3. Planning and Scheduling (1)

Uploaded by

Shubham Sarthak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
11 views48 pages

3. Planning and Scheduling (1)

Uploaded by

Shubham Sarthak
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 48

INDIAN INSTITUTE OF TECHNOLOGY ROORKEE

CEN 411
Construction Planning and Management

Planning and Scheduling

Prof. Anjaneya Dixit


Room 331A;
[email protected];
+91 133228 5106
Planning & Scheduling

CONSTRUCTION PLANNING & MANAGEMENT

BASICS; PROJECT PHASES, PROJECT DELIVERY CONSTRUCTION LABOR: TYPES, PRODUCTIVITY,


SYSTEM, PROJECT TEAM MULTISKILLING & SOCIAL ASPECTS

PROJECT PLANNING AND SCHEDULING:STEPS CONSTRUCTION MATERIAL: MANAGEMENT,


FOR BAR CHART, IMPORTANCE, GANTT CHART PROVISIONING STEPS, INVENTORY

CRITICAL PATH METHODS: PROJECT PLANNING, CONSTRUCTION EQUIPMENT: ACTUAL OUTPUT,


EVENT TIMES, CRITICAL PATHS, ACTIVITY TIES, IDENTIFICATION, EMPLOYMENT COST,
ACTIVITY FLOATS ACQUISITION OPTIONS, FILED VISITS

PERT TECHNIQUE: UNCERTAINTY, PROJECT QUALITY CONTROL:TOTAL QUALTY CONTROL,


PLANNING, PROBABILITY OF COMPLETION ISO 9000, INSPECTION, QUALITY ASSURANCE
PROGRAM, RISK CONTAINMENT,

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 2


Planning & Scheduling

• If you estimate or manage construction, you must plan and


schedule.

• Project planning serves as a foundation for several related


functions including estimating, scheduling and controlling. Planning
involves the process of selecting the one method and order of
work to be used on a project from among all the various methods
and sequences possible.

• Scheduling is the determination of the timing and sequence of


operations in the project and their assembly to give the overall
completion time.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 3


Planning & Scheduling
• Stages of project planning: Pre-tender, Pre-construction and detailed
construction planning
• Process of development of plans and schedules: work break-down
structure, activity lists, assessment of work content, estimating
durations, sequence of activities.
• Planning techniques: Bar charts, Networks: basic terminology, types,
advantages
• Formulation and analysis of CPM networks (AOA , AON and precedence
networks)
• Formulation and analysis of PERT networks.
• Resource Scheduling- resource constraints and conflicts, resource
aggregation, allocation, smoothening and levelling, calendaring
networks.
• Other schedules derived from project schedules
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 4
Objectives of Planning

“To work out a BASE plan and different schedules to


achieve target completion with profit maximization”

To estimate in advance (in practical and feasible manner)


• Material required: Type, Quantity, Time of delivery
• Equipment requirement : Type, Quantity, Time
• Labour Requirement :- Type, Quantity, Time
• Financial requirements (Estimated cash flow)
• Duration estimation
• Feasibility studies (ex. Economic evaluation)

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 5


Stages of Planning
1) Preplanning: (Owner and Consultant)
• Scope and objective definition
• Feasibility
• Alternative
• Financial requirements
• Economic analysis

2) Detailed Planning
• Design, Estimate, Contract :- (Owner & consultant)
• Construction Planning ( Contractor -at HO)

3) Monitoring and controlling Schedules


• Contractor in consultation with Consultant - at site

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 6


Planning Example

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 7


Need for Scheduling ?

• Owner
– Owner Requirement
– Monitor and measure progress
– Communication of the construction plan
• General Contractor/Sub-Contractors/Supervisor
– Establish production goals
– Manage Changes
– Communication of the construction plan

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 8


Importance of Planning & Scheduling

Failure to plan and schedule leads to


• Excessive labor cost,
• Equipment waiting time,
• Delays, waiting for materials,
• Lack of coordination, and management inability to react to
unexpected events (weather, equipment breakdowns, shortages)
• Productivity Loss

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 9


Types of Schedules

• Bar Chart
– Often called Gantt Chart

• Network Diagrams
– Arrow Diagram
– Precedence Diagram
– Often called Critical Path Method (CPM)

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 10


Formats of Schedules

• Summary schedule
– Shows major work elements, such as Design, Civil,
Electrical, commissioning
– Work should be broken down into activities that
comprise not more than 5% of total project
• Short-interval schedule
– Identifies work for upcoming 2-3 weeks
– Usually prepared by superintendent (Junior or
Assistant Engineers)

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 11


Bar Chart

• Graphical description of a project consisting of


well-defined collection of tasks
• Developed by Henry Gantt around 1900 to deal
with complex activities.
• Consists of two coordinates, the horizontal
represents the time elapsed, and the vertical
represents the job or activities performed.
• The jobs or activities are shown in the form of
bars.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 12


Bar Chart

• Length of the bar shows the time the job or that


activity takes for completion
• In every project, jobs can overlapping, mutually
exclusive or mutually dependent
• Hence, some of the bars run parallel or overlap
each other time-wise and some run serially with
one bar beginning after another bar ends.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 13


Bar Chart

 Activities A and B can start simultaneously and proceed concurrently


 Activity C begins 5 days after the start of activity A and B.
 Activity D cannot be started until activity B is over.
 The bars representing B and D therefore run serially.
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 14
Steps to Construct a Bar Chart

• Identify Activities
• Estimate Activity Duration
• Develop Activity Sequence
• Construct Bar Chart

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 15


1. Identification of Activities

• Use the Work Breakdown Structure (WBS) from the


cost estimate
• Add activities as necessary
• Rule of thumb: no activity should comprise more the
5% of the total scope of work
• Rule of thumb: Activity duration should range from 1
day to 15 days

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 16


17

1. Identification of Activities

Work breakdown structure


• Splitting the total scope of the project work into hierarchical
work breakdown levels (sub-projects, tasks, work packages,
activities)
• Each activity with its duration and resources forms the
database for planning, scheduling and monitoring of the
project.
• How many activities in a Project?
– Too large: Complexity and cost of planning increases
– Too small: Impossible to develop realistic schedules and resource
allocation.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 17


1. Identification of Activities

Work breakdown structure

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 18


1. Identification of Activities

Work breakdown structure


 Hierarchical organization of a system – Continued until sub-
system is reduced to a manageable unit.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 19


1. Identification of Activities

Work breakdown structure


It forms the basis for,
• Defining the scope of work,
• Identifying activities,
• Scheduling the work-logic,
• Structuring the organization,
• Assigning responsibilities,
• Estimating costs,
• Codifying systems,
• Organizing data and
• Analyzing the sources of risks.
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 20
2. Estimate Activity Duration

How to estimate duration:


– From company’s historic records
– From asking superintendent or foreman
– From standard estimating guide
– From calculation using the Labor Hour
Productivity equation

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 21


2. Estimate Activity Duration

Labor-Hour Productivity Method

– Total labor-hours required for an activity =


(labor-hours /Unit) x no. of units
total labor hours
Total days = labor-hours / day

total labor hours


Total days = crew size x hrs/day

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 22


2. Estimate Activity Duration

Find the duration (days) of an interior and exterior painting


activities with quantities of 4488 m2 and 3378 m2
respectively, using crews of 11 m2/hour and 14 m2/hour for
the interior and exterior painting activities respectively.
Assume three shifts of 8-h for each activity.

Solution
Interior painting duration = 4488 / 24x11 = 17 days
Exterior painting duration = 3378 / 24x 14 = 10 days
Total work hours = 27 days

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 23


3. Establish the Sequence of Work

• Need to consider the relationships between activities.

• There are four types of relationships:


– Physical: Exists between two or more activities when one
cannot start until another is partially or totally complete

– Safety: Exists when simultaneous performance of two


activities can result in a safety hazard

– Resource: Due to limited resource availability, two activities


may not be able to use a resource at the same time

– Preferential: How the contractor wishes certain activities to


be sequenced

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 24


Example: Bar Chart

Final Design & Work Order for a Building

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 25


Example: Bar Chart
Activity Description Time for Completion
(Weeks)
A Site Surveys 4
B Detailed Design 6 Establish
C Preparation of Drawings 3 Sequence
D Tender Documents Preparation 2
E Tendering 4
F Selection of Contractors 1
G Award of Work Order 1

Which activities can overlap?


• A&B
• B&C
• C&D
• None
What would be the minimum time of completion ?
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 26
Example: Bar Chart

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 27


Example: Bar Chart

Immediate Estimated
Activity Preceding Completion Time
A None 90
B A 15
C B 5
D G 20
E D 21
F A 25
G C,F 14
H D 28
I A 30
J D,I 45

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 28


Example: Bar Chart
90 115
90
A 129
15
B 5 149
194
C 20
D Immediate Estimated
Activity
A
Preceding
None
Completion Time
90
21
E B A 15
25
C B 5
D G 20
F E D 21
F A 25 14
G C,F 14
G H D 28
I A 30 28
J D,I 45
H
30
I 45

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 29


Example Bar Chart-Culvert

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 30


Example Bar Chart-Culvert

Time

June July August September October


Excavation & 20 7
Backfill
10
Pilling

Abutment No. 1 13

Abutment No.2 10

Steel girder
6

Concrete Deck 30
Finishing
Operations 15

20 + 13 + 7 + 6 + 30 + 15 = 91 days
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 31
Advantages of Bar Chart

• Visual representation of entire project


– Information about a project in one central location
– See a project’s progress clearly
• Easy communication:
– Simple to construct, read and interpret
– Stay forward and quick status updates
• Straight forward communication of a network schedule
• Progress management
– Manage time and resources more efficiently
– Quantifiable measure
• Easily produced by all scheduling software

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 32


Disadvantages of Bar Chart

• Can Be Overly Complex


– Work best for simpler projects
– Stretch to multiple pages and loses some of its functionality
• Need to Be Constantly Updated:
– Updating multiple activities
– Cascading effect on following tasks
• No information on quantum of work done/remaining
– Focus of a Gantt chart is time
– No information on quantity of work/resources to complete a task
– Length of bar bears no direct relation with amount of work
• Lack of clarity on activity interdependencies
– Overlap does not necessarily mean interdepence

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 33


Interdependencies of Activities

No interrelationship: If A is delayed by 1 week, what happens to B & C?


Cannot be clearly portrayed

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 34


Project Progress

• The bar chart does not indicate the progress of work


• It cannot be used as a control device
• In a dynamic programming, knowledge of the amount of
work in progress or work completed is very essential
• Usual changes in plans are a necessary part of a large
project and a bar chart does not give much assistance
under such circumstances.
• However, a conventional bar chart can be modified to
give this additional information.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 35


Project Progress

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 36


Monitoring Project Progress
90
A 15
B 5 194
C 20
D
The shaded bars represent
194
E
completed work BY DAY 135. 21
25
F Immediate Estimated
Activity Preceding Completion Time 14
A None 90
G B
C
A
B
15
5
28
D G 20
H E D 21
F A 25 30
G C,F 14
I H D 28 45
I A 30
J D,I 45
J

135
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 37
Time Uncertainties

• Only one time for the completion of project:


– Sometimes uncertainties in determination of Project.
(No pessimistic and optimistic times)
– Can be used for conventional projects with set times
but not for complex R & D Projects.
– Only projects with Fair degree of certainty

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 38


Time Uncertainties

• Bar Charts cannot reflect uncertainty, or tolerances in the


duration of times estimated for various activities
• There are a number of uncertain activities, such as
modern-day space programme, or complex research
projects largely characterized by extensive research,
development and technological progress.
• In such programmes, the completion of various stages of
jobs cannot be forecasted with exactness.
• In these programmes, rescheduling of various events is a
necessary part of the project but this is not reflected by a
bar chart.
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 39
Lack of Degree of Details

No details of sub activities in any activity. Lack in achieving


the effective control
(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 40
Milestone Charts

• Milestones are key events or points in time which can be


identified when completed as project progresses
• A bar, which represents a long-term job is broken down to
several pieces
• Each piece stands for an identifiable major event which is
numbered.
• This work breakdown increases the awareness of the
interdependencies between the tasks.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 41


Milestone Charts

• A milestone is used to represent groups of activities or


significant events or commitments in the project.
• Milestones differ from the bars in a Gantt chart in that
they show only a single date and are usually depicted as a
triangle/square/circle instead of a bar.
• Milestones can be shown in various colours depicting the
status of the milestone.

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 42


Milestone Charts

Task A

Task B

Task C

Task D

Task A 1 2

Task B 3 4 5

Task C 6 7

Task D 8 9 10

1.0 2.0 3.0 4.0

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 43


Additional information may be added to the basic
bar chart
– Cost of activity (“cost-loaded schedule”)
– Labor required for each activity (“man-loaded”)
– Materials required for each activity (“resource-
loaded”)

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 44


Labor Schedule

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 45


Cost loaded Construction Schedule

http://www.projectrisk.com

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 46


Man-Hours loaded Schedule

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 47


Milestone Charts

Task A 1 2
After defining
Task B 4 5 Interrelationship:
3
Network diagram
Task C 6 7 can be prepared

Task D 8 9 10

1.0 2.0 3.0 4.0

2.0
1 2

3 cannot Start until 1 finish, 4


2.0 1.5 cannot start until 3 finishes
3 4 5

6
3.0
7

2.0 1.5
8 9 10

(© Indian Institute of Technology Roorkee) CEN 411: LECTURE NOTES 48