Constructability Concepts File
Constructability Concepts File
,_
'j
I
j
I
I
I
I
I
i!
'.·. ~~i-J
TABLE OF CONTENTS
Section Page
Introduction
INTRODUCTION
represented on the CII Constructability Task Force and on the findings of research
programs directed by the task force. The research convincingly shows that major cost
savings and schedule improvement can result from the effective implementation of the
principles of constructability. The task force defines constructability as "the optimum use
Thirteen constructability concepts are presented in this report, along with sample
applications of the concepts. The first six concepts relate to the conceptual planning phase
of a project. The remaining seven relate to the design and procurement phase. Concepts
practices in a manner that will enable practitioners in any organization to take advantage
of the lessons learned by others and apply them in their organizations and on their projects.
While the reader may find that some of the concepts or applications will be directly
applicable to their projects, the primary purpose of the Conce11ts File is to stimulate
thinking about constructability and how to make it work. This is not a checklist, nor is it a
cook book. Experienced people will have to study the concepts and the sample applications
to determine which will be best for their company and their projects.
I
Conceptual planning involves defining functional and performance requirements,
evaluating project feasibility, and studying criteria for preliminary engineering. The
decisions made during this phase have a major impact during the remainder of the project,
major construction methods that influence the design approach clearly indicate the need to
phase of conceptual planning, the cost impact of decisions here is still very high and many
however, can be quite different. While conceptual planning constructability tends to focus
schedules.
The task force research also identified the best practices in organizing for
constructability among many companies. These practices arc presented in Guidelines for
Implementing a Constructability Program, which will help the reader begin the
development of his own company specific programs. It will also be helpful in thinking
through the nature of the constructability efforts that may be appropriate for a given
2
constructability organization, and in the establishment of the basic procedures to be
followed.
The task force believes that the adoption of new technology such as three-
Constructability personnel must be prepared to adapt to these new approaches and provide
the appropriate planning input to all the participants who will impact directly and
The initial publication by the task force, Constructability: A Primer, and its second
3
--------
CONSTRUCTABILITY CONCEPTS
Concept I-1: Constr11ctability programs are made an integral part of project execution
plans.
Discussion
project, the plan for achieving it must be published as part of the project execution plan.
A project execution plan is an integrated and coordinated program for completing all
project activities and achieving all project objectives. In most cases these plans are
prepared by an owner project manager at a very early stage of the owner's project efforts.
These owner plans then influence the nature of the plans of the designers and constructors,
which will be coordinated with the owner's plan. In the absence of an owner plan,
designers and constructors each benefit from having their own project execution plans
operating procedures, the schedule and budget, and the overall project strategy. It also
5
includes the contracting/subcontracting plan, the procurement plan, and the construction
plan. It defines the project environment and identifies potential constraints to the
successful completion of the project. Project execution plans are prepared in different
ways by owners, designers, and constructors with varying degrees of formality according to
the nature and size of the project. The areas listed above are considered, however, in all
project execution plans - explicitly or implicitly. When a project manager wants a high
effectively on a project, a written plan will be published for that area as an explicit part
organizations. It will not happen unless the change is well planned and well managed.
program is not totally integrated into the project execution plan, constructability will not
planning, design, and construction, then its full benefits will not be achieved.
activities from the outside. They must be a part of the project team and work on the inside
of the project. This can only be achieved when the organization and procedures of doing
so are set forth in a constructability program that is published by the project manager as
6
A project-specific constructability program applies the general constructability
knowledge and experience to meet project objectives. The program should build a team
major decisions during all phases of a project, especially during conceptual planning and
other activities, but rather encourage decision-making based on the needs of the entire
project.
including:
Helping to establish project goals and objectives. Goals of the engineering and
construction groups should support overall project goals, thus avoiding the pitfall of sub-
optimiza ti on.
Providing a logical and systematic manner for integrating design and construction.
process - it is nothing new. The problem lies in getting people (designers and constructors)
from diverse cultural backgrounds and with potentially different driving goals to work
effectively integrating design and construction • a •common sense• need that has been
7
Providing a mechanism for obtaining field. construction expertise as needed.
resolved before design is finalized in a manner that reduces field costs without adversely
impacting design cost/schedule. Better yet, a constructability program can be useful in the
development of project specifications, thus getting construction know'!edge into the design
shared understanding increases mutual respect, aids communication, and can prevent
construction from making a serious mistake from a seemingly insignificant field change.
Implementation of this concept will vary among owners, designers, and constructors,
and from one contracting approach to another. Regardless, it is important that a plan be
the parameters of the overall project execution plan and the execution plans for the
separate phases.
Applications
project, a project execution plan to achieve the project objectives should be prepared early
in the project development effort. This plan defines how the necessary resources will be
brought to bear on the project, including in-house staff and contractor capabilities to
8
owner's execution plan to establish how the owner will acquire and utilize construction
knowledge and experience during the early conceptual planning phase of the project, and
to define what the owner will require contractors to do to achieve constructability for their
responsibility to a single firm, the contract should include a requirement for the contractor
to incorporate constructability into his execution plan. This provision is appropriate under
either a fixed-price or a cost-reimbursable contract. In either case, the owner can set forth
management contractor to act for the owner in planning and achieving the project
objectives. The contract should establish the nature of the constructability program
required of the construction manager. The owner also can require the construction
all of which should be coordinated so that the set of execution plans effectively address all
actions required by all parties in executing the plan. In the absence of an owner plan or a
requirement by the owner for the construction manager to prepare an execution plan,
Design Contractor. Designers prepare their own project execution plans, which
reflect their contractual commitments to owners and their own company approach to
9
---------- -----------------------------
planning and executing their work. These plans arc coordinated with owner execution
plans. Designers should include constructability in their execution plans. These plans will
program to improve the quality of his design products. The designer's program should
constructability efforts.
projects. For cost-reimbursable contracts, these plans reflect the requirements of the owner
in detail and are coordinated with the owner's plan. One of the advantages of the cost-
owner does not prepare an execution plan or does not require the contractor to prepare a
their execution plans and present them to the owners for their concurrence in the
10
constructability in the design, fabrication, and shipping of their products, whether shipped
requirements in requisitions and purchase orders. Examples are water treatment plants,
steam generating units, prefabric.ated buildings, and packaged heating and cooling systems.
manner. The key is the proper and detailed identification of the data in
procurement documents.
e. The site need date should be specified in purchase orders to avoid delays and
11
Concept 1-2: Project planning actively involves construction knowledge and experience.
Discussion
This constructability concept addresses achieving cost and schedule benefits through
the inclusion of construction people in the early planning teams. When faced with a
decision to construct a new facility, owners establish formal or informal project planning
teams. These teams are responsible for determining how best to satisfy a business need, for
example the manufacturing of a new product, increasing existing capacity, reducing costs,
or improving quality. Many factors arc involved in these analyses with most being obvious,
including:
• Cost of labor
• Plant capacity
• Manufacturing process
Often these planning teams do not include members with significant construction
knowledge and experience. A number of construction sensitive factors can influence the
cost and time frame for completion of construction, and these can be acted upon during the
conceptual planning stage of a project when the potential for influence is greatest if people
13
who are sensitive to them participate in the planning process. It is critical that the right
Applications
Establishment of Project Objectives. One of the early efforts by the planning team
is establishing the overall project objectives. These objectives should address the balance
among such areas as cost, schedule, quality, and reliability. Clearly stated objectives and
and the quality assurance program. These objectives also will be important in preparing
the project execution plan, including the budget and schedule. The participation of an
experienced construction person on the team will insure that all implications to
construction operations will be considered. The implications are not always apparent to
people without field construction experience. Highly competent executives and engineers
sometimes are not familiar with construction related issues that may have major cost and
schedule saving potential. It is important that these issues receive consideration during
select major construction methods, and to assure that the design approach is both consistent
considered during the early project planning. Such considerations are important when
14
Site Selection. While business factors normally influence the general geographic
area for a new facility, the choice of a specific site in this area can in many cases impact
construction productivity, cost, and schedule. For example, subsurface conditions normally
are explored by gcotcchnical consultants, but only infrequer..tly are site logistics issues such
as access for heavy equipment, laydown areas for temporary storage, and local
Schedule Feasibility. Most projects arc driven by market forces, and are considered
economical when they deliver a product or other value at the right time. This translates
into an overall project schedule that involves planning, design, procurement, and
construction. The schedule implicitly involves many assumptions and risks. A major risk
factor is the overall duration allowed for construction. Knowledgeable construction people
can minimize the risks and provide experienced input to schedule feasibility.
construction person, particularly one who has previous experience in the region, is well
qualified to prepare these estimates. The availability of skilled labor within commuting
distance, the need for training programs for specific crafts, the need for a construction
workers camp, .and the impact of adverse weather arc all important considerations for
productivity during the project. If these are not accurately assessed during early project
15
Preparing Estimates and Budgets. Construction input is essential in preparing
estimates and budgets for the project. Without specific construction knowledge supported
by site surveys, there is a tendency to apply general company experience from seemingly
similar past projects without recognizing the differences of the current one. Specific
indirect costs, and the unique conditions of the site can be effectively made by a
construction person.
evaluating the alternative contracting strategies available to an owner and in the selection
of the strategy that best suits the ·project's needs. This will involve assessment and
allocation of risk, consideration of the urgency of the schedule, the degree of flexibility
that may be required during the project, and the objectives concerning project cost.
provide valuable input to the owner, designer, and procurement agent concerning past
experience with specific sources, the need for in-plant quality surveillance, and the need
for special purchase order provisions to optimize the delivery of items as specified, on
16
Concept .I-3: The source and qualifications of personnel with construction knowledge and
Discussion
This concept addresses how owners can obtain the assistance of experienced
execution plans, owners develop their contracting strategy. This is governed by the owner's
construction contractors. A variety of strategies are available. The specific strategy for a
given project will be determined by the specific conditions and objectives of the project.
The contracting strategy will have a major influence on the availability of qualified
construction input during conceptual planning has been addressed previously and cannot
from constructability input will be lost. For instance, if the project delivery system
employs the traditional concept of separate contracts for the designer and general
contractor, the owner will have primary responsibility for coordinating early
constructability input. Since award of the general contract depends upon design
17
Some owners have in-house construction knowledge and experience, but many will
need to acquire this capability during the conceptual planning phase by some contractual
arrangement. This is possible through any contracting strategy if the need is recognized
early and specifically included in the strategy. Under any approach the right kind of
construction people must be involved and their qualifications must be clearly specified in
the contract documents. Personal qualifications are important, not just availability. Care
must be taken to avoid having someone who may be available between other assignments
simply plugged into the planning team in order to fill the constructability position. The
right kind of construction person will be mature and experienced, and command respect
from other team members. He should be a broad-gauged person who is able to understand
the full scope of project activities and their interrelationships. He should not be a zealot
who is concerned exclusively with construction needs. He must be able to work with people
from other disciplines and be able to communicate effectively. The need for the right kind
of construction people for early planning teams should be recognized, even if finding
Applications
Using Owner Construction Staff. While this concept addresses obtaining people
with construction knowledge and experience by contract, some owners maintain their own
construction staff that can develop and implement constructability programs without help
from other sources. Owners should be certain that their own staffs have the right
18
Using a Design-Construct Contractor. Construction knowledge and experience can
Using the Construction Contractor. An owner can select the construction contractor
phase of a project with no commitment to using that contractor as the ultimate constructor.
manager. In this case, the construction manager's scope of work should clearly state his
Using the Design Contractor. An owner may select the design contractor early
enough to provide constructability services, but this approach requires great care to assure
that qualified people are available. In this case, the contract with the designer should
specify that the constructability advisor to the owner will be a member of the owner's
consultant who is independent of the designer or constructor. This has the advantage of
19
In all of the above cases, care is required to assure the qualifications of the people
provided.
20
Concept l-4: Overall project schedules are construction sensitive.
Discussion
This concept establishes the principle that the project completion date and the
requirements of the construction phase should be considered in optimizing the project cost
and schedule. This concept addresses the overall project schedule, which balances and
allocates durations of time among the major project activities. A design and procurement
concept, "Design and procurement schedules arc construction sensitive," addresses the
detailed sequencing of effort for these activities within their allocated durations. The
optimizing time and costs to meet the owner's required date. While design, procurement,
and construction each has its own optimum sequence and duration, few overall project
schedules allow the optimization of all of them. Compromises are necessary and should be
The planning process often uses the "forward pass" schedule technique: satisfying
planning, design, and procurement time frames first, then leaving the balance to
construction. This occurs because the owner and designer representatives generally are
assume that construction has the flexibility to finish the field work in the remaining time.
To achieve the benefits of constructability, owners should guard against this approach and
require overall project schedules to be determined using a "backward pass" basis with an
21
analysis of the balance required among the times allocated to planning, design, procurment,
and construction.
has the potential of trading more costly field work for less costly planning, design, and
procurement activities. The result is a cost-effective overall project schedule. If the cost
of land and major engineered material and equipment items is set aside, field construction
activities result in about 40 percent of the project cost. There are many more construction
remoteness, etc.) less controllable than design and procurement. A construction sensitive
conceptual planning. Insufficient or ineffective planning can severely inpact costs during
expertise must be involved in the conceptual planning effort to establish a balanced overall
project schedule. This involvement will best facilitate the allocation of the total time
construction-sensitive schedules:
22
0 Establishment of realistic durations for construction activity to prevent costly
0 The lead times for delivery of major items of equipment under different
procurement approaches.
0 The allocation of sufficient time for mobilization in remote areas including the
0 The allocation of sufficient time for the contracting and subcontracting process.
allocation of overall project schedule time. Owners and planners must be sensitive to
project.
23
Applications
should address the several areas set forth as applications under Concept I-2,
and schedules.
4. When designs are prepared for single projects for which construction will be
competitively bid, owners must assure a proper balance among all project
activities, including their own planning phases, design, the contracting process,
and construction.
24
Concept 1-S: Basic design approaches consider major construction methods.
Discussion
This concept establishes the principle that major construction methods must be
considered during conceptual planning. These methods have significant influence on both
conceptual planning and design. Their consideration during conceptual planning, a brief
window of opportunity (as illustrated in Figure 1), raises cost effectiveness, design, and
HIGH
CONCEPTUAL PLANNING
1
§ DESIGN
i...
3... PROCUREMENT
!
.l2
!: CONSTRUCTION
=
•c
l
Lowl_~~~~~~~__::::::::::=~=----~
START
TIME
IST4RTUP I
COMPLETE
25
Major construction methods can be defined as the use of construction equipment,
labor, and work sequencing in such a way that the methods become a major design "driver."
In this case, a design driver is a construction method, condition, or technique that design
engineering must address, and which if exchanged later in the design or construction
Major construction methods for building and industrial projects relate to: site
grading and excavation; foundations; superstructure; enclosure; major building and process
during the start of conceptual planning. All members of the project team interact and
agree on the methodology that will quantitatively and qualitatively measure the output of
Detailed design issues related to major construction methods are discussed later
26
Applications
where local labor, resources, remote locations, or adverse weather are limiting factors.
conditions is a well point or other method for dewatering. A well point system can be
architectural, mechanical, and electrical features could be preassembled on the ground and
lifted into final position. Commercial or institutional buildings that consist of repetitive
27
Concept 1-6: Site layouts promote efficient construction.
·Discussion
Construction concerns often are neglected in the layout of permanent facilities, and
the layout of temporary facilities is seldomly integrated with that of permanent facilities.
coordinated with temporary facility plans. When temporary facilities are not well thought
out in advance and instead are "left to the field," the effects can be both costly and long-
term. Temporary facilities are expensive project clements that can adversely affect
Effective site layout can facilitate construction activities and thereby reduce cost in
I. Provide adequate space for laydown and fabrication yards and give serious
consideration to the location of such yards relative to the work site. Consider the
impact of adjacencies of and the efficiencies associated with flow and traffic
29
establishing clearances, give particular attention to heavy lift operations,
among different types of traffic such as vehicular and pedestrian, and locate
possible.
expense of temporary construction facilities may be avoided when the design and
field operations. Permanent utilities, enclosed space, and pavement should all be
considered.
low areas and areas of heavy runoff. Where snowfall is heavy, make plans for its
stockpiling.
30
7. Where pollutant emissions may adversely affect construction, seek alternatives in
which the effects are minimized. Where necessary, provide holding areas and
8. Consider potential needs for emergency access and evacuations. Site layout
considerations.
Layout plans for permanent and temporary facilities should be based on knowledge
of other subsidiary plans, such as the site organization, materials management plan,
The broad issue of expanded vs. consolidated layouts is worthy of analysis. While
can be very costly. Consolidated layouts, for example, can make accessibility problematic
and reduce productivity. On the other hand, cost savings may result from shorter piping
and electrical runs. Similarly, there are trade-offs in the vertical vs. horizontal layout
decision. This decision is often driven by land availability or the desire to minimize
The effects of poor site layout can be costly: reduced productivity, more frequent
accidents, and higher site utility expenses. The tactics described above reiterate the
temporary and permanent facility layout often significantly impact constructability and in
31
many cases, up-front analyses of temporary facilities have a significant impact on the
Applications
sequence, material flow, and crane location. Arca sterilization should be avoided.
3. The shoring of adjacent buildings may often be avoided by distancing new construction
4. Analyze installation traffic paths, cross traffic, and conflict points and consider void
5. Sites with adjacent railroad spurs and waterways should be considered for their
6. Plans for temporary facilities should be compatible with project schedules, with
consideration being given to the timing of space needs among various organizations.
commitment.
32
7. Scaffolding requirements and the need for elevated pipe racks can be minimized by
supporting major pipe runs on sleepers at grade. In this scheme, road crossings can be
8. Simulation programs are available for modelling construction traffic. They should be
given serious consideration on projects where construction operations arc dense and
site traffic is complex. The use of block models may also be beneficial, especially for
building/structure enclosure.
a. Utilities: permanent fire protection water lines servicing hydro-testing needs for
water, electric supply, permanent site drainage system and sewage system in place early
b. Enclosed space: permanent enclosed space constructed early to serve needs for
construction warehousing, contractor office space, service shops, or satellite tool rooms.
c. Pavement: roads, parking, and site pavement completed early to serve construction
needs.
33
d. Other: security gates; fire stations.
11. Where crusher plants are involved, consider the effects of dust in determining their
location. Wind effects on stockpiling of loose materials (soil, fine aggregates, etc.)
34
II
CONSTRUCTABILITY CONCEPTS
Concept II-1: Project constructability is enhanced when design and procurement schedules
Discussion
intitial project planning seeks to optimize the overall schedule for maximum benefit to the
entire project. This optimization almost always centers around cost or schedule issues.
Both design and procurement decisions have high cost and schedule leverage and should be
arrived at in a deliberate and accurate manner. The relatively large cost of construction
when compared to design and procurement, however, usually gives construction the greatest
weight in schedule optimization. Project planning should address these relationships and
cost values as early as possible. This analysis usually will confirm the generalization that
project cost effectiveness is best served when both design and procurement schedules
The failure to consider the construction schedule and its momentum, characteristics,
and cost in relation to design and procurement is an expensive management error. Some of
35
the most frequent management problems in the design and procurement phase of project
development stem from incomplete planning, cost analysis, and schedule reconciliation for
the entire project. Often there is great pressure to get design started, which may create an
The owner, the project manager, the construction manager, the designer, and the
contractor have three major areas to work with in optimizing a schedule: design;
procurement; and construction. Although each has a certain sequence for its most efficient
accomplishment, they must be integrated to provide the most efficient overall project
schedule.
Design. This cannot be started until basic criteria, space allocation, aesthetics,
functionality, capacity, flow size, or process parameters are fixed. Once started there are
path or area is possible if it is identified early and incorporated into the design work plan.
Design also can exert a strong impact on the schedules for both procurement and
construction through the choice of materials and equipment. Design choices also impact
the design schedule itself. For example, the design time required for a steel-framed
structure is less than the design time required for an equivalent concrete structure. These
36
From a cost viewpoint, design normally represents as much as 8 to 16 percent of the
total project cost, and thus lends itself to schedule adjustment to accomodate the more
costly area of construction, which typically accounts for approximately 40 percent or more
of project cost.
Conversely, the worst impact of failure to consider construction schedules during design
may occur when design and construction are done separately. The risk here is that the
Procurement. The procurement schedule for major items is generally fixed by vendor
production capacity and has relatively low flexibility to accelerate. Occasionally, payment
of large cost premiums can accelerate these major procurements, but is an exception.
The project critical path generally runs through a limited number of long lead, usually
big ticket, procurements. These procurements cannot be placed until sufficient design is
completed to describe and specify them adequately. The cost of tho procurement is usually
large compared to the cost of the design required to place the order, which suggests that
acceleration of design may be appropriate. There is also the option of shifting design to
37
Much of the remainder of the project procurement such as basic commodities of
cement, lumber, and cable is not particularly time sensitive, and can await the normal
Procurement, other than for long lead items, has moderate schedule flexibility. It can
be scheduled to optimize the construction schedule and cost, and can be largely sub-
during conceptual planning, this flexibility may entail large cost penalties. A limited array
Usually it is most cost effective to shape the design and procurement schedules to match
the needs of the construction schedule, where the major project costs are incurred.
Two factors limit the ability of construction to shift its schedule to match design or
procurement. First, there is generally the natural best fit physical sequence to the most
expensive. Second, construction has a large overhead or support component that once
started, entails large cost. From a cost viewpoint, it becomes very expensive to extend the
construction duration. Planning studies will almost always conclude that short construction
Summary. Construction normally is the largest cost segment of a project and thus
exerts great cost leverage on a "backward pass• schedule through both procurement and
38
design. Generally, construction has a natural sequence to its most cost-effective order of
operations. Construction also has a very large cost momentum that is hard to change once
started. Certainly there are many examples of the high cost penalties paid to change
construction sequences.
Procurement, other than for long lead times, has moderate ability to conform to the
needs of the construction segment of the overall schedule. Responsibility for managing
this interface with the construction schedule will vary with contractual format. It will
Design has the greatest flexibility of all in accomodating the needs of both
procurement and construction. This may entail significant change in the level of effort of
the various design disciplines and may create the need for intense management of design
coordination. Design is a complex and demanding process, but frequently is the most
fruitful area in optimizing the entire project schedule. Unfortunately, design often has a
firm momentum of its own and departs from that only with difficulty. Additionally,
design generally is placed close to the planners and process or product groups, and it
becomes easy to get "design started" without the more thorough analysis and leveling of the
entire project schedule. This is a potential first step toward an undesirable cost or schedule
overrun.
Owners and their project managers should be sensitive to cost and schedule trade-offs
over the entire period of project activity. This analysis usually will conclude that the cost
leverage of construction operations supports the concept that the least cost project is
39
one in which the construction schedule is a principal driver of both the design and
procurement schedules.
Applications
I. The procurement schedule has a high cost impact linkage to the construction schedule.
For example, bulk materials such as cement or lumber may deteriorate if purchased too
early. Storage costs are increased if such bulks are ordered out of synch with
multiple handling and the need for storage facilities, and improve the quality of shelf
life sensitive commodities. Of course, the need for a surge inventory and the cost
systems sometimes must be installed prior to major equipment or other systems. This
may be facilitated by early design of a "larger than precisely needed" system to enable
trade-offs can only be made in an integrated planning environment with strong project
management.
3. Construction of modules of up to S,000 tons such as those for the Alaskan North Slope oil
projects has introduced new absolutes in project scheduling. Module launch dates to
meet ocean shipping windows geared to Artie ice pack movement leaves zero schedule
flexibility under penalty of losing an entire year. The "backward pass• from launch
40
date through construction, procurement, and design has created an environment of
schedule absolutes that are regularly achieved. The intensive planning that wraps
design and procurement schedules around the very expensive and largely inflexible
4. A major recurrent problem that affects construction schedule and costs is the
coordination of specific staged construction needs for single buy items such as structural
steel. Typically all the structural steel is purchased under a single purchase order from
a single supplier. Unless the detail delivery sequence for the steel components is
specified in the purchase order, the supplier may deliver in a sequence convenient to
him. If he is paid on a tons delivered basis, he may ship all the heavy members as early
as possible but not fabricate the lighter connecting steel until much.later. He may have
mill run scheduling problems for heavy steel and elect to ship all the handrails and
gratings first. He may have engineering/shop drawing approval problems and not ship
5. It is essential that the specific needs of the construction schedule be reflected in the
delivery schedule set forth in the purchase order. Delivery schedules affect supplier
prices, so there is significant cost impact to these schedule arrangements. Similarly there
is usually a loop of shop drawing preparation and engineer approvals that can impact
the fabrica.tion schedule. This cycle can involve procurement, engineering, the supplier,
and construction, and therefore must be closely managed so that the right steel is on the
scene at the right time. If it is not, the owner also risks an interlocking series of
41
subcontractor schedule delay and impact claims.
This scenario applies not only to structural steel but also to other major areas such as
piping and HY AC, which arc subject to the same fabrication and delivery schedule
risks. The entire sequence of procurement brings into focus the necessity for total
move more of the design to the field. This is particularly effective if the project is
characterized by change and the need for rapid response. Joint planning and
7. Design and procurement usually operate on a mix of early and late finish schedules.
Focusing on the early finish schedule and managing on that basis will provide more
8. Procurement schedules for the major equipment items arc particularly critical. The ideal
situation is to deliver the major equipment directly to its final base plate location. This
eliminates the expensive and sometimes risky double handling that can entail large costs
for heavy rigging and set up. Construction has already adopted may "just-in-time• (JIT)
delivery sequences such as those used in manufacturing and delivering prccase segments.
This trend toward JIT deliveries in construction will accelerate, and thus increase the
linkage among design, procurement and construction. CADD and the use of an
42
integrated project database will assist in this trend.
9. In seeking the most economical facilities owners sometimes use multiple fixed-price
manager should develop the construction schedule for use in such project optimization.
10. Design schedules should also be keyed to purchase order and bid package advertising
descriptions must be available to be part of the bid package provided to vendors. This
necessitates a close coordination of design with both the construction need date and the
11. Procurement activities after award of the purchase order are frequently complex and
subject to slippage. These activities include quality control surveillance, various shop
schedule.
12. Occasionally there are other schedule factors that must be factored into overall project
constraint that can have a major and sometimes unpredictable impact on a construction
43
Concept 11-2: Designs are configured to enable efficient construction.
Discussion
This concept emphasizes constructability's input to the design effort. The major
construction methods established during the conceptual planning phase are at this stage
expanded and refined. The desired result is to facilitate the exchange of ideas between
conform to the criteria of the client. Plans and specifications are generated on this basis
by each design discipline. Aesthetics, operability, maintainability, and safety are project
objectives that heavily influence designs. Their respective layouts and possibly a project
constructability deliberations:
is in the best interest of no one and markedly increases the probability of an unsatisfactory
finished product. Special drawings and instructions may be required to improve the
projects.
45
Flexibility for the field construction forces to select alternative methods or innovative
approaches is highly desirable. Designs should specify the desired results and not limit
approaches to attain these results. In the fully open and competitive market, it is highly
desirable to provide designs that do not limit the construction methods or approaches.
construction consideration. Many times designs have evolved so that during construction it
is discovered too late that 'we have built ourselves out of access to the next construction
operation" or because of the layout or spacing of facilities only one way remains to
sequences.
Substitutions or alternatives warrant attention, but too often are passed by with 'we
have always done it this way." Improperly considered material applications will impact
Labor skill/availability are often not considered early enough in a project life cycle.
The availability of labor and the skill level of the workers should be fully explored. The
absence of either skill levels or availability of the work force can have a costly impact on a
project and require consideration during the design phase. Use of shop
Designs that require special skills should be minimized in all cases, along with ones that arc
46
These factors will become even more important. CADD and simulation technologies are
The purpose is broader involvement in and the establishment of earlier control of the.
This occurs when completed or substantially completed products from design are merely
design products is prima facie evidence that the program is not operating on an effective
basis. Contractual formats and personnel arrangements for constructabilty must facilitate
design.
47
The end resJJlt is not to dictate the designs· that arc the easiest to bJJild. Consideration
of construction factors will assure that the completed designs and details recognize their
Applications
Architectural
Show only dimensions and details required for installation; redundant information
configurations are available to choose from, the design is quite critical. Form costs can
quantity.
48
Concrete embediments should be checked for compatibility with surface finish
Structural
Detail simple, easy to execute connections with minimum requirements for highly skilled
fabricator /constructor.
Use prefabricated L-shaped steel plates installed with the structural steel to eliminate.
Specify 'north' or 'east' end of beams for piece mark locations; this helps in orientation
during erection.
Mechanical
49
Piping
Expansion joints for rack piping runs should be nested together in a common location.
This allows several join ts to be supported at a common point, and reduces the likelihood of
Underground piping and electrical conduit should each be run at consistent elevations in
Electrical
Electrical grounds should be stub-up coiled cable in lieu of ground plates embedded in
concrete slabs. Ground plates are difficult to place correctly during a slab pour and
is difficult to align prior to equipment installation and requires more labor and material
50
Group elevated cable junctions in as few places as possible to minimize scaffolding
needs.
Instrumentation
Instruments that are precalibrated or self-calibrating can reduce testing and turnover
time.
General
apply.
Complexity not only slows construction, but may make it difficult to verify integrity.
51
Concept 11-3: Constructability is enhanced when design elements are standardized.
Discussion
This concept addresses the achic:>'cmcnt of cost and schedule benefits through the use of
standardization, a process by which project clements are both regularly and widely used,
are available, or are readily supplied. Many of the project elements have standardization
potential. Dimensions, material types, design drawing format, construction details, and
Standardization will result, with management support, through the efforts of design·
selection of off-the-shelf material. The project execution plan that is discussed in Concept
advantages and disadvantages to the project. Overall project objectives must remain
foremost in mind during this examination process. Usually the predominant trade-off is a
cost reduction that results from a time savings in construction and volume discounts in
53
Some advantages of standardization are:
spare parts and reducing the variety of spare parts stocked in the warehouse.
required:
3. Volume purchase and early shipment of materials could increase field storage costs.
54
In line with standardization, most manufacturers have established a limited number of
standard product designs. If the engineers specify changes to these designs, additional
costs and longer delivery times occur, depending on current marketplace demands, the
degree of change required, the nature of the change, and the number of items purchased.
Applications
components, minimizing the number of variations used in such items as valves and pipe
supports where possible. This should simplify CADD on a project by reducing the
variables to be addressed.
2. A void the use of unique connections in the design of structural steel in an attempt to
save a slight amount of structural steel. Bolt sizes are particularly well suited for
standardization.
corridors or pipe racks, electrical junction boxes or panels, instrument junction boxes, and
piping utility stations could each be assigned to designated zones such as one particular
55
5. Maximize the number of similar foundation sizes to permit the maximum reuse of form
6. Structural members should be standardized for supporting piping, cable trays, and
7. Piping subassemblies such as those for vents, drains, pressure gauges, orifice taps, steam
tracing manifolds, steam traps, and sample connections should be standardized and
preassembled.
8. Standardizing dimensions for such things as foundations, supports, controls stations, and
material types such as valves and architectural components will assist computer aided
56
Concept 11-4: Project constructability is enhanced when construction efficiency is
Discussion
One of the major factors affecting the efficiency and cost of field construction is the
which the designer conveys the detailed design intent to the constructor and the equipment
fabricator. Constructability helps produce specifications that are clear and complete,
standing or guide specifications from which the project specifications are derived. If the
57
constructability .are intertwined with the structure and condition of the corporate standing
specifications.
A similar relationship exists with corporate standards. They can enhance or inhibit
constructability with a direct impact on construction costs. This includes the standard
Specification development. This process starts with the first feasibility or conceptual
study on a project. This start may not be recognized, but as soon as cost values start to be
recognized and managed. It is never too early to recognize the intrinsic impact of
I. The underlying corporate guide specifications offer clear-cut options so that the
project team can readily match the needs of the project to an available specification or
to an option within a specification. The less new specification writing required, the
full and early involvement of personnel with appropriate construction knowledge and
experience.
58
3. Sufficient time is allowed to develop good project specifications. They will exert
great impact on efficiency, cost, and schedule during construction of the project. The
Rework, delays, and increased costs often have their roots in a specification that was
Maximum use of drawings, sketches, pictures, tabularized data, and formulas will help
convey precision of the design intent. Word descriptions that arc subject to
interpretation may not carry the message and should be avoided. Construction
clarity.
comprehensive.
incorporated by reference. Too often this simply passes the problem to the field,
59
6. The cost saving potential of "or equal" specifications is balanced against the risk
involved. The specification should be clear as to intent and how that intent is
make specifications obsolete with equal speed. Specifications should take advantage of
greatly in forming specifications that will allow the use of the latest and best
Applications
a. Consider the need for soil stabilization of the construction operations area
c. Maximize use of site materials for backfill in lieu of imported select materials.
60
2. Structural
a. For safety and efficiency during erection, specify that seat angles be fabricated on all
to be used to show individual piecemark number, shop order number, and project
number. This tagging method to be used on all fabricated steel items including
plus or minus tolerances where tolerance should be permitted in only one direction
3. Electrica I
a. Consider cable tray systems in lieu of rigid conduit where permitted by the National
61
4. Instrumentation
5. Piping
a. Clearly specify hydro and pneumatic test requirements on all line classifications.
b. Use service testing of low pressure air and water systems in lieu of hydro testing.
c. Avoid the use of screwed piping above 2-inch diameter unless required by fire codes.
d. Permit the use of bent small bore pipe to minimize screw fittings and welds. Use bent
6. Paint/coatings
a. Shop vs. fiela coating should be addressed to minimize work in the field.
62
b. Engineered coating systems should specify time requirements between coats in view of
7. Insulation
c. Maximize the use of a single layer of insulation as opposed to double layers. This
a. Ensure that electrical, instrument, and mechanical specifications for vendor furnished
equipment are consistent with and to the same standards as construction specifications.
Inconsistencies between specifications causes confusion and added work when the
b. Requirements for vendor drawings and data including their submittal schedule should
be spelled out in the purchase order. Be specific regarding requirements for certified
63
The need for bills of material and vendor drawings in advance of receipt of
c. In the case of fabricated components (e.g., superstructure steel and pipe spools), the
on the purchase order or contract delivery schedule. Where schedules are tight,
construction/assembly sequence.
addressed. This will save time, reduce confusion, and facilitate audit and purchase
order closeout.
64
Packaging, transportation, and related logistical considerations must be addressed
and included in !he purchase order. Improper packaging or handling procedures can
9. General
with particular construction materials may be solved by using other more readily
65
Concept 11-5: Constructability is enhanced when module/preassembly designs are prepared
Discussion
This concept establishes the principle that when the decision has been made during
preassembly, and/or prefabrication), special factors must be addressed during design and
When modules are mentioned, most people first think of the jumbo modules being
transported to the North Slope or offshore. Consider, however, a completely wired control
room no larger than a truck trailer that is delivered to the jobsite with only external
addressed for both of these during design and procurement are essentially the same:
these parameters and failure to incorporate them into the module design at an early stage
can cause extensive modifications, resulting in schedule delays and increased costs during
construction.
67
Fabrication
shop under controlled conditions, tolerances can be more stringent. If the work is
performed at the jobsite, however, the designer should incorporate flexibility into the
design due to the difficulties in achieving the same exacting standards that can only be
Requirements for lifting eyes and beams, weight limitations, hook capacity, impact, and
wind loads must be defined. Crane lifts are extremely sensitive to module weight and
center of gravity and require constant attention during the design and construction.
accessibility/maneuverability, and the lift capacity for the required angle of lift. If the
module is to be jacked into position, the position of each jacking point and its maximum
Designers must consider the routing of underground services, drainage, and conduits.
The design of these services must include possible impose loads by site vehicles and cranes,
joining of piping and utilities. Depending on the type of equipment used for module
68
placement and the degree of fabrication and setting tolerances achievable, piping may be
joined by a single buttweld or by employing a spacer piece of pipe. This will require
double welding. Using single-buttwelded joints reduces field labor, but requires more
stringent design, fabrication·, and erection tolerances for piping and structural steel to
achieve correct matching of pipe ends. The designer also needs to consider thermal
expansion and contraction occuring between the time of module fabrication and placement.
The operation for modularization usually requires a combination of two operations that
construction (EPC) cycle of conventional projects, namely shop fabrication and field
erection. These two operations involve the shop fabrication, inspection, and expediting
normally associated with vendor supplied equipment and all of the planning and logistics
type.
I. Skilled labor
3. Large open and enclosed material storage, fabrication, and assembly areas serviced
69
4. Load-out facilities
8. A well qualified engineering staff familiar with projects of this type (if they are to
Transportation
assemblies. These activities will form a major new scope for the project and will introduce
key physical or schedule restraints based on the availability of transportation and handling
equipment.
Design criteria for land transporation will depend on the type and number of
transporters selected. The loads associated with land transportation are wind, roadway
gradient, braking, and traction forces. The criteria for marine shipment of modules are
70
.. I
governed by the type of barge or heavy-lift ship selected, and by the equipment used to
load and offload the modules. At sea, modules are subjected to wind load and to inertial
forces caused by motion of the ship; sea-transferred modules themselves must meet
The first step in a successful module transportation program is a thorough route survey
covering movement of the complete assemblies from fabrication yards to their installed
location at the construction site. Generally, these routes will involve both land and marine
transport, each of which requires the choice of one or more specialized types of heavy haul
vehicles or vessels. These choices must be made early since they impact design and
Land Transoort. Land transport vehicle options usually include conventional trucks and
tractor-trailer units, rail cars, and heavy haul transporters. Since most assemblies will be
beyond the size and weight-carrying abilities of conventional truck and rail systems, land
haul transporters. These versatile but expensive vehicles are available in two basic types:
load-size weight and route conditions. They also incorporate hydraulic jacking mechanisms
to raise and lower their load-carrying platforms, a useful feature in loading and unloading
71
I. Weight limits (gross and permissible wheel loads)
3. Existing route surfacing, and grades with limiting situations and required
improvements identified
7. Construction site offloading and installation method and facilities (lifting, roll-off,
skidding, etc.)
Marine Transport. Heavy-lift vessels arc capable of using their own gear for loading and
discharge of assemblies. These self-propelled vessels are rated on the capacity of their
derricks. This type of vessel serves as a valuable tool for a project that has a few large
72
Roll-on/roll-off heavy-lift vessels are powered vessels with a flat deck capable of
carrying heavy pieces. As the name implies, these vessels are loaded by moving the load on
wheeled vehicles over a ramp into the hold or onto the deck of the ship.
Roll-on/roll-off barges are non-powered, ocean going units that are towed from one
location to another.
for exposure protection must be developed for use by the various design entities on the
project. Additionally, each module should be reviewed on an individual case basis to see if
Shipping stresses for which assemblies must be designed depend on the shipping route,
size and characteristics of the carrier, module characteristics, and the season of the
shipment.
73
4. Receiving port offloading methods, facilities, and limitations with required
improvements identified
9. Insurance
Installation
The installation method of modules affects the module design, the overall plot layout,
and the design of underground services and foundations. Thus, it is important to choose
the method of placement at the beginning of the project to minimize design changes.
Placement methods include jacking, crane lift, sliding, and placement directly by
transporters. Selection of the proper equipment depends on the module's final resting site,
weight, size, erection requirements and tie-in connections for piping between adjacent
74
When setting modules at grade, with single-weld joints between piping, jacks having the
capability of lowering the modules, as Well as aligning them in both horizontal and vertical
positions are ideal. Elevated modules can be set directly by transporters. Rubber-tired
transporters with sliding platform mechanisms can be used to achieve for single buttweld
joints between pipes of adjacent elevated modules. Cranes may be more practical for
The delivery schedule of modules to the jobsite must be sequenced. This will minimize
Projects that do not incorporate input from persons possessing knowledge and experience of
these special construction methods cannot be as successful as projects that do reflect this
Applications
classes of modules should be developed enabling numerous repetitive lifts using the
75
2. Designs should reflect the entire transportation system including consideration of
movers, i.e., ships, barges, railcars, trucks, and special heavy transporters.
3. Designs should consider how modules and preassemblies will be installed with specific
4. The procurement contracts or purchase orders for modules and preassemblies should
specify in detail the quality standards required to ensure compatibility with the
permanent facility.
5. The procurement system should provide for an appropriate vendor in-shop quality
assurance program.
6. The procurement control procedures should specify the required delivery dates of
modules and should be expedited so they will be delivered when needed. This also
allows them to be moved into place, immediately eliminating double handling, storage,
7. Modularization and underground conduit must be designed for the additional loads
imposed by lifting equipment. Additional fill and matting may be required, which
might delay the lifts and increase costs. This additional field work may be eliminated
if designers substitute steel for underground plastic conduit in these lift locations.
76
8. Fabrication of the upper sections of piperack modules may be performed adjacent to the
workface. Designers can specify that these modules be supported on temporary supports
with sufficient elevation, allowing trailers access from below. This design would
eliminate additional handling otherwise required to load these modules onto trailers.
9. Pipe spools received from vendors can be preassembled into larger spools prior to field
preassembled pipe spools should be determined and indicated on the design drawings.
10. Dressing out of all major vessels and equipment prior to erection can be performed in a
fireproofing of skirts, vessel internals (refractory linings, trays), and column davits.
11. Insufficient attention to fit-up of modules prior to shipment can cause the field to
expend 400 percent or more work-hours during field fit-up and installation than had
77
I
Concept II-6: Designs promote construction accessibility of personnel, material, and
equipment.
Discussion
This concept establishes the position that constructability will be enhanced when
adequate access of personnel, materials, and equipment are considered during the design
stage of a project. It is closely related to Concept I-6 under Conceptual Planning, which
addresses site layouts. Difficult access for personnel can severely impact productivity
since craft personnel must move to and from their work stations frequently. The time lost
in traversing slow, cumbersome paths is a direct loss. In addition, difficult access routes
frequently present unsafe working conditions with their adverse impacts. Similarly,
difficult access routes for high volume commodity materials such as steel, pipe, cable,
concrete, wall board, window frames, glass, and roofing materials will adversely impact
cost and schedule. Such routes may require addtional material handling, which could be
eliminated by a more careful design. In both personnel and high volume commodity
material there is a significant multiplier effect that justifies a close study of these
accessibility issues. These studies should also consider the several elements of the
construction plan of execution such as the material management plan to assure full
compatibility.
The need for accessibility studies for major pieces of equipm.~nt and temporary erection
access openings are as important as those for personnel and commodities. The need for
heavy lift studies to provide clear ·1aydown and lifting paths and location of temporary
79
erection access openings should be considered. This is particularly true when modules or
The early design and installation of permanent services such as lighting, fire protection,
compressed air, and potable water can eliminate the congestion of temporary factilities in
personnel can result in a better understanding of the problems involved and in designs that
provide for the best possible accessibility within the overall project objectives.
80
JO. Flow pattern of personnel to and from job site
The use of CADD techniques can be helpful in the analysis of accessibility problems.
In some cases, it may be possible to computer model access flow patterns in specific
construction input.
Applications
I. Layout of craft labor parking, access, change rooms, and eating areas should promote
2. Number, sizing, and spacing of personnel lifts should permit rapid access to and from
working areas.
3. Laydown areas and temporary warehouses should permit easy transfer of materials and
equipment to working areas and should be close to rail siding or truck delivery areas.
4. Structural designs, including ladders, are sized to permit easy access during construction
81
5. Access of late delivered large pieces of equipment should be determined to permit easy
6. Layout of underground installations should recognize the need to move heavy items of
equipment across the site in order to avoid difficult delivery routes or delays in
7. Space needed to perform welding and install insulation must be considered during
design.
8. Reel sizes and working space required around pull points must be considered during
design.
10. The design of structural system should consider how it may be used. to facilitate
11. Specify access lanes that can be used for construction and maintenance.
13. Place structural steel to support tower crane loads when supported from structural steel.
82
14. Consider available locations of major lifting equipment adjacent to and within building
15. Early design and use of permanent facilities such as office, warehouse, shops, and
paved roads and laydown areas during construction should be considered to avoid site
congestion.
16. Interface problems with existing plant operations regarding access needs and
83
Concept 11-7: Designs facilitate construction under adverse weather conditions.
Discussion
This concept establishes the principle that weather conditions influence and/or dictate
many decisions on a project. It should be recognized that adverse weather conditions can
have significant impact on construction costs and schedule. To some degree, adverse
weather conditions must be accepted as an additional challenge for the particular project.
In many cases, however, the effects of adverse weather can be alleviated with proper
The designers need to investigate and be fully aware of the weather conditions that will
be encountered at the construction site. With this knowledge and with input from
construction, the weather should be considered in all areas of design to alleviate the effects
extremes.
3. The selection of materials of construction that are the most acceptable insofar as
deterioration before and after installation and are the most compatible for
85
4. The degree of utilization of offsite preassembly and or modules to reduce
weather.
6. The design of equipment and the selection of materials of construction that can be
restrictions.
7. Construction lighting for shorter days in winter and/or for night work.
construction site.
10. Adequate temporary protected storage at the construction site for weather sensitive
equipment/materials.
86
Applications
2. Consider the use of enclosed permanent spaces to double as temporary fabricating shops
3. Accelerate and possibly alter design of permanent heating systems so work areas may be
heated.
4. Provide for early paving, early installation of rode base, temporary surfacing, and mud
5. Layout staging area for materials and equipment in manner that provides surfaced areas
6. Specify concrete admixtures and curing techniques to overcome effects of heat or cold.
8. Specify systems that will cure and/or do not require curing during cold weather.
87
9. Modularize systems so that they can be built, tested, painted, insulated, and
11. Utilize permanent lighting facilities if tem.porary lighting will be required during
12. Assure adequate drainage of construction site, including staging areas. Incorporate
designs that allow utilization of permanent drainage systems, which may include
88
ABOUT YOUR CONSTRUCTABILITY IDEAS
The Construction Industry Institute is interested in your opinion of this and other Cn
Publications
Austin, TX 78705
FIELD OPERATIONS
utilized.
Discussion
Just as there is a need to draw upon construction knowledge and experience during
is also a need to apply this knowledge and experience to improve the effectiveness of
primarily directed toward owners and designers, this concept is primarily directed toward·
constructor organizations.
The term "construction methods" is broad in scope and refers to the technical manner
in which the various construction resources are employed. Innovative construction methods
are methods that are not generally considered common practice and which are creative
Construction method innovations are numerous and are typically "small" advances.
These should not be overlooked however. Collectively, the ·potential benefit is substantial.
89
Innovative construction methods may involve:
S. Constructor-optional preassembly
of permanent materials
this concept.
Applications
I-4 and in Engineering & Procurement concept II-I. Sequencing can also improve Field
90
installation, architectural concrete, fine wood mill work, and others. Mock-ups may
2. Sequencing can serve to minimize congestion and keep access routes open.
requirements.
6. Early installation of pavement can minimize mud problems and facilitate the use of
rolling scaffolding.
7. Late sequencing of finishing activities in heavily traveled corridors and stairwells can
91
Innovative Uses of Temporary Construction Materials/Systems
Temporary construction materials and systems arc important elements for many
construction methods. In this area, new technology developments can often be employed
I. The use of seal slabs or polyethylene sheet beneath foundation rcbar or underground
2. Modular, easily transportable, and easily ercctablc forms and scaffolding such as
Golden Gate Bridge Restoration scaffolding systems, flying formwork systems, and
ground freezing.
standard spark boxes for the containment of welding spark, eliminating the need for
scaffolding; and tents used to shield underwater concrete placement from fast
currents.
92
Innovative Uses of Hand Tools
Constructability is enhanced with the use of tools that reduce labor intensity, increase
Tools may be "off the shelf," require some modification of an available tool, or be
innovation that can significantly enhance constructability. For example, on one project a
template was devised to enable workers to install four uplift connectors (chucks) with a
single jacking. In making the operation more efficient, costs were cut in excess of
$50,000.
I. Labor-reducing power hand tools such as the automatic nailing gun and the
4. Extended hand drill for at-grade installation of hanging wire for suspended ceilings,
93
---------- ·-~--··
7. P-shooter made out of small bore pipe with an inserted rebar for the purpose of
equipment by contractors themselves. On one project, steel rods were attached to the ends
solution to the same problem was devised by a contractor who attached a laser sensor to a
grader, which was then operated relative to a laser datum. In another case, constructors
responded to the challenge of achieving a smooth slab underside which would receive a
extensive planning, design, and procurement consideration prior to field operations, many
94
3. Mobile, hydraulic man-lifts in lieu of scaffolding
5. Pipe manipulators
6. Welding systems such as the plate-crawler welder and shielded active gas forge
welding
7. Pavement systems such as the sloped pavement system and the narrow, single-lane
paver
8. Remote, non-destructive sensing and inspection systems such as the nuclear soil
density meter, infrared thermography, ground penetration radar, and the cable-stay
95
e. Shotcrete robot
Constructor-Optional Preassembly
consists of that which does not require such support. Such preassembly work is strictly at
the option of the constructor, and may offer substantial opportunity for enhancing
work is typically more constructable at grade, and eliminates the need for scaffolding.
Productivity and safety can be enhanced by transferring work in congested areas to less
96
3. Anchor bolt grouping
5. HV AC duct work
Innovative ways of providing for temporary facilities can have the effect of reducing
labor intensity, reducing the likelihood of delays in providing for utilities, or improving
the permanent structural frame; the use of large shipping containers; and the use of
ribbed tents or air-inflated bubbles for moderately large enclosures needed over
bridging the area between two trailers with roof trusses and tent cloth.
97
2. Centralized utility supply networks when outlet demands are high, or where access
compressed air, and electricity. On one building site, welding gas was contained in
one large tank adjacent to the building, with outlets on each floor. The need to
periodically transport several smaller tanks from floor to floor was eliminated.
considered for temporary pavement to provide a clean and firm work surface. Shell
is commonly used for such a purpose in coastal areas; culm in mining areas; and
Conszructabi/ity Concepts File, constructor preferences arc identified early-on, prior to bid,
and are effectively treated during design and procurement and reflected in the initial
issue of drawings and specifications. Under such ideal circumstances, "design breakage" is
minimal and the preferences are given full considerations by design and procurement
personnel.
While post-bid constructor preferences arc often of limited value due to their
untimeliness, such options are introduced with open "or equal" specifications, value
98
enhance constructability. In addition, the reality of design is such that post·bid
preferences are sometimes remedial tactics that are desirable, if not required, for project
constructability.
The solicitation of constructor preferences need not be a costly effort, and should not
should be documented for the benefit of future projects. In this way, future
99