Rate Analysis
Rate Analysis
Machinaries & Equipments Unit Qty Price Months Weightahe Amount Salvage Value Recovered Amount
Concrete Equipments
Batching Plant CP 30 / CP 40 Nos 1 4,400,000 4,400,000 40% 1,760,000
Tansit Mixer - 3 Nos Nos 3 2,600,000 7,800,000 55% 4,290,000 3,510,000
Concrete Pump with Line upto 200 Metre Nos 2 2,600,000 5,200,000 50% 2,600,000
JCB Nos 1 2,800,000 2,800,000 60% 1,680,000
(Rates for all cement concrete items plain and reinforced described below shall include
work from lowest Basement to top of last roof including roof of machine room, mumty,
overhead tanks and parapets above. This section covers cast in situ structural and
architectural as well as precast structural and architectural concrete.) Note :- Contractor
shall use Marble Powder and Mechanical grinder in repairing joints and honeycombs if
required.
Providing and laying plain cement concrete of specified grade as bed concrete under
foundation, bases for rafts, underground water tank, building machine equipments,
column footing, under floor landings, below road and pathways,cill, coping, screeding at
roof to required slope and other locations as called for laid, consolidated and cured etc.
complete including finishing the top surface to receive the next course / layer as per
specification and drawing excluding the cost of centering and shuttering.
1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm and down gauge)
1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm and down gauge)
1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 20 mm and down gauge)
1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40mm and down gauge)
Providing and laying damp proof course 40mm thick with cement concrete 1:2:4 (1
cement : 2 coarse sand : 4 graded stone aggreate 20mm nominal size) including providing
and mixing of water proofing compound @ 2% of cement content and providing and
applying two layers of bitumen of grade 85/25 and as directed by the Project Manager.
Providing & laying cast - in - place structural controlled design mix cement concrete of
M25 grade using pump with 20mm down gauge coarse aggregates excluding cost of
centering, shuttering and steel reinforcement but including cost of making shear keys and
provision of construction / control joints in various locations, laid, consolidated and
cured, item to include all structural items like base raft, ramp, column, column capitals,
wall, footings, equipment foundations, fins, mullions, beams, lintels, pergola, chajja, facia,
parapet, railing, slab, trenches, drains and sumps etc. of any shape and sizes. The rates of
concrete to include the cost of Fly ash /admixtures / plasticisers/superplasticers/
bonding agent to achieve specified strength and to facilitate pumpable concrete etc
complete for all height and level.
Foundation, raft slab, raft beams, plinth beam, lift pits, sump pits, pedestals / bases of
2.3.1 coloum, wall foundations grade slab etc.
Suspended floors, roofs, balconies, shelves/ counters, stair waist slabs, folded plate stairs
2.3.2 and landings, lintel and floor beams, girders (deep beams), RCC bands, cantilever
projections, slab of tank, arches, other non-structural elements etc.
Columns, pillars, piers, abutments, posts and struts,wall, offset and projection of columns,
2.3.3 etc.
2.3.4 Retaining Walls, water tank wall, shear wall, lift wall (any thickness)
Parapets, planters, facias, fins, vertical projection of balconies, pergolas, copings, cills etc.
2.3.5 (for all heights as shown in the drawing)
2.4 Extra for add or deduct for using Richer or leaner mix in place of M-25 Concrete.
(Rates for all cement concrete items plain and reinforced described below shall
include work from lowest Basement to top of last roof including roof of machine
room, mumty, overhead tanks and parapets above. This section covers cast in situ
structural and architectural as well as precast structural and architectural concrete.)
Note :- Contractor shall use Marble Powder and Mechanical grinder in
repairing joints and honeycombs if required.
2.1.1 Providing and laying plain cement concrete of specified grade as bed concrete
under foundation, bases for rafts, underground water tank, building machine
equipments, column footing, under floor landings, below road and pathways,cill,
coping, screeding at roof to required slope and other locations as called for laid,
consolidated and cured etc. complete including finishing the top surface to receive
the next course / layer as per specification and drawing excluding the cost of
centering and shuttering.
a. 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm and down cum 475 6,711.41 3,187,919
gauge)
b. 1:3:6 (1 cement : 3 coarse sand : 6 graded stone aggregate 20 mm and down cum - 6,081.97 -
gauge)
c. 1:4:8 (1 cement : 4 coarse sand : 8 graded stone aggregate 20 mm and down cum 760 5,657.38 4,299,608
gauge)
d. 1:5:10 (1 cement : 5 coarse sand : 10 graded stone aggregate 40mm and down cum - 5,391.87 -
gauge)
2.2 Damp proof course
Providing and laying damp proof course 40mm thick with cement concrete 1:2:4 (1 sqm. - 393.90 -
cement : 2 coarse sand : 4 graded stone aggreate 20mm nominal size) including
providing and mixing of water proofing compound @ 2% of cement content and
providing and applying two layers of bitumen of grade 85/25 and as directed by the
Project Manager.
Providing & laying cast - in - place structural controlled design mix cement
concrete of M25 grade (Minimum Cement Content 330 Kg per cum) using pump
with 20mm down gauge coarse aggregates excluding cost of centering, shuttering
and steel reinforcement but including cost of making shear keys and provision of
construction / control joints in various locations, laid, consolidated and cured, item
to include all structural items like base raft, ramp, column, column capitals, wall,
footings, equipment foundations, fins, mullions, beams, lintels, pergola, chajja,
facia, parapet, railing, slab, trenches, drains and sumps etc. of any shape and
sizes. The rates of concrete to include the cost of Fly ash /admixtures /
plasticisers/superplasticers/ bonding agent to achieve specified strength and to
facilitate pumpable concrete etc complete for all height and level.
3 of
2.3.1 Foundation, raft slab, raft beams, plinth beam, lift pits, sump pits, pedestals / bases cum 11,900 7,627.10 90,762,532
of coloum, wall foundations grade slab etc.
2.3.2 Suspended floors, roofs, balconies, shelves/ counters, stair waist slabs, folded cum 32,300 8,613.13 278,204,228
plate stairs and landings, lintel and floor beams, girders (deep beams), RCC bands,
cantilever projections, slab of tank, arches, other non-structural elements etc.
2.3.3 Columns, pillars, piers, abutments, posts and struts,wall, offset and projection of cum 3,460 8,758.27 30,303,618
columns, etc.
2.3.4 Retaining Walls, water tank wall, shear wall, lift wall (any thickness) cum 26,290 8,384.04 220,416,303
2.3.5 Parapets, planters, facias, fins, vertical projection of balconies, pergolas, copings, cum 1,241 9,067.27 11,252,823
cills etc. (for all heights as shown in the drawing)
2.4 Extra for add or deduct for using Richer or leaner mix in place of M-25
Concrete.
2.4.1 M-30 instead of M-25 cum 44,200.0 292.84 12,943,616
2.4.2 M-35 instead of M-25 cum
2.4.3 M-40 instead of M-25 cum 33,352.0 537.44 17,924,632
2.4.4 M-45 instead of M-25 cum
2.4.5 M-50 instead of M-25 ( WITH SILICA CONTENT) cum
2.4.6 (a) M-50 instead of M-25 ( WITHOUT SILICA CONTENT) cum 1,658.0 1,939.94 3,216,417
2.4.6 (b) M-60 instead of M-25 ( WITH SILICA CONTENT) cum 5,260.0 3,951.68 20,785,858
Total : 2 : - 693,297,553
4 of
Comparison of Storm Water works at Reach Airia Mall
M/s Paramaah M/s Rajesh Industrial
S.No. Description Unit Qty Rate Amount Rate
Providing and laying non-pressure class NP3 R.C.C. pipes with collars
1 jointed with stiff mixture of cement mortar in the proportion of 1:2 (1
cement : 2 fine sand) including testing of joints etc. complete :
0.91 m deep with S.F.R.C. cover and frame (heavy duty, HD-20
grade designation) 560 mm internal diameter conforming to I.S.
12592, total weight of cover and frame to be not less than 182 kg., fixed
in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone Nos. 3 9,000 27,000 15,750
aggregate 20 mm nominal size) including centering, shuttering all
complete. (Excavation, foot rests and 12mm thick cement plaster at
the external surface shall be paid for separately) :
With common burnt clay F.P.S. (non modular) bricks of class designation
7.5
Extra depth for circular type manhole 0.91m internal dia (at bottom)
4 beyond 0.91m to 1.67m
RM 2 4,000 8,000 10,000
With common burnt clay F.P.S. (non modular) bricks of class designation
7.5
(1 cement : 3 coarse sand) finished with a floating coat of neat cement
5 foundation concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone
aggregate 40 mm nominal size) and making necessary channel in
1.68 m deep with SFRC Cover and frame (heavy duty HD-20
grade designation) 560 mm internal diameter conforming to I.S.
12592, total weight of cover and frame to be not less than 182 kg. fixed
in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded Nos. RO
stonecommon
With aggregate 20 mm
burnt clay nominal size)
F.P.S. (non including
modular) centering,
bricks shuttering
of class all
designation
complete.
7.5 (Excavation, foot rests and 12 mm thick cement plaster at the
Extra depth
external forshall
surface circular type
be paid formanhole 1.22
separately) : m internal dia (at
6 bottom) beyond 1.68 m to 2.29 m :
RM RO
With common burnt clay F.P.S. (non modular) bricks of class designation
7.5
TOTAL 128,500
Service Tax @ 6% 7,710
Err:509
307,600 Err:508
18,456 Err:508
3,076 Err:508
329,132 Err:508
BASIC RATES
NP2 Pipes
NP2 Pipe 150mm Dia Rmt 225
NP2 Pipe 200mm Dia Rmt 300
NP2 Pipe 250mm Dia Rmt 350
NP2 Pipe 300mm Dia Rmt 450
NP2 Pipe 350mm Dia Rmt 525
NP2 Pipe 400mm Dia Rmt 575
NP2 Pipe 450mm Dia Rmt 700
NP3 Pipes
NP3 Pipe 150mm Dia Rmt 250
NP3 Pipe 200mm Dia Rmt 375
NP3 Pipe 250mm Dia Rmt 485
NP3 Pipe 300mm Dia Rmt 700
NP3 Pipe 400mm Dia Rmt 1100
NP3 Pipe 450mm Dia Rmt 1275
Manhole Cover 560 mm Dia - Class - HD 20 Nos 1250
Cement OPC 43 Grade Bag 280
Cement PPC Bag 280
Aggregate 10mm Cum 1550
Aggregate 20mm Cum 1450
Aggregate 40mm Cum 1350
Coarse Sand Zone III Cum 1550
Fine Sand Cum 800
Bricks - Designation Class 7.5 Nos 4.5
Mason 1st Class (For 8 Hours) Day 387.66
Mason 2nd Class (For 8 Hours) Day 351.11
Beldar / Bhisti / Labour (For 8 Hours) Day 318.46
Cement for slurry over bed @ 3.3 kg per sqm Bag 0.66 320 211
Cement Mortar for Pointing With White Cement LS 0.25 900 225
Misc., Nails, Drum, Sundries including carriage of cement Charges @ 3% LS 175
Labour:
Mason for Tile Work Day 2.0 550 1,100
Mason for Mortar Day #REF! 550
Beldar / Coolie for Tile Work Day 2.0 400 800
Beldar / Coolie for Mortar Day #REF! 400
Total Cost - A 7,907
Water & Electricity Charges 2% 158
Total Amount - B 8,065
Add Contractor Profit & Overheads @ 15% 1,210
Total Cost for 10 Sqm 9,274
Rate for 10 Sqm 9,274
Total Rate for 1 Sqm 927
plus Taxes as applicable
Cement Mortar 1: 2 (1 cement : 2 Coarse sand)
Brick work with common burnt clay F.P.S. (non modular) bricks of class
designation 7.5 in foundation and plinth in:
Cement Mortar (1 Cement : 5 Coarse Sand )
Cost For 1 Cum
Material :
Non Modular Bricks - Class 7.5 Nos 500 4.50 2,250
Carriage of Bricks Nos 500 0.28 138
Cement Mortar (1 Cement : 5 Coarse Sand ) Cum 0.25 #REF! #REF!
Misc. Charges @ 3% LS #REF!
Labour:
Mason - 1st Class Day 0.36 388 140
Mason - 2nd Class Day 0.36 351 126
Beldar /Coolie Day 1.37 318 436
Bhisti Day 0.2 318 64
Total Cost - A #REF!
Water Charges 1% #REF!
Electricicty Charges 2% #REF!
Total Amount - B #REF!
Add Contractor Prophit @ 15% #REF!
Total Cost for 1 Cum #REF!
Rate for 1Cum #REF!
Add Service Tax @ 6% #REF!
Brick Work (1 Cement : 5 Coarse Sand ) Total Rate for 1 Cum #REF!
Brick work with common burnt clay F.P.S. (non modular) bricks of class
designation 7.5 in foundation and plinth in:
Cement Mortar (1 Cement : 6 Coarse Sand )
Cost For 1 Cum
Material :
Non Modular Bricks - Class 7.5 Nos 500 4.50 2,250
Carriage of Bricks Nos 500 0.28 138
Cement Mortar (1 Cement : 6 Coarse Sand ) Cum 0.25 #REF! #REF!
Misc. Charges @ 3% LS #REF!
Labour:
Mason - 1st Class Day 0.36 388 140
Mason - 2nd Class Day 0.36 351 126
Beldar /Coolie Day 1.37 318 436
Bhisti Day 0.2 318 64
Total Cost - A #REF!
Water Charges 1% #REF!
Electricicty Charges 2% #REF!
Total Amount - B #REF!
Add Contractor Prophit @ 15% #REF!
Total Cost for 1 Cum #REF!
Rate for 1Cum #REF!
Add Service Tax @ 6% #REF!
Brick Work (1 Cement : 6 Coarse Sand ) Total Rate for 1 Cum #REF!
Providing and laying non-pressure class NP3 R.C.C. pipes with collars
jointed with stiff mixture of cement mortar in the proportion of 1:2 (1
cement : 2 fine sand) including testing of joints etc. complete :
Material :
NP 3 - 250 mm Dia Pipe Rmt 10 485.00 4,850.00
Carriage of Pipes Rmt 10 26 259
Portland Cement - cement of 4 joints Bag 0.24 280 67
Fine Sand - cement of 4 joints Cum 0.017 800 14
Misc. Charges @ 3% LS 156
Labour:
Mason - 1st Class Day 0.6375 388 247
Beldar Day 2.125 318 677
Bhisti Day 0.5 318 159
Total Cost - A 6,429
Water Charges 1% 64
Electricicty Charges 2% 129
Total Amount - B 6,622
Add Contractor Prophit @ 15% 993
Total Cost for 10 Rmt 7,615
Rate for 1 Rmt 761
Add Service
Providing & Laying - NP3TaxPipe
@ 6%- 46
Total Rate for 1 Rmt for Pipe Dia 250 mm 807
Providing and laying non-pressure class NP3 R.C.C. pipes with collars
jointed with stiff mixture of cement mortar in the proportion of 1:2 (1
cement : 2 fine sand) including testing of joints etc. complete :
Material :
NP 3 - 300 mm Dia Pipe Rmt 10 700.00 7,000.00
Carriage of Pipes Rmt 10 26 259
Portland Cement - cement of 4 joints Bag 0.24 280 67
Fine Sand - cement of 4 joints Cum 0.017 800 14
Misc. Charges @ 3% LS 220
Labour:
Mason - 1st Class Day 0.675 388 262
Beldar Day 2.25 318 717
Bhisti Day 0.5 318 159
Total Cost - A 8,698
Water Charges 1% 87
Electricicty Charges 2% 174
Total Amount - B 8,959
Add Contractor Prophit @ 15% 1,344
Total Cost for 10 Rmt 10,303
Rate for 1 Rmt 1,030
Add Service
Providing & Laying - NP3TaxPipe
@ 6%- 62
Total Rate for 1 Rmt for Pipe Dia 250 mm 1,092
Providing and laying non-pressure class NP3 R.C.C. pipes with collars
jointed with stiff mixture of cement mortar in the proportion of 1:2 (1
cement : 2 fine sand) including testing of joints etc. complete
4 Nos Pipes - 2.5 x 4 = 10 M (Including Collars & Spigot)
Material :
NP 3 - 400 mm Dia Pipe Rmt 10 1,100.00 11,000.00
Carriage of Pipes Rmt 10 26 259
Portland Cement - cement of 4 joints Bag 0.24 280 67
Fine Sand - cement of 4 joints Cum 0.017 800 14
Misc. Charges @ 3% LS 340
Labour:
Mason - 1st Class Day 0.75 388 291
Beldar Day 2.5 318 796
Bhisti Day 0.5 318 159
Total Cost - A 12,926
Water Charges 1% 129
Electricicty Charges 2% 259
Total Amount - B 13,314
Add Contractor Prophit @ 15% 1,997
Total Cost for 10 Rmt 15,311
Rate for 1 Rmt 1,531
Add Service
Providing & Laying - NP3TaxPipe
@ 6%- 92
Total Rate for 1 Rmt for Pipe Dia 400mm 1,623
Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10
graded stone aggregate 40 mm nominal size) all-round on jointing collar
ofRC.C. pipes over the bed concrete as per standard design : (Considered
150 mm thick alround) ,The cost of PCC bed concrete shall be paid in
seperate item.
250 mm dia - Rate Analysis for For 7.24 Rmt. Pipe = 1 Cum (PCC) 0.138 7.24 1.00
Material :
PCC 1:5:10 All Around Cum 1 Err:508 Err:508
Misc. Charges @ 3% LS Err:508
Labour:
Mason - 1st Class Day 0.2 388 78
Beldar Day 0.6 318 191
Total Cost - A Err:508
Water Charges 1% Err:508
Electricicty Charges 2%
Total Amount - B Err:508
Add Contractor Prophit @ 15% Err:508
Total Cost for 7.24 Rmt Err:508
Rate for 1 Rmt Err:508
PCC 1:5:10 All Around 150mm - Total Rate for Add Service
1 Rmt Tax @Dia
for Pipe 6% Err:508
250mm Err:508
Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse sand : 10
graded stone aggregate 40 mm nominal size) all-round on jointing collar
ofRC.C. pipes over the bed concrete as per standard design : (Considered
150 mm thick alround) ,The cost of PCC bed concrete shall be paid in
seperate item.
300 mm dia - Rate Analysis for For 5.94 Rmt. Pipe = 1 Cum (PCC) 0.168 5.94 1.00
Material :
PCC 1:5:10 All Around Cum 1 Err:508 Err:508
Misc. Charges @ 3% LS Err:508
Labour:
Mason - 1st Class Day 0.25 388 97
Beldar Day 0.75 318 239
Total Cost - A Err:508
Water Charges 1% Err:508
Electricicty Charges 2%
Total Amount - B Err:508
Add Contractor Prophit @ 15% Err:508
Total Cost for 5.94 Rmt Err:508
Rate for 1 Rmt Err:508
PCC 1:5:10 All Around 150mm - Total Rate for Add Service
1 Rmt Tax @Dia
for Pipe 6% Err:508
300mm Err:508
400 mm dia - Rate Analysis for For 1.86 Rmt. Pipe = 1 Cum (PCC) 0.403 2.48 1.00
Material :
Stone Aggregate 40mm Cum 0.89 1,350 1,202
Carriage of Stone as above Cum 0.89 103 92
Coarse Sand Zone III Cum 0.47 1,550 729
Carriage of Coarse sand Cum 0.47 103 48
Cements OPC 43 Grade Bag 2.6 280 728
Carriage of Cement Bag Bag 0.13 92 12.00
Misc. Charges @ 3% LS 84
Labour:
Mason - 1st Class Day 0.3 388 116
Beldar Day 0.8 318 255
Total Cost - A 3,266
Water Charges 1% 33
Electricicty Charges 2%
Total Amount - B 3,299
Add Contractor Prophit @ 15% 495
Total Cost for 2.48 Rmt 3,794
Rate for 1 Rmt 1,530
PCC 1:5:10 All Around 150mm - Total Rate for Add Service
1 Rmt Tax @Dia
for Pipe 6% 92
400mm 1,622
0.91 m deep with S.F.R.C. cover and frame (heavy duty, HD-20 grade
designation) 560 mm internal diameter conforming to I.S. 12592, total
weight of cover and frame to be not less than 182 kg., fixed in cement
concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20
mm nominal size) including centering, shuttering all complete.
(Excavation, foot rests and 12mm thick cement plaster at the external
surface shall be paid for separately) :
Cost for 1 Manhole Depth Upto 910mm with Cover Int. Dia 560mm Class - HD-20
Material & concrete
Foundation Labour Included
1:3:6 mixIn(1The Rates:
cement : 3 coarse sand : 6 graded stone
aggregate 40 mm nominal size) - 225mm Thickness of Bed Concrete Cum 0.585 5,009 2,930
FormWork Sqm 2.09 350 731
Brick Workchannel
Necessary cementinmortar
cement 1:4 (1 cement
concrete 1:2:4:4(1coarse
cementsand)
: 2 coarse sand : 4 graded Cum 0.559 #REF! #REF!
stone aggregate
Cement 20mm
plaster 12 mmthick
nominal
withsize)
cement mortar 1:3 (1 cement : 3 coarse sand) Cum 0.15 5,703 855
finished with a floating coat of neat cement, Sqm 2.100 #REF! #REF!
Fixing of Manhole Cover HD -20 Nos 1 1,250 1,250
Misc. Charges @ 3% LS #REF!
Labour for Manhole Cover Fixing & Handling
Mason - 1st Class Day 0.2 388 78
Beldar Day 0.5 318 159
Total Cost - A #REF!
Water Charges 1% #REF!
Electricicty Charges 2%
Total Amount - B #REF!
Add Contractor Prophit @ 15% #REF!
Total Cost for 1 Nos Manhole #REF!
Rate for 1 Nos #REF!
Add Service Tax @ 6% #REF!
Total Rate for 1 MANHOLE #REF!
Extra depth for circular type manhole 0.91m internal dia (at bottom)
beyond 0.91m to 1.67m
Cost for 1 Manhole Depth Upto 910mm with Cover Int. Dia 560mm Class - HD-20
Material & Labour
Foundation concreteIncluded In(1
1:3:6 mix The Rates:
cement : 3 coarse sand : 6 graded stone
Aggregate 40 mm nominal size) - 300mm Thickness of Bed Concrete Cum 1.18 5,009 5,910
Form Work Sqm 2.09 350 731
Brick Work
Cement cement
plaster 12 mmmortar
thick1:4 (1cement
with cementmortar
:4 coarse sand)
1:3 (1 cement : 3 coarse sand) Cum 1.29 #REF! #REF!
finished with a floating coat of neat cement, Sqm 4.480 #REF! #REF!
Extra depth for circular type manhole 1.22 m internal dia (at bottom)
beyond 1.68 m to 2.29 m :
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Material & Labour
Foundation concreteIncluded In The
1:5:10 mix Rates: : 5 coarse sand : 10 graded stone
(1 cement
Aggregate 40 mm nominal size) - 300mm Thickness of Bed Concrete Cum 0.18 Err:508 Err:508
Form Work Sqm 1.30 350 455
Brick
CementWork cement
plaster 12 mmmortar
thick1:4 (1cement
with cementmortar
:4 coarse sand)
1:3 (1 cement : 3 coarse sand) Cum 0.29 Err:508 Err:508
finished with a floating coat of neat cement, Sqm 1.080 Err:508 Err:508
Precast R.C.C. grating with frame 500x450 mm horizontal grating Cum 0.150 Err:508 Err:508
Fixing of Grating Cover - Pre Cast Horizontal (450x500)mm Nos 1 650 650
Misc. Charges
Labour @ 1% Channel, Fixing of Foot Rest & Manhole Cover Fixing &
for Making LS Err:508
Handling
Mason - 1st Class Day 0.2 388 78
Beldar Day 0.4 318 127
Total Cost - A Err:508
Water Charges 1% Err:508
Electricicty Charges 2%
Total Amount - B Err:508
Add Contractor Prophit @ 15% Err:508
Total Cost for 1 Nos Manhole Err:508
Rate for 1 Nos Err:508
Add Service Tax @ 6% Err:508
Total Rate for 1 Road Gully Chamber Err:508
Extra depth for masonry road gully chamber 50x45x60 cm beyond 0.6 m to
0.9 m :
With common burnt clay F.P.S. (non modular) bricks of class designation 7.5
Constructing masonry Chamber 60x45x50 cm inside, in brick work in cement mortar 1:4
(1 cement : 4 coarse sand) for water meter & butterfly valve complete with C.I. double
flap surface box 400x200x200 mm (inside) with locking arrangement and RCC top slab
1:2:4 mix (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) ,
i/c necessary excavation, foundation concrete 1:5:10 ( 1 cement : 5 fine sand:10 graded
stone aggregate 40 mm nominal size) and inside plastering with cement mortar 1:3 (1
cement : 3 coarse sand) 12 mm thick, finished with a floating coat of neat cement
complete as per standard design :
With common burnt clay F.P.S.(non modular) bricks of class designation 7.5
Excavation Rmt 1.66 130 215 1.21 1.06 4.54 0.454
PCC - (1:5:10) Cum 0.13 Err:508 Err:508 1.06 0.91 3.94 0.394
100 mm dia - Rate Analysis for For 17 Rmt. Pipe = 1 Cum (PCC) - All Round 75mm 0.059 17.00 1.00
Material :
Total Cost of M-5 (1:5:10) Cum 1 Err:508 Err:508
Misc. Charges @ 3% LS Err:508
Labour:
Mason - 1st Class Day 0.1 351 35
Beldar Day 0.5 318 159
Total Cost - A Err:508
Water Charges 1% Err:508
Electricicty Charges 2%
Total Amount - B Err:508
Add Contractor Prophit @ 15% Err:508
Total Cost for 17 Rmt Err:508
Rate for 1 Rmt Err:508
Add Service Tax @ 6% Err:508
PCC 1:5:10 All Around - Total Rate for 1 Rmt for Pipe Dia 100mm Err:508
150 mm dia - Rate Analysis for For 13 Rmt. Pipe = 1 Cum (PCC) - All Round 75mm 0.077 13.00 1.00
Material :
Total Cost of M-5 (1:5:10) Cum 1 Err:508 Err:508
Misc. Charges @ 3% LS Err:508
Labour:
Mason - 1st Class Day 0.15 351 53
Beldar Day 0.6 318 191
Total Cost - A Err:508
Water Charges 1% Err:508
Electricicty Charges 2% Err:508
Total Amount - B Err:508
Add Contractor Prophit @ 15% Err:508
Total Cost for 13 Rmt Err:508
Rate for 1 Rmt Err:508
Add Service Tax @ 6% Err:508
PCC 1:5:10 All Around - Total Rate for 1 Rmt for Pipe Dia 150mm Err:508
160 mm dia - Rate Analysis for For 14.9 Rmt. Pipe = 1 Cum (PCC) -
All Round 75mm 0.067 14.90 1.00
Material :
Total Cost of M-5 (1:5:10) Cum 1 Err:508 Err:508
Misc. Charges @ 3% LS Err:508
Labour:
Mason - 1st Class Day 0.1 388 39
Beldar Day 0.5 318 159
Total Cost - A Err:508
Water Charges 1% Err:508
Electricicty Charges 2%
Total Amount - B Err:508
Add Contractor Prophit @ 15% Err:508
Total Cost for 14.9 Rmt Err:508
Rate for 1 Rmt Err:508
Add Service Tax @ 6% Err:508
PCC 1:5:10 All Around 75mm - Total Rate for 1 Rmt for Pipe Dia 160mm Err:508
200 mm dia - Rate Analysis for For 13 Rmt. Pipe = 1 Cum (PCC) -
All Round 75mm 0.078 12.75 1.00
Material :
Total Cost of M-5 (1:5:10) Cum 1 Err:508 Err:508
Misc. Charges @ 3% LS Err:508
Labour:
Mason - 1st Class Day 0.1 388 39
Beldar Day 0.5 318 159
Total Cost - A Err:508
Water Charges 1% Err:508
Electricicty Charges 2%
Total Amount - B Err:508
Add Contractor Prophit @ 15% Err:508
Total Cost for 12.7 Rmt Err:508
Rate for 1 Rmt Err:508
Add Service Tax @ 6% Err:508
PCC 1:5:10 All Around 75mm - Total Rate for 1 Rmt for Pipe Dia 160mm Err:508
Providing, fixing, jointing and testing in position the following uPVC pipes
conforming to IS : 4985 of 10 kg/cm2 pressure rating including all fittings like T
- bend , elbow , reducer etc .with solvent joint complete and making good the
same complete as required.
Providing & laying UPVC pressure pipes of 6Kg/Sq.cm pressure rating class V
(IS : 4985-2000) including fittings, tees, bends, clamps, coupling and adaptors
supports, and jointing with solvent joint, testing and & fittings and thrust
blocks at bends as per standard design (For garden hydrants).
Cost of 10 M
Material
G.I. pipes :25 mm dia metre 11.50 110.00 1265.00(A) Weight for carriage = pipe weight
+ 15% for fiitings = 11.5 Rmt including carriage Rmt 11.5 115 1,323
White lead, hemp, oil etc. LS 10 2 20
Cement, sand and grit etc. if Any LS 5 2 10
Two or more Coats of Enamel Paint & primer @ Area 1.1 sqm Rmt 11.5 13 144
Misc. Charges @ 3% LS 41
Labour:
Fitter / Welder /Blacksmith 1st Class (For 8 Hours) Day 0.33 426 141
Fitter / Welder/blcksmith 2nd Class (For 8 Hours) Day 0.98 386 378
Beldar / Bhisti / Labour (For 8 Hours) Day 0.66 318 210
Total Cost - A 2,267
Water Charges 1% 23
Electricicty Charges 2% 45
Total Amount - B 2,335
Add Contractor Prophit @ 15% 350
Total Cost for 10 Rmt 2,685
Rate for 1 Rmt 268
Add Service Tax @ 6% 16
25mm Dia - GI Medium Duty Pipe Class B - Total Rate for 1 Rmt 285
Work Schedule for External Development Works on South Side
SL No Description
Unit Total Qty Rate Amount REMARK
97.00
Part 4 - Draingae Works Base Price
With common burnt clay F.P.S.(non modular) bricks of class (Black Bituminous paint detail not mentioned in item for C.I. cover & Fixing /
2.1 EACH 27- Err:508 Err:508
designation 7.5 provision of sleeves details for water meter not clear.
Providing and fixing cast iron double flanged butterfly valves - CONSIDERED:
3 conforming to IS 13095 PN 1.6 complete with bolts, nuts, 3.0 mm - - ADVANCE/ mi
3.1 thick
100 MMcompressed
DIA asbestos gasket. EACH - 1,650.00 - AUDCO/
Providing, fixing, jointing and testing in position the C.I. class LA - MAKE
4 pipe conforming to IS :1536 including all necessary fittings & - - CONSIDERED:
4.1 specials
100 MM DIAsuch as bends, junctions etc., Lead Joint RM 60.00 1,100.43 66,025.98 NICO
4.2 Excavating
150 MM DIA trenches
For STP of requried width for pipes, cables,etc RM 140.00 1,742.48 243,947.03
including excavation for sockets and dressing of sides ramming of
bottoms depth upto 1.5 m including gtting out the excavated soil -
5 and then
Pipes, returning
cables the soil as 80
etc. exceeding required in but
mm dia. layers
notnot exceeding
exceeding 30020 - -
5.1 cm. in
mm diadepth including cosolidating each deposited layer by RM 200.00 175.39 35,077.30
ramming watering etc. and disposing of surplus excavated soils as
Providing and laying
directed within a leadcement
of 50 m concrete 1:5:10 (1 cement : 5 -
coarse sand : 10 graded stone aggregate 40 mm nominal size) all-
6 - -
round CI- LA class pipes including bed concrete as per standard
6.1 100 MM: DIA
design RM 60.00 Err:508 Err:508 150 mm bed concrete, 75 mm allaround
6.2 150 MM DIA RM 140.00 Err:508 Err:508
-
MAKE
2 - including all fittings (plain or door) eg., bends, junctions, cowls, offsets, access pieces jointingCONSIDERED;
Providing and fixing Spun cast iron soil, waste, vent and rain water pipes conforming to IS : 3989 NiKo
drip seal joints and painting also as per manufacturer's specification, and making good complete in all respects. FROM BASEMENT TO MANHOLE
2.1 200 MM DIA RM 80.00 3,770.90 301,672.25 KAPILANSH
Providing and laying cement concrete 1:5:10 (1 cement : 5
coarse sand : 10 graded stone aggregate 40 mm nominal size) all-
3 -
round UPVC & CI pipes including bed concrete as per standard
3.1 160 MM: DIA
design RM 85.00 Err:508 Err:508 150 mm bed concrete, 75 mm alaround
3.2 200 MM DIA RM 80.00 Err:508 Err:508
Providing and laying non-pressure class NP3 R.C.C. pipes with collars MAKE
4 jointed with stiff mixture of cement mortar in the proportion of 1:2 (1 - - CONSIDERED:
cement : 2 fine sand) including testing of joints etc. complete : JAI SPUN PIPE
0.91 m deep with S.F.R.C. cover and frame (heavy duty, HD-20
grade designation) 560 mm internal diameter conforming to I.S.
12592, total weight of cover and frame to be not less than 182 kg.,
MAKE FOR
fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4
- SFRC: JAI SPUN
graded stone aggregate 20 mm nominal size) including centering,
PIPE
shuttering all complete. (Excavation, foot rests and 12mm thick
cement plaster at the external surface shall be paid for
separately) :
Extra depth for circular type manhole 0.91m internal dia (at
-
bottom) beyond 0.91m to 1.67m
1.68 m deep with SFRC Cover and frame (heavy duty HD-20
grade designation) 560 mm internal diameter conforming to I.S.
12592, total weight of cover and frame to be not less than 182 kg.
MAKE FOR
fixed in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4
- SFRC: JAI SPUN
graded stone aggregate 20 mm nominal size) including centering,
PIPE
shuttering all complete. (Excavation, foot rests and 12 mm thick
cement plaster at the external surface shall be paid for
separately) :
Extra depth for circular type manhole 1.22 m internal dia (at
-
bottom) beyond 1.68 m to 2.29 m :
10.1 pipes cables etc. exceedign 80 mm dia but not exceeding 300 mm RM 565.00 175.39 99,093.37
10.2 pipes cables etc. exceedign 300 mm dia but not exceeding 600 mm RM 305.00 272.95 83,250.51
De-Silting Chamber: -
Drilling: -
Providing and laying pea gravel all around the casing pipe. - No. of Boring Required
Rate shall include excavation, back filling and all other operations Tentative - Rate for B/W Harvesting Pit for Complete Item (Detail
11.1 EACH 4.00 370,000.00 1,480,000.00
necessary for completing the job. required)
Providing & laying UPVC pressure pipes of 6Kg/Sq.cm pressure UPVC PIPE
rating class V (IS : 4985-2000) including fittings, tees, bends, CONSIDERED
1 clamps, coupling and adaptors supports, and jointing with solvent 10Kg/Sq.cm AKG , Ajay
joint, testing and & fittings and thrust blocks at bends as per class V Make:
standard design (For garden hydrants). Prince Pipe
3.1 25 MM DIA RM 15.00 268.48 4,027.16 Basic Rate of Pipe as per Class B
AUTH. SIGN.
Comparison of Storm Water works at Reach Airia Mall
S.No. Description Unit Qty Rate Amount
Providing and laying non-pressure class NP3 R.C.C. pipes with collars
1 jointed with stiff mixture of cement mortar in the proportion of 1:2 (1
cement : 2 fine sand) including testing of joints etc. complete :
250 mm dia RM RO
300 mm dia RM RO
400 mm dia RM 55 -
250 mm dia RM RO
300 mm dia RM RO
400 mm dia RM 11 -
Providing and laying cement concrete 1:5:10 (1 cement : 5 coarse
2b sand : 10 graded stone aggregate 40 mm nominal size) Haunches for
the RCC pipe.
250 mm dia RM RO
300 mm dia RM RO
400 mm dia RM 55 -
Constructing brick masonry circular type manhole 0.91 m internal
dia at bottom and 0.56m dia at top in cement mortar 1:4 (1
cement :4 coarse sand), in side cement plaster 12 mm thick with cement
mortar 1:3 (1 cement : 3 coarse sand) finished with a floating coat of
3 neat cement, foundation concrete 1:3:6 mix (1 cement : 3 coarse sand :
6 graded stone aggregate 40 mm nominal size), and making necessary
channel in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded
stone aggregate 20 mm nominal size) finished with a floating coat of
neat cement, all complete as per standard design :
0.91 m deep with S.F.R.C. cover and frame (heavy duty, HD-20
grade designation) 560 mm internal diameter conforming to I.S.
12592, total weight of cover and frame to be not less than 182 kg., fixed
in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone Nos. 2 -
aggregate 20 mm nominal size) including centering, shuttering all
complete. (Excavation, foot rests and 12mm thick cement plaster at
the external surface shall be paid for separately) :
With common burnt clay F.P.S. (non modular) bricks of class designation
7.5
Extra depth for circular type manhole 0.91m internal dia (at bottom)
4 beyond 0.91m to 1.67m
RM 1 -
With common burnt clay F.P.S. (non modular) bricks of class designation
7.5
Constructing brick masonry circular manhole 1.5 m internal dia at
bottom and 0.56 m dia at top in cement mortar 1:4 (1 cement :4
coarse sand) inside cement plaster 12 mm thick with cement mortar 1:3
(1 cement : 3 coarse sand) finished with a floating coat of neat cement
5 foundation concrete 1:3:6 (1 cement : 3 coarse sand : 6 graded stone
aggregate 40 mm nominal size) and making necessary channel in
cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone
aggregate 20 mm nominal size) finished with a floating coat of neat
cement, all complete as per standard design :
1.68 m deep with SFRC Cover and frame (heavy duty HD-20
grade designation) 560 mm internal diameter conforming to I.S.
12592, total weight of cover and frame to be not less than 182 kg. fixed
in cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded Nos. 2 -
stone aggregate 20 mm nominal size) including centering, shuttering all
complete. (Excavation, foot rests and 12 mm thick cement plaster at the
external surface shall be paid for separately) :
With common burnt clay F.P.S. (non modular) bricks of class designation
7.5
Extra depth for circular type manhole 1.5 m internal dia (at bottom)
6 beyond 1.68 m to 2.29 m :
RM 2 -
With common burnt clay F.P.S. (non modular) bricks of class designation
7.5
7 Constructing Brick Buffel wall inside 1.5 m Internal dia Nos. 1 -
TOTAL -
Service Tax @ 6% -
COST OF TRIPS
1 2 3 4 5 6 7 8
Capacity Considered Cost per Trip per unit i/c 15% CP & OH
MATERIAL Unit of Rates
Per Trip Quantity
Saving (7,002,206)
COST OF TRIPS
1 2 3 4 5 6 7 8
Capacity Considered Cost per Trip per unit i/c 15% CP & OH
MATERIAL Unit of Rates
Per Trip Quantity
PS
9 10 11 12 13 14
253 34
320 43
388 53
514 72
642 91
OH
2
15.16
15.16
1,288,281
1,064,979
223,302
PS
9 10 11 12 13 14
209 28
265 36
320 44
425 60
531 75
OH
2
12.53
12.53
1,064,979
Description Of Item Unit Rate Excl. ST Remarks if Any
Cement Mortar with Fine Sand
Cement Mortar 1: 1 (1 cement : 1 Fine sand) Cum #ERROR!
Cement Mortar 1: 2 (1 cement : 2 Fine sand) Cum Err:508
Cement Mortar 1: 3 (1 cement : 3 Fine sand) Cum Err:508
Cement Mortar 1: 4 (1 cement : 4 Fine sand) Cum Err:508
Cement Mortar 1: 5 (1 cement : 5 Fine sand) Cum Err:508
Cement Mortar 1: 6 (1 cement : 6 Fine sand) Cum Err:508
Cement Mortar with Coarse Sand
Cement Mortar 1: 1 (1 cement : 1 Coarse sand) Cum Err:508
Cement Mortar 1: 2 (1 cement : 2 Coarse sand) Cum Err:508
Cement Mortar 1: 3 (1 cement : 3 Coarse sand) Cum Err:508
Cement Mortar 1: 4 (1 cement : 4 Coarse sand) Cum Err:508
Cement Mortar 1: 5 (1 cement : 5 Coarse sand) Cum Err:508
Cement Mortar 1: 6 (1 cement : 6 Coarse sand) Cum Err:508
Cement Concretes
Err:509 Cum Err:508
Err:509 Cum Err:508
Err:509 Cum Err:508
Err:509 Cum Err:508
Brick work with common burnt clay F.P.S. (non modular) bricks of clas designation 7.5 in
Brick Works
foundation upto Plinth Level
Brick workand plinth
with in:
common burnt clay F.P.S. (non modular) bricks of class
Cement Mortar (1
designation Cement : 4 Coarse Sand ) plinth in: Cum Err:508
Brick work with common burntand
7.5 in foundation clay F.P.S. (non modular) bricks of class
Cement Mortar
designation (1 foundation
7.5 in Cement : 5and Coarse Sand
plinth in: ) Cum Err:508
Cement Mortar (1 Cement : 6 Coarse Sand ) Cum Err:508
Finishing Works
Cement plaster 1:3 (1 cement: 3 coarse sand) finished with a floating coat
of neat cement. Sqm Err:508
Description of Item Unit Nos L B H Total
All Round PCC as per Fig. No. 19.11
Dia of Pipe -400mm - Thickness -32mm
Bottom Bed Cum 1 1 0.764 0.15 0.115
Around Above of Pipe R - 540mm Cum 0.5 3.14 0.2916 1 0.458
Less Volumne of Pipe Cum -1 3.14 0.054 1 -0.169
Total Qty of PCC for 1 M 0.403
1 Cum Consumption Length of Pipe 2.479
Circular Manhole Dia 910mm at Bottom & 560mm
Dia at top.
Foundation Concrete 225mm Offset & Thickness Cum 1 3.14 0.828 0.225 0.585
FormWork Cum 1 6.28 0.910 0.225 1.286
Brick Work (1:4) (Avarage Dia = 0.85mm) Cum 6.28 0.425 0.23 0.91 0.559
Internal Plaster 12mm (1:3) Sqm 6.28 0.3675 0.91 2.100
Neat Cement Punning / Floating Coat of Cement Sqm 6.28 0.3675 0.91 2.100
Cement Concrete 1:2:4 for Drain Channel Cum 6.28 0.425 0.23 0.91 0.559
1.47
0.735
1.195
0.66
0.55
0.33
0.37