S23
S23
RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. S23/714
School Name Ibnul-Athir Secondary School- Boys School Code S23
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 2-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low
Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 3 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 1 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 1
Project Control Team 1 Steelfixer 5 Portable Generator 0
QA/QC 1 E/M 0 Mobile Crane 0
Tech. Support 1 Mason 0 Tower Crane 0
Purch & Procurement 1 Painter Loabor 0 Pick up 0
Set. Manager 1 Plastering man 0 Water Tanker 0
Site Engineer 1 labor 3 Welding Machine 0
General Fork Lift
Safety/ HSE 1 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 2 Levelling Machine 0
Total station 0
Container 0
Water Tank 0
Portacabin 0
Temporary Genset 0
Sub Total/Main 17 12 2
Sub-contractors
Sub Total/Subcon 0 0 0
Grand Total 17 12 2
Page 1 of 2
Electric Room 25-Mar-17 22-Apr-17 Canteen Wiring Devices First Fix (Pipes ) 75.00% 21-Feb-17
No R_Type Of Work Electric Room 16-Apr-17 19-Apr-17 Wiring Devices Second Fix (Wires ) 55.00% 18-Feb-17
Panelboards 60.00% 19-Feb-17
Lighting System First Fix (Pipes ) 65.00% 21-Feb-17
Guard House Lighting System First Fix (Pipes ) 95.00% 18-Feb-17
Wiring Devices First Fix (Pipes ) 75.00% 19-Feb-17
IP Telephone System First Fix (Pipes ) 35.00% 19-Feb-17
Doors Main Building - GF Hollow Metal Doors 20.00% 1-Apr-17
Main Building - FF Hollow Metal Doors 20.00% 3-Apr-17
Main Building - SF Hollow Metal Doors 20.00% 1-Apr-17
Main Building - RF Hollow Metal Frames 50.00% 24-Dec-16
Windows Main Building - GF Aluminum Windows 90.00% 4-Mar-17
Main Building - FF Aluminum Windows 90.00% 4-Mar-17
Main Building - SF Aluminum Windows 90.00% 4-Mar-17
Main Building - RF Structural Steel Frames Supporting To Curtain Walls 50.00% 24-Apr-17
Aluminum Windows 53.00% 25-Apr-17
Multi-purpose hall Aluminum Windows 50.00% 7-May-17
Tiling Main Building - GF Porcelain Tiles 90.00% 11-Oct-16
Main Building - FF Ceramic Tiles for wall 50.00% 12-Feb-17
Ceiling Main Building - GF Solid Gypsum Ceiling 90.00% 3-Sep-16
Main Building - SF Solid Gypsum Ceiling 90.00% 9-Oct-16
Paint Main Building - GF Paint (1ST Coat) 90.00% 14-Dec-16
Main Building - SF Paint preparation 80.00% 4-Feb-17
Main Building - RF Paint (1ST Coat) for external 90.00% 29-Jan-17
Final Coat Paint for external 90.00% 29-Jan-17
Handrail Main Building - FF Pipe and Tube Railings 25.00% 25-Feb-17
Main Building - SF Pipe and Tube Railings 25.00% 25-Feb-17
Exposed Aggr. Main Building - RF Colour Exposed Aggregate 95.00% 29-Jan-17
Site layout Exposed Color Aggregate 30.00% 20-Apr-17
No R_Type Of Work Main Building - RF Installation of glass 60.00% 20-Apr-17
Site layout Metal Casting 20.00% 2-Apr-17
* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).
Page 2 of 2