Sche Dulling
Sche Dulling
Scheduling is used to find the basic start date and basic end date of
the Production order.
Scheduling is performed when Mrp run takes place and it find the
Procurement date of a material Procured externally and Production
date of an in-house material.
When material is procured externally it calculate the Purchasing
time, vendor lead time and goods receipt processing time.
When material is made in-house there are two scheduling methods.
First is basic scheduling and second is lead time scheduling.
BASIC SCHEDULLING -BASIC scheduling is done only for Planned
Orders. BASIC scheduling only Calculate the Inhouse Production Date
for inhouse material and Planned delivery time for externally
Procured Materials.
Inhouse production date can be dependent to lot size and also can be
Independent to lot size.
For lot size dependent to lot size, we maintain in work scheduling
view
BACKWARD SCHEDULING: