Project No._________________________
Complete a general review of the plans, proposals and cross Project Manager
5 F F sections and review project site. and/or Inspector
Obtain a copy of the CMS materials report from the Office Project Manager
6 F F Coordinator or CMS Technician. and/or
Bookkeeper
Format disks to be used for data transfer to the area machine and Project Manager
8 F F daily backup, (M,W,F)(T,Th,S). and/or
Bookkeeper
Review the CMS Materials Report and mark material items Project Manager
9 F F which will not be required
Review the CMS Materials Report for basis of acceptance of Project Manager
10 F F primary and component materials.
259 & Send a letter to the successful bidder to advise him who to Office
260 contact to schedule preconstruction conference, include copies of
12 F F breakdown of trade wages. Include copies of KDOT forms no.
259 and 260, request for approval of subcontractors.
13 F F
14 F F
1
Required Submittals from Contractor
(Office will give copies to the Project Manager)
2
Preconstruction Meeting
3
Project Started
Submit for approval contractor borrow and/or waste areas, (cross section if Project Manager and/or
1 F F applicable.) Inspector
At least one month before construction of drilled shafts insure that the Project Manager and/or
2 F F contractor has submitted a drilled shaft installation plan. Inspector
Sample soil from borrow area and submit to regional materials lab for Project Manager and/or
3 F F standard proctor & atterburg limits. Inspector
Enter all test results and pay quantities (at a minimum of weekly.) Project Manager and/or
4 F F Inspector
Insure that all survey information is turned in to meet specification which Project Manager and/or
5 F F should include that the section corners have been referenced Inspector
6 F F 258 Check with CMS technician /Office Coordinator to insure that notice to
proceed has been issued.
Project Manager
Check with CMS technician/Office Coordinator to insure that all Project Manager
7 F F subcontractors for the project have been approved.
8 F F 258A Notify the CMS technician/Office Coordinator of work starting this date,
same day work begins. Notice of Work Starting
Project Manager
7 days in advance of the work, submit any information concerning road Project Manager and/or
9 F F closures, lasting for more than one day to the Construction Office. Inspector
Submit daily to the Construction Office: Lane closures or traffic control Project Manager and/or
1 F F changes for the next days work prior to 3:30 PM. Inspector
Submit Bi-monthly: Data transfer disk containing template data, which has Project Manager and/or
12 F F been checked against field books for contractor pay estimates. Bookkeeper
Check contractor bulletin board to insure conformance with special Project Manager and/or
13 F F provisions. Inspector
Videotape designated haul roads that were submitted at the preconstruction Project Manager and/or
14 F F conference. Inspector
Check to insure that the contractor has submitted an information sheet Project Manager and/or
15 F F (information on surveyor) to the office. Inspector
Check certified payrolls weekly for both the Prime and sub-contractors. Project Manager and/or
16 F F Inspector
18 F F 209 Conduct wage rate interviews, one per quarter, per contractor or sub-
contractor.
Project Manager and/or
Inspector
4
Enter test reports, as certifications are received, of materials used to complete Project Manager and/or
19 F F the Contract Materials Report Final. Inspector
Review Contract Materials Report @25%, 50%, 75%, or 20%, 40%, 60% Project Manager and/or
20 F F complete to insure that it is accurate and up to date. Inspector
Submit as required: verification samples, i.e., Lime, Thermo plastic fly ash, Project Manager and/or
22 F F pavement marking beads, re-steel, cement, ect. Inspector
Begin a punch list for items requiring the contractor’s attention at the end of Project Manager and/or
24 F F phase or completion of project. Inspector
Record the completion date of pavement marking installation. Project Manager and/or
25 F F Inspector
27 F F 232 Have the project reviewed by the Engineer for issuance of Notice of partial
acceptance or, Notice of Acceptance.
Project Manager
28 F F 290 Submit form no. 290 for all accidents in the work zone. Project Manager and/or
Inspector
Check the percent of work completed against the percent of time completed. Project Manager and/or
29 F F See sect. 108.04, Std. Spec. Inspector
Check on QC/QA price adjustment during the contract. Project Manager and/or
3 F F Inspector
32 F F 242B
242C
or Check smoothness recap when complete. Project Manager and/or
Inspector
On projects with full federal oversight the FHWA must be notified of major Office and Project
34 F F changes in contractor. Manager
Deduct liquidated damages as soon as incurred, with approval of the Bureau Project Manager and/or
35 F F of Construction and Maintenance. Inspector
36 F F
37 F F
5
Finaling the Project
Establish the final quantities for each contract item. Project Manager and/or
1. F F Inspector
Enter comment into field documentation for all lines that are zeroed by Project Manager and/or
2. F F change order. Inspector
Write final change orders for the project based on final quantities and Project Manager and/or
3. F F submit to Construction Office. Inspector
292 Complete Price adjustment for Bituminous material on project. (IF Project Manager and/or
4. F F QC/QA project only need this form for the Commercial Grade Material, Inspector
i.e.: Class A or Class B)
Insure that the computations and recaps are submitted with the change Project Manager and/or
5. F F orders. Inspector
Balance Materials Report Final based on final change order quantities. Project Manager and/or
6. F F Inspector
Insure that the contractor has submitted all staking notes per Std. Spec. Project Manager and/or
7. F F Inspector
Pay final estimate quantities at the time of change order approval. Project Manager and/or
8. F F Inspector
Review pavement marking at the end of the 180 day evaluation. Project Manager and/or
10. F F Inspector
12. F F Std.
77
Std. Form no. 77, Tax exempt projects Office
6
When 657 form from the District Engineer is received, archive the Office, Project Manager &
22. F F project off of the area machine and submit files and field books to the Bookkeeper
district office.
7
COMPLETION OF PROJECT
1. 299 Forms 299 shall be submitted when all items are Office
F F complete.
2. 235 LPA Projects – Complete Project Related Items Checklist LPA Coordinator
F F
5. F F
6. F F