GSES Powerfactor 2 1
GSES Powerfactor 2 1
au
As Australia continues to see the trend to increase Fixed Power Factor & Reactive Power Modes
system capacity to medium or large scale Grid- (AS/NZS 4777.2:2015)
connected PV system, it becomes valuable for
AS/NZS 4777.2 :2015 Clause 6.3.3 prescribes the
Inverter Energy Systems (IES) to have ways to
behaviour of the two inverter response modes
support the power quality of the grid. The most
which allows inverter to output reactive power.
recent revision of the Australian Standard AS/
These are the Fixed Power Factor mode and Reactive
NZS 4777.2: Grid connection of energy systems
Power mode. While these functions are disabled
via inverters Part 2: Inverter requirements reflects
by default, the local distributed network service
this sentiment.
provider (DNSP) may require them to be enabled as
AS4777.2 introduced inverter functions which part of connection conditions.
controls the way inverter produces reactive power
Fixed Power factor mode
to demand, known as the fixed power factor mode
and reactive power mode, and outlines their If this mode is enabled, then the inverter will be
required operational behaviour. Local distributed required to operate between the range of 0.8
network service providers (DNSPs) may require leading to 0.8 lagging and no lesser. When the
these functions to be enabled. For a refresher on inverter power output changes, the inverter will
what power factor is, take a look at the previous vary the reactive power output to ensure that the
GSES article Power Factor and Grid-Connected target power factor is met.
Photovoltaics System.
Reactive Power mode
A factor to consider when these modes are enabled
If this mode is enabled in an inverter, then the
is their effect on the voltage rise calculations; while
maximum ratio of the reactive power (Vars) to the
leading power factors will reduce voltage rise
rated apparent power (VA) should be 100%. The
compared to a power factor of unity, a lagging
electrical distributor can fix the reactive power at a
power factor will increase the voltage rise, and may
constant value depending on the grid requirement.
result in the system requiring bigger cables ensure
This means that the power factor may fall below
that the expected voltage rise of the system falls
0.8 leading/lagging to supply a fixed amount of
within the voltage rise requirements outlined by AS/
reactive power.
NZS 4777.1:2016 Grid connection of energy systems
via inverters Part 1: Installation requirements. Voltage rise requirement
This article highlights the power factor modes (AS/NZS 4777.1:2016)
requirements and voltage rise requirements, AS/NZS 4777.1:2016 specifies that the overall voltage
explains how voltage drop calculations is affected by rise from the point of supply to the inverter AC
enabling power factors, and demonstrates methods terminal to be 2% or less of the nominal voltage at
for carrying out the voltage rise calculations for the point of supply.
different power factors as per AS/NZS 3008.1.1 :2017
Figure 1 below illustrates how the 2% voltage rise
Electrical installations—Selection of cables.
allowance is a combination of voltage rise between
the point of supply and the main switchboard
Page | 1
Copyright © 2017 Global Sustainable Energy Solutions Pty Ltd. All Rights Reserved.
www.gses.com.au
Inverter Power Factor Modes: How do they affect voltage rise calculations? Page | 2
Copyright © 2017 Global Sustainable Energy Solutions Pty Ltd. All Rights Reserved.
www.gses.com.au
RAY RRAY
PV AR PV A
• θ = phase angle corresponding to the power
factor experienced Three-phase final
subcircuit to inverter
The voltage rise is the difference in length Point of supply
(pillar/LV kiosk)
60 metre cable
Consider the installation below: a 3 phase Grid- • Vr3ф sub-mains = 4.04 V (Vc = 1.55 mV/A.m for
Connected inverter is installed on a commercial sub-mains from table 41 column 6)
building. The sub-mains (with max output of 30kVA
• Vr3ф consumer mains = 3.69 V (Vc = 2.43 mV/A.m
and AC nominal output of 30kW) run from the
from table 41 column 6)
inverter AC terminal to the Main Switchboard is 60
metres and the consumer mains run from the Main • Vr3ф = Vr3ф sub-mains + Vr3ф consumer mains
Switchboard to the Point of Supply is 35 metres. The • Vr3ф= 4.04 + 3.69
size of the installed sub-mains cable is 25 mm2 (PVC
insulation) and the size of the existing consumer • Vr3ф= 7.73 V
mains cable is 16 mm2 (PVC insulation). Since this value is below 8V, the selected cable
size will be compliant with the 2% Voltage rise
requirement.
Inverter Power Factor Modes: How do they affect voltage rise calculations? Page | 3
Copyright © 2017 Global Sustainable Energy Solutions Pty Ltd. All Rights Reserved.
www.gses.com.au
I × L × [ √3 × (Rc × cos θ − Xc × sin θ)] As this value is above 8V, the selected cable size
Vr3Φ = will not be compliant with the 2% Voltage rise
1000 requirement. This means that the cable size will
need to be increased to keep the voltage rise value
• Vr3фsub-mains = 3.60 V (Rc = 0.884 ohm/Km below 2%.
from table 34 column 4; Xc = 0.116 ohm/Km
from table 31 column 6) Conclusion
• Vr3фConsumer mains = 3.45 V (Rc = 1.4 ohm/ With the introduction of power factor mode and
Km from table 34 column 4; Xc = 0.120 ohm/Km fixed factor mode in AS/NZS 4777.2:2015, inverters
from table 31 column 6) may be asked to operate at varying power factors.
As power factor affects voltage rise calculations,
• Vr3ф = 3.60 + 3.45 additional caution needs to be taken to ensure the
• Vr3ф = 7.05 V 2% voltage rise requirement specified by AS/NZS
4777.1:2016 is met.
As this value is below 8V, the selected cable size will
be compliant with the 2% Voltage rise requirement. As shown in the worked examples, while
leading power factors can reduce the voltage rise
experienced at a site, a lagging power factor will
Case 3 - 0.8 Lagging Power Factor increase the voltage rise. This means that a larger
cable may need to be sized if it is anticipated
The electrical distributor has asked the site owner to
that the inverter will be operating with a lagging
set the inverter to 0.8 lagging operation.
power factor.
From AS/NZS 4777.1,
Keeping on top of changes in the industry
• Vr3ф = Vr3ф sub-mains + Vr3ф consumer mains
To assist PV installers in keeping on top of changes
• Vr3ф = 2% of 400V in the industry, the Clean Energy Council have put
= 8V in place a continuous professional development
(CPD) program. In response to this, GSES provide
30,000
Inverter rated current (at 0.8 lagging pf) = Professional Development Days at locations around
3 × 230 × 0.8
Australia, which give installers the opportunity
= 54.33 A
to achieve their yearly required 100 CPD points
in a single day. Topics covered in recent GSES
Professional Development days include:
Inverter Power Factor Modes: How do they affect voltage rise calculations? Page | 4
Copyright © 2017 Global Sustainable Energy Solutions Pty Ltd. All Rights Reserved.
www.gses.com.au
Inverter Power Factor Modes: How do they affect voltage rise calculations? Page | 5
Copyright © 2017 Global Sustainable Energy Solutions Pty Ltd. All Rights Reserved.