Activity-based Costing Worksheet- answers 2
Activity-based Costing Worksheet- answers 2
08 (1) OF
Avoids apportioning overheads using a basis that may not be relevant. e.g. machine hours
for administration costs (1)
More realistic / fair (1)
Considers batch sizes which are ignored by absorption costing. (1)
It charges each product with an accurate cost based on its use of an activity (1). (cost driver)
(1)
If the activity(cost driver) changes then the relevant effect on the cost can be assessed so
costs are controlled (1). eg how much will costs increase if there is another batch run? (1)
Helps to set a selling price (1)
Expensive costs may be outsourced (1)
Drawbacks
ABC is often of little benefit if there is only one product (1) because the overhead cost per
unit will be the same. (1)
There are still cost pools that are not caused by one particular cost driver (1) but by several
e.g. marketing (1)
This method may be time consuming (1) and require a specialist (1) to collect the data, which
will be more expensive (1)
The costs for implementing such a system for a small business often outweigh the benefits
(1)
The level of accuracy may be immaterial for management decisions (1)
[Total: 25]
6 (a) (i) A cash budget deals with the future whilst a statement of cash flows deals with historic
data (1).
A cash budget does not deal with non-cash items whereas a statement of cash flows
does, e.g. depreciation (1)
A cash budget is an internal document whilst a statement of cash flows is published. (1)
Max (1) [1]
(ii) Identify and solve cash flow problems (1). E.g. avoid overdrafts
Identify possible investment opportunities for surplus cash (1).
Control of cash (1)
Plan timing of expenditure (1)
Co-ordination and communication of departmental cash needs (1)
Motivates staff to achieve departmental objectives (1) Max 2 [2]
© UCLES 2016
9706/31 Cambridge International AS/A Level – Mark Scheme May/June 2017
PUBLISHED
Question Answer Marks
Machine hrs
Product X 10 000 units × 2.5hrs = 25 000
Product Y 14 000 units × 0.5 hrs = 7 000
32 000
Overhead costs
$264 000
Machine maintenance costs 32 000 = $8.25 Per machine hour (1)OF
$54 000
Ordering costs = $675 Per order (1)
80
$24 000
Production run costs = $500 Per set up (1)
48
Product X Product Y
$ $
Machine hrs 25 000 × $8.25 206 250 7000 × $8.25 57 750 (1) OF both
Orders 20 × $675 13 500 60 × $675 40 500 (1) OF both
Production runs 12 × $500 6 000 36 × $500 18 000 (1) OF both
225 750 116 250
$ $
Overhead cost 22.58 (1of) Overhead cost 8.30 (1)OF
9706/31 Direct cost +Cambridge
100.00International AS/A Level
Direct cost + – Mark Scheme
50.00 May/June 2017
Full cost per unit 122.58 PUBLISHED
Full costLevel
per unit 58.30 (1) OF both
9706/31 Cambridge International AS/A – Mark Scheme May/June 2017
Question
© UCLES 2017
PUBLISHED
Answer
Page 14 of 16 Marks
3 Question
6(b) Answer
Product X Product Y Marks3
$ $
6(b) Product X
9.00 (1) OF Product
18.00 Y
(1)OF 3
Direct labour hour basis $342 000
= $12 / hr × 0.75 $
× 1.50
$
Direct
Direct labour
labour hours
hour basis 28 500000
$342 (1) 9.00 (1) OF 18.00 (1)OF
= $12 / hr × 0.75 × 1.50
Direct labour hours 28 500 (1)
6(c) If he uses ABC 4
4 6(c) If he uses ABC
• The cost of X increases. }
4
• The cost of Y decreases. (1) both
• The cost of X increases. }
• Thelabour
Direct cost of Y decreases. (1) both
hours
Direct labour hours
• Based on direct labour hours. Product Y has 2 times more hours per unit than product X. Therefore two times more share
of overhead costs. (1)
• Based on direct labour hours. Product Y has 2 times more hours per unit than product X. Therefore two times more share
ABCof overhead costs. (1)
ABC
• X has less set ups and orders than Y so takes less share of overhead costs (1)
• X has more machine hours than Y so takes larger portion of machine based overheads (1)
• X has less set ups and orders than Y so takes less share of overhead costs (1)
• The largest overhead costs are machine maintenance costs. The cost driver is machine hours, X has five times more
• X has more machine hours than Y so takes larger portion of machine based overheads (1)
hours per unit than Y so gets the largest portion. (1)
• Max
The largest
3 overhead costs are machine maintenance costs. The cost driver is machine hours, X has five times more
9706/31 Cambridge
hours per unit than Y so gets the International
largest portion. (1) AS/A Level – Mark Scheme May/June 2017
Max 3 PUBLISHED
Question Answer Marks
5 6(d) ABC 6
$ unit
Full cost 122.58
Mark-up 40% 49.03
Selling price 171.61 (1)OF
X 50 units
Order price $8580.50 (1)OF
Advice
© UCLES 2017 Page 15 of 16
• Ahmed should reject the offer as the offer price ($8450) is less than his required price. (1)
© UCLES 2017 • Ahmed still makes profit (1) Page 15 of 16
• May be able to build relationship with customer / further orders (1)
• Ensures work force is not idle / spare capacity (1)
Total: 25
Advice
• Ahmed should reject the offer as the offer price ($8450) is less than his required price. (1)
• Ahmed still makes profit (1)
• May be able to build relationship with customer / further orders (1)
• Ensures work force is not idle / spare capacity (1)
6(f) [1 mark
Cost for–decision
driver + 1 max
the separate method
activities + 1 max
of each non-financial
department. (1) + 2 max for comparison A versus B] 2
Cost pool – an account collecting the cost of each activity. (1)
12 9706/31
6(f) Cost driver – the separate activitiesCambridge International
of each department. (1) AS/A Level – Mark Scheme May/June 2018 2
PUBLISHED
Cost pool – an account collecting the cost of each activity. (1)
9706/31 Cambridge International AS/A Level – Mark Scheme May/June 2018
Question PUBLISHED
Answer Marks
13 Question
6(a)(i) Answer
Alpha Omega Marks3
$ $
6(a)(i) Direct materials Alpha
2 000 000 Omega
968 000 3
Direct labour $
480 000 $
48 000
Direct materials
Overheads 2 000
330 000
000 968
66 000
000 (1)
Direct labour
Total production costs 2 480
810 000
000 (1) 48 000
1 082 000 (1)
Overheads 330 000 66 000 (1)
6(a)(ii) Cost per unit $140.5 Total production
$135.25 (1) costs 2 810 000 (1) 1 082 000 (1) 1
6(a)(ii)
6(b) Cost per unit $140.5 $135.25 (1) $ $ 1
2
Cost per unit 140.50 135.25
14 6(b) Add 50% $70.25 $67.63 (1) OF both 2
Costper
SP perunit
unit 140.50
210.75 135.25
202.88 (1) OF both
Add 50% 70.25 67.63 (1) OF both
6(c) SP per unit
It is not possible to attribute all costs to activities. (1) 210.75 202.88 (1) OF both 2
6(c) It is not additional
It takes possible tocosts
attribute all usually
(1) as costs tospecialist
activities.employees
(1) are required (1) or extensive training may be required. (1) 2
It takes
It is additional
expensive costs (1)implement
to develop, as usually and
specialist employees
maintain. (1) are required (1) or extensive training may be required. (1)
© UCLES 2017 It
2 is
× 1expensive to develop,
mark for any two validimplement and maintain. (1)
disadvantages Page 14 of 14
It takes
It is additional
expensive costs (1)implement
to develop, as usually and
specialist employees
maintain. (1) are required (1) or extensive training may be required. (1)
20
© UCLES 2018 Page 18 of 18
6(a)(i) Alpha Omega 3
$ $
Direct materials 2 000 000 968 000
Direct labour 480 000 48 000
Overheads 330 000 66 000 (1)
Total production costs 2 810 000 (1) 1 082 000 (1)
6(b) $ $ 2
Cost per unit 140.50 135.25
Add 50% 70.25 67.63 (1) OF both
SP per unit 210.75 202.88 (1) OF both
It takes additional costs (1) as usually specialist employees are required (1) or extensive training may be required. (1)
6(d) Total 4
Overhead Alpha Omega
$ $ $
Machine set-up 90 000 54 000 36 000
Materials handling 80 000 24 000 56 000 (1)
Machine maintenance 46 000 26 000 20 000
Product inspection 180 000 120 000 60 000 (1)
396 000 224 000 (1) OF 172 000 (1) OF