S15
S15
RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. S13/701
School Name ABDULLAH IBNU-A'MER ELEMENTARY SCHOOL- BOYS School Code S13
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 17-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low
Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 2 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 1 BOBCAT 1
Precast Manager 1 Carpenter 2 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 0
Project Control Team 1 Steelfixer 1 Portable Generator 0
QA/QC 1 E/M 7 Mobile Crane 0
Tech. Support 1 Mason 0 Tower Crane 0
Purch & Procurement 1 Painter Loabor 0 Pick up 0
Set. Manager 1 Plastering man 0 Water Tanker 1
Site Engineer 1 labor 8 Welding Machine 0
General Fork Lift
Safety/ HSE 1 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 2
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 2 Levelling Machine 0
Total station 0
Container 1
Water Tank 3
Portacabin 3
Temporary Genset 0
Sub Total/Main 17 21 4
Sub-contractors
Sub Total/Subcon 0 0 0
Grand Total 17 21 4
Page 1 of 2
Main Building - SF 15-Oct-16 25-Feb-17 Drainage Pipes for Toilets 80.00% 22-Feb-17
Water Tank 9-Mar-17 9-Mar-17 Roof Drain 90.00% 1-May-17
Doors Electric Room 7-Mar-17 9-Mar-17 Elevator Main Building - RF Install Steelwork Support For Elevator 50.00% 22-Mar-17
Windows Electric Room 7-Mar-17 9-Mar-17 Electric Traction Elevators 50.00% 15-Mar-17
Exposed Aggr. Main Building - RF 15-Jun-16 4-Jul-16 Electrical Main Building - GF Grounding System , UPS &Low-Voltage Electrical Power Conductors
80.00% and20-Sep-16
Cables
Electric Room 19-Mar-17 24-Mar-17 Lighting System Second Fix (Wires ) 90.00% 3-Sep-16
No R_Type Of Work Electric Room 7-Feb-17 26-Mar-17 Panelboards 70.00% 22-Feb-17
Wiring Devices Second Fix (Wires ) 92.00% 27-Apr-17
Fire Alarm Second Fix (Wires ) 92.00% 27-Apr-17
Data Communications System Second Fix (Wires ) 92.00% 27-Apr-17
IP Telephone System Second Fix (Wires ) 92.00% 27-Apr-17
Main Building - FF Lighting System Second Fix (Wires ) 92.00% 27-Apr-17
Panelboards 70.00% 22-Feb-17
Wiring Devices Second Fix (Wires ) 92.00% 27-Apr-17
Fire Alarm Second Fix (Wires ) 92.00% 27-Apr-17
Data Communications System Second Fix (Wires ) 92.00% 27-Apr-17
IP Telephone System Second Fix (Wires ) 92.00% 27-Apr-17
Grounding System , UPS &Low-Voltage Electrical Power Conductors
80.00% and21-Sep-16
Cables
Main Building - SF Lighting System Second Fix (Wires ) 92.00% 27-Apr-17
Panelboards 70.00% 22-Feb-17
Wiring Devices Second Fix (Wires ) 92.00% 27-Apr-17
Data Communications System Second Fix (Wires ) 92.00% 27-Apr-17
IP Telephone System Second Fix (Wires ) 92.00% 27-Apr-17
Fire Alarm Second Fix (Wires ) 92.00% 27-Apr-17
Grounding System , UPS &Low-Voltage Electrical Power Conductors
80.00% and14-Sep-16
Cables
Main Building - RF Panelboards 20.00% 15-Apr-17
Lighting Units (all building ) 50.00% 15-Apr-17
Multi-purpose hall Public Address System First Fix (Pipes ) 60.00% 5-May-17
IP Telephone System First Fix (Pipes ) 90.00% 29-Apr-17
Lighting System First Fix (Pipes ) 75.00% 29-Apr-17
Wiring Devices First Fix (Pipes ) 70.00% 30-Apr-17
Fire Alarm System First Fix (Pipes ) 35.00% 1-May-17
Canteen Panelboards 50.00% 15-Apr-17
Guard House Panelboards 50.00% 15-Apr-17
Gate Work Panelboards 50.00% 15-Apr-17
Doors Main Building - GF Hollow Metal Doors 50.00% 23-Mar-17
Main Building - FF Hollow Metal Doors 50.00% 28-Mar-17
Main Building - SF Hollow Metal Doors 50.00% 19-Mar-17
Windows Main Building - GF Aluminum Windows 50.00% 23-Mar-17
Main Building - FF Aluminum Windows 50.00% 23-Mar-17
Main Building - SF Aluminum Windows 53.00% 22-Mar-17
Space Frame Multi-purpose hall Install & Supply Space Frame 95.00% 22-Feb-17
Tiling Main Building - GF Granite Tiling 50.00% 20-Mar-17
Stairs Granite 75.00% 20-Mar-17
Porcelain Tiles 80.00% 21-Dec-16
Main Building - FF Granite Tiling 50.00% 22-Mar-17
Stairs Granite 70.00% 18-Mar-17
Porcelain Tiles 90.00% 9-Nov-16
Main Building - SF Granite Tiling 53.00% 22-Mar-17
Stairs Granite 70.00% 20-Mar-17
Porcelain Tiles 90.00% 21-Dec-16
Ceiling Main Building - GF Solid Gypsum Ceiling 80.00% 21-Dec-16
Main Building - FF Solid Gypsum Ceiling 90.00% 9-Nov-16
Main Building - SF Solid Gypsum Ceiling 90.00% 21-Dec-16
Paint Electric Room Final Coat Paint 40.00% 29-Mar-17
No R_Type Of Work Main Building - GF Porcelain Skirting 80.00% 21-Dec-16
Main Building - FF Granit Skirting 50.00% 20-Mar-17
Porcelain Skirting 90.00% 14-Nov-16
Main Building - SF Porcelain Skirting 90.00% 21-Dec-16
* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).
Page 2 of 2