CONTRACTS GROUP 5
CONTRACTS GROUP 5
Should the amount of additional work of any kind or other special circumstances of any
kind whatsoever occur such as to fairly entitle the Contractor of the extension of Contract
Time for the completion of the Contract Works under this Contract, the Owner shall
determine the time for such extension.
The owner shall not be bound to take into account any claim for an extension of time
unless the Contractor has, prior to the expiration of the Contract Time and within 30
calendar days after such work has been commenced or after the circumstances leading
to such claim have arisen.
No extension of contract time whatsoever shall be granted to the Contractor due to
ordinary unfavorable weather conditions.
Non availability of equipment or materials to be furnished by him
Labor problems, and such other causes for which the Owner is not directly responsible. Or
when the affected activities do not fall within the so called CRITICAL PATH METHOD of the
approved PERT/CPM network. Or when the reason given to support the request for
extension was already considered in the determination of the Orginal Contract Time
during the conduct of detailed engineering.
WHAT IS PERT/CPM?
PERT
- is Program Evaluation and Review Technique
is a control tool for difining the parts of construction job in a network form
CPM
- is Critical Path Method
this is a tool used in planning, scheduling, and control of construction work
slidesmania.com
GENERAL
CONSTRUCTION METHODS AND
CONDITIONS
PROJECT MANAGEMENT
GENERAL
CONSTRUCTION METHODS AND
CONDITIONS
PROJECT MANAGEMENT
***Note: A surety bond is a three-party agreement between a surety, a contractor, and an owner. The surety,
(typically an insurance company) promises to satisfy the contractor’s obligations if the contractor fails to perform
in accordance with the construction contract.
***Note:
Contract Price is the total amount agreed upon by two parties for a service or good.
Total Expenditure is the total amount of money that is spent on a product or service in a given time period
GC-44
PAYMENT FOR
TERMINATED
CONTRACT
Payment
for
Completed
Work:
CONTRACTOR IS PAID FOR
ALL COMPLETED WORK UP
TO TERMINATION DATE
AT CONTRACT RATES.
Conditions:
Any previous
Outstanding
payments made to
balances due to
Contractor for the
Contractor for
execution of the
advances.
Works.
GC-45 Final
Inspection
Completion
Notification
Contractor notifies Owner of
completion of Contract Works.
Preliminary Inspection
Conducted by supervising Architect or Engineer upon Contractor's notice.
o Satisfactory Work:
Final acceptance is recommended, subject to GC-54 Warranty for Defects.
o Unsatisfactory Work:
Contractor receives instructions for correction.
Correction and Re-inspection:
CONTRACTOR MUST PROMPTLY CORRECT ISSUES AND A RE -INSPECTION WILL BE CONDUCTED.
Notification of
Final
Acceptance:
Owner notifies Contractor of
final acceptance in writing
within ten (10) calendar days
or as soon as practicable.