0% found this document useful (0 votes)
22 views2 pages

S23

SCHOOL S23
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
22 views2 pages

S23

SCHOOL S23
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Project name EDUCATIONAL BUILDINGS CONSTRUCTION IN RIYADH Project no.

RIYADH 111
Contractor name Al Bawani Co. Project Manager Eng / Shehzad khanzada
Consultant name AECOM Data Date 14-May-17
To the Engineer Report no. S23/714
School Name Ibnul-Athir Secondary School- Boys School Code S23
Temperature Max : 34°C Min : 20°C Site Hand-Over Day 2-Feb-15
Weather Sunny Cloudy Rainy Humidity High Medium Low

Contractor's Manpower (including Subcontractors)* Plant/Equipment*

Status (Idle
Staff No. Direct Labor No Type Qty. Location
or Repair)
Projt. MGR. 1 Supervisor/Foreman 3 Excavator/ Poclain/ Excavator 0
Tech. Team 1 Precast Man 0 Shovel/ Loader/ Grader 0
Contract MGR. 1 Equipment Optr. 0 BOBCAT 1
Precast Manager 1 Carpenter 1 Dump Truck 0
Const. Manager 1 Welder 0 Roller/ Compactor 1
Project Control Team 1 Steelfixer 5 Portable Generator 0
QA/QC 1 E/M 0 Mobile Crane 0
Tech. Support 1 Mason 0 Tower Crane 0
Purch & Procurement 1 Painter Loabor 0 Pick up 0
Set. Manager 1 Plastering man 0 Water Tanker 0
Site Engineer 1 labor 3 Welding Machine 0
General Fork Lift
Safety/ HSE 1 0
Contractor JCB
Timekeeper 1 0
Electro Mechanical Engrs 1 Water Pump 0
Surveyor & Survayor Assistant 1 Bulldozer 0
Guard 2 Levelling Machine 0
Total station 0
Container 0
Water Tank 0
Portacabin 0
Temporary Genset 0

Sub Total/Main 17 12 2

Sub-contractors
Sub Total/Subcon 0 0 0

Grand Total 17 12 2

Activities and Tasks*


COMPLETED ACTIVITIES ON-GOING ACTIVITIES
Percentage
Type of Work Building Name Start Date Finish Date Type of Work Building Name Activity name Start Date Finish Date
Complete
Excavation Main Building - GF 28-Jul-15 22-Aug-15 Sub Structure Water Tank Bituminous Sheet Waterproofing for Water Tank 70.00% 14-Mar-17
Multi-purpose hall 11-May-16 30-May-16 Boundary Wall Bituminous Waterproofing for Boundary Wall 90.00% 22-Nov-16
Electric Room 6-Jun-16 15-Jun-16 R.C Concrete Grade Beams for Boundary Wall 50.00% 24-Dec-16
Canteen 6-Jun-16 20-Aug-16 Backfilling Backfilling Work for Boundary Wall 90.00% 26-Nov-16
Guard House 13-Jul-16 11-Dec-16 Precast Precast Concret Columns for Boundary Wall 40.00% 16-Jan-17
Site layout 21-Jun-15 31-Jul-15 Precast Concret Panels for Boundary Wall 40.00% 16-Jan-17
Water Tank 13-Jul-16 30-Jan-17 Mechanical Main Building - GF Fire Extingushers 20.00% 5-Jan-17
Boundary Wall 25-Jul-16 26-Nov-16 Air Distribution System & Testing 95.00% 15-Sep-16
Earth Works Site layout 14-Feb-15 30-May-15 Plumbing Fixtures 80.00% 7-Jan-17
Sub Structure Main Building - GF 16-Sep-15 19-Mar-16 Ventilation Fans & Testing 50.00% 7-Jan-17
Multi-purpose hall 6-Jul-16 18-Oct-16 Diffusers & Grills 30.00% 9-Feb-17
Electric Room 16-Jul-16 26-Dec-16 Split Units & Testing 50.00% 8-Feb-17
Canteen 27-Jul-16 9-Jan-17 Main Building - FF Ventilation Fans & Testing 10.00% 8-Feb-17
Guard House 19-Jul-16 8-Jan-17 Diffusers & Grills 30.00% 9-Feb-17
Backfilling Main Building - GF 29-Nov-15 4-Mar-16 Split Units & Testing 50.00% 9-Feb-17
Multi-purpose hall 22-Aug-16 17-Oct-16 Plumbing Fixtures 80.00% 9-Feb-17
Electric Room 9-Aug-16 22-Nov-16 Fire Extingushers 10.00% 7-Feb-17
Canteen 25-Jan-17 12-Feb-17 Main Building - SF Ventilation Fans & Testing 10.00% 9-Feb-17
Guard House 25-Jan-17 12-Feb-17 Diffusers & Grills 30.00% 11-Feb-17
Slab On Grade Main Building - GF 6-Mar-16 19-Mar-16 Split Units & Testing 50.00% 7-Feb-17
Multi-purpose hall 14-Sep-16 3-Nov-16 HVAC Duct & Testing 95.00% 19-Oct-16
Electric Room 28-Aug-16 17-Jan-17 Floor Drain & Clean Out & Testing 95.00% 22-Nov-16
Canteen 21-Feb-17 21-Feb-17 Plumbing Fixtures 80.00% 8-Feb-17
Guard House 12-Sep-16 24-Jan-17 Pipe Fitting & Testing 95.00% 22-Nov-16
Water Proofing Main Building - GF 15-Nov-15 3-Sep-16 Fire Extingushers 10.00% 8-Feb-17
Main Building - RF 1-Jan-17 18-Apr-17 Air Distribution System & Testing 90.00% 8-Dec-16
Precast Main Building - GF 5-Mar-16 25-May-16 Main Building - RF Pipe Fitting & Testing 15.00% 5-Dec-16
Main Building - FF 12-May-16 17-Nov-16 Multi-purpose hall Split Units 50.00% 6-Feb-17
Main Building - SF 24-May-16 17-Nov-16 Package Unit 80.00% 16-Apr-17
Main Building - RF 6-Sep-16 10-Nov-16 Plumbing Fixtures 80.00% 9-Feb-17
Multi-purpose hall 20-Aug-16 15-Dec-16 Canteen Plumbing Fixtures 80.00% 21-Feb-17
Electric Room 4-Sep-16 8-Feb-17 Fire Extinguisher 10.00% 23-Feb-17
Canteen 19-Feb-17 20-Mar-17 Split Unit 10.00% 21-Feb-17
Guard House 19-Feb-17 20-Mar-17 Ventilation Fans 10.00% 22-Feb-17
Concrete Works Multi-purpose hall 3-Oct-16 7-Mar-17 Guard House Plumbing Fixtures 80.00% 6-Apr-17
Block Work Main Building - GF 17-May-16 24-Jul-16 Site layout Connection Sewage Network on General Network 60.00% 8-Apr-17
Main Building - FF 31-May-16 24-Jul-16 Elevator Main Building - RF Electric Traction Elevators 60.00% 12-Mar-17
Main Building - SF 15-Jul-16 23-Sep-16 Electrical Main Building - SF Grounding System , UPS &Low-Voltage Electrical Power Conductors
65.00% and15-Oct-16
Cables
Multi-purpose hall 12-Feb-17 19-Feb-17 Main Building - RF Sub Main Distribution Board 75.00% 22-Feb-17
Plaster Main Building - GF 10-Jul-16 19-Sep-16 Lighting System Second Fix (Wires ) 90.00% 23-Feb-17
Main Building - FF 1-Aug-16 22-Aug-16 Grounding and Bonding for Electrical Systems 55.00% 5-Oct-16
Main Building - SF 25-Sep-16 30-Nov-16 Multi-purpose hall Public Address System Second Fix (Wires ) 60.00% 2-Apr-17
Multi-purpose hall 29-Mar-17 4-Apr-17 IP Telephone System Second Fix (Wires ) 10.00% 5-Apr-17
Mechanical Electric Room 7-Feb-17 22-Mar-17 Fire Alarm System Second Fix (Wires ) 70.00% 4-Apr-17
Doors Electric Room 17-Apr-17 25-Apr-17 Lighting System First Fix (Pipes ) 90.00% 18-Dec-16
Windows Electric Room 13-Apr-17 18-Apr-17 Lighting System Second Fix (Wires ) 50.00% 6-Apr-17
Space Frame Multi-purpose hall 3-Oct-16 16-Jan-17 Wiring Devices Second Fix (Wires ) 13.00% 4-Apr-17
Paint Electric Room 15-Mar-17 22-Mar-17 Panelboards 60.00% 8-Apr-17
Exposed Aggr. Multi-purpose hall 2-Mar-17 11-Mar-17 Fire Alarm System First Fix (Pipes ) 90.00% 18-Dec-16

Page 1 of 2
Electric Room 25-Mar-17 22-Apr-17 Canteen Wiring Devices First Fix (Pipes ) 75.00% 21-Feb-17
No R_Type Of Work Electric Room 16-Apr-17 19-Apr-17 Wiring Devices Second Fix (Wires ) 55.00% 18-Feb-17
Panelboards 60.00% 19-Feb-17
Lighting System First Fix (Pipes ) 65.00% 21-Feb-17
Guard House Lighting System First Fix (Pipes ) 95.00% 18-Feb-17
Wiring Devices First Fix (Pipes ) 75.00% 19-Feb-17
IP Telephone System First Fix (Pipes ) 35.00% 19-Feb-17
Doors Main Building - GF Hollow Metal Doors 20.00% 1-Apr-17
Main Building - FF Hollow Metal Doors 20.00% 3-Apr-17
Main Building - SF Hollow Metal Doors 20.00% 1-Apr-17
Main Building - RF Hollow Metal Frames 50.00% 24-Dec-16
Windows Main Building - GF Aluminum Windows 90.00% 4-Mar-17
Main Building - FF Aluminum Windows 90.00% 4-Mar-17
Main Building - SF Aluminum Windows 90.00% 4-Mar-17
Main Building - RF Structural Steel Frames Supporting To Curtain Walls 50.00% 24-Apr-17
Aluminum Windows 53.00% 25-Apr-17
Multi-purpose hall Aluminum Windows 50.00% 7-May-17
Tiling Main Building - GF Porcelain Tiles 90.00% 11-Oct-16
Main Building - FF Ceramic Tiles for wall 50.00% 12-Feb-17
Ceiling Main Building - GF Solid Gypsum Ceiling 90.00% 3-Sep-16
Main Building - SF Solid Gypsum Ceiling 90.00% 9-Oct-16
Paint Main Building - GF Paint (1ST Coat) 90.00% 14-Dec-16
Main Building - SF Paint preparation 80.00% 4-Feb-17
Main Building - RF Paint (1ST Coat) for external 90.00% 29-Jan-17
Final Coat Paint for external 90.00% 29-Jan-17
Handrail Main Building - FF Pipe and Tube Railings 25.00% 25-Feb-17
Main Building - SF Pipe and Tube Railings 25.00% 25-Feb-17
Exposed Aggr. Main Building - RF Colour Exposed Aggregate 95.00% 29-Jan-17
Site layout Exposed Color Aggregate 30.00% 20-Apr-17
No R_Type Of Work Main Building - RF Installation of glass 60.00% 20-Apr-17
Site layout Metal Casting 20.00% 2-Apr-17

Materials delivered to Site*


Item Unit Qty. Approved submittal reference

Contractor's authorized signatory Engineer's authorized signatory


Name: Mohammad Alden Name:
Signature: Signature:
Date: 14-May-17 Date: 14-May-17

* This form is to be used by the General Contractor to capture the above required information on a daily basis to report to the
Construction Supervisor (Engineer).

Page 2 of 2

You might also like