Lecture 10
Lecture 10
■ Cement Concrete
■ Reinforcement Bars
1
Bar Bending Schedule (BBS)
2
Bar Bending Schedule (BBS)
It comprise of:
■ Member Identification (Beam, Column, Slab, etc.)
■ Bar Mark (Top, Bottom, Stirrup, etc.)
■ Shape of bar
■ Type of Steel
■ Diameter of bar
■ Length of each bar
■ Number of bar
■ Total Length
■ Weight
3
Member Identification
4
Bar Mark and No. of Bars
■ For each structural members each bars has a mark or a
designation
Top, Bottom, Stirrups, Bent-up, Extra, etc.
5
Shape and Length of Bar
6
Weight of Steel
2
𝑈𝑛𝑖𝑡 𝑊𝑒𝑖𝑔ℎ𝑡 𝑜𝑓 𝑆𝑡𝑒𝑒𝑙 = 𝐷 𝑘𝑔/𝑚
162.5
7
8
Clear Cover = 25 mm
Length of 2 legs of stirrups = 24 d
9
Development Length
Ld = 16d
10
Lap Length or Lap Splices
11
End Anchorage
12
End Anchorage
13
End Anchorage
45 degree Bend
B = 12d
Total Length = L+B
14
Legs of Stirrup
15
Bent-up bars
16
L1 L2
Bent-up bars
L= L1 + h + L2 h
45⁰
h 17
Bent-up bars
30⁰
1.732h 18
Bent-up bars
60⁰
0.577h 19
Estimate quantity of Steel Reinforcement
for Beam
400
20
Estimate quantity of Steel Reinforcement for
Slab
21
Estimate
quantity of
Steel
Reinforce
ment for
Footing
and
Column
22