (LST ; LFT)
10)
18)
A ( O
12(D(1208:;2B;44)0)
(18;26) 10:18) 4;40))
T¸ = 40
T=0
(21:03 18
G(18;26)
8(18; 26)
Te=26
(9
T
I(26;34)
10(30 ;40)
26 s4:40)
T= 40 Te= 52
K(40;52)
12(40; 52)
8
T= 52
TË=0 18) 18)
6(12;
E(12;