Report
Report
MICROGRID PROTECTION
140 450
400
120
IA
350
100 IB
IA IC
300
IB
80 Fault current seen by Relay R2
IC 250
in case of fault F2
If, A
If, A
60 200
150
40 Fault currents seen by R1
in case of fault af F1
100
20
50
0 0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
a)
Time, s
0 0.2 0.4
Time, s b)
0.6 0.8 1
500 900
450 800
IA IA
400 IB 700 IB
IC IC
350
600
300
500
If, A
If, A
250 Fault current seen by Relay R3
in case of phase-to-phase fault F3 Fault currents seen by Relay R4
400 in case of fault at F4
200
300
150
200
100
100
50
0
0 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
0 0.2 0.4 0.6 0.8 1
Time, s
Time, s
c) d)
Figure 2 – Time-fault current curves seen by various relays
in case of phase-to-phase faults at the end of their corresponding feeders
The values of these fault currents registered by various relays when faults occur
at the end of their corresponding feeders are summarized in the Table 1.
Table 1 – Fault current values and overcurrent relay setting parameters
160
Cut-Out (FCOs) installed at the beginning of 140
80
60
40
20
0
500 1000 1500 2000 2500 3000 3500
I, A
distribution network. The melting time-current curve of a commonly used FCO is
presented in Fig.3.
However, according to the new European Grid Codes [1], these PV elements that
are connected to un-faulted feeder should maintain their operation after an event of
fault either inside or outside the microgrid. This refers to the requirement entitled Fault
Ride Through (FRT) applicable for all electronically interfaced generation units,
especially for PV systems. Therefore, the author also proposes the application of FRT-
based protection units to prevent PV unit on un-faulted feeder from isolating from the
microgrid. In order to validate the effectiveness of the FRT integrated PV protection
system, faults at various locations on different feeders are also conducted and
discussed as follows.
The microgrid with the conventional protection scheme using FCO is illustrated
in Fig. 4.
a) Fault on feeder 1
3000
600
2500
400
200
IfPV, A
2000
0
If, A
1500 -200
-400
1000
-600
500 -800
0
-1000
0 0.2 0.4 0.6 0.8 1
Figu
0 0.5 1 1.5 2 2.5
Time, s
Time, s
b) Fault on feeder 2
For fault at F7, due to the larger fault current value, the FCO-2 of the faulted
feeder melts more quickly after about 1600ms to isolate the fault. However, all the PV
units are also removed from the grid by their under-voltage protection units (Fig. 8).
3500 80
60
3000
40
2500
20
If PV, A
2000
If, A
1500
-20
1000 -40
-60
500
-80
0 0.5 1 1.5 2 2.5
0
0 0.5 1 1.5 2 2.5 Time, s
Time, s
For fault at F8, the FCO-3 of the faulted feeder melts after about 1850ms to clear
the fault. In addition, all the PV units are removed from the grid by their under-voltage
protection units (Fig. 10).
2500 100
80
2000 60
40
1500 20
If P V , A
If, A
1000 -20
-40
500 -60
-80
0 -100
0 0.5 1 1.5 2 2.5 0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time, s Time, s
Figu
a) Fault on feeder 1
200
150
100
50
If PV, A
-50
-100
-150
-200
-250
0 0.5 1 1.5 2 2.5
Time, s
20
15
10
If PV, A
0
-5
-10
-15
-20
-25
0 0.5 1 1.5 2 2.5
Time, s
The two following figures illustrate the benefit of the application of FRT feature.
Fig. 11 and 12 show the time-current curves of a PV connected to feeder 1 and the
other to feeder 2, respectively. It is clear that only a few PV units on the un-affected
branches fail to maintain their operation after fault disappearance while those on
faulted feeders are all isolated from the network after 100ms;
b) Fault on feeder 2
80
60
40
20
If PV, A
-20
-40
-60
-80
0 0.5 1 1.5 2 2.5
Time, s
20
10
If PV, A
-10
-20
-30
0 0.5 1 1.5 2 2.5
Time, s
Similar to what discussed above, these illustrations indicate that the FRT function
could only preserve the continual operation of a number of PV units. A few PV units
are still interrupted due to the large melting time of FCO.
c) Fault on feeder 3
The time-current characteristics of PV units in this case are also included in Fig.
15 and 16 respectively to confirm again these statements mentioned in above
discussions.
60
40
20
0
If PV, A
-20
-40
-60
-80
0 0.5 1 1.5 2 2.5
Time, s
20
15
10
If PV, A 0
-5
-10
-15
-20
-25
0 0.5 1 1.5 2 2.5
Time, s
In this section, the author carries out the simulation of faults at various locations
inside the microgrid in both cases with and without the implementation of FRT-based
protection function for PV units.
The FCOs installed in the microgrid operate properly in both cases, isolating the
fault arising on its corresponding feeder. Moreover, the FRT units also help to
maintain the uninterrupted operation of some PV units on the sound branches in the
event of faults.
However, due to the quite long melting time of the used FCOs, faults inside the
microgrid last for a long period of time. As the results, there are several PV units
working on un-faulted feeders being isolated from the grid. In this case, the stable
operation of the microgrid is affected and some PV units cannot fulfill the FRT
requirements.
Therefore, this research adopts the protection scheme proposed in the following
section for microgrid protection and satisfaction of FRT requirement imposed by
ENTSO codes.
The microgrid is connected with the utility through a circuit breaker with an
integrated relay consisting of an overcurrent and an under-voltage unit. The setting
parameters of each relay are presented in the table 2. The pickup current of the
overcurrent element of each relay is calculated by the formula 1.
(1)
The voltage pickup parameters of the voltage element for each feeder relay have
the same values as for the PV protection.
Table 2 – The setting parameters for the proposed protection system
Function of
Relay Unit Pickup value Time delay, ms
protection
Overcurrent (A) 132 380 Primary
R1
Under-voltage (pu) 0.8 80 Backup
Overcurrent (A) 480 80 Primary
R2
Under-voltage (pu) 0.8 200 Backup
Overcurrent (A) 564 80 Primary
R3
Under-voltage (pu) 0.8 200 Backup
Overcurrent (A) 960 80 Primary
R4
Under-voltage (pu) 0.8 200 Backup
For fault at F6, feeder 1 (Fig. 15), the relay R2 reacts as primary protection
triggering a tripping signal to open the circuit breaker CB-2 in 80ms to isolate the fault
(Fig. 16).
1 1
Untrip
0.8 0.8
Tripping signal
Tripping signal
0.6 0.6
0.4 0.4
0.2 0.2
Trip
0 0
-0.2 -0.2
0 0.2 0.4 0.6 0.8 1 0 0.2 0.4 0.6 0.8 1
Time, s Time, s
The fluctuation of the current flowing on the feeder 1 is presented in the Fig. 17.
3000
2500
2000
If, A
1500
1000
500
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time, s
150 600
400
100
200
IfPV, A
50 0
IfPV, A
0
-200
-400
-50
-600
-100 -800
-1000
-150 0 0.2 0.4 0.6 0.8 1
0 0.2 0.4 0.6 0.8 1 Time, s
Time, s
a) PV fault currents in case of far fault b) PV fault currents in case of close fault
Figure 18 – PV fault currents in the event of faults at various locations on the feeder 1
As can be seen from the Fig. 18, in the event of fault occurring at F2, only those
PV units that are connected to feeder 2 are stopped feeding the currents to the grid
(Fig. 18a). On the contrary, when fault happens at those places near to the low voltage
bus, for example at F6, all the PV units are separated after a time delay of 100ms (Fig.
18b). This results in a significant power shortage that can lead to instability of the
microgrid and causing the wide-area load shedding. Therefore, this issue should be
taken into consideration to maintain the connection of the PV units on the sound
feeders in order to ensure the proper operation of the microgrid.
5.2. Case study 2: with application of FRT element
30 80
20 60
10 40
IfPV
If PV, A
0 20
-10 0
-20 -20
-30 -40
0 0.2 0.4 0.6 0.8 1 0 0.2 0.4 0.6 0.8 1
Time, s Time, s
1400
1200
1000
800
If, A
600
400
200
0
0 0.2 0.4 0.6 0.8 1 1.2 1.4 1.6 1.8 2
Time, s
400
200
If PV, A
-200
-400
-600
-800
0 0.5 1 1.5 2
Time, s
Figure 23 – Fault currents of all PV units in an event of fault inside the microgrid
The fault current flowing through the FCO on the faulty feeder and the fault
currents of all PV units are demonstrated in the Fig. 22 and 23 correspondingly.
The simulation results indicate that due to the limited level of fault currents
generated by inverter-interfaced PV units, the FCO takes a very long time to operate.
Consequently, the faults practically turn permanent, causing the collapse of the
microgrid operation. Moreover, all the PV units are tripped in both cases, whether
using FRT function or not. Therefore, circuit breakers with integrated digital relays
should be used to protect this islanded microgrid.
3. Microgrid protection system based on relays and circuit
breakers
In this section, the performance of a protection system based on the coordination
of digital relays and circuit breakers are carried out. Additionally, the benefit of FRT
element is also evaluated.
The one-line diagram of the microgrid with the proposed protection system is
presented in Fig. 24.
Figure 24 – One-line diagram of the isolated microgrid with the proposed protection system
The protection system evaluation has been performed. All the simulated faults
are cleared properly by the installed relays. For example, for the occurrence of fault at
F6, the overcurrent protection of relay R3 detects and clears the faults in about 150ms.
The fault current flowing into the fault point through relay R3 is depicted in Fig. 25.
Although the overcurrent function of the relay has suitable tripping time, all the
PV units are removed from service by the integrated under-voltage protection that is
demonstrated by Fig. 26. It is evident that all PV units on either faulted or un-faulted
feeders have been separated from the network.
3000
2500
2000
If, A
1500
1000
500
0
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time, s
600
400
200
If PV, A
-200
-400
-600
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time, s
60
40
20
If PV, A
0
-20
-40
-60
-80
0 0.1 0.2 0.3 0.4 0.5 0.6
Time, s
600
400
200
If PV, A
-200
-400
-600
0 0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1
Time, s
III. Conclusion
In this research, various protection strategies for microgrid operated in grid-
connected mode and islanded mode of operation have been studied. The research has
also considered the effectiveness of using FRT for PV unit protection.
For the microgrid operated in parallel with the main grid or separately, the usage
of FCO has imposed several disadvantages on the operation of the microgrid. For the
grid-tied mode of operation, although all the FCOs have operated properly to isolate
the faults on the corresponding feeders, all PV units have been tripped due to the very
large melting time of these FCO. For the latter mode of operation, fault currents
generated by all the PV units are insufficient for the FCO to cut out. As a result, the
faults become permanent and the microgrid has collapsed.
Therefore, it is undeniable that the protection strategy for the studied microgrid
should be implemented through digital relays and fast tripping circuit breakers. The
effectiveness of the proposed protection plan has been demonstrated in the research.
For the grid-connected mode of operation, all the relays have triggered tripping signal
in a predefined time period to clear the faults on the corresponding feeders. All PV
units with the integrated FRT element remain supplying power to the network after
faults have been cleared. In case the relay responsible for primary protection fails to
clear the fault, the relay at the point of common coupling will take responsibility as a
backup protection to handle the fault.