Hazard identification and risk assessment
OHS-PR-02-03-F07 Safe Work Procedure
Job/Task Type: Installation and assembly of the meter box
Department / Department: ARAR Electricity Department Prepared by: SULTAN MOAHMED / BASIL SARI Safe Work Procedure No.SWP-CN-PRJ- / RAKAN NWAF 20 Director Approval: SAED HAMED 01/01/2024 to Date: 01/01/2025 respirators safety clothing safety shoe Face and eyes Helmet protection Required personal protective equipment Other Select Arc Protection Equipment hand gloves safety belts Hearing protection
Safe work procedure analysis
the dangers The necessary controls to reduce or effect In each step, what are the things that Put all the steps needed to perform this task in order number eliminate this risk (Injury - damage - may cause injury, loss, damage or material losses) step interruption?= Not working without proper safety tools Injury - damage - Burning, electrical short, injury to the Use proper equipment and tools for all technicians and 1 and equipment material losses face, eyes, hands, feet, body. contractors Non-specialists are not allowed to enter Injury - damage - the work area. material losses Not to enable unauthorized persons to work/ensure the regularity of the labor at Electrocution, falling tools and the site/not to open or close any valves or equipment, injuring the body, falling secure the site 2 electrical switches or operate any part in into the hole. the company’s facilities in the absence of the work permit designated for that and provided that this is only done under the supervision of the operating observer Use of personal protective equipment Injury - damage - Minor cut, injury, meter damage, flying Caution while moving the meter box from material losses meter box installation 3 objects the vehicle to the site of31Page Approved Document Rev. 01 [May - 2020] Hazard identification and risk assessment OHS-PR-02-03-F07 Safe Work Procedure
Install the meter box correctly.
Ensure that human factors engineering procedures are followed while transporting heavy objects from the physical strength of the contractor's labor and the correct lifting method. Use personal protective equipment from: Injury - damage - 1- hand insulating glovesClass 0) material losses 2- safety shoe (Class EH) Electrocution, wounding, injury to the Ensure that the source of nutrition is isolated 4 3- safety helmet (Class E) face, eyes and body 4- electric arc prosthesis (CAT 2) 5- face shield (CAT 2) Follow and apply the work permit steps Injury - damage - Receiving the work permit and making sure that the arrest Ensure that arrest cards are hung on each material losses Minor cut, injury, electrocution 5 cards and locks are hung, as possible, on the isolation points. isolation point. Ensure that the cables are connected Injury - damage - correctly and the cable insulators are in material losses good condition Minor cut, injury Connecting the cables to the power supply 6 Wear personal protective equipment (safety helmet, safety shoes, hand gloves) Ensure that the work is finished and that Injury - damage - the site is free of employees or the general material losses public. Minor cut, injury, electrocution Handing over arrest cards and termination of work 7 Assign someone to monitor the site during the re-current process.
of32Page Approved Document Rev. 01 [May - 2020]
Hazard identification and risk assessment OHS-PR-02-03-F07 Safe Work Procedure
Use personal protective equipment from: Injury - damage -
1- hand insulating glovesClass 0) material losses 2- safety shoe (Class EH) Electrocution, injury Ensure that the current reaches the subscriber 8 3- safety helmet (Class E) 4- electric arc prosthesis (CAT 2) 5- face shield (CAT 2)